83_FR_31877 83 FR 31746 - Portland Natural Gas Transmission System; Notice of Applications

83 FR 31746 - Portland Natural Gas Transmission System; Notice of Applications

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 83, Issue 131 (July 9, 2018)

Page Range31746-31747
FR Document2018-14558

Federal Register, Volume 83 Issue 131 (Monday, July 9, 2018)
[Federal Register Volume 83, Number 131 (Monday, July 9, 2018)]
[Notices]
[Pages 31746-31747]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2018-14558]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP18-506-000]


Portland Natural Gas Transmission System; Notice of Applications

    Take notice that on June 19, 2018, Portland Natural Gas 
Transmission System (Portland Natural Gas), 700 Louisiana Street, Suite 
700, Houston, TX 77002-2700, filed an application under section 7(c) 
and 7(b) of the Natural Gas Act (NGA), 15 U.S.C. Sections 717f(c) and 
717f(b), and Parts 157 and 284 of the Commission's rules \1\ and 
regulations for Phase III of the Portland Xpress Project. Portland 
Natural Gas requests authorization to install one new 6,300 horsepower 
compressor unit at the existing Eliot Compressor Station located in 
York County, Maine and modifications to the infrastructure at the 
existing Westbrook Compressor Station and Dracut Metering and 
Regulating Station located in Cumberland County, Maine and Middlesex 
County, Massachusetts respectively. Upon completion, the project will 
increase the certificated capacity on Portland Natural Gas' wholly-
owned north system from Pittsburg, New Hampshire, to Westbrook, Maine, 
by 24.375 MMcf/d, and increase Portland Natural Gas' certificated 
capacity on the system it jointly owns with Maritimes & Northeast 
Pipeline, L.L.C. from Westbrook, Maine, to Dracut, Massachusetts by 
22.339 MMcf/d. Additionally, Portland Natural Gas is requesting to 
abandon the leased capacity previously requested in CP18-479-000 and to 
acquire a proportionate share of ownership interest in a compressor 
unit at the Westbrook Compressor Station. Portland Natural Gas 
estimates the total cost of the project to be $90.3 million, all as 
more fully described in the application which is on file with the 
Commission and open to public inspection. The filing may also be viewed 
on the web at http://www.ferc.gov using the ``eLibrary'' link. Enter 
the docket number excluding the last three digits in the docket number 
field to access the document. For assistance, contact FERC at 
[email protected] or call toll-free, (866) 208-3676 or TTY, 
(202) 502-8659.
---------------------------------------------------------------------------

    \1\ 18 CFR parts 157 and 284 (2017).
---------------------------------------------------------------------------

    Any questions regarding this application should be directed to 
Robert Jackson, Manager, Certificates & Regulatory Administration, 
Portland Natural Gas Transmission System, 700 Louisiana Street, Suite 
700, Houston, Texas 77002-2700, or call (832) 320-5487, or email: 
[email protected].
    Pursuant to section 157.9 of the Commission's rules (18 CFR 157.9), 
within 90 days of this Notice, the Commission staff will either: 
complete its environmental assessment (EA) and place it into the 
Commission's public record (eLibrary) for this proceeding; or issue a 
Notice of Schedule for Environmental Review. If a Notice of Schedule 
for Environmental Review is issued, it will indicate, among other 
milestones, the anticipated date for the Commission staff's issuance of 
the final environmental impact statement (FEIS) or EA for this 
proposal. The filing of the EA in the Commission's public record for 
this proceeding or the issuance of a Notice of Schedule for 
Environmental Review will serve to notify federal and state agencies of 
the timing for the completion of all necessary reviews, and the 
subsequent need to complete all federal authorizations within 90 days 
of the date of issuance of the Commission staff's FEIS or EA.
    There are two ways to become involved in the Commission's review of 
this project. First, any person wishing to obtain legal status by 
becoming a party to the proceedings for this project should, on or 
before the comment date stated below file with the Federal Energy 
Regulatory Commission, 888 First Street NE, Washington, DC 20426, a 
motion to intervene in accordance with the requirements of the 
Commission's Rules of Practice and Procedure (18 CFR 385.214 or 
385.211) and the Regulations under the NGA (18 CFR 157.10). A person 
obtaining party status will be placed on the service list maintained by 
the Secretary of the Commission and will receive copies of all 
documents filed by the applicant and by all other parties. A party must 
submit 7 copies of filings made in the proceeding with the Commission 
and must mail a copy to the applicant and to every other party. Only 
parties to the

