80_FR_18683 80 FR 18617 - Transcontinental Gas Pipe Line Company, LLC; Notice of Application

80 FR 18617 - Transcontinental Gas Pipe Line Company, LLC; Notice of Application

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 80, Issue 66 (April 7, 2015)

Page Range18617-18618
FR Document2015-07924

Federal Register, Volume 80 Issue 66 (Tuesday, April 7, 2015)
[Federal Register Volume 80, Number 66 (Tuesday, April 7, 2015)]
[Notices]
[Pages 18617-18618]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2015-07924]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP15-118-000]


Transcontinental Gas Pipe Line Company, LLC; Notice of 
Application

    Take notice that on March 23, 2015, Transcontinental Gas Pipe Line 
Company, LLC (Transco), 2800 Post Oak Boulevard, Houston, Texas 77056, 
filed in the above referenced docket an application pursuant to section 
7(c) of the Natural Gas Act (NGA), and Part 157 of the Commission's 
regulations requesting authorization to construct and operate the 
Virginia Southside Expansion Project II (Project). Specifically, the 
Project will enable Transco to provide 250,000 dekatherms per day (Dth/
d) of incremental firm transportation service to one shipper, Virginia 
Power Services Energy Corp., Inc., all as more fully set forth in the 
application which is on file with the Commission and open to public 
inspection. The filing is available for review at the Commission in the 
Public Reference Room or may be viewed on the Commission's Web site web 
at  http://www.ferc.gov using the ``eLibrary'' link. Enter the docket 
number excluding the last three digits in the docket number field to 
access the document. For assistance, contact FERC at 
[email protected] or call toll-free, (886) 208-3676 or TYY, 
(202) 502-8659.
    Any questions concerning this application may be directed to 
Derrick Hughey, Senior Regulatory Analyst, P.O. Box 1396, Houston, 
Texas 77251, by telephone at (713) 215-2450.
    Transco states that, the firm transportation service on the Project 
will be rendered by Transco pursuant to Rate Schedule FT of Transco's 
FERC Gas Tariff and Transco's blanket certificate under Part 284(G) of 
the Commission's Regulations. Transco states that the Project will 
involve the construction and operation of 4.33 miles of new 24-inch 
diameter pipeline facilities, 21,830 horsepower of gas turbine driven 
compression, 25,000 horsepower of electric motor driven compression and 
the construction or modification of associated aboveground and 
underground facilities. The cost of the project will be approximately 
$190.8 million.
    Pursuant to section 157.9 of the Commission's rules (18 CFR 157.9), 
within 90 days of this Notice, the Commission staff will either: 
Complete its environmental assessment (EA) and place it into the 
Commission's public record (eLibrary) for this proceeding; or issue a 
Notice of Schedule for Environmental Review. If a Notice of Schedule 
for Environmental Review is issued, it will indicate, among other 
milestones, the anticipated date for the Commission staff's issuance of 
the final environmental impact statement (FEIS) or EA for this 
proposal. The filing of the EA in the Commission's public record for 
this proceeding or the issuance of a Notice of Schedule for 
Environmental Review will serve to notify federal and state agencies of 
the timing for the completion of all necessary reviews, and the 
subsequent need to complete all federal authorizations within 90 days 
of the date of issuance of the Commission staff's FEIS or EA.
    There are two ways to become involved in the Commission's review of 
this project. First, any person wishing to obtain legal status by 
becoming a party to the proceedings for this project should, on or 
before the comment date stated below file with the Federal Energy 
Regulatory Commission, 888 First Street NE., Washington, DC 20426, a 
motion to intervene in accordance with the requirements of the 
Commission's Rules of Practice and Procedure (18 CFR 385.214 or 
385.211) and the Regulations under the NGA (18 CFR 157.10). A person 
obtaining party status will be placed on the service list maintained by 
the Secretary of the Commission and will receive copies of all 
documents filed by the applicant and by all other parties. A party must 
submit five copies of filings made in the proceeding with the 
Commission and must mail a copy to the applicant and to every other 
party. Only parties to the proceeding can ask for court review of 
Commission orders in the proceeding.

