80_FR_12207 80 FR 12163 - Dominion Transmission, Inc., Atlantic Coast Pipeline, LLC; Notice of Intent To Prepare an Environmental Impact Statement for the Planned Supply Header Project and Atlantic Coast Pipeline Project, Request for Comments on Environmental Issues, and Notice of Public Scoping Meetings

80 FR 12163 - Dominion Transmission, Inc., Atlantic Coast Pipeline, LLC; Notice of Intent To Prepare an Environmental Impact Statement for the Planned Supply Header Project and Atlantic Coast Pipeline Project, Request for Comments on Environmental Issues, and Notice of Public Scoping Meetings

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 80, Issue 44 (March 6, 2015)

Page Range12163-12166
FR Document2015-05248

Federal Register, Volume 80 Issue 44 (Friday, March 6, 2015)
[Federal Register Volume 80, Number 44 (Friday, March 6, 2015)]
[Notices]
[Pages 12163-12166]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2015-05248]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket Nos. PF15-5-000; PF15-6-000]


Dominion Transmission, Inc., Atlantic Coast Pipeline, LLC; Notice 
of Intent To Prepare an Environmental Impact Statement for the Planned 
Supply Header Project and Atlantic Coast Pipeline Project, Request for 
Comments on Environmental Issues, and Notice of Public Scoping Meetings

    The staff of the Federal Energy Regulatory Commission (FERC or 
Commission) will prepare an environmental impact statement (EIS) that 
will discuss the environmental impacts of the Supply Header Project 
(SHP) involving construction and operation of facilities by Dominion 
Transmission, Inc. (Dominion) in Pennsylvania and West Virginia, and 
the Atlantic Coast Pipeline Project (ACP Project) involving 
construction and operation of facilities by Atlantic Coast Pipeline, 
LLC (Atlantic) in West Virginia, Virginia, and North Carolina. The 
environmental impacts of both projects will be considered in one EIS, 
which will be used by the Commission in its decision-making process to 
determine whether the projects are in the public convenience and 
necessity.
    This notice announces the opening of the scoping process the 
Commission will use to gather input from the public and interested 
agencies on the projects. Your input will help the Commission staff 
determine what issues they need to evaluate in the EIS. Please note 
that the scoping period will close on April 28, 2015.
    You may submit comments in written form or verbally. Further 
details on how to submit written comments are in the Public 
Participation section of this notice. If you sent comments on the SHP 
or ACP Projects to the Commission before the opening of the dockets on 
October 31, 2014, you will need to file those comments under Docket No. 
PF15-5-000 or PF15-6-000 to ensure they are considered as part of this 
proceeding. In lieu of or in addition to sending written comments, the 
Commission invites you to attend any of the public scoping meetings 
scheduled as follows:

------------------------------------------------------------------------
               Date and time                          Location
------------------------------------------------------------------------
Monday, March 9, 2015, 7:00 p.m.            Pine Forest High School, 525
                                             Andrews Road, Fayetteville,
                                             NC 28311.
Tuesday, March 10, 2015, 7:00 p.m.          Forest Hills Middle School,
                                             1210 Forest Hills Road,
                                             Wilson, NC 27896.
Wednesday, March 11, 2015, 7:00 p.m.        William R. Davie Middle
                                             School, 4391 Hwy. 158,
                                             Roanoke Rapids, NC 27870.
Thursday, March 12, 2015, 7:00 p.m.         Jolliff Middle School, 1021
                                             Jolliff Road, Chesapeake,
                                             VA 23331.
Monday, March 16, 2015, 7:00 p.m.           Dinwiddie Middle School,
                                             11608 Courthouse Road,
                                             Dinwiddie, VA 23841.
Tuesday, March 17, 2015, 7:00 p.m.          Prince Edward County High
                                             School Auditorium, 1482
                                             Zion Hill Road, Farmville,
                                             VA 23901.
Wednesday, March 18, 2015, 7:00 p.m.        Nelson County Middle School,
                                             6925 Thomas Nelson Highway,
                                             Lovingston, VA 22949.
Thursday, March 19, 2015, 7:00 p.m.         Stuarts Draft High School,
                                             1028 Augusta Farms Road,
                                             Stuarts Draft, VA 24477.
Monday, March 23, 2015, 7:00 p.m.           Elkins High School, 100
                                             Kennedy Drive, Elkins, WV
                                             26241.
Tuesday, March 24, 2015, 7:00 p.m.          Bridgeport High School, 515
                                             Johnson Avenue, Bridgeport,
                                             WV 26330.
------------------------------------------------------------------------

    The purpose of these scoping meetings is to provide an opportunity 
to verbally comment on the projects. If a significant number of people 
are interested in commenting at the meetings, we \1\ may establish a 3- 
to 5-minute time limit for each commentor to ensure that all people 
wishing to comment have the opportunity in the time allotted for the 
meeting. If time limits on comments are implemented, they will be 
strictly enforced. A transcript of each meeting will be added to the 
Commission's administrative record to ensure that your comments are 
accurately recorded.
---------------------------------------------------------------------------

    \1\ ``We,'' ``us,'' and ``our'' refer to the environmental staff 
of the Commission's Office of Energy Projects.
---------------------------------------------------------------------------

    This notice is being sent to the Commission's current environmental 
mailing list for these projects. State and local government 
representatives should notify their constituents of these

[[Page 12164]]

planned projects and encourage them to comment on their areas of 
concern.
    If you are a landowner receiving this notice, a pipeline company 
representative may contact you about the acquisition of an easement to 
construct, operate, and maintain the planned facilities. The company 
would seek to negotiate a mutually acceptable agreement. However, if 
the Commission approves the projects, that approval conveys with it the 
right of eminent domain. Therefore, if easement negotiations fail to 
produce an agreement, the pipeline company could initiate condemnation 
proceedings where compensation would be determined in accordance with 
state law.
    A fact sheet prepared by the FERC entitled ``An Interstate Natural 
Gas Facility On My Land? What Do I Need To Know?'' is available for 
viewing on the FERC Web site (www.ferc.gov). This fact sheet addresses 
a number of typically asked questions, including the use of eminent 
domain and how to participate in the Commission's proceedings.