[[Page 31747]]

proceeding can ask for court review of Commission orders in the 
proceeding.
    However, a person does not have to intervene in order to have 
comments considered. The second way to participate is by filing with 
the Secretary of the Commission, as soon as possible, an original and 
two copies of comments in support of or in opposition to this project. 
The Commission will consider these comments in determining the 
appropriate action to be taken, but the filing of a comment alone will 
not serve to make the filer a party to the proceeding. The Commission's 
rules require that persons filing comments in opposition to the project 
provide copies of their protests only to the party or parties directly 
involved in the protest.
    Persons who wish to comment only on the environmental review of 
this project should submit an original and two copies of their comments 
to the Secretary of the Commission. Environmental commentors will be 
placed on the Commission's environmental mailing list, will receive 
copies of the environmental documents, and will be notified of meetings 
associated with the Commission's environmental review process. 
Environmental commentors will not be required to serve copies of filed 
documents on all other parties. However, the non-party commentors will 
not receive copies of all documents filed by other parties or issued by 
the Commission (except for the mailing of environmental documents 
issued by the Commission) and will not have the right to seek court 
review of the Commission's final order.
    The Commission strongly encourages electronic filings of comments, 
protests and interventions in lieu of paper using the eFiling link at 
http://www.ferc.gov. Persons unable to file electronically should 
submit an original and 5 copies of the protest or intervention to the 
Federal Energy regulatory Commission, 888 First Street NE, Washington, 
DC 20426.
    Comment Date: July 19, 2018.

    Dated: June 28, 2018.
Kimberly D. Bose,
Secretary.
[FR Doc. 2018-14558 Filed 7-6-18; 8:45 am]
 BILLING CODE 6717-01-P