[[Page 18618]]

    However, a person does not have to intervene in order to have 
comments considered. The second way to participate is by filing with 
the Secretary of the Commission, as soon as possible, an original and 
two copies of comments in support of or in opposition to this project. 
The Commission will consider these comments in determining the 
appropriate action to be taken, but the filing of a comment alone will 
not serve to make the filer a party to the proceeding. The Commission's 
rules require that persons filing comments in opposition to the project 
provide copies of their protests only to the party or parties directly 
involved in the protest.
    Persons who wish to comment only on the environmental review of 
this project should submit an original and two copies of their comments 
to the Secretary of the Commission. Environmental commentors will be 
placed on the Commission's environmental mailing list, will receive 
copies of the environmental documents, and will be notified of meetings 
associated with the Commission's environmental review process. 
Environmental commentors will not be required to serve copies of filed 
documents on all other parties. However, the non-party commentors will 
not receive copies of all documents filed by other parties or issued by 
the Commission (except for the mailing of environmental documents 
issued by the Commission) and will not have the right to seek court 
review of the Commission's final order.
    The Commission strongly encourages electronic filings of comments, 
protests and interventions in lieu of paper using the ``eFiling'' link 
at http://www.ferc.gov. Persons unable to file electronically should 
submit an original and 5 copies of the protest or intervention to the 
Federal Energy Regulatory Commission, 888 First Street NE., Washington, 
DC 20426.
    Comment Date: April 22, 2015.

    Dated: April 1, 2015.
Kimberly D. Bose,
Secretary.
[FR Doc. 2015-07924 Filed 4-6-15; 8:45 am]
BILLING CODE CODE 6717-01-P



                                                                                  Federal Register / Vol. 80, No. 66 / Tuesday, April 7, 2015 / Notices                                           18617