Summary of the Planned Projects

    The SHP would involve the construction and operation of 
approximately 38.7 miles of pipeline loop \2\ and the modification of 
existing compression facilities in Pennsylvania and West Virginia. The 
pipeline facilities associated with the SHP would be comprised of two 
main components: (1) Approximately 3.8 miles of 30-inch-diameter 
natural gas pipeline loop adjacent to Dominion's existing LN-25 
pipeline in Westmoreland County, Pennsylvania; and (2) approximately 
34.9 miles of 36-inch-diameter pipeline loop adjacent to Dominion's 
existing TL-360 pipeline in Harrison, Doddridge, Tyler, and Wetzel 
Counties, West Virginia.
---------------------------------------------------------------------------

    \2\ A pipeline ``loop'' is a segment of pipe constructed 
parallel to an existing pipeline to increase capacity.
---------------------------------------------------------------------------

    In addition to the planned pipelines, Dominion plans to modify four 
existing compressor stations in Westmoreland and Green Counties, 
Pennsylvania and Marshall and Wetzel Counties, West Virginia. Dominion 
would install new gas-fired turbines that would provide for a combined 
increase of 75,700 horsepower of compression. Dominion would also 
install new valves, pig launcher/receiver sites,\3\ and associated 
appurtenances at these existing compressor station locations.
---------------------------------------------------------------------------

    \3\ A ``pig'' is a tool that the pipeline company inserts into 
and pushes through the pipeline for cleaning the pipeline, 
conducting internal inspections, or other purposes.
---------------------------------------------------------------------------

    The ACP Project would involve the construction and operation of 554 
miles of variable diameter natural gas pipeline in West Virginia, 
Virginia, and North Carolina. The pipeline facilities associated with 
the ACP Project would be comprised of four main components as follows:
     Approximately 295.6 miles of 42-inch-diameter pipeline in 
Harrison, Lewis, Upshur, Randolph, and Pocahontas Counties, West 
Virginia; Highland, Augusta, Nelson, Buckingham, Cumberland, Prince 
Edward, Nottoway, Dinwiddie, Brunswick, and Greensville Counties, 
Virginia; and Northampton County, North Carolina;
     approximately 179.9 miles of 36-inch-diameter pipeline in 
Northampton, Halifax, Nash, Wilson, Johnston, Sampson, Cumberland, and 
Robeson Counties, North Carolina;
     approximately 75.7 miles of 20-inch-diameter lateral 
pipeline in Northampton County, North Carolina; and Greensville, 
Southampton, Suffolk, and Chesapeake Counties, Virginia; and
     approximately 3.1 miles of 16-inch-diameter natural gas 
lateral pipeline in Brunswick County, Virginia.
    In addition to the planned pipelines, Atlantic plans to construct 
and operate three new compressor stations totaling 108,275 horsepower 
of compression. These compressor stations would be located in Lewis 
County, West Virginia; Buckingham County, Virginia; and Northampton 
County, North Carolina. Atlantic would also install metering stations, 
valves, pig launcher/receiver sites, and associated appurtenances along 
the planned pipeline system.
    The SHP and ACP Projects would be capable of delivering 1.5 billion 
cubic feet of natural gas per day to seven planned distribution points 
in West Virginia, Virginia, and North Carolina. If approved, 
construction of the projects is proposed to begin in September 2016. 
The general location of the projects' facilities and a number of 
alternatives under consideration are shown in the maps in appendix 
1.\4\
---------------------------------------------------------------------------

    \4\ The appendices referenced in this notice will not appear in 
the Federal Register. Copies of the appendices were sent to all 
those receiving this notice in the mail and are available at 
www.ferc.gov using the link called ``eLibrary'' or from the 
Commission's Public Reference Room, 888 First Street NE., 
Washington, DC 20426, or call (202) 502-8371. For instructions on 
connecting to eLibrary, refer to the last page of this notice.
---------------------------------------------------------------------------

Land Requirements for Construction

    Construction of the planned facilities would disturb about 12,972 
acres of land for the pipeline and aboveground facilities. The typical 
construction right-of-way for pipeline facilities would vary between 
125 feet wide for the 42-inch-diameter pipeline and 75 feet wide for 
the 16-inch-diameter lateral pipeline, with additional workspace needed 
in some locations due to site-specific conditions. Following 
construction, approximately 4,370 acres of land would be retained for 
permanent operation of the facilities. Land affected by construction 
but not required for operation would generally be allowed to revert to 
former uses.

The EIS Process

    The FERC will be the lead federal agency for the preparation of the 
EIS. The U.S. Forest Service (USFS) is participating as a cooperating 
agency because the ACP Project would cross the Monongahela and George 
Washington National Forests in West Virginia and Virginia. As a 
cooperating agency, the USFS intends to adopt the EIS per Title 40 of 
the Code of Federal Regulations, Part 1506.3 to meet its 
responsibilities under the National Environmental Policy Act (NEPA) 
regarding Atlantic's planned application for a Right-of-Way Grant and 
Temporary Use Permit for crossing federally administered lands. The 
USFS additionally will assess how the planned pipeline conforms to the 
direction contained in the Monongahela and George Washington National 
Forests' Land and Resource Management Plans (LRMP). Changes in the LRMP 
could be required if the pipeline is authorized across the National 
Forests. The EIS will provide the documentation to support any needed 
amendments to the LRMPs.
    NEPA requires the Commission to take into account the environmental 
impacts that could result from an action whenever it considers the 
issuance of a Certificate of Public Convenience and Necessity. NEPA 
also requires us to discover and address concerns the public may have 
about proposals. This process is referred to as scoping. The main goal 
of the scoping process is to focus the analysis in the EIS on the 
important environmental issues. By this notice, the Commission requests 
public comments on the scope of the issues to address in the EIS. We 
will consider all filed comments during the preparation of the EIS.
    In the EIS we will discuss impacts that could occur as a result of 
the construction and operation of the planned projects under these 
general headings:
     Geology and soils;
     land use;

[[Page 12165]]

     water resources, fisheries, and wetlands;
     cultural resources;
     vegetation and wildlife;
     air quality and noise;
     endangered and threatened species;
     socioeconomics; and
     public safety.
    We will present our recommendations in the EIS on how to lessen or 
avoid impacts on the various resource areas, as applicable.
    Dominion and Atlantic are evaluating several route alternatives 
that were developed through the company's route selection and 
constraint analysis processes or identified by stakeholders during 
public outreach efforts. Major route alternatives that have been 
identified by Dominion and Atlantic are presented in appendix 1. More 
detailed maps of these, and other, potential alternative routes can be 
found on the FERC Web site at www.ferc.gov, or Dominion's Web site at 
https://www.dom.com/corporate/what-we-do/natural-gas/atlantic-coast-pipeline. Part of our NEPA analysis will include evaluating possible 
alternatives to the planned projects or portions of the projects. Thus, 
as part of our scoping process, we are specifically soliciting comments 
on the range of alternatives for both of the projects.
    Although no formal application has been filed, we have already 
initiated our NEPA review under the Commission's pre-filing process. 
The purpose of the pre-filing process is to encourage early involvement 
of interested stakeholders and to identify and resolve issues before 
the FERC receives an application. As part of our pre-filing review, we 
have begun to contact some federal and state agencies to discuss their 
involvement in the scoping process and the preparation of the EIS.
    The EIS will present our independent analysis of the issues. We 
will publish and distribute the draft EIS for public comment. After the 
comment period, we will consider all timely comments and revise the 
document, as necessary, before issuing a final EIS. To ensure we have 
the opportunity to consider and address your comments, please carefully 
follow the instructions in the Public Participation section beginning 
on page 8.
    With this notice, we are asking agencies with jurisdiction by law 
and/or special expertise with respect to the environmental issues 
related to these projects to formally cooperate with us in the 
preparation of the EIS.\5\ Agencies that would like to request 
cooperating agency status should follow the instructions for filing 
comments provided under the Public Participation section of this 
notice. As discussed above, the USFS has expressed its intention to 
participate as a cooperating agency in the preparation of the EIS to 
satisfy its NEPA responsibilities related to these projects. In 
addition to the USFS, the U.S. Bureau of Land Management, U.S. Fish and 
Wildlife Service Great Dismal Swamp National Wildlife Refuge, and the 
U.S. Army Corps of Engineers have also agreed to participate as 
cooperating agencies.
---------------------------------------------------------------------------