                                                31746                            Federal Register / Vol. 83, No. 131 / Monday, July 9, 2018 / Notices

                                                April 30, 2018 on behalf of the Village                    p. Register online at http://                           is on file with the Commission and open
                                                of Enosburg Falls Municipal Water and                    www.ferc.gov/docs-filing/                                 to public inspection. The filing may also
                                                Light Department, and provided public                    esubscription.asp to be notified via                      be viewed on the web at http://
                                                notice of the request on April 27, 2018.                 email of new filings and issuances                        www.ferc.gov using the ‘‘eLibrary’’ link.
                                                In a letter dated June 28, 2018, the                     related to this or other pending projects.                Enter the docket number excluding the
                                                Director of the Division of Hydropower                   For assistance, contact FERC Online                       last three digits in the docket number
                                                Licensing approved Enosburg Falls’                       Support.                                                  field to access the document. For
                                                request to use the Traditional Licensing                   Dated: June 28, 2018.                                   assistance, contact FERC at
                                                Process.                                                                                                           FERCOnlineSupport@ferc.gov or call
                                                                                                         Kimberly D. Bose,
                                                   k. With this notice, we are initiating                                                                          toll-free, (866) 208–3676 or TTY, (202)
                                                informal consultation with the U.S. Fish                 Secretary.                                                502–8659.
                                                and Wildlife Service and NOAA                            [FR Doc. 2018–14568 Filed 7–6–18; 8:45 am]                   Any questions regarding this
                                                Fisheries under section 7 of the                         BILLING CODE 6717–01–P                                    application should be directed to Robert
                                                Endangered Species Act and the joint                                                                               Jackson, Manager, Certificates &
                                                agency regulations thereunder at 50 CFR                                                                            Regulatory Administration, Portland
                                                part 402; and NOAA Fisheries under                       DEPARTMENT OF ENERGY                                      Natural Gas Transmission System, 700
                                                section 305(b) of the Magnuson-Stevens                                                                             Louisiana Street, Suite 700, Houston,
                                                Fishery Conservation and Management                      Federal Energy Regulatory                                 Texas 77002–2700, or call (832) 320–
                                                Act and implementing regulations at 50                   Commission                                                5487, or email: robert_jackson@
                                                CFR 600.920. We are also initiating                      [Docket No. CP18–506–000]                                 transcanada.com.
                                                consultation with the Vermont State                                                                                   Pursuant to section 157.9 of the
                                                Historic Preservation Officer, as                        Portland Natural Gas Transmission                         Commission’s rules (18 CFR 157.9),
                                                required by section 106 of the National                  System; Notice of Applications                            within 90 days of this Notice, the
                                                Historic Preservation Act, and the                                                                                 Commission staff will either: complete
                                                implementing regulations of the                            Take notice that on June 19, 2018,                      its environmental assessment (EA) and
                                                Advisory Council on Historic                             Portland Natural Gas Transmission                         place it into the Commission’s public
                                                Preservation at 36 CFR 800.2.                            System (Portland Natural Gas), 700                        record (eLibrary) for this proceeding; or
                                                   l. With this notice, we are designating               Louisiana Street, Suite 700, Houston,                     issue a Notice of Schedule for
                                                Enosburg Falls as the Commission’s                       TX 77002–2700, filed an application                       Environmental Review. If a Notice of
                                                non-federal representative for carrying                  under section 7(c) and 7(b) of the                        Schedule for Environmental Review is
                                                out informal consultation pursuant to                    Natural Gas Act (NGA), 15 U.S.C.                          issued, it will indicate, among other
                                                section 7 of the Endangered Species Act;                 Sections 717f(c) and 717f(b), and Parts                   milestones, the anticipated date for the
                                                and consultation pursuant to section                     157 and 284 of the Commission’s rules 1                   Commission staff’s issuance of the final
                                                106 of the National Historic                             and regulations for Phase III of the                      environmental impact statement (FEIS)
                                                Preservation Act.                                        Portland Xpress Project. Portland                         or EA for this proposal. The filing of the
                                                   m. Enosburg Falls filed a Pre-                        Natural Gas requests authorization to                     EA in the Commission’s public record
                                                Application Document (PAD; including                     install one new 6,300 horsepower                          for this proceeding or the issuance of a
                                                a proposed process plan and schedule)                    compressor unit at the existing Eliot                     Notice of Schedule for Environmental
                                                with the Commission on behalf of the                     Compressor Station located in York                        Review will serve to notify federal and
                                                Village of Enosburg Falls Municipal                      County, Maine and modifications to the                    state agencies of the timing for the
                                                Water and Light Department, pursuant                     infrastructure at the existing Westbrook                  completion of all necessary reviews, and
                                                to 18 CFR 5.6 of the Commission’s                        Compressor Station and Dracut                             the subsequent need to complete all
                                                regulations.                                             Metering and Regulating Station located                   federal authorizations within 90 days of
                                                   n. A copy of the PAD is available for                 in Cumberland County, Maine and                           the date of issuance of the Commission
                                                review at the Commission in the Public                   Middlesex County, Massachusetts                           staff’s FEIS or EA.
                                                Reference Room or may be viewed on                       respectively. Upon completion, the                           There are two ways to become
                                                the Commission’s website (http://                        project will increase the certificated                    involved in the Commission’s review of
                                                www.ferc.gov), using the eLibrary link.                  capacity on Portland Natural Gas’                         this project. First, any person wishing to
                                                Enter the docket number, excluding the                   wholly-owned north system from                            obtain legal status by becoming a party
                                                last three digits in the docket number                   Pittsburg, New Hampshire, to                              to the proceedings for this project
                                                field to access the document. For                        Westbrook, Maine, by 24.375 MMcf/d,                       should, on or before the comment date
                                                assistance, contact FERC Online                          and increase Portland Natural Gas’                        stated below file with the Federal
                                                Support at FERCOnlineSupport@                            certificated capacity on the system it                    Energy Regulatory Commission, 888
                                                ferc.gov, (866) 208–3676 (toll free), or                 jointly owns with Maritimes &                             First Street NE, Washington, DC 20426,
                                                (202) 502–8659 (TTY). A copy is also                     Northeast Pipeline, L.L.C. from                           a motion to intervene in accordance
                                                available for inspection and                             Westbrook, Maine, to Dracut,                              with the requirements of the
                                                reproduction at 42 Village Drive,                        Massachusetts by 22.339 MMcf/d.                           Commission’s Rules of Practice and
                                                Enosburg Falls, VT 05450.                                Additionally, Portland Natural Gas is                     Procedure (18 CFR 385.214 or 385.211)
                                                   o. The licensee states its unequivocal                requesting to abandon the leased                          and the Regulations under the NGA (18
                                                intent to submit an application for a                    capacity previously requested in CP18–                    CFR 157.10). A person obtaining party
                                                new license for Project No. 2905.                        479–000 and to acquire a proportionate                    status will be placed on the service list
                                                Pursuant to 18 CFR 16.8, 16.9, and                                                                                 maintained by the Secretary of the
sradovich on DSK3GMQ082PROD with NOTICES