                                                  Release Agreements—3/27/2015 to be                      accordance with Rule 211 of the                          Transco states that, the firm
                                                  effective 3/27/2015.                                    Commission’s Regulations (18 CFR                      transportation service on the Project
                                                    Filed Date: 3/27/15.                                  385.211) on or before 5:00 p.m. Eastern               will be rendered by Transco pursuant to
                                                    Accession Number: 20150327–5193.                      time on the specified comment date.                   Rate Schedule FT of Transco’s FERC
                                                    Comments Due: 5 p.m. ET 4/8/15.                          The filings are accessible in the                  Gas Tariff and Transco’s blanket
                                                    Docket Numbers: RP15–715–000.                         Commission’s eLibrary system by                       certificate under Part 284(G) of the
                                                    Applicants: Transcontinental Gas                      clicking on the links or querying the                 Commission’s Regulations. Transco
                                                  Pipe Line Company.                                      docket number.                                        states that the Project will involve the
                                                    Description: Section 4(d) rate filing                    eFiling is encouraged. More detailed               construction and operation of 4.33 miles
                                                  per 154.204: Non-Conforming                             information relating to filing                        of new 24-inch diameter pipeline
                                                  Agreement—Woodbridge/CPV to be                          requirements, interventions, protests,                facilities, 21,830 horsepower of gas
                                                  effective 4/1/2015.                                     service, and qualifying facilities filings            turbine driven compression, 25,000
                                                    Filed Date: 3/27/15.                                  can be found at: http://www.ferc.gov/                 horsepower of electric motor driven
                                                    Accession Number: 20150327–5241.                      docs-filing/efiling/filing-req.pdf. For               compression and the construction or
                                                    Comments Due: 5 p.m. ET 4/8/15.                       other information, call (866) 208–3676                modification of associated aboveground
                                                    Docket Numbers: RP15–716–000.                         (toll free). For TTY, call (202) 502–8659.            and underground facilities. The cost of
                                                    Applicants: Enable Gas Transmission,                                                                        the project will be approximately $190.8
                                                                                                            Dated: March 30, 2015.
                                                  LLC.                                                                                                          million.
                                                    Description: Compliance filing per                    Nathaniel J. Davis, Sr.,
                                                                                                                                                                   Pursuant to section 157.9 of the
                                                  154.203: Order No. 801 Compliance                       Deputy Secretary.                                     Commission’s rules (18 CFR 157.9),
                                                  Filing—System Map to be effective 4/1/                  [FR Doc. 2015–07931 Filed 4–6–15; 8:45 am]            within 90 days of this Notice, the
                                                  2015.                                                   BILLING CODE CODE 6717–01–P                           Commission staff will either: Complete
                                                    Filed Date: 3/27/15.                                                                                        its environmental assessment (EA) and
                                                    Accession Number: 20150327–5258.                                                                            place it into the Commission’s public
                                                    Comments Due: 5 p.m. ET 4/8/15.                       DEPARTMENT OF ENERGY                                  record (eLibrary) for this proceeding; or
                                                    Docket Numbers: RP15–717–000.                                                                               issue a Notice of Schedule for
                                                    Applicants: Enable Mississippi River                  Federal Energy Regulatory                             Environmental Review. If a Notice of
                                                  Transmission, L.                                        Commission                                            Schedule for Environmental Review is
                                                    Description: Compliance filing per                    [Docket No. CP15–118–000]                             issued, it will indicate, among other
                                                  154.203: Order No. 801 Compliance                                                                             milestones, the anticipated date for the
                                                  Filing—System Map to be effective 4/1/                  Transcontinental Gas Pipe Line                        Commission staff’s issuance of the final
                                                  2015.                                                   Company, LLC; Notice of Application                   environmental impact statement (FEIS)
                                                    Filed Date: 3/27/15.                                                                                        or EA for this proposal. The filing of the
                                                    Accession Number: 20150327–5255.                         Take notice that on March 23, 2015,                EA in the Commission’s public record
                                                    Comments Due: 5 p.m. ET 4/8/15.                       Transcontinental Gas Pipe Line                        for this proceeding or the issuance of a
                                                    Docket Numbers: RP15–718–000.                         Company, LLC (Transco), 2800 Post Oak                 Notice of Schedule for Environmental
                                                    Applicants: Transcontinental Gas                      Boulevard, Houston, Texas 77056, filed                Review will serve to notify federal and
                                                  Pipe Line Company.                                      in the above referenced docket an                     state agencies of the timing for the
                                                    Description: Section 4(d) rate filing                 application pursuant to section 7(c) of               completion of all necessary reviews, and
                                                  per 154.204: Update List of Non-                        the Natural Gas Act (NGA), and Part 157               the subsequent need to complete all
                                                  Coforming Service Agreements                            of the Commission’s regulations                       federal authorizations within 90 days of
                                                  (Woodbridge/CPV) to be effective 4/1/                   requesting authorization to construct                 the date of issuance of the Commission
                                                  2015.                                                   and operate the Virginia Southside                    staff’s FEIS or EA.
                                                    Filed Date: 3/27/15.                                  Expansion Project II (Project).                          There are two ways to become
                                                    Accession Number: 20150327–5310.                      Specifically, the Project will enable                 involved in the Commission’s review of
                                                    Comments Due: 5 p.m. ET 4/8/15.                       Transco to provide 250,000 dekatherms                 this project. First, any person wishing to
                                                    Any person desiring to intervene or                   per day (Dth/d) of incremental firm                   obtain legal status by becoming a party
                                                  protest in any of the above proceedings                 transportation service to one shipper,                to the proceedings for this project
                                                  must file in accordance with Rules 211                  Virginia Power Services Energy Corp.,                 should, on or before the comment date
                                                  and 214 of the Commission’s                             Inc., all as more fully set forth in the              stated below file with the Federal
                                                  Regulations (18 CFR 385.211 and                         application which is on file with the                 Energy Regulatory Commission, 888
                                                  385.214) on or before 5:00 p.m. Eastern                 Commission and open to public                         First Street NE., Washington, DC 20426,
                                                  time on the specified comment date.                     inspection. The filing is available for               a motion to intervene in accordance
                                                  Protests may be considered, but                         review at the Commission in the Public                with the requirements of the
                                                  intervention is necessary to become a                   Reference Room or may be viewed on                    Commission’s Rules of Practice and
                                                  party to the proceeding.                                the Commission’s Web site web at                      Procedure (18 CFR 385.214 or 385.211)
                                                                                                          http://www.ferc.gov using the                         and the Regulations under the NGA (18
                                                  Filings in Existing Proceedings                         ‘‘eLibrary’’ link. Enter the docket                   CFR 157.10). A person obtaining party
                                                    Docket Numbers: RP15–681–001.                         number excluding the last three digits in             status will be placed on the service list
                                                    Applicants: MIGC LLC.                                 the docket number field to access the                 maintained by the Secretary of the
                                                    Description: Compliance filing per                    document. For assistance, contact FERC                Commission and will receive copies of
mstockstill on DSK4VPTVN1PROD with NOTICES




                                                  154.203: Amendment to Docket No.                        at FERCOnlineSupport@ferc.gov or call                 all documents filed by the applicant and
                                                  RP15–681–000 to be effective 4/24/                      toll-free, (886) 208–3676 or TYY, (202)               by all other parties. A party must submit
                                                  2015.                                                   502–8659.                                             five copies of filings made in the
                                                    Filed Date: 3/27/15.                                     Any questions concerning this                      proceeding with the Commission and
                                                    Accession Number: 20150327–5336.                      application may be directed to Derrick                must mail a copy to the applicant and
                                                    Comments Due: 5 p.m. ET 4/8/15.                       Hughey, Senior Regulatory Analyst, P.O.               to every other party. Only parties to the
                                                    Any person desiring to protest in any                 Box 1396, Houston, Texas 77251, by                    proceeding can ask for court review of
                                                  of the above proceedings must file in                   telephone at (713) 215–2450.                          Commission orders in the proceeding.


