80_FR_19730 80 FR 19660 - Decision To Issue Clean Air Act Permit for the Four Corners Power Plant

80 FR 19660 - Decision To Issue Clean Air Act Permit for the Four Corners Power Plant

ENVIRONMENTAL PROTECTION AGENCY

Federal Register Volume 80, Issue 70 (April 13, 2015)

Page Range19660-19661
FR Document2015-08476

This notice announces that the Environmental Protection Agency (EPA) issued a final permit decision for a Clean Air Act Prevention of Significant Deterioration (PSD) permit and Minor New Source Review (NSR) Permit in Indian Country to Arizona Public Service Company (APS) for the construction of add-on pollution controls for the Four Corners Power Plant (FCPP). Specifically, the permit authorizes APS to construct and operate selective catalytic reduction (SCR) systems, including ancillary equipment, on two existing coal-fired electric steam generating units at FCPP.

Federal Register, Volume 80 Issue 70 (Monday, April 13, 2015)
[Federal Register Volume 80, Number 70 (Monday, April 13, 2015)]
[Notices]
[Pages 19660-19661]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2015-08476]


-----------------------------------------------------------------------

ENVIRONMENTAL PROTECTION AGENCY

[EPA-R09-OAR-2014-0545; FRL-9926-14-Region-9]


Decision To Issue Clean Air Act Permit for the Four Corners Power 
Plant

AGENCY: United States Environmental Protection Agency (EPA).

ACTION: Notice of final agency action.

-----------------------------------------------------------------------

SUMMARY: This notice announces that the Environmental Protection Agency 
(EPA) issued a final permit decision for a Clean Air Act Prevention of 
Significant Deterioration (PSD) permit and Minor New Source Review 
(NSR) Permit in Indian Country to Arizona Public Service Company (APS) 
for the construction of add-on pollution controls for the Four Corners 
Power Plant (FCPP). Specifically, the permit authorizes APS to 
construct and operate selective catalytic reduction (SCR) systems, 
including ancillary equipment, on two existing coal-fired electric 
steam generating units at FCPP.

DATES: EPA Region 9 issued a final PSD permit decision for the FCPP on 
December 19, 2014. The permit became effective 30 days after the 
service of notice of the final permit decision. Pursuant to section 
307(b)(1) of the Clean Air Act, 42 U.S.C. 7607(b)(1), judicial review 
of this final permit decision, to the extent it is available, may be 
sought by filing a petition for review in the United States Court of 
Appeals for the Ninth Circuit within 60 days of April 13, 2015.

ADDRESSES: Documents relevant to the above-referenced permit are 
available for public inspection during normal business hours at the 
following address: U.S. Environmental Protection Agency, Region 9, 75 
Hawthorne Street, San Francisco, CA 94105-3901. To arrange for viewing 
of these documents, call Lisa Beckham at (415) 972-3811. Due to 
building security procedures, at least 48 hours advance notice is 
required.

FOR FURTHER INFORMATION CONTACT: Lisa Beckham, EPA Region 9, (415) 972-
3811, [email protected]. Key portions of the administrative record 
for this decision (including the final permit, all public comments, 
EPA's responses to the public comments, and additional supporting 
information) are available through a link at Region 9's Web site, 
http://www.epa.gov/region9/air/permit/r9-permits-issued.html#psd, or at 
www.regulations.gov (Docket ID # EPA-R09-OAR-2014-0545).

NOTICE OF FINAL ACTION AND SUPPLEMENTARY INFORMATION: On December 19, 
2014, EPA Region 9

