Conformity Determination for the East River Waterfront Esplanade and Piers Project City of New York, New York County, NY

In accordance with the federal Clean Air Act General Conformity rule, the Lower Manhattan Development Corporation (LMDC) has prepared a general conformity determination (Conform...

Department of Housing and Urban Development
  1. [Docket No. FR-5162-N-02]

AGENCY:

Office of the Assistant Secretary for Community Planning and Development, HUD.

ACTION:

Notice.

SUMMARY:

In accordance with the federal Clean Air Act General Conformity rule, the Lower Manhattan Development Corporation (LMDC) has prepared a general conformity determination (Conformity Determination) for the East River Waterfront Esplanade and Piers Project (the Selected Project) pursuant to the October 2007 National Environmental Policy Act Record of Decision and Lead Agency Findings Statement (ROD). LMDC is a subsidiary of the Empire State Development Corporation (a political subdivision and public benefit corporation of the State of New York) and is responsible, pursuant to federal statute 42 U.S.C. 5304(g) as the recipient of U.S. Department of Housing and Urban Development (HUD) Community Development Block Grant program funds, for conducting reviews of projects receiving HUD funds in accordance with 24 CFR part 58, as well as other laws and regulations. These responsibilities include compliance with the National Environmental Policy Act and the Clean Air Act, 42 U.S.C. 7401 et seq. (particularly sections 7506(c) and (d)), in accordance with 24 CFR 58.4 and 58.5.

The Selected Project will improve a two mile portion of the East River waterfront in Manhattan and create a City-owned public open space. The area of the Selected Project will generally encompass the waterfront, the upland area adjacent to and under the elevated FDR Drive and South Street extending from the Whitehall Ferry Terminal and Peter Minuit Plaza on the South to East River Park on the North, as well as Pier 15, the New Market Building pier, Pier 35, Pier 36, and Pier 42. The Selected Project is fully described in the Final Environmental Impact Statement for the East River Waterfront Esplanade and Piers Project.

The Selected Project is located in Manhattan, New York County, which has been designated by the United States Environmental Protection Agency (EPA) as a moderate non-attainment area for particulate matter less than 10 micrometers in aerodynamic diameter (PM10), a non-attainment area for particulate matter less than 2.5 micrometers in aerodynamic diameter (PM2.5), and a moderate non-attainment area for the 8-hour ozone standard. New York County was previously designated by the EPA as a severe non-attainment area for the 1-hour ozone standard. The area is in attainment for all other criteria pollutants: Nitrogen dioxide (NO2), lead, sulfur dioxide (SO2), and carbon monoxide (CO). MDC's review has been conducted consistent with the requirements of 40 CFR Part 93, Subpart B: “Determining Conformity of Federal Actions to State or Federal Implementation Plans” issued on November 30, 1993 (as amended on July 17, 2006, to address PM2.5 emissions). LMDC has determined that, during the peak construction year of 2008, potential emissions for all the criteria pollutants would be below the de minimis thresholds established under federal regulations at 40 CFR 93.153(b) which are currently applicable in New York County. Nonetheless, the construction emissions could exceed the 25 tons per year (tpy) annual nitrogen oxides (NOX) threshold for severe ozone non-attainment areas, which was applicable to New York County under the previous 1-hour ozone standard designation. Accordingly, LMDC has prepared its Conformity Determination to demonstrate that the federally-funded portion of the Selected Project will conform with the 1-hour ozone State Implementation Plan (SIP). Pursuant to the requirements of 40 CFR 93.153(h)(4), this notice lists the activities that are presumed to conform to the New York ozone SIP.

The Draft Conformity Determination for the Proposed East River Waterfront Esplanade and Piers Project was made available for public review beginning May 18, 2007. Notices of its availability were published in the New York State Department of Environmental Conservation Environmental Notice Bulletin and newspapers of general circulation on May 30, 2007. The Draft Conformity Determination was also published in the Federal Register on July 27, 2007. No comments on the Draft Conformity Determination were received.

ADDRESSES:

The Conformity Determination is available at the following location: Lower Manhattan Development Corporation, One Liberty Plaza, 20th Floor, New York, NY 10006. The Conformity Determination is also available on the LMDC Web site at www.renewnyc.com in the “Planning, Design & Development” section and is an exhibit to LMDC's ROD.

FOR FURTHER INFORMATION CONTACT:

Christina Hynes, Lower Manhattan Development Corporation, One Liberty Plaza, 20th Floor, New York, NY 10006; Telephone: (212) 962-2300; Fax: (212) 962-2431.