                                             VerDate Sep<11>2014   17:46 Apr 06, 2015   Jkt 235001   PO 00000   Frm 00032   Fmt 4703   Sfmt 4703   E:\FR\FM\07APN1.SGM   07APN1


                                                  18618                           Federal Register / Vol. 80, No. 66 / Tuesday, April 7, 2015 / Notices

                                                     However, a person does not have to                   DEPARTMENT OF ENERGY                                  stock pond; (d) a 5-foot-high concrete
                                                  intervene in order to have comments                                                                           intake box with a fish-debris screen; (e)
                                                  considered. The second way to                           Federal Energy Regulatory                             two 850-foot-long penstocks, one 8
                                                  participate is by filing with the                       Commission                                            inches and one 16 inches in diameter;
                                                  Secretary of the Commission, as soon as                 [Project No. 10852–007]                               (f) a 28-foot by 12-foot wood frame
                                                  possible, an original and two copies of                                                                       powerhouse containing two generating
                                                  comments in support of or in opposition                 Richard Bertea; Notice of Termination                 units rated at 80-kilowatts and 15-
                                                  to this project. The Commission will                    of License (Minor Project) By Implied                 kilowatts, operating under a head of 130
                                                  consider these comments in                              Surrender and Soliciting Comments                     feet; (g) an 800-foot-long, 480-volt
                                                                                                          and Protests                                          underground transmission line,
                                                  determining the appropriate action to be
                                                                                                                                                                connecting to the reversible ranch
                                                  taken, but the filing of a comment alone                   Take notice that the following                     meter, the point of connection with the
                                                  will not serve to make the filer a party                hydroelectric proceeding has been                     existing Sierra Pacific Power Company
                                                  to the proceeding. The Commission’s                     initiated by the Commission:                          line; and (h) related facilities.
                                                  rules require that persons filing                          a. Type of Proceeding: Termination of                 k. Description of Proceeding: The
                                                  comments in opposition to the project                   license by implied surrender                          licensee is in violation of Article 16 of
                                                  provide copies of their protests only to                   b. Project No.: 10852–007                          its license, which was granted
                                                  the party or parties directly involved in                  c. Date Initiated: April 1, 2015                   November 30, 1990 (53 FERC ¶ 62,202).
                                                  the protest.                                               d. Licensee: Richard Bertea                        Article 16 states in part: If the Licensee
                                                                                                             e. Name and Location of Project: The               shall abandon or discontinue good faith
                                                     Persons who wish to comment only                     Ace Ranch Project, located on the West
                                                  on the environmental review of this                                                                           operation of the project or refuse or
                                                                                                          Fork Carson River in Alpine County,                   neglect to comply with the terms of the
                                                  project should submit an original and                   California.
                                                  two copies of their comments to the                                                                           license and the lawful orders of the
                                                                                                             f. Filed Pursuant to: Standard Article             Commission, the Commission will deem
                                                  Secretary of the Commission.                            16                                                    it to be the intent of the Licensee to
                                                  Environmental commentors will be                           g. Licensee Contact Information: Mr.               surrender the license.
                                                  placed on the Commission’s                              Richard Bertea, 369 San Miguel Dr.                       Commission records indicate that the
                                                  environmental mailing list, will receive                Suite 300 Newport Beach, CA 92660,                    project was transferred to Mr. Richard
                                                  copies of the environmental documents,                  (714) 640–1982.                                       Bertea by a Commission order issued
                                                  and will be notified of meetings                           h. FERC Contact: M. Joseph Fayyad,                 May 6, 1991 (55 FERC ¶ 62,108). Since
                                                  associated with the Commission’s                        (202) 502–8759, mo.fayyad@ferc.gov                    that time, the licensee (Mr. Bertea) has
                                                  environmental review process.                              i. Deadline for filing comments and                sold the project to Bently Family
                                                  Environmental commentors will not be                    protests is 30 days from the issuance                 Limited Partnership around January
                                                  required to serve copies of filed                       date of this notice by the Commission.                1999, without getting our approval for a
                                                  documents on all other parties.                         Please file your submittal electronically             transfer of license. Since then, the
