[Federal Register Volume 91, Number 1 (Friday, January 2, 2026)]
[Notices]
[Pages 140-141]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2025-24189]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP25-219-000]


Gulf South Pipeline Company, LLC; Notice of Availability of the 
Environmental Assessment for the Proposed Southeast Compression Utility 
and Reliability Expansion Project

    The staff of the Federal Energy Regulatory Commission (FERC or 
Commission) has prepared an environmental assessment (EA) for the 
Southeast Compression Utility and Reliability Expansion Project (SECURE 
Project or Project), proposed by Gulf South Pipeline Company, LLC (Gulf 
South) in the above-referenced docket.\1\ Gulf South requests 
authorization to construct and operate certain natural gas pipeline 
facilities in Madison Parish, Louisiana and Jasper, Forrest, and Hinds 
Counties, Mississippi. The proposed Project would involve modifications 
at three existing compressor stations and construction of one new 
compressor station. The SECURE Project would provide 280,000 dekatherms 
per day (Dth/d) of firm transportation service to certain southeast 
markets on Gulf South's system, including power generation customers.
---------------------------------------------------------------------------

    \1\ For tracking purposes under the National Environmental 
Policy Act, the unique identification number for documents relating 
to this environmental review is EAXX-019-20-000-1754481444.
---------------------------------------------------------------------------

    Any person wishing to comment on the EA may do so. To ensure 
consideration of your comments on the proposal prior to making a 
decision on the Project, it is important that the Commission receive 
your comments on or before 5:00 p.m. Eastern Time on January 28, 2026. 
Instructions for filing comments are provided on page 3.
    FERC is the lead federal agency for authorizing interstate natural 
gas transmission facilities under the Natural Gas Act of 1938 and the 
lead federal agency for preparation of the EA. The EA assesses the 
potential environmental effects of the SECURE Project in accordance 
with the requirements of the National Environmental Policy Act \2\ and 
the Commission's implementing regulations.\3\ The principal purposes of 
the EA are to: identify and assess the potential effects on the natural 
and human environment; describe and evaluate reasonable alternatives; 
identify and recommend mitigation measures; and facilitate public 
involvement in the environmental review process. The EA concludes that 
approval of the proposed Project would not constitute a major federal 
action significantly affecting the quality of the human environment.
---------------------------------------------------------------------------

    \2\ National Environmental Policy Act of 1969, as amended 
(Public Law [Pub. L.] 91-190. 42 U.S.C. 4321-4347, as amended by 
Pub. L. 94-52, July 3, 1975; Pub. L. 94-83, August 9, 1975; Pub. L. 
97-258, 4(b), September 13, 1982; Pub. L. 118-5, June 3, 2023; Pub. 
L. 119-21, July 4, 2025).
    \3\ Title 18 Code of Federal Regulations Part 380.
---------------------------------------------------------------------------

    The EA addresses the potential environmental effects of the 
construction and operation of the following Project facilities:
    <bullet> installation of one 27,677-horsepower (hp) Solar Titan 250 
compressor unit at the existing Tallulah Compressor Station in Madison 
Parish, Louisiana;
    <bullet> installation of one 13,290-hp Solar Mars 100 compressor 
unit at the existing Jasper Compressor Station in Jasper County, 
Mississippi;
    <bullet> installation of one 16,997-hp Solar Titan 130 compressor 
unit and restaging the existing Solar Mars 100 compressor unit at the 
existing Forrest Compressor Station in Forrest County, Mississippi; and
    <bullet> construction of the new Hinds Compressor Station, 
including one 27,667-hp Solar Titan 250 compressor unit, in Hinds 
County, Mississippi.
    The Commission mailed a copy of the Notice of Availability of the 
EA to federal, state, and local government representatives and 
agencies; elected officials; environmental and public interest groups; 
Native American tribes; potentially affected landowners and other 
interested individuals and groups; and newspapers and libraries in the 
project area. The EA is only available in electronic format. It may be 
viewed and downloaded from the FERC's website (<a href="http://www.ferc.gov">www.ferc.gov</a>), on the 
natural gas environmental documents page (<a href="https://www.ferc.gov/industries-data/natural-gas/environment/environmental-documents">https://www.ferc.gov/industries-data/natural-gas/environment/environmental-documents</a>). In 
addition, the EA may be accessed by using the eLibrary link on the 
FERC's website. Click on the eLibrary link (<a href="https://elibrary.ferc.gov/eLibrary/search">https://elibrary.ferc.gov/eLibrary/search</a>), select ``General Search'' and enter the docket number 
in the ``Docket Number'' field, excluding the last three digits (i.e., 
CP25-219). Be sure you have selected an appropriate date range. For 
assistance, please contact FERC Online Support at 
<a href="/cdn-cgi/l/email-protection#0d4b687f6e4263616463685e787d7d627f794d6b687f6e236a627b"><span class="__cf_email__" data-cfemail="62240710012d0c0e0b0c07311712120d101622040710014c050d14">[email&#160;protected]</span></a> or toll free at (866) 208-3676, or for TTY, 
contact (202) 502-8659.
    The EA is not a decision document. It presents Commission staff's 
independent analysis of the environmental issues for the Commission to 
consider when addressing the merits of all issues in this proceeding. 
Under section 7(c) of the Natural Gas Act, the Commission determines 
whether interstate natural gas transportation facilities are in the 
public convenience and necessity and, if so, grants a Certificate of 
Public Convenience and Necessity to construct and operate them. The 
Commission bases its decisions on both economic issues, including need, 
and environmental effects.
    Your comments should focus on the EA's disclosure and discussion of 
potential environmental effects, reasonable alternatives, and measures 
to avoid or lessen environmental effects.

