Department of Energy
Bonneville Power Administration
AGENCY:
Bonneville Power Administration (BPA), Department of Energy (DOE).
ACTION:
Notice of Floodplain and Wetlands Involvement.
SUMMARY:
This notice announces BPA's proposal to rebuild its existing Shelton-Kitsap No.2 115-kV transmission line as a double circuit 230-kV line in the existing right-of-way in floodplain and wetlands located in Mason and Kitsap Counties, Washington. In accordance with DOE regulations for compliance with floodplain and wetlands environmental review requirements, BPA will prepare a floodplain and wetlands assessment and will perform this proposed action in a manner so as to avoid or minimize potential harm to or within the affected floodplain and wetlands. The assessment will be included in the environmental assessment being prepared for the proposed project in accordance with the requirements of the National Environmental Policy Act. A floodplain statement of findings will be included in any finding of no significant impact that may be issued following the completion of the environmental assessment.
DATES:
Comments are due to the address below no later than October 2, 2000.
ADDRESSES:
Submit comments to Communications, Bonneville Power Administration—KC-7, P.O. Box 12999, Portland, Oregon 97212. Internet address: comment@bpa.gov.
FOR FURTHER INFORMATION CONTACT:
Dawn R. Boorse—KECN-4, Bonneville Power Administration, P.O. Box 3621, Portland, Oregon, 97208-3621, phone number 503-230-5678, fax number 503-230-5699.