DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP19-99-000]


Natural Gas Pipeline Company of America; Notice of Intent To 
Prepare an Environmental Assessment for the Proposed Gulf Coast 
Southbound Project and Request for Comments on Environmental Issues

    The staff of the Federal Energy Regulatory Commission (FERC or 
Commission) will prepare an environmental assessment (EA) that will 
discuss the environmental impacts of the Gulf Coast Southbound Project 
involving construction and operation of facilities by Natural Gas 
Pipeline Company of America (Natural) in Victoria, Wharton, Harrison, 
Angelina, and Cass Counties, Texas. The Commission will use this EA in 
its decision-making process to determine whether the project is in the 
public convenience and necessity.
    This notice announces the opening of the scoping process the 
Commission will use to gather input from the public and interested 
agencies about issues regarding the project. The National Environmental 
Policy Act (NEPA) requires the Commission to take into account the 
environmental impacts that could result from its action whenever it 
considers the issuance of a Certificate of Public Convenience and 
Necessity. NEPA also requires the Commission to discover concerns the 
public may have about proposals. This process is referred to as 
``scoping.'' The main goal of the scoping process is to focus the 
analysis in the EA on the important environmental issues. By this 
notice, the Commission requests public comments on the scope of issues 
to address in the EA. To ensure that your comments are timely and 
properly recorded, please submit your comments so that the Commission 
receives them in Washington, DC on or before 5:00 p.m. Eastern Time on 
May 9, 2019.
    You can make a difference by submitting your specific comments or 
concerns about the project. Your comments should focus on the potential 
environmental effects, reasonable alternatives, and measures to avoid 
or lessen environmental impacts. Your input will help the Commission 
staff determine what issues they need to evaluate in the EA. Commission 
staff will consider all filed comments during the preparation of the 
EA.
    If you sent comments on this project to the Commission before the 
opening of this docket on February 28, 2019, you

[[Page 15208]]

will need to file those comments in Docket No. CP19-99-000 to ensure 
they are considered as part of this proceeding.
    This notice is being sent to the Commission's current environmental 
mailing list for this project. State and local government 
representatives should notify their constituents of this proposed 
project and encourage them to comment on their areas of concern.
    Natural provided landowners with a fact sheet prepared by the FERC 
entitled ``An Interstate Natural Gas Facility On My Land? What Do I 
Need To Know?'' This fact sheet addresses a number of typically asked 
questions, including the use of eminent domain and how to participate 
in the Commission's proceedings. It is also available for viewing on 
the FERC website (www.ferc.gov) at https://www.ferc.gov/resources/guides/gas/gas.pdf.

Public Participation

    The Commission offers a free service called eSubscription which 
makes it easy to stay informed of all issuances and submittals 
regarding the dockets/projects to which you subscribe. These instant 
email notifications are the fastest way to receive notification and 
provide a link to the document files which can reduce the amount of 
time you spend researching proceedings. To sign up go to www.ferc.gov/docs-filing/esubscription.asp.
    For your convenience, there are three methods you can use to submit 
your comments to the Commission. The Commission encourages electronic 
filing of comments and has staff available to assist you at (866) 208-
3676 or [email protected]. Please carefully follow these 
instructions so that your comments are properly recorded.
    (1) You can file your comments electronically using the eComment 
feature, which is located on the Commission's website (www.ferc.gov) 
under the link to Documents and Filings. Using eComment is an easy 
method for submitting brief, text-only comments on a project;
    (2) You can file your comments electronically by using the eFiling 
feature, which is located on the Commission's website (www.ferc.gov) 
under the link to Documents and Filings. With eFiling, you can provide 
comments in a variety of formats by attaching them as a file with your 
submission. New eFiling users must first create an account by clicking 
on ``eRegister.'' You will be asked to select the type of filing you 
are making; a comment on a particular project is considered a ``Comment 
on a Filing''; or
    (3) You can file a paper copy of your comments by mailing them to 
the following address. Be sure to reference the project docket number 
(CP19-99-000) with your submission: Kimberly D. Bose, Secretary, 
Federal Energy Regulatory Commission, 888 First Street NE, Room 1A, 
Washington, DC 20426.

Summary of the Proposed Project

    The Project would consist of the addition of new compressor units 
at three existing compressor stations on Natural's system and 
modifications to auxiliary facilities at two existing compressor 
stations, all within the State of Texas. The Project would allow 
Natural to provide 300,000 dekatherms of southbound firm transportation 
capacity to Corpus Christi Liquefaction, L.L.C., and would include:
     Installation of one new electric motor driven compressor 
unit with a rating of 10,000 horsepower, and auxiliary facilities, 
including additional cooling equipment and a new filter separator, at 
existing Compressor Station 300 in Victoria County.
     Installation of one Solar Mars 100 turbine with a rating 
of 15,900 horsepower, and auxiliary facilities, including additional 
cooling equipment and replacement of two filter separators, at existing 
Compressor Station 301 in Wharton County.
     Installation of two Solar Titan 130 turbines with a rating 
of 23,470 horsepower each, and auxiliary facilities, including 
additional cooling equipment and filter separators, at existing 
Compressor Station 304 in Harrison County.
     Installation of an additional gas cooler and filter 
separator at existing Compressor Station 303 in Angelina County and at 
existing Compressor Station 394 in Cass County.
    The general location of the project facilities is shown in appendix 
1.\1\
---------------------------------------------------------------------------

    \1\ The appendices referenced in this notice will not appear in 
the Federal Register. Copies of appendices were sent to all those 
receiving this notice in the mail and are available at www.ferc.gov 
using the link called ``eLibrary'' or from the Commission's Public 
Reference Room, 888 First Street NE, Washington, DC 20426, or call 
(202) 502-8371.
---------------------------------------------------------------------------

Land Requirements for Construction

    Construction of the Project would disturb about 147 acres of land, 
all within the fenced operational areas of existing natural gas 
compression facilities. Access to the facilities would be over 
Natural's existing access roads and no new land would need to be 
acquired for construction or operation of these facilities.