                                                                                                         share of ownership interest in a
                                                16.10, each application for a new                        compressor unit at the Westbrook                          Commission and will receive copies of
                                                license and any competing license                        Compressor Station. Portland Natural                      all documents filed by the applicant and
                                                applications must be filed with the                      Gas estimates the total cost of the                       by all other parties. A party must submit
                                                Commission at least 24 months prior to                   project to be $90.3 million, all as more                  7 copies of filings made in the
                                                the expiration of the existing license.                  fully described in the application which                  proceeding with the Commission and
                                                All applications for license for this                                                                              must mail a copy to the applicant and
                                                project must be filed by April 30, 2021.                      1 18   CFR parts 157 and 284 (2017).                 to every other party. Only parties to the


                                           VerDate Sep<11>2014   18:00 Jul 06, 2018   Jkt 244001   PO 00000     Frm 00032     Fmt 4703   Sfmt 4703   E:\FR\FM\09JYN1.SGM   09JYN1


                                                                                 Federal Register / Vol. 83, No. 131 / Monday, July 9, 2018 / Notices                                                  31747

                                                proceeding can ask for court review of                   DEPARTMENT OF ENERGY                                  Market-Based Rate Authority to be
                                                Commission orders in the proceeding.                                                                           effective 8/27/2018.
                                                                                                         Federal Energy Regulatory                                Filed Date: 6/27/18.
                                                   However, a person does not have to
                                                                                                         Commission                                               Accession Number: 20180627–5129.
                                                intervene in order to have comments
                                                considered. The second way to                                                                                     Comments Due: 5 p.m. ET 7/18/18.
                                                                                                         Combined Notice of Filings #1
                                                participate is by filing with the                                                                                 The filings are accessible in the
                                                Secretary of the Commission, as soon as                     Take notice that the Commission                    Commission’s eLibrary system by
                                                possible, an original and two copies of                  received the following electric rate                  clicking on the links or querying the
                                                comments in support of or in opposition                  filings:                                              docket number.
                                                to this project. The Commission will                        Docket Numbers: ER11–47–009;                          Any person desiring to intervene or
                                                                                                         ER12–1540–007; ER12–1541–007;                         protest in any of the above proceedings
                                                consider these comments in
                                                                                                         ER12–1542–007; ER12–1544–007;                         must file in accordance with Rules 211
                                                determining the appropriate action to be
                                                                                                         ER14–594–011; ER11–46–012; ER11–                      and 214 of the Commission’s
                                                taken, but the filing of a comment alone                                                                       Regulations (18 CFR 385.211 and
                                                will not serve to make the filer a party                 41–009; ER12–2343–007; ER13–1896–
                                                                                                         013; ER16–323–005; ER17–1930–001;                     385.214) on or before 5:00 p.m. Eastern
                                                to the proceeding. The Commission’s                                                                            time on the specified comment date.
                                                rules require that persons filing                        ER17–1931–001; ER17–1932–001.
                                                                                                            Applicants: Appalachian Power                      Protests may be considered, but
                                                comments in opposition to the project                                                                          intervention is necessary to become a
                                                                                                         Company, Indiana Michigan Power
                                                provide copies of their protests only to                                                                       party to the proceeding.
                                                                                                         Company, Kentucky Power Company,
                                                the party or parties directly involved in                                                                         eFiling is encouraged. More detailed
                                                                                                         Kingsport Power Company, Wheeling
                                                the protest.                                             Power Company, AEP Texas Inc., Public                 information relating to filing
                                                   Persons who wish to comment only                      Service Company of Oklahoma,                          requirements, interventions, protests,
                                                on the environmental review of this                      Southwestern Electric Power Company,                  service, and qualifying facilities filings
                                                project should submit an original and                    Ohio Power Company, AEP Energy                        can be found at: http://www.ferc.gov/
                                                two copies of their comments to the                      Partners, Inc., AEP Retail Energy                     docs-filing/efiling/filing-req.pdf. For
                                                Secretary of the Commission.                             Partners LLC, AEP Energy, Inc., AEP                   other information, call (866) 208–3676
                                                Environmental commentors will be                         Generation Resources Inc., Ohio Valley                (toll free). For TTY, call (202) 502–8659.