    \5\ The Council on Environmental Quality regulations addressing 
cooperating agency responsibilities are at Title 40, Code of Federal 
Regulations, Part 1501.6.
---------------------------------------------------------------------------

Consultations Under Section 106 of the National Historic Preservation 
Act

    In accordance with the Advisory Council on Historic Preservation's 
implementing regulations for Section 106 of the National Historic 
Preservation Act, we are using this notice to initiate consultation 
with the applicable State Historic Preservation Offices, and to solicit 
their views and those of other government agencies, interested Indian 
tribes, and the public on the projects' potential effects on historic 
properties.\6\ We will define the project-specific Area of Potential 
Effects (APE) in consultation with the SHPOs as the projects develop. 
On natural gas facility projects, the APE at a minimum encompasses all 
areas subject to ground disturbance (examples include construction 
right-of-way, contractor/pipe storage yards, compressor stations, and 
access roads). Our EIS for these projects will document our findings on 
the impacts on historic properties and summarize the status of 
consultations under Section 106.
---------------------------------------------------------------------------

    \6\ The Advisory Council on Historic Preservation regulations 
are at Title 36, Code of Federal Regulations, Part 800. Those 
regulations define historic properties as any prehistoric or 
historic district, site, building, structure, or object included in 
or eligible for inclusion in the National Register of Historic 
Places.
---------------------------------------------------------------------------

Currently Identified Environmental Issues

    We have already identified several issues that we think deserve 
attention based on a preliminary review of the planned facilities and 
the environmental information provided by Dominion and Atlantic. This 
preliminary list of issues may change based on your comments and our 
analysis.
     Land use impacts, including the exercise of eminent domain 
and future land use restrictions;
     impacts on property values, tourism, and recreational 
resources;
     safety issues, such as construction and operation of the 
planned facilities near existing residences, schools, businesses, and 
military training facilities, and in karst and steep slope terrain;
     alternatives, including routing within existing linear 
corridors, avoiding private property, National Forests, National 
Parkway lands, National Wildlife Refuge land, and other sensitive 
environmental features;
     impacts on local emergency management systems;
     impacts on forested areas and other vegetation;
     impacts on surface water resources including springs, 
seeps, and wetlands;
     impacts on groundwater resources and wells;
     impacts on protected species and habitat;
     impacts on cultural resources including battlefields, 
cemeteries, and historic properties; and
     concerns regarding construction and operational noise, 
especially related to compressor stations.

Public Participation

    You can make a difference by providing us with your specific 
comments or concerns about the projects. Your comments should focus on 
the potential environmental effects, reasonable alternatives, and 
measures to avoid or lessen environmental impacts. The more specific 
your comments, the more useful they will be. To ensure that your 
comments are timely and properly recorded, please send your comments so 
that the Commission receives them in Washington, DC on or before April 
28, 2015.
    For your convenience, there are three methods you can use to submit 
your comments to the Commission. In all instances, please reference the 
appropriate project docket number(s) (PF15-5-000 for the SHP and PF15-
6-000 for the ACP Project) with your submission. The Commission 
encourages electronic filing of comments and has expert staff available 
to assist you at (202) 502-8258 or efiling@ferc.gov.
    (1) You can file your comments electronically using the eComment 
feature located on the Commission's Web site (www.ferc.gov) under the 
link to Documents and Filings. This is an easy method for interested 
persons to submit brief, text-only comments on a project;
    (2) You can file your comments electronically using the eFiling 
feature located on the Commission's Web site (www.ferc.gov) under the 
link to Documents and Filings. With eFiling,

[[Page 12166]]

you can provide comments in a variety of formats by attaching them as a 
file with your submission. New eFiling users must first create an 
account by clicking on ``eRegister.'' You must select the type of 
filing you are making. If you are filing a comment on a particular 
project, please select ``Comment on a Filing;'' or
    (3) You can file a paper copy of your comments by mailing them to 
the following address: Kimberly D. Bose, Secretary, Federal Energy 
Regulatory Commission, 888 First Street NE., Room 1A, Washington, DC 
20426.

Environmental Mailing List

    The environmental mailing list includes federal, state, and local 
government representatives and agencies; elected officials; 
environmental and public interest groups; Native American Tribes; other 
interested parties; and local libraries and newspapers. This list also 
includes all affected landowners (as defined in the Commission's 
regulations) who are potential right-of-way grantors, whose property 
may be used temporarily for project purposes, or who own homes within 
certain distances of aboveground facilities, as well as anyone who 
submits comments on the projects. We will update the environmental 
mailing list as the analysis proceeds to ensure that we send the 
information related to this environmental review to all individuals, 
organizations, and government entities interested in and/or potentially 
affected by the planned projects.
    Copies of the completed draft EIS will be sent to the environmental 
mailing list for public review and comment. If you would prefer to 
receive a paper copy of the document instead of the CD version or would 
like to remove your name from the mailing list, please return the 
attached Information Request (appendix 2).

Becoming an Intervenor

    Once Dominion and Atlantic file applications with the Commission, 
you may want to become an ``intervenor,'' which is an official party to 
the Commission's proceeding. Intervenors play a more formal role in the 
process and are able to file briefs, appear at hearings, and be heard 
by the courts if they choose to appeal the Commission's final ruling. 
An intervenor formally participates in the proceeding by filing a 
request to intervene. Instructions for becoming an intervenor are in 
the User's Guide under the ``e-filing'' link on the Commission's Web 
site. Please note that the Commission will not accept requests for 
intervenor status at this time. You must wait until the Commission 
receives formal applications for the projects.

