Columbia Gas Transmission, LLC; Notice of Intent To Prepare an 
Environmental Assessment for the Proposed VNG Suffolk No. 3 Meter 
Station Expansion Project and Request for Comments on Environmental 
Issues

    The staff of the Federal Energy Regulatory Commission (FERC or 
Commission) will prepare an environmental assessment (EA) that will 
discuss the environmental impacts of the VNG Suffolk No. 3 Meter 
Station Expansion Project involving construction and operation of 
facilities by Columbia Gas Transmission, LLC (Columbia) in Suffolk, 
Virginia. The Commission will use this EA in its decision-making 
process to determine whether the project is in the public convenience 
and necessity.
    This notice announces the opening of the scoping process the 
Commission will use to gather input from the public and interested 
agencies about issues regarding the project. The National Environmental 
Policy Act (NEPA) requires the Commission to take into account the 
environmental impacts that could result from its action whenever it 
considers the issuance of a Certificate of Public Convenience and 
Necessity. NEPA also requires the Commission to discover concerns the 
public may have about proposals. This process is referred to as 
scoping. The main goal of the scoping process is to focus the analysis 
in the EA on the important environmental issues. By this notice, the 
Commission requests public comments on the scope of the issues to 
address in the EA. To ensure that your comments are timely and properly 
recorded, please submit your comments so that the Commission receives 
them in Washington, DC on or before 5:00 pm Eastern Time on March 29, 
2019.
    You can make a difference by submitting your specific comments or 
concerns about the project. Your comments should focus on the potential 
environmental effects, reasonable alternatives, and measures to avoid 
or lessen environmental impacts. Your input will help the Commission 
staff determine what issues they need to evaluate in the EA. Commission 
staff will consider all filed comments during the preparation of the 
EA.
    If you sent comments on this project to the Commission before the 
opening of this docket on January 17, 2019, you

[[Page 8094]]

will need to file those comments in Docket No. CP19-51-000 to ensure 
they are considered as part of this proceeding.
    This notice is being sent to the Commission's current environmental 
mailing list for this project. State and local government 
representatives should notify their constituents of this proposed 
project and encourage them to comment on their areas of concern.
    If you are a landowner receiving this notice, a pipeline company 
representative may contact you about the acquisition of an easement to 
construct, operate, and maintain the proposed facilities. The company 
would seek to negotiate a mutually acceptable easement agreement. You 
are not required to enter into an agreement. However, if the Commission 
approves the project, that approval conveys with it the right of 
eminent domain. Therefore, if you and the company do not reach an 
easement agreement, the pipeline company could initiate condemnation 
proceedings in court. In such instances, compensation would be 
determined by a judge in accordance with state law.
    Columbia provided landowners with a fact sheet prepared by the FERC 
entitled ``An Interstate Natural Gas Facility On My Land? What Do I 
Need To Know?'' This fact sheet addresses a number of typically asked 
questions, including the use of eminent domain and how to participate 
in the Commission's proceedings. It is also available for viewing on 
the FERC website (www.ferc.gov) at https://www.ferc.gov/resources/guides/gas/gas.pdf.

Public Participation

    The Commission offers a free service called eSubscription which 
makes it easy to stay informed of all issuances and submittals 
regarding the dockets/projects to which you subscribe. These instant 
email notifications are the fastest way to receive notification and 
provide a link to the document files which can reduce the amount of 
time you spend researching proceedings. To sign up go to www.ferc.gov/docs-filing/esubscription.asp.
    For your convenience, there are three methods you can use to submit 
your comments to the Commission. The Commission encourages electronic 
filing of comments and has staff available to assist you at (866) 208-
3676 or [email protected]. Please carefully follow these 
instructions so that your comments are properly recorded.
    (1) You can file your comments electronically using the eComment 
feature, which is on the Commission's website (www.ferc.gov) under the 
link to Documents and Filings. Using eComment is an easy method for 
submitting brief, text-only comments on a project;
    (2) You can file your comments electronically by using the eFiling 
feature, which is on the Commission's website (www.ferc.gov) under the 
link to Documents and Filings. With eFiling, you can provide comments 
in a variety of formats by attaching them as a file with your 
submission. New eFiling users must first create an account by clicking 
on eRegister. You will be asked to select the type of filing you are 
making; a comment on a particular project is considered a Comment on a 
Filing; or
    (3) You can file a paper copy of your comments by mailing them to 
the following address. Be sure to reference the project docket number 
(CP19-51-000) with your submission: Kimberly D. Bose, Secretary, 
Federal Energy Regulatory Commission, 888 First Street NE, Room 1A, 
Washington, DC 20426

Summary of the Proposed Project

    Columbia proposes to install new meter station facilities to 
replace its existing facilities at the VNG Suffolk No. 3 Meter Station 
(MS-831056) in the City of Suffolk, Virginia. The purpose of the 
project is to realign and increase the current Maximum Daily Delivery 
Obligations of natural gas from 3.73 million cubic feet per day to 12 
million cubic feet per day between various points of delivery on the 
Columbia system in southeastern Virginia. The realignment would serve 
and meet the market demand on Columbia's system by providing an 
additional point of delivery and operational flexibility. Columbia 
would design the proposed facilities for a maximum allowable operating 
pressure of 600 pounds per square inch gauge, which is consistent with 
the supply pressure of Columbia's existing VM-107 and VM-108 pipeline 
system. Upon completion of the new meter station facilities, Columbia 
would abandon the existing meter station.
    The general location of the project is shown in appendix 1.\1\
---------------------------------------------------------------------------

    \1\ The appendices referenced in this notice will not appear in 
the Federal Register. Copies of appendices were sent to all those 
receiving this notice in the mail and are available at www.ferc.gov 
using the link called eLibrary or from the Commission's Public 
Reference Room, 888 First Street NE, Washington, DC 20426, or call 
(202) 502-8371. For instructions on connecting to eLibrary, refer to 
the last page of this notice.
---------------------------------------------------------------------------

Land Requirements for Construction

    The land requirements for the proposed project include the use of 
existing permanent right-of-way, new permanent right-of-way, additional 
temporary workspace, and permanent access roads. Columbia would disturb 
up to 3.1 acres of land for construction activities and up to 1.0 acres 
for facilities operation. Following construction, Columbia would 
restore the land affected during construction to preconstruction 
contours, except for permanent roads and aboveground facilities needed 
for operations.