                                                  However, the non-party commentors                       via the Internet (eFiling) in lieu of                 project stopped operating around the
                                                  will not receive copies of all documents                paper. Please refer to the instructions on            end of 1999. The Commission’s San
                                                                                                          the Commission’s Web site under                       Francisco Regional Office has had
                                                  filed by other parties or issued by the
                                                                                                          http://www.ferc.gov/docs-filing/                      several correspondences with the new
                                                  Commission (except for the mailing of
                                                                                                          efiling.asp and filing instructions in the            owner and requested a plan and
                                                  environmental documents issued by the
                                                                                                          Commission’s Regulations at 18 CFR                    schedule to return the project to
                                                  Commission) and will not have the right                 385.2001(a)(1)(iii). To assist you with
                                                  to seek court review of the                                                                                   operation and to complete a formal
                                                                                                          eFilings you should refer to the                      request for a transfer of the license to
                                                  Commission’s final order.                               submission guidelines document at                     the Bently Family Limited Partnership.
                                                     The Commission strongly encourages                   http://www.ferc.gov/help/submission-                  Nothing was filed. On January 20, 2015,
                                                  electronic filings of comments, protests                guide/user-guide.pdf. In addition,                    staff sent the licensee (Mr. Bertea), to his
                                                  and interventions in lieu of paper using                certain filing requirements have                      mailing address on record, a letter
                                                  the ‘‘eFiling’’ link at http://                         statutory or regulatory formatting and                requiring the filing within 30 days, of an
                                                  www.ferc.gov. Persons unable to file                    other instructions. You should refer to               application for a transfer of license and
                                                  electronically should submit an original                a list of these ‘‘qualified documents’’ at            a plan and schedule for restoring the
                                                  and 5 copies of the protest or                          http://www.ferc.gov/docs-filing/efiling/              operation of the project or an
                                                  intervention to the Federal Energy                      filing.pdf. You must include your name                application to surrender the project’s
                                                  Regulatory Commission, 888 First Street                 and contact information at the end of                 license. Staff also sent a copy of the
                                                  NE., Washington, DC 20426.                              your comments. Please include the                     letter to the Bently Family Limited
                                                                                                          project number (10852–007) on any                     Partnership. The letter stated that if no
                                                     Comment Date: April 22, 2015.                        documents or motions filed. The                       response is filed, the Commission will
                                                    Dated: April 1, 2015.                                 Commission strongly encourages                        take action to terminate license by
                                                  Kimberly D. Bose,                                       electronic filings; otherwise, you should             implied surrender pursuant to the
                                                  Secretary.                                              submit an original and seven copies of                Commission’s regulations at 18 CFR 6.4.
                                                                                                          any submittal to the following address:               The letter to the licensee was returned
                                                  [FR Doc. 2015–07924 Filed 4–6–15; 8:45 am]
                                                                                                          The Secretary, Federal Energy                         due to lack of a forwarding address.
                                                  BILLING CODE CODE 6717–01–P
mstockstill on DSK4VPTVN1PROD with NOTICES




                                                                                                          Regulatory Commission, Mail Code:                     Nothing was filed.
                                                                                                          DHAC, PJ–12, 888 First Street NE.,                       l. This notice is available for review
                                                                                                          Washington, DC 20426.                                 and reproduction at the Commission in
                                                                                                             j. Description of Project Facilities: (a)          the Public Reference Room, Room 2A,
                                                                                                          An existing diversion dam on the West                 888 First Street NE., Washington, DC
                                                                                                          Fork Carson River with a headgate                     20426. The filing may also be viewed on
                                                                                                          structure; (b) the Heimsoth Upper West                the Commission’s Web site at http://
                                                                                                          Ditch, discharging into (c) an irrigation-            www.ferc.gov/docs-filing/elibrary.asp.


                                             VerDate Sep<11>2014   17:46 Apr 06, 2015   Jkt 235001   PO 00000   Frm 00033   Fmt 4703   Sfmt 4703   E:\FR\FM\07APN1.SGM   07APN1



Document Created: 2018-02-21 10:05:29
Document Modified: 2018-02-21 10:05:29
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
DatesApril 22, 2015.
FR Citation80 FR 18617 