Additional Information

    Additional information about the projects is available from the 
Commission's Office of External Affairs, at (866) 208-FERC, or on the 
FERC Web site (www.ferc.gov) using the eLibrary link. Click on the 
eLibrary link, click on ``General Search,'' and enter the docket 
number, excluding the last three digits in the Docket Number field 
(i.e., PF15-5 or PF15-6). Be sure you have selected an appropriate date 
range. For assistance, please contact FERC Online Support at 
FercOnlineSupport@ferc.gov or toll free at (866) 208-3676, or for TTY, 
contact (202) 502-8659. The eLibrary link also provides access to the 
texts of formal documents issued by the Commission, such as orders, 
notices, and rulemakings.
    In addition, the Commission offers a free service called 
eSubscription that allows you to keep track of all formal issuances and 
submittals in specific dockets. This can reduce the amount of time you 
spend researching proceedings by automatically providing you with 
notification of these filings, document summaries, and direct links to 
the documents. Go to www.ferc.gov/docs-filing/esubscription.asp.
    Finally, public meetings or site visits will be posted on the 
Commission's calendar located at www.ferc.gov/EventCalendar/EventsList.aspx along with other related information.

    Dated: February 27, 2015.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2015-05248 Filed 3-5-15; 8:45 am]
 BILLING CODE 6717-01-P



                                                                                  Federal Register / Vol. 80, No. 44 / Friday, March 6, 2015 / Notices                                                    12163

                                                  have an average annual generation of                    DEPARTMENT OF ENERGY                                      Date and time                 Location
                                                  421 gigawatt-hours (GWh). The average
                                                  pumping power used by the project                       Federal Energy Regulatory                             Tuesday, March 10,         Forest Hills Middle
                                                  would be 554 GWh.                                       Commission                                              2015, 7:00 p.m.            School, 1210 For-
                                                                                                                                                                                             est Hills Road, Wil-
                                                     o. A copy of the application is                      [Docket Nos. PF15–5–000; PF15–6–000]                                               son, NC 27896.
                                                  available for review at the Commission                                                                        Wednesday, March           William R. Davie Mid-
                                                  in the Public Reference Room or may be                  Dominion Transmission, Inc., Atlantic                  11, 2015, 7:00 p.m.         dle School, 4391
                                                  viewed on the Commission’s Web site at                  Coast Pipeline, LLC; Notice of Intent                                              Hwy. 158, Roa-
                                                  http://www.ferc.gov using the                           To Prepare an Environmental Impact                                                 noke Rapids, NC
                                                                                                          Statement for the Planned Supply                                                   27870.
                                                  ‘‘eLibrary’’ link. Enter the docket                                                                           Thursday, March 12,        Jolliff Middle School,
                                                  number excluding the last three digits in               Header Project and Atlantic Coast
                                                                                                          Pipeline Project, Request for                           2015, 7:00 p.m.            1021 Jolliff Road,
                                                  the docket number field to access the                                                                                                      Chesapeake, VA
                                                  document. For assistance, contact FERC                  Comments on Environmental Issues,                                                  23331.
                                                                                                          and Notice of Public Scoping Meetings
                                                  Online Support. A copy is also available                                                                      Monday, March 16,          Dinwiddie Middle
                                                  for inspection and reproduction at the                    The staff of the Federal Energy                      2015, 7:00 p.m.             School, 11608
                                                  address in item h above.                                                                                                                   Courthouse Road,
                                                                                                          Regulatory Commission (FERC or
                                                                                                                                                                                             Dinwiddie, VA
                                                     You may also register online at http://              Commission) will prepare an                                                        23841.
                                                  www.ferc.gov/docs-filing/                               environmental impact statement (EIS)                  Tuesday, March 17,         Prince Edward Coun-
                                                  esubscription.asp to be notified via                    that will discuss the environmental                     2015, 7:00 p.m.            ty High School Au-
                                                  email of new filings and issuances                      impacts of the Supply Header Project                                               ditorium, 1482 Zion
                                                  related to this or other pending projects.              (SHP) involving construction and                                                   Hill Road,
                                                                                                          operation of facilities by Dominion                                                Farmville, VA
                                                  For assistance, contact FERC Online                                                                                                        23901.
                                                                                                          Transmission, Inc. (Dominion) in
                                                  Support.                                                                                                      Wednesday, March           Nelson County Mid-
                                                                                                          Pennsylvania and West Virginia, and
                                                     p. Procedural schedule: The                          the Atlantic Coast Pipeline Project (ACP               18, 2015, 7:00 p.m.         dle School, 6925
                                                  application will be processed according                                                                                                    Thomas Nelson
                                                                                                          Project) involving construction and                                                Highway,
                                                  to the following preliminary Hydro                      operation of facilities by Atlantic Coast                                          Lovingston, VA
                                                  Licensing Schedule. Revisions to the                    Pipeline, LLC (Atlantic) in West                                                   22949.
                                                  schedule will be made as appropriate.                   Virginia, Virginia, and North Carolina.               Thursday, March 19,        Stuarts Draft High
                                                                                                          The environmental impacts of both                       2015, 7:00 p.m.            School, 1028 Au-
                                                  Issue Notice of Acceptance or
                                                                                                          projects will be considered in one EIS,                                            gusta Farms Road,
                                                     Deficiency April 2015                                                                                                                   Stuarts Draft, VA
                                                                                                          which will be used by the Commission
                                                  Request Additional Information April                    in its decision-making process to                                                  24477.
                                                     2015                                                 determine whether the projects are in                 Monday, March 23,          Elkins High School,
                                                                                                                                                                 2015, 7:00 p.m.             100 Kennedy
                                                  Issue Acceptance Letter July 2015                       the public convenience and necessity.
                                                                                                                                                                                             Drive, Elkins, WV
                                                                                                            This notice announces the opening of                                             26241.
                                                  Issue Scoping Document 1 for                            the scoping process the Commission
                                                     comments August 2015                                                                                       Tuesday, March 24,         Bridgeport High
                                                                                                          will use to gather input from the public                2015, 7:00 p.m.            School, 515 John-
                                                  Comments on Scoping Document 1                          and interested agencies on the projects.                                           son Avenue,
                                                     September 2015                                       Your input will help the Commission                                                Bridgeport, WV
                                                  Issue Scoping Document 2 October                        staff determine what issues they need to                                           26330.
                                                     2015                                                 evaluate in the EIS. Please note that the
                                                                                                          scoping period will close on April 28,                   The purpose of these scoping
                                                  Issue notice of ready for environmental                 2015.                                                 meetings is to provide an opportunity to
                                                     analysis October 2015                                  You may submit comments in written                  verbally comment on the projects. If a
                                                  Commission issues EA, draft EA, or                      form or verbally. Further details on how              significant number of people are
                                                     draft EIS April 2016                                 to submit written comments are in the                 interested in commenting at the
                                                  Comments on EA, draft EA, or draft EIS                  Public Participation section of this                  meetings, we 1 may establish a 3- to 5-
                                                     June 2016                                            notice. If you sent comments on the SHP               minute time limit for each commentor
                                                                                                          or ACP Projects to the Commission                     to ensure that all people wishing to
                                                  Commission issues final EA or final EIS                 before the opening of the dockets on                  comment have the opportunity in the
                                                     August 2016                                          October 31, 2014, you will need to file               time allotted for the meeting. If time
                                                  Nathaniel J. Davis, Sr.,                                those comments under Docket No.                       limits on comments are implemented,
                                                                                                          PF15–5–000 or PF15–6–000 to ensure                    they will be strictly enforced. A
                                                  Deputy Secretary.
                                                                                                          they are considered as part of this                   transcript of each meeting will be added
                                                  [FR Doc. 2015–05251 Filed 3–5–15; 8:45 am]
                                                                                                          proceeding. In lieu of or in addition to              to the Commission’s administrative
                                                  BILLING CODE 6717–01–P                                  sending written comments, the                         record to ensure that your comments are
                                                                                                          Commission invites you to attend any of               accurately recorded.
                                                                                                          the public scoping meetings scheduled
                                                                                                                                                                   This notice is being sent to the
                                                                                                          as follows:
mstockstill on DSK4VPTVN1PROD with NOTICES