                                                placed on the Commission’s                               Electric Corporation.                                   Dated: June 28, 2018.
                                                environmental mailing list, will receive                    Description: Updated Market Power                  Kimberly D. Bose,
                                                copies of the environmental documents,                   Analysis in the Southwest Power Pool                  Secretary.
                                                and will be notified of meetings                         balancing area authority of the AEP                   [FR Doc. 2018–14567 Filed 7–6–18; 8:45 am]
                                                associated with the Commission’s                         MBR affiliates.                                       BILLING CODE 6717–01–P
                                                environmental review process.                               Filed Date: 6/26/18.
                                                Environmental commentors will not be                        Accession Number: 20180626–5244.
                                                required to serve copies of filed                           Comments Due: 5 p.m. ET 8/27/18.                   DEPARTMENT OF ENERGY
                                                documents on all other parties.                             Docket Numbers: ER11–1858–007.
                                                However, the non-party commentors                           Applicants: NorthWestern                           Federal Energy Regulatory
                                                                                                         Corporation.                                          Commission
                                                will not receive copies of all documents
                                                filed by other parties or issued by the                     Description: Triennial Market Power
                                                                                                         Analysis for the Southwest Power Pool                 [Project No. 14642–002]
                                                Commission (except for the mailing of
                                                                                                         Region of NorthWestern Corporation.
                                                environmental documents issued by the                                                                          San Diego County Water Authority,
                                                                                                            Filed Date: 6/26/18.
                                                Commission) and will not have the right                     Accession Number: 20180626–5246.                   City of San Diego; Notice of
                                                to seek court review of the                                 Comments Due: 5 p.m. ET 8/27/18.                   Preliminary Permit Application
                                                Commission’s final order.                                                                                      Accepted for Filing and Soliciting
                                                                                                            Docket Numbers: ER18–1861–000.
                                                   The Commission strongly encourages                       Applicants: New England Power                      Comments, Motions To Intervene, and
                                                electronic filings of comments, protests                 Company.                                              Competing Applications
                                                and interventions in lieu of paper using                    Description: Tariff Cancellation:                  (June 28, 2018)
                                                the eFiling link at http://www.ferc.gov.                 Notice of Cancellation of Service                        On May 1, 2018, the San Diego
                                                Persons unable to file electronically                    Agreement with Wheelabrator Millbury,                 County Water Authority and the City of
                                                should submit an original and 5 copies                   Inc. to be effective 8/27/2018.                       San Diego, California, jointly filed an
                                                of the protest or intervention to the                       Filed Date: 6/27/18.                               application for a preliminary permit,
                                                Federal Energy regulatory Commission,                       Accession Number: 20180627–5047.                   pursuant to section 4(f) of the Federal
                                                888 First Street NE, Washington, DC                         Comments Due: 5 p.m. ET 7/18/18.                   Power Act (FPA), proposing to study the
                                                20426.                                                      Docket Numbers: ER18–1862–000.                     feasibility of the San Vicente Energy
                                                   Comment Date: July 19, 2018.                             Applicants: Duke Energy Progress,                  Storage Facility, to be located at San
                                                                                                         LLC.                                                  Vicente reservoir, in Lakeside,
                                                  Dated: June 28, 2018.                                     Description: § 205(d) Rate Filing: DEP-            California. The sole purpose of a
                                                Kimberly D. Bose,                                        Five Towns Reimbursement Agreements                   preliminary permit, if issued, is to grant
                                                Secretary.                                               to be effective 9/1/2018.                             the permit holder priority to file a
sradovich on DSK3GMQ082PROD with NOTICES




                                                [FR Doc. 2018–14558 Filed 7–6–18; 8:45 am]                  Filed Date: 6/27/18.                               license application during the permit
                                                BILLING CODE 6717–01–P                                      Accession Number: 20180627–5067.                   term. A preliminary permit does not
                                                                                                            Comments Due: 5 p.m. ET 7/18/18.                   authorize the permit holder to perform
                                                                                                            Docket Numbers: ER18–1863–000.                     any land-disturbing activities or
                                                                                                            Applicants: Coolidge Solar I, LLC.                 otherwise enter upon lands or waters
                                                                                                            Description: Baseline eTariff Filing:              owned by others without the owners’
                                                                                                         Coolidge Solar I, LLC Application for                 express permission.


                                           VerDate Sep<11>2014   18:00 Jul 06, 2018   Jkt 244001   PO 00000   Frm 00033   Fmt 4703   Sfmt 4703   E:\FR\FM\09JYN1.SGM   09JYN1



Document Created: 2018-07-07 00:42:12
Document Modified: 2018-07-07 00:42:12
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
DatesJuly 19, 2018.
FR Citation83 FR 31746 