[[Page 19661]]

issued its final permit decision to APS authorizing the construction 
and operation of add-on pollution controls at the FCPP--PSD Permit No. 
NN 14-01 and Tribal Minor NSR Permit T-002-NN. EPA issued a Prevention 
of Significant Deterioration (PSD) permit and Minor New Source Review 
(NSR) Permit in Indian Country that grants conditional approval to APS, 
in accordance with the PSD regulations (40 CFR 52.21) and the Minor NSR 
regulations for Indian Country (40 CFR 49.151-161). The permit 
authorizes APS to construct and operate SCR systems, including 
ancillary equipment, on two existing coal-fired electric steam 
generating units at FCPP.
    During the public comment period and public hearings, EPA received 
written and oral comments regarding its proposed permit action to 
approve the FCPP SCR project. EPA carefully reviewed the public hearing 
testimony and each of the written comments submitted and, after 
consideration of the expressed views of all commenters, the pertinent 
Federal statutes and regulations, and additional material relevant to 
the application and contained in our Administrative Record, EPA made a 
decision, in accordance with 40 CFR 52.21, to issue a final PSD permit 
and, in accordance with 40 CFR 49.151-161, to issue a final Tribal 
Minor NSR permit to APS.
    Within 30 days after the service of notice announcing the final 
permit decision, any person who filed comments on the proposed permit 
for the FCPP SCR project or participated in any of the public hearings 
for the FCPP SCR project had the opportunity pursuant to 40 CFR part 
124 to petition EPA's Environmental Appeals Board (EAB) to review any 
condition of the final permit. Any person who did not file comments or 
participate in the public hearings could petition for administrative 
review only to the extent that changes were made from the proposed to 
the final permit decision. No petitions for review were filed with the 
EAB. As such, the final permit became effective 30 days after the 
service of notice of the final permit decision.

    Dated: March 31, 2015.
Deborah Jordan,
Director, Air Division, Region IX.
[FR Doc. 2015-08476 Filed 4-10-15; 8:45 am]
 BILLING CODE 6560-50-P