                                                                                                                                                                Commission’s current environmental
                                                                                                                Date and time                 Location          mailing list for these projects. State and
                                                                                                                                                                local government representatives should
                                                                                                          Monday, March 9,             Pine Forest High         notify their constituents of these
                                                                                                           2015, 7:00 p.m.               School, 525 An-
                                                                                                                                         drews Road, Fay-         1 ‘‘We,’’ ‘‘us,’’ and ‘‘our’’ refer to the
                                                                                                                                         etteville, NC          environmental staff of the Commission’s Office of
                                                                                                                                         28311.                 Energy Projects.



                                             VerDate Sep<11>2014   18:59 Mar 05, 2015   Jkt 235001   PO 00000   Frm 00026   Fmt 4703   Sfmt 4703   E:\FR\FM\06MRN1.SGM   06MRN1


                                                  12164                            Federal Register / Vol. 80, No. 44 / Friday, March 6, 2015 / Notices

                                                  planned projects and encourage them to                   appurtenances at these existing                        land for the pipeline and aboveground
                                                  comment on their areas of concern.                       compressor station locations.                          facilities. The typical construction right-
                                                    If you are a landowner receiving this                     The ACP Project would involve the                   of-way for pipeline facilities would vary
                                                  notice, a pipeline company                               construction and operation of 554 miles                between 125 feet wide for the 42-inch-
                                                  representative may contact you about                     of variable diameter natural gas pipeline              diameter pipeline and 75 feet wide for
                                                  the acquisition of an easement to                        in West Virginia, Virginia, and North                  the 16-inch-diameter lateral pipeline,
                                                  construct, operate, and maintain the                     Carolina. The pipeline facilities                      with additional workspace needed in
                                                  planned facilities. The company would                    associated with the ACP Project would                  some locations due to site-specific
                                                  seek to negotiate a mutually acceptable                  be comprised of four main components                   conditions. Following construction,
                                                  agreement. However, if the Commission                    as follows:                                            approximately 4,370 acres of land
                                                  approves the projects, that approval                        • Approximately 295.6 miles of 42-                  would be retained for permanent
                                                  conveys with it the right of eminent                     inch-diameter pipeline in Harrison,                    operation of the facilities. Land affected
                                                  domain. Therefore, if easement                           Lewis, Upshur, Randolph, and                           by construction but not required for
                                                  negotiations fail to produce an                          Pocahontas Counties, West Virginia;                    operation would generally be allowed to
                                                  agreement, the pipeline company could                    Highland, Augusta, Nelson,                             revert to former uses.
                                                  initiate condemnation proceedings                        Buckingham, Cumberland, Prince
                                                                                                                                                                  The EIS Process
                                                  where compensation would be                              Edward, Nottoway, Dinwiddie,
                                                  determined in accordance with state                      Brunswick, and Greensville Counties,                      The FERC will be the lead federal
                                                  law.                                                     Virginia; and Northampton County,                      agency for the preparation of the EIS.
                                                                                                           North Carolina;                                        The U.S. Forest Service (USFS) is
                                                    A fact sheet prepared by the FERC                         • approximately 179.9 miles of 36-                  participating as a cooperating agency
                                                  entitled ‘‘An Interstate Natural Gas                     inch-diameter pipeline in Northampton,                 because the ACP Project would cross the
                                                  Facility On My Land? What Do I Need                      Halifax, Nash, Wilson, Johnston,                       Monongahela and George Washington
                                                  To Know?’’ is available for viewing on                   Sampson, Cumberland, and Robeson                       National Forests in West Virginia and
                                                  the FERC Web site (www.ferc.gov). This                   Counties, North Carolina;                              Virginia. As a cooperating agency, the
                                                  fact sheet addresses a number of                            • approximately 75.7 miles of 20-                   USFS intends to adopt the EIS per Title
                                                  typically asked questions, including the                 inch-diameter lateral pipeline in                      40 of the Code of Federal Regulations,
                                                  use of eminent domain and how to                         Northampton County, North Carolina;                    Part 1506.3 to meet its responsibilities
                                                  participate in the Commission’s                          and Greensville, Southampton, Suffolk,                 under the National Environmental
                                                  proceedings.                                             and Chesapeake Counties, Virginia; and                 Policy Act (NEPA) regarding Atlantic’s
                                                  Summary of the Planned Projects                             • approximately 3.1 miles of 16-inch-               planned application for a Right-of-Way
                                                                                                           diameter natural gas lateral pipeline in               Grant and Temporary Use Permit for
                                                    The SHP would involve the                              Brunswick County, Virginia.                            crossing federally administered lands.
                                                  construction and operation of                               In addition to the planned pipelines,               The USFS additionally will assess how
                                                  approximately 38.7 miles of pipeline                     Atlantic plans to construct and operate                the planned pipeline conforms to the
                                                  loop 2 and the modification of existing                  three new compressor stations totaling                 direction contained in the Monongahela
                                                  compression facilities in Pennsylvania                   108,275 horsepower of compression.                     and George Washington National
                                                  and West Virginia. The pipeline                          These compressor stations would be                     Forests’ Land and Resource
                                                  facilities associated with the SHP would                 located in Lewis County, West Virginia;                Management Plans (LRMP). Changes in
                                                  be comprised of two main components:                     Buckingham County, Virginia; and                       the LRMP could be required if the
                                                  (1) Approximately 3.8 miles of 30-inch-                  Northampton County, North Carolina.                    pipeline is authorized across the
                                                  diameter natural gas pipeline loop                       Atlantic would also install metering                   National Forests. The EIS will provide
                                                  adjacent to Dominion’s existing LN–25                    stations, valves, pig launcher/receiver                the documentation to support any
                                                  pipeline in Westmoreland County,                         sites, and associated appurtenances                    needed amendments to the LRMPs.
                                                  Pennsylvania; and (2) approximately                      along the planned pipeline system.                        NEPA requires the Commission to
                                                  34.9 miles of 36-inch-diameter pipeline                     The SHP and ACP Projects would be                   take into account the environmental
                                                  loop adjacent to Dominion’s existing                     capable of delivering 1.5 billion cubic                impacts that could result from an action
                                                  TL–360 pipeline in Harrison,                             feet of natural gas per day to seven                   whenever it considers the issuance of a
                                                  Doddridge, Tyler, and Wetzel Counties,                   planned distribution points in West                    Certificate of Public Convenience and
                                                  West Virginia.                                           Virginia, Virginia, and North Carolina. If             Necessity. NEPA also requires us to
                                                    In addition to the planned pipelines,                  approved, construction of the projects is              discover and address concerns the
                                                  Dominion plans to modify four existing                   proposed to begin in September 2016.                   public may have about proposals. This
                                                  compressor stations in Westmoreland                      The general location of the projects’                  process is referred to as scoping. The
                                                  and Green Counties, Pennsylvania and                     facilities and a number of alternatives                main goal of the scoping process is to
                                                  Marshall and Wetzel Counties, West                       under consideration are shown in the                   focus the analysis in the EIS on the
                                                  Virginia. Dominion would install new                     maps in appendix 1.4                                   important environmental issues. By this
                                                  gas-fired turbines that would provide for                                                                       notice, the Commission requests public
                                                                                                           Land Requirements for Construction
                                                  a combined increase of 75,700                                                                                   comments on the scope of the issues to
                                                  horsepower of compression. Dominion                       Construction of the planned facilities                address in the EIS. We will consider all
                                                  would also install new valves, pig                       would disturb about 12,972 acres of                    filed comments during the preparation
                                                                                                                                                                  of the EIS.
mstockstill on DSK4VPTVN1PROD with NOTICES




