Document

Southern Nuclear Operating Company, Inc.; Vogtle Electric Generating Plant, Units 3 and 4; Reactor Vessel Head Vent Capacity

The U.S. Nuclear Regulatory Commission (NRC) is granting an exemption to allow a departure from elements of the certification information of Tier 1 of the generic AP1000 design ...

The U.S. Nuclear Regulatory Commission (NRC) is granting an exemption to allow a departure from elements of the certification information of Tier 1 of the generic AP1000 design control document (DCD) and is issuing License Amendment Nos. 114 and 113 to Combined Licenses (COL), NPF-91 and NPF-92, respectively. The COLs were issued to Southern Nuclear Operating Company, and Georgia Power Company, Oglethorpe Power Corporation, MEAG Power SPVM, LLC, MEAG Power SPVJ, LLC, MEAG Power SPVP, LLC, and the City of Dalton, Georgia (collectively referred to as the licensee); for construction and operation of the Vogtle Electric Generating Plant (VEGP) Units 3 and 4, located in Burke County, Georgia. The granting of the exemption allows the changes to Tier 1 information asked for in the amendment. Because the acceptability of the exemption was determined in part by the acceptability of the amendment, the exemption and amendment are being issued concurrently. The exemption revises the plant-specific Tier 1 information and corresponding changes to COL Appendix C, and the amendment changes the associated plant-specific DCD Tier 2 material incorporated into the VEGP Updated Final Safety Analysis Report (UFSAR), to update Reactor Coolant System (RCS) requirements for reactor vessel head vent (RVHV) mass flow rate for the VEGP Units 3 and 4.

Legal Citation

Federal Register Citation

Use this for formal legal and research references to the published document.

83 FR 13528

Web Citation

Suggested Web Citation

Use this when citing the archival web version of the document.

“Southern Nuclear Operating Company, Inc.; Vogtle Electric Generating Plant, Units 3 and 4; Reactor Vessel Head Vent Capacity,” thefederalregister.org (March 29, 2018), https://thefederalregister.org/documents/2018-06261/southern-nuclear-operating-company-inc-vogtle-electric-generating-plant-units-3-and-4-reactor-vessel-head-vent-capacity.