The EA Process

    The EA will discuss impacts that could occur as a result of the 
construction and operation of the proposed project under these general 
headings:
     Geology and soils;
     water resources and wetlands;
     vegetation and wildlife;
     threatened and endangered species;
     cultural resources;
     socioeconomics;
     air quality and noise;
     public safety; and
     cumulative impacts
    Commission staff will also evaluate reasonable alternatives to the 
proposed project or portions of the project, and make recommendations 
on how to lessen or avoid impacts on the various resource areas.
    The EA will present Commission staffs' independent analysis of the 
issues. The EA will be available in electronic format in the public 
record through eLibrary \2\ and the Commission's website (https://www.ferc.gov/industries/gas/enviro/eis.asp). If eSubscribed, you will 
receive instant email notification when the EA is issued. The EA may be 
issued for an allotted public comment period. Commission staff will 
consider all comments on the EA before making recommendations to the 
Commission. To ensure Commission staff have the opportunity to address 
your comments, please carefully follow the instructions in the Public 
Participation section, beginning on page 2.
---------------------------------------------------------------------------

    \2\ For instructions on connecting to eLibrary, refer to page 5 
of this notice.
---------------------------------------------------------------------------

    With this notice, the Commission is asking agencies with 
jurisdiction by law and/or special expertise with respect to the 
environmental issues of this project to formally cooperate in the 
preparation of the EA.\3\ Agencies that would like to request 
cooperating agency status should follow the instructions for filing 
comments provided under the Public Participation section of this 
notice.
---------------------------------------------------------------------------

    \3\ The Council on Environmental Quality regulations addressing 
cooperating agency responsibilities are at Title 40, Code of Federal 
Regulations, Part 1501.6.
---------------------------------------------------------------------------

Consultation Under Section 106 of the National Historic Preservation 
Act

    In accordance with the Advisory Council on Historic Preservation's 
implementing regulations for section 106 of the National Historic 
Preservation Act, the Commission is using this notice to initiate 
consultation with the applicable State Historic Preservation Office, 
and to solicit their views and those of other government

[[Page 15209]]

agencies, interested Indian tribes, and the public on the project's 
potential effects on historic properties.\4\ The EA for this project 
will document findings on the impacts on historic properties and 
summarize the status of consultations under section 106.
---------------------------------------------------------------------------

    \4\ The Advisory Council on Historic Preservation's regulations 
are at Title 36, Code of Federal Regulations, Part 800. Those 
regulations define historic properties as any prehistoric or 
historic district, site, building, structure, or object included in 
or eligible for inclusion in the National Register of Historic 
Places.
---------------------------------------------------------------------------

Environmental Mailing List

    The environmental mailing list includes federal, state, and local 
government representatives and agencies; elected officials; 
environmental and public interest groups; Native American Tribes; other 
interested parties; and local newspapers. This list also includes all 
affected landowners (as defined in the Commission's regulations) those 
who own homes within certain distances of aboveground facilities, and 
anyone who submits comments on the project. Commission staff will 
update the environmental mailing list as the analysis proceeds to 
ensure that Commission notices related to this environmental review are 
sent to all individuals, organizations, and government entities 
interested in and/or potentially affected by the proposed project.
    If the Commission issues the EA for an allotted public comment 
period, a Notice of Availability of the EA will be sent to the 
environmental mailing list and will provide instructions on how to 
access the electronic document on the FERC's website (www.ferc.gov). If 
you need to make changes to your name/address, or if you would like to 
remove your name from the mailing list, please return the attached 
``Mailing List Update Form'' (appendix 2).

Additional Information

    Additional information about the project is available from the 
Commission's Office of External Affairs, at (866) 208-FERC, or on the 
FERC website at www.ferc.gov using the eLibrary link. Click on the 
eLibrary link, click on ``General Search'' and enter the docket number 
in the ``Docket Number'' field, excluding the last three digits (i.e., 
CP19-99). Be sure you have selected an appropriate date range. For 
assistance, please contact FERC Online Support at 
[email protected] or (866) 208-3676, or for TTY, contact (202) 
502-8659. The eLibrary link also provides access to the texts of all 
formal documents issued by the Commission, such as orders, notices, and 
rulemakings.
    Public sessions or site visits will be posted on the Commission's 
calendar located at www.ferc.gov/EventCalendar/EventsList.aspx along 
with other related information.

    Dated: April 9, 2019.
Kimberly D. Bose,
Secretary.
[FR Doc. 2019-07419 Filed 4-12-19; 8:45 am]
 BILLING CODE 6717-01-P


Current View
Publication Title Federal Register Volume 84, Issue 72 (April 15, 2019)
CategoryRegulatory Information
CollectionFederal Register
SuDoc Class NumberAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
Agency NamesDEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
Page Number Range15207-15209
Federal Register Citation84 FR 15207 
Docket NumbersDocket No. CP19-99-000
FR Doc Number2019-07419
agenciesEnergy Department;Federal Energy Regulatory Commission
browsePath2019/04/04-15\/2
digitizedFRfalse
fetchChildrenOnly1
granuleId2019-07419
packageIdFR-2019-04-15
showPublinkTabfalse