                                                  launcher/receiver sites,3 and associated                   4 The appendices referenced in this notice will
                                                                                                                                                                     In the EIS we will discuss impacts
                                                                                                           not appear in the Federal Register. Copies of the
                                                    2 A pipeline ‘‘loop’’ is a segment of pipe
                                                                                                           appendices were sent to all those receiving this       that could occur as a result of the
                                                  constructed parallel to an existing pipeline to          notice in the mail and are available at www.ferc.gov   construction and operation of the
                                                  increase capacity.                                       using the link called ‘‘eLibrary’’ or from the         planned projects under these general
                                                    3 A ‘‘pig’’ is a tool that the pipeline company        Commission’s Public Reference Room, 888 First          headings:
                                                  inserts into and pushes through the pipeline for         Street NE., Washington, DC 20426, or call (202)
                                                  cleaning the pipeline, conducting internal               502–8371. For instructions on connecting to               • Geology and soils;
                                                  inspections, or other purposes.                          eLibrary, refer to the last page of this notice.          • land use;


                                             VerDate Sep<11>2014   18:59 Mar 05, 2015   Jkt 235001    PO 00000   Frm 00027   Fmt 4703   Sfmt 4703   E:\FR\FM\06MRN1.SGM   06MRN1


                                                                                    Federal Register / Vol. 80, No. 44 / Friday, March 6, 2015 / Notices                                              12165