The EA Process

    The EA will discuss impacts that could occur as a result of the 
construction and operation of the proposed project under these general 
headings:
     Geology and soils;
     water resources and wetlands;
     vegetation and wildlife;
     threatened and endangered species;
     cultural resources;
     land use;
     air quality and noise;
     public safety; and
     cumulative impacts
    Commission staff will also evaluate reasonable alternatives to the 
proposed project or portions of the project, and make recommendations 
on how to lessen or avoid impacts on the various resource areas.
    The EA will present Commission staffs' independent analysis of the 
issues. The EA will be available in electronic format in the public 
record through eLibrary \2\ and the Commission's website (https://www.ferc.gov/industries/gas/enviro/eis.asp). If eSubscribed, you will 
receive instant email notification when the EA is issued. The EA may be 
issued for an allotted public comment period. Commission staff will 
consider all comments on the EA before making recommendations to the 
Commission. To ensure Commission staff have the opportunity to address 
your comments, please carefully follow the instructions in the Public 
Participation section, beginning on page 2.
---------------------------------------------------------------------------

    \2\ For instructions on connecting to eLibrary, refer to the 
last page of this notice.
---------------------------------------------------------------------------

    With this notice, the Commission is asking agencies with 
jurisdiction by law and/or special expertise with respect to the 
environmental issues of this project to formally cooperate in the 
preparation of the EA.\3\ Agencies that would like to request 
cooperating agency status should follow the instructions for filing

[[Page 8095]]

comments provided under the Public Participation section of this 
notice.
---------------------------------------------------------------------------

    \3\ The Council on Environmental Quality regulations addressing 
cooperating agency responsibilities are at Title 40, Code of Federal 
Regulations, Part 1501.6.
---------------------------------------------------------------------------

Consultation Under Section 106 of the National Historic Preservation 
Act

    In accordance with the Advisory Council on Historic Preservation's 
implementing regulations for section 106 of the National Historic 
Preservation Act, the Commission is using this notice to initiate 
consultation with the applicable State Historic Preservation Office 
(SHPO), and to solicit their views and those of other government 
agencies, interested Indian tribes, and the public on the project's 
potential effects on historic properties.\4\ The EA for this project 
will document findings on the impacts on historic properties and 
summarize the status of consultations under section 106.
---------------------------------------------------------------------------

    \4\ The Advisory Council on Historic Preservation's regulations 
are at Title 36, Code of Federal Regulations, Part 800. Those 
regulations define historic properties as any prehistoric or 
historic district, site, building, structure, or object included in 
or eligible for inclusion in the National Register of Historic 
Places.
---------------------------------------------------------------------------

Environmental Mailing List

    The environmental mailing list includes federal, state, and local 
government representatives and agencies; elected officials; 
environmental and public interest groups; Native American Tribes; other 
interested parties; and local libraries. This list also includes all 
affected landowners (as defined in the Commission's regulations) who 
are potential right-of-way grantors, whose property may be used 
temporarily for project purposes, or who own homes within certain 
distances of aboveground facilities, and anyone who submits comments on 
the project. Commission staff will update the environmental mailing 
list as the analysis proceeds to ensure that Commission notices related 
to this environmental review are sent to all individuals, 
organizations, and government entities interested in and/or potentially 
affected by the proposed project.
    If the Commission issues the EA for an allotted public comment 
period, a Notice of Availability of the EA will be sent to the 
environmental mailing list and will provide instructions to access the 
electronic document on the FERC's website (www.ferc.gov). If you need 
to make changes to your name/address, or if you would like to remove 
your name from the mailing list, please return the attached Mailing 
List Update Form (appendix 2).

Additional Information

    Additional information about the project is available from the 
Commission's Office of External Affairs, at (866) 208-FERC, or on the 
FERC website at www.ferc.gov using the eLibrary link. Click on the 
eLibrary link, click on General Search and enter the docket number in 
the Docket Number field, excluding the last three digits (i.e., CP19-
51). Be sure you have selected an appropriate date range. For 
assistance, please contact FERC Online Support at 
[email protected] or (866) 208-3676, or for TTY, contact (202) 
502-8659. The eLibrary link also provides access to the texts of all 
formal documents issued by the Commission, such as orders, notices, and 
rulemakings.
    Public sessions or site visits will be posted on the Commission's 
calendar located at www.ferc.gov/EventCalendar/EventsList.aspx along 
with other related information.

    Dated: February 28, 2019.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2019-03998 Filed 3-5-19; 8:45 am]
BILLING CODE 6717-01-P


Current View
Publication Title Federal Register Volume 84, Issue 44 (March 6, 2019)
CategoryRegulatory Information
CollectionFederal Register
SuDoc Class NumberAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
Agency NamesDEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
Page Number Range8093-8095
Federal Register Citation84 FR 8093 
Docket NumbersDocket No. CP19-51-000
FR Doc Number2019-03998
fetchChildrenOnly1
granuleId2019-03998
digitizedFRfalse
showPublinkTabfalse
packageIdFR-2019-03-06
agenciesEnergy Department;Federal Energy Regulatory Commission
browsePath2019/03/03-06\/4