                                                  19660                          Federal Register / Vol. 80, No. 70 / Monday, April 13, 2015 / Notices

                                                  In re: St. Albans Gas and Light Company                 Agreement would resolve certain                       ENVIRONMENTAL PROTECTION
                                                  Superfund Site, U.S. EPA Docket No.                     potential claims of the United States                 AGENCY
                                                  01–2015–0023.                                           under sections 106 and 107(a) of
                                                                                                                                                                [EPA–R09–OAR–2014–0545; FRL–9926–14–
                                                  FOR FURTHER INFORMATION CONTACT: A                      CERCLA, 42 U.S.C. 9606 and 9607(a)                    Region–9]
                                                  copy of the proposed settlement may be                  against Reichhold LLC, a Delaware
                                                  obtained from Michelle Lauterback,                      corporation (the Purchaser). The                      Decision To Issue Clean Air Act Permit
                                                  Senior Enforcement Counsel, U.S.                        Purchaser plans to acquire Reichhold,                 for the Four Corners Power Plant
                                                  Environmental Protection Agency, 5                      Inc.’s chemical plant, comprising
                                                  Post Office Square, Suite 100 (OES04–                   approximately 8.878 acres, located at                 AGENCY:  United States Environmental
                                                  3), Boston, MA 02109–3912; (617) 918–                   237 South Motor Avenue, Azusa,                        Protection Agency (EPA).
                                                  1774; Lauterback.michelle@epa.gov).                     California, within the Baldwin Park                   ACTION: Notice of final agency action.
                                                  SUPPLEMENTARY INFORMATION: In this                      Operable Unit (BPOU) of the San
                                                                                                          Gabriel Valley Area 2 Superfund Site.                 SUMMARY:   This notice announces that
                                                  proposed administrative settlement for                                                                        the Environmental Protection Agency
                                                  recovery of response costs under                        The proposed settlement would provide
                                                                                                          the following benefit to EPA: The                     (EPA) issued a final permit decision for
                                                  CERCLA section 122(h)(1) and 104(e)(6),                                                                       a Clean Air Act Prevention of
                                                  concerning the St. Albans Gas and Light                 purchaser will pay $800,000 in cash, to
                                                                                                          be held in reserve in a special account               Significant Deterioration (PSD) permit
                                                  Company Superfund Site in St. Albans,                                                                         and Minor New Source Review (NSR)
                                                  Vermont, requires settling party, Adam                  for future cleanup work at the BPOU, as
                                                                                                          needed. Reichhold, Inc., is not a                     Permit in Indian Country to Arizona
                                                  Spell to pay $41,694 to the Hazardous                                                                         Public Service Company (APS) for the
                                                  Substance Superfund, with interest. The                 signatory to the Prospective Purchaser
                                                                                                          Agreement. The Purchaser is not                       construction of add-on pollution
                                                  settlement includes a covenant not to                                                                         controls for the Four Corners Power
                                                  sue pursuant to sections 106 and 107(a)                 directly affiliated with Reichhold, Inc.
                                                                                                            For 30 calendar days following the                  Plant (FCPP). Specifically, the permit
                                                  of CERCLA, 42 U.S.C. 9606 and 9607,                                                                           authorizes APS to construct and operate
                                                  relating to the Site, and protection from               date of publication of this notice, EPA
                                                                                                          will receive written comments relating                selective catalytic reduction (SCR)
                                                  contribution actions or claims as                                                                             systems, including ancillary equipment,
                                                  provided by sections 113(f)(2) and                      to the proposed settlement. EPA’s
                                                                                                          response to any comments received will                on two existing coal-fired electric steam
                                                  122(h)(4) of CERCLA, 42 U.S.C.                                                                                generating units at FCPP.
                                                  9613(f)(2) and 9622(h)(4). The                          be available for public inspection at the
                                                                                                          U.S. Environmental Protection Agency,                 DATES: EPA Region 9 issued a final PSD
                                                  settlement has been approved by the
                                                                                                          75 Hawthorne Street, San Francisco, CA                permit decision for the FCPP on
                                                  Environmental and Natural Resources
                                                                                                          94105.                                                December 19, 2014. The permit became
                                                  Division of the United States
                                                                                                                                                                effective 30 days after the service of
                                                  Department of Justice.                                  DATES: Submit comments on or before
                                                                                                                                                                notice of the final permit decision.
                                                    Dated: March 17, 2015.                                May 13, 2015.
                                                                                                                                                                Pursuant to section 307(b)(1) of the
                                                  Nancy Barmakian,                                        ADDRESSES: The proposed Prospective                   Clean Air Act, 42 U.S.C. 7607(b)(1),
                                                  Acting Director, Office of Site Remediation             Purchaser Agreement is available for                  judicial review of this final permit
                                                  and Restoration.                                        public inspection at the U.S.                         decision, to the extent it is available,
                                                  [FR Doc. 2015–08428 Filed 4–10–15; 8:45 am]             Environmental Protection Agency, 75                   may be sought by filing a petition for
                                                  BILLING CODE 6560–50–P
                                                                                                          Hawthorne Street, San Francisco, CA                   review in the United States Court of
                                                                                                          94105. The document can be accessed                   Appeals for the Ninth Circuit within 60
                                                                                                          through the Internet on EPA Region 9’s                days of April 13, 2015.
                                                  ENVIRONMENTAL PROTECTION                                Web site located at: http://www.epa.gov/
                                                                                                                                                                ADDRESSES: Documents relevant to the
                                                  AGENCY                                                  region09/waste/brown/ppa.html.
                                                                                                                                                                above-referenced permit are available
                                                                                                            A copy of the proposed settlement
                                                  [9926–13–Region 9]                                                                                            for public inspection during normal
                                                                                                          may also be obtained from Janet A.
                                                                                                                                                                business hours at the following address:
                                                                                                          Magnuson, Assistant Regional Counsel,
                                                  San Gabriel Valley Area 2 Superfund                                                                           U.S. Environmental Protection Agency,
                                                                                                          (ORC–3), Office of Regional Counsel,
                                                  Site; Proposed Notice of                                                                                      Region 9, 75 Hawthorne Street, San
                                                                                                          U.S. EPA Region IX, 75 Hawthorne
                                                  Administrative Settlement                                                                                     Francisco, CA 94105–3901. To arrange
                                                                                                          Street, San Francisco 94105. Comments
                                                                                                                                                                for viewing of these documents, call
                                                  AGENCY: Environmental Protection                        should reference ‘‘Reichhold, LLC PPA,
                                                                                                                                                                Lisa Beckham at (415) 972–3811. Due to
                                                  Agency (EPA).                                           San Gabriel Valley Area 2 Superfund
                                                                                                                                                                building security procedures, at least 48
                                                  ACTION: Notice; request for public                      Site’’ and ‘‘Docket No. 2015–04’’ and
                                                                                                                                                                hours advance notice is required.
                                                  comment.                                                should be addressed to Janet A.
                                                                                                          Magnuson at the above address.                        FOR FURTHER INFORMATION CONTACT: Lisa
                                                  SUMMARY:   In accordance with the                                                                             Beckham, EPA Region 9, (415) 972–
                                                                                                          FOR FURTHER INFORMATION CONTACT:
                                                  Comprehensive Environmental                                                                                   3811, beckham.lisa@epa.gov. Key
                                                                                                          Janet Magnuson, Assistant Regional                    portions of the administrative record for
                                                  Response, Compensation and Liability                    Counsel (ORC–3), Office of Regional
                                                  Act of 1980, as amended by the                                                                                this decision (including the final permit,
                                                                                                          Counsel, U.S. EPA Region IX, 75                       all public comments, EPA’s responses to
                                                  Superfund Amendments and                                Hawthorne Street, San Francisco, CA
                                                  Reauthorization Act of 1986 (CERCLA),                                                                         the public comments, and additional
                                                                                                          94105; phone: (415) 972–3887; fax: (415)              supporting information) are available
                                                  42 U.S.C. 9600 et seq., notice is hereby                947–3570; email: magnuson.janet@                      through a link at Region 9’s Web site,
mstockstill on DSK4VPTVN1PROD with NOTICES