                                                     • water resources, fisheries, and                     Agencies that would like to request                         • safety issues, such as construction
                                                  wetlands;                                                cooperating agency status should follow                   and operation of the planned facilities
                                                     • cultural resources;                                 the instructions for filing comments                      near existing residences, schools,
                                                     • vegetation and wildlife;                            provided under the Public Participation                   businesses, and military training
                                                     • air quality and noise;                              section of this notice. As discussed                      facilities, and in karst and steep slope
                                                     • endangered and threatened species;                  above, the USFS has expressed its                         terrain;
                                                     • socioeconomics; and                                 intention to participate as a cooperating                   • alternatives, including routing
                                                     • public safety.                                                                                                within existing linear corridors,
                                                     We will present our recommendations                   agency in the preparation of the EIS to
                                                                                                           satisfy its NEPA responsibilities related                 avoiding private property, National
                                                  in the EIS on how to lessen or avoid
                                                                                                           to these projects. In addition to the                     Forests, National Parkway lands,
                                                  impacts on the various resource areas,
                                                                                                           USFS, the U.S. Bureau of Land                             National Wildlife Refuge land, and other
                                                  as applicable.
                                                     Dominion and Atlantic are evaluating                  Management, U.S. Fish and Wildlife                        sensitive environmental features;
                                                  several route alternatives that were                     Service Great Dismal Swamp National                         • impacts on local emergency
                                                  developed through the company’s route                    Wildlife Refuge, and the U.S. Army                        management systems;
                                                                                                           Corps of Engineers have also agreed to                      • impacts on forested areas and other
                                                  selection and constraint analysis
                                                                                                           participate as cooperating agencies.                      vegetation;
                                                  processes or identified by stakeholders
                                                                                                                                                                       • impacts on surface water resources
                                                  during public outreach efforts. Major                    Consultations Under Section 106 of the                    including springs, seeps, and wetlands;
                                                  route alternatives that have been                        National Historic Preservation Act                          • impacts on groundwater resources
                                                  identified by Dominion and Atlantic are                                                                            and wells;
                                                  presented in appendix 1. More detailed                     In accordance with the Advisory
                                                                                                           Council on Historic Preservation’s                          • impacts on protected species and
                                                  maps of these, and other, potential                                                                                habitat;
                                                  alternative routes can be found on the                   implementing regulations for Section
                                                                                                                                                                       • impacts on cultural resources
                                                  FERC Web site at www.ferc.gov, or                        106 of the National Historic
                                                                                                                                                                     including battlefields, cemeteries, and
                                                  Dominion’s Web site at https://                          Preservation Act, we are using this
                                                                                                                                                                     historic properties; and
                                                  www.dom.com/corporate/what-we-do/                        notice to initiate consultation with the
                                                                                                                                                                       • concerns regarding construction
                                                  natural-gas/atlantic-coast-pipeline. Part                applicable State Historic Preservation
                                                                                                                                                                     and operational noise, especially related
                                                  of our NEPA analysis will include                        Offices, and to solicit their views and
                                                                                                                                                                     to compressor stations.
                                                  evaluating possible alternatives to the                  those of other government agencies,
                                                  planned projects or portions of the                      interested Indian tribes, and the public                  Public Participation
                                                  projects. Thus, as part of our scoping                   on the projects’ potential effects on                        You can make a difference by
                                                  process, we are specifically soliciting                  historic properties.6 We will define the                  providing us with your specific
                                                  comments on the range of alternatives                    project-specific Area of Potential Effects                comments or concerns about the
                                                  for both of the projects.                                (APE) in consultation with the SHPOs                      projects. Your comments should focus
                                                     Although no formal application has                    as the projects develop. On natural gas                   on the potential environmental effects,
                                                  been filed, we have already initiated our                facility projects, the APE at a minimum                   reasonable alternatives, and measures to
                                                  NEPA review under the Commission’s                       encompasses all areas subject to ground                   avoid or lessen environmental impacts.
                                                  pre-filing process. The purpose of the                   disturbance (examples include                             The more specific your comments, the
                                                  pre-filing process is to encourage early                 construction right-of-way, contractor/                    more useful they will be. To ensure that
                                                  involvement of interested stakeholders                   pipe storage yards, compressor stations,                  your comments are timely and properly
                                                  and to identify and resolve issues before                and access roads). Our EIS for these                      recorded, please send your comments so
                                                  the FERC receives an application. As                     projects will document our findings on                    that the Commission receives them in
                                                  part of our pre-filing review, we have                   the impacts on historic properties and                    Washington, DC on or before April 28,
                                                  begun to contact some federal and state                  summarize the status of consultations                     2015.
                                                  agencies to discuss their involvement in                 under Section 106.                                           For your convenience, there are three
                                                  the scoping process and the preparation                                                                            methods you can use to submit your
                                                                                                           Currently Identified Environmental
                                                  of the EIS.                                                                                                        comments to the Commission. In all
                                                     The EIS will present our independent                  Issues
                                                                                                                                                                     instances, please reference the
                                                  analysis of the issues. We will publish                     We have already identified several                     appropriate project docket number(s)
                                                  and distribute the draft EIS for public                  issues that we think deserve attention                    (PF15–5–000 for the SHP and PF15–6–
                                                  comment. After the comment period, we                    based on a preliminary review of the                      000 for the ACP Project) with your
                                                  will consider all timely comments and                    planned facilities and the                                submission. The Commission
                                                  revise the document, as necessary,                       environmental information provided by                     encourages electronic filing of
                                                  before issuing a final EIS. To ensure we                 Dominion and Atlantic. This                               comments and has expert staff available
                                                  have the opportunity to consider and                     preliminary list of issues may change                     to assist you at (202) 502–8258 or
                                                  address your comments, please carefully                  based on your comments and our                            efiling@ferc.gov.
                                                  follow the instructions in the Public                    analysis.                                                    (1) You can file your comments
                                                  Participation section beginning on page                     • Land use impacts, including the                      electronically using the eComment
                                                  8.                                                       exercise of eminent domain and future                     feature located on the Commission’s
                                                     With this notice, we are asking                       land use restrictions;                                    Web site (www.ferc.gov) under the link
                                                  agencies with jurisdiction by law
                                                                                                              • impacts on property values,                          to Documents and Filings. This is an
                                                  and/or special expertise with respect to
mstockstill on DSK4VPTVN1PROD with NOTICES




                                                                                                           tourism, and recreational resources;                      easy method for interested persons to
                                                  the environmental issues related to                                                                                submit brief, text-only comments on a
                                                  these projects to formally cooperate                       6 The Advisory Council on Historic Preservation         project;
                                                  with us in the preparation of the EIS.5                  regulations are at Title 36, Code of Federal                 (2) You can file your comments
                                                                                                           Regulations, Part 800. Those regulations define           electronically using the eFiling feature
                                                    5 The Council on Environmental Quality                 historic properties as any prehistoric or historic
                                                  regulations addressing cooperating agency                district, site, building, structure, or object included
                                                                                                                                                                     located on the Commission’s Web site
                                                  responsibilities are at Title 40, Code of Federal        in or eligible for inclusion in the National Register     (www.ferc.gov) under the link to
                                                  Regulations, Part 1501.6.                                of Historic Places.                                       Documents and Filings. With eFiling,


                                             VerDate Sep<11>2014    18:59 Mar 05, 2015   Jkt 235001   PO 00000   Frm 00028   Fmt 4703    Sfmt 4703   E:\FR\FM\06MRN1.SGM   06MRN1