SUPPLEMENTARY INFORMATION:

A. Background

The Clean Air Act (CAA), as amended in 1990, defines a non-attainment area (NAA) as a geographic region that has been designated as not meeting one or more of the National Ambient Air Quality Standards (NAAQS). The Selected Project is located in New York County, which has been designated by the EPA as a moderate NAAQS NAA for PM10, a NAA for PM2.5, and a moderate NAA for ozone. The area is in attainment for all other criteria pollutants: Nitrogen dioxide (NO2), lead, sulfur dioxide (SO2), and carbon monoxide (CO). EPA had re-designated New York City as in attainment for CO on April 19, 2002 (67 FR 19337); the CAA requires that a maintenance plan ensure continued compliance with the CO NAAQS for former NAAs.

A State Implementation Plan (SIP) is a state's plan on how it will meet the NAAQS under the deadlines established by the CAA. In November 1998, New York State submitted its Phase II Alternative Attainment Demonstration for Ozone, which addressed attainment of the 1-hour ozone NAAQS by 2007 (New York submitted subsequent filings to EPA in subsequent years). On February 4, 2002, EPA approved New York's 1-hour ozone SIP (67 FR 5170).

The general conformity requirements in 40 CFR part 93, subpart B, apply to those federal actions that are located in a non-attainment or maintenance area, and that are not subject to transportation conformity requirements at 40 CFR part 51, subpart T, or part 93, subpart A, ( printed page 69701) where the action's direct and indirect emissions have the potential to emit one or more of the criteria pollutants or precursors, in the case of ozone and PM2.5, at emission rates equal to or exceeding the prescribed rates at 40 CFR 93.153(b), or where the action encompasses 10 percent or more of a NAA or maintenance area's total emissions inventory for that pollutant. In the case of New York County, the prescribed annual rates are 50 tons of VOCs and 100 tons of NOX (ozone precursors in moderate 8-hour ozone NAA and PM2.5 precursors in PM2.5 NAA), 100 tons of CO (CO maintenance area), 100 tons of PM10 (moderate PM10 NAA), 100 tons of PM2.5 (PM2.5 NAA), and 100 tons of SO2 (PM2.5 precursor in PM2.5 NAA).

LMDC has determined that the total annual direct and indirect emissions of all such criteria pollutants from the Selected Project are less than the de minimis rates prescribed in 40 CFR 93.153(b), as currently in effect, that would trigger the requirement to conduct a general conformity determination. Therefore, a general conformity determination is not necessarily required by current federal regulations. Nonetheless, temporarily, during construction, annual NOX emissions are predicted to exceed the threshold of 25 tons per year that would apply to a severe ozone non-attainment area under the former 1-hour ozone NAAQS. Accordingly, LMDC prepared a Conformity Determination to demonstrate the Selected Project's conformity with the ozone SIP.

B. Requirements of the Conformity Determination

The purpose of the conformity analysis is to establish that the Selected Project will conform to the New York ozone SIP, thereby demonstrating that total direct and indirect emissions of the ozone precursors, in this case NOX, from the Selected Project, will not:

1. A demonstration of reasonably further progress (RFP),

2. A demonstration of attainment, or

3. A maintenance plan.

For the purposes of a general conformity determination, direct and indirect emissions are defined as follows (40 CFR 93.152):

1. Are caused by the federal action, but may occur later in time and/or may be further removed in distance from the action itself but are still reasonably foreseeable; and

2. The federal agency can practicably control and will maintain control over due to a continuing program responsibility of the federal agency.

LMDC has determined that the predicted emissions due to the Selected Project during construction that should be subject to its general conformity review include direct emissions from (1) non-road engines operating on-site during construction, (2) marine vessels carrying materials to and from the site and conducting other work along the waterfront, and (3) emissions from construction-related vehicles traveling to and from the site.

C. Presumption of Conformity

The Selected Project will be located in an area previously designated as a severe ozone non-attainment area under the 1-hour ozone NAAQS. The NOX emissions during two years of construction were predicted to potentially exceed the prescribed level for severe ozone non-attainment areas (25 tons per year). Therefore, LMDC has determined the following:

Based on these determinations, the Selected Project is presumed to conform to the ozone SIP for the project area. The activities that are presumed to conform include all construction-related activities that will receive federal funding for the East River Waterfront Esplanade and Piers Project.

Dated: November 30, 2007.

Nelson R. Bregón,

General Deputy Assistant Secretary for Community Planning and Development.

[FR Doc. E7-23832 Filed 12-7-07; 8:45 am]

BILLING CODE 4210-67-P

Legal Citation

Federal Register Citation

Use this for formal legal and research references to the published document.

72 FR 69700

Web Citation

Suggested Web Citation

Use this when citing the archival web version of the document.

“Conformity Determination for the East River Waterfront Esplanade and Piers Project City of New York, New York County, NY,” thefederalregister.org (December 10, 2007), https://thefederalregister.org/documents/E7-23832/conformity-determination-for-the-east-river-waterfront-esplanade-and-piers-project-city-of-new-york-new-york-county-ny.