                                                  given that a proposed Agreement and                     epa.gov.
                                                  Covenant Not to Sue (Prospective                                                                              http://www.epa.gov/region9/air/permit/
                                                  Purchaser Agreement) associated with                      Dated: March 31, 2015.                              r9-permits-issued.html#psd, or at
                                                  the San Gabriel Valley Area 2                           Enrique Manzanilla,                                   www.regulations.gov (Docket ID # EPA–
                                                  Superfund Site was executed by the                      Superfund Division Director, U.S. EPA Region          R09–OAR–2014–0545).
                                                  United States Environmental Protection                  IX.                                                   NOTICE OF FINAL ACTION AND
                                                  Agency (EPA) on March 25, 2015. The                     [FR Doc. 2015–08427 Filed 4–10–15; 8:45 am]           SUPPLEMENTARY INFORMATION: On
                                                  proposed Prospective Purchaser                          BILLING CODE 6560–50–P                                December 19, 2014, EPA Region 9


                                             VerDate Sep<11>2014   18:02 Apr 10, 2015   Jkt 235001   PO 00000   Frm 00031   Fmt 4703   Sfmt 4703   E:\FR\FM\13APN1.SGM   13APN1


                                                                                 Federal Register / Vol. 80, No. 70 / Monday, April 13, 2015 / Notices                                              19661