                                                  12166                           Federal Register / Vol. 80, No. 44 / Friday, March 6, 2015 / Notices

                                                  you can provide comments in a variety                   must wait until the Commission                           Description: Self-Certification of EG of
                                                  of formats by attaching them as a file                  receives formal applications for the                  Sandow Power Company LLC.
                                                  with your submission. New eFiling                       projects.                                                Filed Date: 3/2/15.
                                                  users must first create an account by                                                                            Accession Number: 20150302–5141.
                                                                                                          Additional Information                                   Comments Due: 5 p.m. ET 3/23/15.
                                                  clicking on ‘‘eRegister.’’ You must select
                                                  the type of filing you are making. If you                  Additional information about the                      Take notice that the Commission
                                                  are filing a comment on a particular                    projects is available from the                        received the following electric rate
                                                  project, please select ‘‘Comment on a                   Commission’s Office of External Affairs,              filings:
                                                  Filing;’’ or                                            at (866) 208–FERC, or on the FERC Web                    Docket Numbers: ER13–2109–003;
                                                     (3) You can file a paper copy of your                site (www.ferc.gov) using the eLibrary                ER13–2106–003; ER10–1410–003; ER13–
                                                  comments by mailing them to the                         link. Click on the eLibrary link, click on            321–003; ER13–412–002; ER13–450–002;
                                                  following address: Kimberly D. Bose,                    ‘‘General Search,’’ and enter the docket              ER13–434–002; ER13–518–002; ER13–
                                                  Secretary, Federal Energy Regulatory                    number, excluding the last three digits               1403–004; ER14–2140–003; ER14–2141–
                                                  Commission, 888 First Street NE., Room                  in the Docket Number field (i.e., PF15–               003; ER15–632–001; ER15–634–001;
                                                  1A, Washington, DC 20426.                               5 or PF15–6). Be sure you have selected               ER14–2466–002; ER14–2465–002;
                                                  Environmental Mailing List                              an appropriate date range. For                           Applicants: Fowler Ridge Wind Farm
                                                                                                          assistance, please contact FERC Online                LLC, Cottonwood Solar, LLC, CID Solar,
                                                     The environmental mailing list                       Support at FercOnlineSupport@ferc.gov                 LLC, RE Camelot LLC, RE Columbia
                                                  includes federal, state, and local                      or toll free at (866) 208–3676, or for                Two LLC, Selmer Farm, LLC, Mulberry
                                                  government representatives and                          TTY, contact (202) 502–8659. The                      Farm, LLC, Dominion Retail, Inc.,
                                                  agencies; elected officials;                            eLibrary link also provides access to the             Dominion Energy Manchester Street,
                                                  environmental and public interest                       texts of formal documents issued by the               Inc., Dominion Energy Marketing, Inc.,
                                                  groups; Native American Tribes; other                   Commission, such as orders, notices,                  Dominion Nuclear Connecticut, LLC,
                                                  interested parties; and local libraries                 and rulemakings.                                      Fairless Energy, LLC, NedPower Mount
                                                  and newspapers. This list also includes                    In addition, the Commission offers a               Storm, LLC, Dominion Bridgeport Fuel
                                                  all affected landowners (as defined in                                                                        Cell, LLC, Virginia Electric and Power
                                                                                                          free service called eSubscription that
                                                  the Commission’s regulations) who are                                                                         Company.
                                                                                                          allows you to keep track of all formal
                                                  potential right-of-way grantors, whose                                                                           Description: Supplement to January 9,
                                                                                                          issuances and submittals in specific
                                                  property may be used temporarily for                                                                          2015 Notice of Non-Material Change in
                                                                                                          dockets. This can reduce the amount of
                                                  project purposes, or who own homes                                                                            Status of the Dominion Companies.
                                                                                                          time you spend researching proceedings
                                                  within certain distances of aboveground                                                                          Filed Date: 2/19/15.
                                                                                                          by automatically providing you with
                                                  facilities, as well as anyone who                                                                                Accession Number: 20150219–5211.
                                                                                                          notification of these filings, document
                                                  submits comments on the projects. We                                                                             Comments Due: 5 p.m. ET 3/12/15.
                                                                                                          summaries, and direct links to the
                                                  will update the environmental mailing                                                                            Docket Numbers: ER14–1639–003.
                                                                                                          documents. Go to www.ferc.gov/docs-
                                                  list as the analysis proceeds to ensure                                                                          Applicants: ISO New England Inc.
                                                                                                          filing/esubscription.asp.
                                                  that we send the information related to                                                                          Description: Compliance filing per 35:
                                                                                                             Finally, public meetings or site visits
                                                  this environmental review to all                                                                              Compliance Filing Concerning the
                                                                                                          will be posted on the Commission’s
                                                  individuals, organizations, and                                                                               Renewable Technology Resource
                                                                                                          calendar located at www.ferc.gov/
                                                  government entities interested in and/or                                                                      Exemption to be effective 3/2/2015.
                                                                                                          EventCalendar/EventsList.aspx along
                                                  potentially affected by the planned                                                                              Filed Date: 3/2/15.
                                                                                                          with other related information.
                                                  projects.                                                                                                        Accession Number: 20150302–5275.
                                                     Copies of the completed draft EIS will                 Dated: February 27, 2015.                              Comments Due: 5 p.m. ET 3/23/15.
                                                  be sent to the environmental mailing list               Nathaniel J. Davis, Sr.,                                 Docket Numbers: ER15–124–002.
                                                  for public review and comment. If you                   Deputy Secretary.                                        Applicants: Tucson Electric Power
                                                  would prefer to receive a paper copy of                 [FR Doc. 2015–05248 Filed 3–5–15; 8:45 am]            Company.
                                                  the document instead of the CD version                  BILLING CODE 6717–01–P                                   Description: Tariff Amendment per
                                                  or would like to remove your name from                                                                        35.17(b): Response to Deficiency Letter
                                                  the mailing list, please return the                                                                           dated January 15, 2015 to be effective 9/
                                                  attached Information Request (appendix                  DEPARTMENT OF ENERGY                                  17/2014.
                                                  2).                                                                                                              Filed Date: 3/2/15.
                                                                                                          Federal Energy Regulatory                                Accession Number: 20150302–5180.
                                                  Becoming an Intervenor                                                                                           Comments Due: 5 p.m. ET 3/23/15.
                                                                                                          Commission
                                                     Once Dominion and Atlantic file                                                                               Docket Numbers: ER15–542–001.
                                                  applications with the Commission, you                   Combined Notice of Filings #1                            Applicants: Midcontinent
                                                  may want to become an ‘‘intervenor,’’                                                                         Independent System Operator, Inc.
                                                  which is an official party to the                         Take notice that the Commission
                                                                                                                                                                   Description: Compliance filing per 35:
                                                  Commission’s proceeding. Intervenors                    received the following exempt
                                                                                                                                                                2015–03–02_Land Costs Recovery
                                                  play a more formal role in the process                  wholesale generator filings:
                                                                                                                                                                Compliance Filing to be effective 1/31/
                                                  and are able to file briefs, appear at                    Docket Numbers: EG15–58–000.
                                                                                                                                                                2015.
                                                  hearings, and be heard by the courts if                   Applicants: Oak Grove Management                       Filed Date: 3/2/15.
                                                  they choose to appeal the Commission’s                  Company LLC.                                             Accession Number: 20150302–5304.
                                                                                                            Description: Self-Certification of EG of               Comments Due: 5 p.m. ET 3/23/15.
mstockstill on DSK4VPTVN1PROD with NOTICES




                                                  final ruling. An intervenor formally
                                                  participates in the proceeding by filing                Oak Grove Management Company LLC.                        Docket Numbers: ER15–933–001.
                                                  a request to intervene. Instructions for                  Filed Date: 3/2/15.                                    Applicants: Midcontinent
                                                  becoming an intervenor are in the User’s                  Accession Number: 20150302–5139.                    Independent System Operator, Inc.
                                                  Guide under the ‘‘e-filing’’ link on the                  Comments Due: 5 p.m. ET 3/23/15.                       Description: Tariff Amendment per
                                                  Commission’s Web site. Please note that                   Docket Numbers: EG15–59–000.                        35.17(b): 2015–03–02_Amend Schedule
                                                  the Commission will not accept requests                   Applicants: Sandow Power Company                    31 Annual Update to be effective 4/1/
                                                  for intervenor status at this time. You                 LLC.                                                  2015.


                                             VerDate Sep<11>2014   18:59 Mar 05, 2015   Jkt 235001   PO 00000   Frm 00029   Fmt 4703   Sfmt 4703   E:\FR\FM\06MRN1.SGM   06MRN1



Document Created: 2018-02-21 09:33:45
Document Modified: 2018-02-21 09:33:45
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation80 FR 12163 