[[Page 141]]

The more specific your comments, the more useful they will be. For your 
convenience, there are three methods you can use to file your comments 
to the Commission. The Commission encourages electronic filing of 
comments and has staff available to assist you at (866) 208-3676 or 
<a href="/cdn-cgi/l/email-protection#4a0c2f382905242623242f193f3a3a25383e0a2c2f3829642d253c"><span class="__cf_email__" data-cfemail="ebad8e9988a4858782858eb89e9b9b84999fab8d8e9988c58c849d">[email&#160;protected]</span></a>. Please carefully follow these instructions 
so that your comments are properly recorded.
    (1) You can file your comments electronically using the eComment 
feature on the Commission's website (<a href="http://www.ferc.gov">www.ferc.gov</a>) under the link to 
FERC Online. This is an easy method for submitting brief, text-only 
comments on a project;
    (2) You can also file your comments electronically using the 
eFiling feature on the Commission's website (<a href="http://www.ferc.gov">www.ferc.gov</a>) under the 
link to FERC Online. With eFiling, you can provide comments in a 
variety of formats by attaching them as a file with your submission. 
New eFiling users must first create an account by clicking on 
``eRegister.'' You must select the type of filing you are making. If 
you are filing a comment on a particular project, please select 
``Comment on a Filing''; or
    (3) You can file a paper copy of your comments by mailing them to 
the Commission. Be sure to reference the Project docket number (CP25-
219-000) on your letter. Submissions sent via the U.S. Postal Service 
must be addressed to: Debbie-Anne A. Reese, Secretary, Federal Energy 
Regulatory Commission, 888 First Street NE, Room 1A, Washington, DC 
20426. Submissions sent via any other carrier must be addressed to: 
Debbie-Anne A. Reese, Secretary, Federal Energy Regulatory Commission, 
12225 Wilkins Avenue, Rockville, MD 20852.
    Filing environmental comments will not give you intervenor status, 
but you do not need intervenor status to have your comments considered. 
Only intervenors have the right to seek rehearing or judicial review of 
the Commission's decision. At this point in this proceeding, the 
timeframe for filing timely intervention requests has expired. Any 
person seeking to become a party to the proceeding must file a motion 
to intervene out-of-time pursuant to Rule 214(b)(3) and (d) of the 
Commission's Rules of Practice and Procedures (Title 18 Code of Federal 
Regulations, Parts 385.214(b)(3) and (d)) and show good cause why the 
time limitation should be waived. Motions to intervene are more fully 
described at <a href="https://www.ferc.gov/how-intervene">https://www.ferc.gov/how-intervene</a>.
    For public inquiries and assistance with making filings such as 
interventions, comments, or requests for rehearing, contact the Office 
of Public Participation at (202) 502-6595 or <a href="/cdn-cgi/l/email-protection#024d525242646770612c656d74"><span class="__cf_email__" data-cfemail="b8f7e8e8f8deddcadb96dfd7ce">[email&#160;protected]</span></a>. Additional 
information about the Project is available from the FERC website 
(<a href="http://www.ferc.gov">www.ferc.gov</a>) using the eLibrary link. The eLibrary link also provides 
access to the texts of all formal documents issued by the Commission, 
such as orders, notices, and rulemakings.
    In addition, the Commission offers a free service called 
eSubscription which allows you to keep track of all formal issuances 
and submittals in specific dockets. This can reduce the amount of time 
you spend researching proceedings by automatically providing you with 
notification of these filings, document summaries, and direct links to 
the documents. Go to <a href="https://www.ferc.gov/ferc-online/overview">https://www.ferc.gov/ferc-online/overview</a> to 
register for eSubscription.

(Authority: 18 CFR 2.1.)

     Dated: December 29, 2025.
Debbie-Anne A. Reese,
Secretary.
[FR Doc. 2025-24189 Filed 12-31-25; 8:45 am]
BILLING CODE 6717-01-P


</pre><script data-cfasync="false" src="/cdn-cgi/scripts/5c5dd728/cloudflare-static/email-decode.min.js"></script></body>
</html>

Legal Citation

Federal Register Citation

Use this for formal legal and research references to the published document.

91 FR 140

Web Citation

Suggested Web Citation

Use this when citing the archival web version of the document.

“Gulf South Pipeline Company, LLC; Notice of Availability of the Environmental Assessment for the Proposed Southeast Compression Utility and Reliability Expansion Project,” thefederalregister.org (January 2, 2026), https://thefederalregister.org/documents/2025-24189/gulf-south-pipeline-company-llc-notice-of-availability-of-the-environmental-assessment-for-the-proposed-southeast-compre.