                                                  issued its final permit decision to APS                 FEDERAL COMMUNICATIONS                                418–0530 (voice), (202) 418–0432
                                                  authorizing the construction and                        COMMISSION                                            (TTY).
                                                  operation of add-on pollution controls                                                                        Synopsis
                                                  at the FCPP—PSD Permit No. NN 14–01                     [GN Docket No. 12–268; FCC 14–50]
                                                  and Tribal Minor NSR Permit T–002–                                                                              As required by the Paperwork
                                                  NN. EPA issued a Prevention of                          Information Collection Approval for the               Reduction Act of 1995 (44 U.S.C. 3507),
                                                  Significant Deterioration (PSD) permit                  Certification of TV Broadcast Licensee                the FCC is notifying the public that it
                                                  and Minor New Source Review (NSR)                       Technical Information in Advance of                   received OMB approval on March 31,
                                                                                                          Incentive Auction                                     2015, for the information collection
                                                  Permit in Indian Country that grants
                                                                                                                                                                requirements contained in the
                                                  conditional approval to APS, in                         AGENCY:  Federal Communications                       information collection 3060–1206.
                                                  accordance with the PSD regulations (40                 Commission.                                             Under 5 CFR 1320, an agency may not
                                                  CFR 52.21) and the Minor NSR                            ACTION: Announcement of approval date                 conduct or sponsor a collection of
                                                  regulations for Indian Country (40 CFR                  for information collection.                           information unless it displays a current,
                                                  49.151–161). The permit authorizes APS                                                                        valid OMB Control Number.
                                                  to construct and operate SCR systems,                   SUMMARY:    In this document, the                       No person shall be subject to any
                                                  including ancillary equipment, on two                   Commission announces that the Office                  penalty for failing to comply with a
                                                  existing coal-fired electric steam                      of Management and Budget (OMB)                        collection of information subject to the
                                                  generating units at FCPP.                               approved on March 31, 2015, for a                     Paperwork Reduction Act that does not
                                                     During the public comment period                     period for three years, an information                display a current, valid OMB Control
                                                  and public hearings, EPA received                       collection for the FCC Certification of               Number. The OMB Control Number is
                                                                                                          TV Broadcast Licensee Technical                       3060–1206. The foregoing document is
                                                  written and oral comments regarding its
                                                                                                          Information in Advance of Incentive                   required by the Paperwork Reduction
                                                  proposed permit action to approve the
                                                                                                          Auction, FCC Form 2100, Schedule 381.                 Act of 1995, Pub. L. 104–13, October 1,
                                                  FCPP SCR project. EPA carefully                         With this document, the Commission is
                                                  reviewed the public hearing testimony                                                                         1995, and 44 U.S.C. 3507.
                                                                                                          announcing OMB approval and the                         The total annual reporting burdens
                                                  and each of the written comments                        effective date of the information                     and costs for the respondents are as
                                                  submitted and, after consideration of the               collection requirements for FCC Form                  follows:
                                                  expressed views of all commenters, the                  2100, Schedule 381.                                     OMB Control Number: 3060–1206.
                                                  pertinent Federal statutes and                          DATES: FCC Form 2100, Schedule 381,                     OMB Approval Date: March 31, 2015.
                                                  regulations, and additional material                    was approved by OMB on March 31,                        OMB Expiration Date: March 31,
                                                  relevant to the application and                         2015 and is effective on April 13, 2015.              2018.
                                                  contained in our Administrative Record,                                                                         Title: Certification of TV Broadcast
                                                                                                          FOR FURTHER INFORMATION CONTACT: For
                                                  EPA made a decision, in accordance                                                                            Licensee Technical Information in
                                                                                                          additional information contact Cathy
                                                  with 40 CFR 52.21, to issue a final PSD                 Williams, Cathy.Williams@fcc.gov, (202)               Advance of Incentive Auction.
                                                  permit and, in accordance with 40 CFR                                                                           Form No.: FCC Form 2100, Schedule
                                                                                                          418–2918.
                                                  49.151–161, to issue a final Tribal Minor                                                                     381, Pre-Auction Technical Certification
                                                                                                          SUPPLEMENTARY INFORMATION: This                       Form.
                                                  NSR permit to APS.
                                                                                                          document announces that, on March 31,                   Respondents: Business or other for
                                                     Within 30 days after the service of                  2015, OMB approved the information                    profit entities; Not for profit institutions.
                                                  notice announcing the final permit                      collection requirements for the FCC                     Number of Respondents and
                                                  decision, any person who filed                          Certification of TV Broadcast Licensee                Responses: 2,170 respondents and 2,170
                                                  comments on the proposed permit for                     Technical Information in Advance of                   responses.
                                                  the FCPP SCR project or participated in                 Incentive Auction, FCC Form 2100,                       Estimated Time Per Response: 2
                                                  any of the public hearings for the FCPP                 Schedule 381, published at 79 FR 48442                hours.
                                                  SCR project had the opportunity                         on August 15, 2014. The OMB Control                     Frequency of Response: One-time
                                                  pursuant to 40 CFR part 124 to petition                 Number is 3060–1206. The Commission                   reporting requirement.
                                                  EPA’s Environmental Appeals Board                       publishes this document as an                           Obligation to Respond: Required to
                                                  (EAB) to review any condition of the                    announcement of the effective date of                 obtain or retain benefits. The statutory
                                                  final permit. Any person who did not                    the requirements. If you have any                     authority for this collection is contained
                                                  file comments or participate in the                     comments on the burden estimates                      in Pub. L. 112–96, sections 6402
                                                  public hearings could petition for                      listed below, or how the Commission                   (codified at 47 U.S.C. 309(j)(8)(G)), 6403
                                                  administrative review only to the extent                can improve the collections and reduce                (codified at 47 U.S.C. 1452), 126 Stat.
                                                  that changes were made from the                         any burdens caused thereby, please                    156 (2012) (Spectrum Act).
                                                  proposed to the final permit decision.                  contact Cathy Williams, Federal                         Total Annual Burden: 2,170 hours.
                                                                                                          Communications Commission, Room 1–                      Total Annual Cost: $542,500.
                                                  No petitions for review were filed with
                                                                                                          C823, 445 12th Street, SW., Washington,                 Privacy Act Impact Assessment: No
                                                  the EAB. As such, the final permit
                                                                                                          DC 20554. Please include the OMB                      impact(s).
                                                  became effective 30 days after the
                                                                                                          Control Number, 3060–1206, in your                      Nature and Extent of Confidentiality:
                                                  service of notice of the final permit                   correspondence. The Commission will                   Some assurances of confidentiality are
                                                  decision.                                               also accept your comments via the                     being provided to the respondents.
mstockstill on DSK4VPTVN1PROD with NOTICES




