Record of Decision for Issuing a Presidential Permit to Transmission Developers, Inc.-New England, for the New England Clean Power Link Transmission Line Project

The Department of Energy (DOE) announces its decision to issue a Presidential permit to Champlain VT, LLC, d/b/a Transmission Developers, Inc.--New England (TDI-NE), to construc...

The Department of Energy (DOE) announces its decision to issue a Presidential permit to Champlain VT, LLC, d/b/a Transmission Developers, Inc.--New England (TDI-NE), to construct, operate, maintain, and connect an electric transmission line across the U.S./ Canada international border in northern Vermont. The potential environmental impacts associated with the transmission line are analyzed in the New England Clean Power Link (NECPL) Project Final Environmental Impact Statement (DOE/EIS-0503). As proposed, the NECPL Transmission Line would extend south from the U.S./Canada international border approximately 154 miles to a new converter station in Ludlow, Vermont and the existing Coolidge Substation in the towns of Ludlow and Cavendish, Vermont.

Legal Citation

Federal Register Citation

Use this for formal legal and research references to the published document.

81 FR 89450

Web Citation

Suggested Web Citation

Use this when citing the archival web version of the document.

“Record of Decision for Issuing a Presidential Permit to Transmission Developers, Inc.-New England, for the New England Clean Power Link Transmission Line Project,” thefederalregister.org (December 12, 2016), https://thefederalregister.org/documents/2016-29700/record-of-decision-for-issuing-a-presidential-permit-to-transmission-developers-inc-new-england-for-the-new-england-clea.