                                                    Dated: March 31, 2015.                                Internet if you send them to PRA@                     Parties filing Form 2100, Schedule 381
                                                  Deborah Jordan,                                         fcc.gov.                                              may seek confidential treatment of
                                                  Director, Air Division, Region IX.                         To request materials in accessible                 information they provide pursuant to
                                                  [FR Doc. 2015–08476 Filed 4–10–15; 8:45 am]
                                                                                                          formats for people with disabilities                  the Commission’s existing
                                                                                                          (Braille, large print, electronic files,              confidentiality rules (See 47 CFR 0.459).
                                                  BILLING CODE 6560–50–P
                                                                                                          audio format), send an email to fcc504@                 Needs and Uses: The information
                                                                                                          fcc.gov or call the Consumer and                      gathered in this collection will be used
                                                                                                          Governmental Affairs Bureau at (202)                  to support the Federal Communications


                                             VerDate Sep<11>2014   18:02 Apr 10, 2015   Jkt 235001   PO 00000   Frm 00032   Fmt 4703   Sfmt 4703   E:\FR\FM\13APN1.SGM   13APN1



Document Created: 2015-12-18 11:21:56
Document Modified: 2015-12-18 11:21:56
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
ActionNotice of final agency action.
DatesEPA Region 9 issued a final PSD permit decision for the FCPP on December 19, 2014. The permit became effective 30 days after the service of notice of the final permit decision. Pursuant to section 307(b)(1) of the Clean Air Act, 42 U.S.C. 7607(b)(1), judicial review of this final permit decision, to the extent it is available, may be sought by filing a petition for review in the United States Court of Appeals for the Ninth Circuit within 60 days of April 13, 2015.
ContactLisa Beckham, EPA Region 9, (415) 972- 3811, [email protected] Key portions of the administrative record for this decision (including the final permit, all public comments, EPA's responses to the public comments, and additional supporting information) are available through a link at Region 9's Web site, http://www.epa.gov/region9/air/permit/r9-permits-issued.html#psd, or at www.regulations.gov (Docket ID # EPA-R09-OAR-2014-0545).
FR Citation80 FR 19660 