80_FR_23605 80 FR 23524 - Georgia Power Company; Notice of Intent To File License Application, Filing of Pre-Application Document (Pad), Commencement of Pre-Filing Process, and Scoping; Request for Comments on the Pad and Scoping Document, and Identification of Issues and Associated Study Requests

80 FR 23524 - Georgia Power Company; Notice of Intent To File License Application, Filing of Pre-Application Document (Pad), Commencement of Pre-Filing Process, and Scoping; Request for Comments on the Pad and Scoping Document, and Identification of Issues and Associated Study Requests

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 80, Issue 81 (April 28, 2015)

Page Range23524-23525
FR Document2015-09747

Federal Register, Volume 80 Issue 81 (Tuesday, April 28, 2015)
[Federal Register Volume 80, Number 81 (Tuesday, April 28, 2015)]
[Notices]
[Pages 23524-23525]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2015-09747]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 2413-117]


Georgia Power Company; Notice of Intent To File License 
Application, Filing of Pre-Application Document (Pad), Commencement of 
Pre-Filing Process, and Scoping; Request for Comments on the Pad and 
Scoping Document, and Identification of Issues and Associated Study 
Requests

    a. Type of Filing: Notice of Intent to File License Application for 
a New License and Commencing Pre-filing Process.
    b. Project No.: 2413-117.
    c. Dated Filed: February 18, 2015.
    d. Submitted By: Georgia Power Company (Georgia Power).
    e. Name of Project: Wallace Dam Pumped Storage Project.
    f. Location: On the Oconee River, in Hancock, Putnam, Green, and 
Morgan Counties, Georgia. The project occupies about 370 acres of 
federal land administered by the U.S. Forest Service.
    g. Filed Pursuant to: 18 CFR part 5 of the Commission's 
Regulations.
    h. Potential Applicant Contact: Courtenay R. O'Mara, P.E., Wallace 
Dam Hydro Relicensing Manager, Southern Company Generation, BIN 10193, 
241 Ralph McGill Blvd. NE., Atlanta, GA 30308-3374; (404) 506-7219; 
[email protected].
    i. FERC Contact: Allan Creamer at (202) 502-8365, or email at 
[email protected].
    j. Cooperating agencies: Federal, state, local, and tribal agencies 
with jurisdiction and/or special expertise with respect to 
environmental issues that wish to cooperate in the preparation of the 
environmental document should follow the instructions for filing such 
requests described in item o below. Cooperating agencies should note 
the Commission's policy that agencies that cooperate in the preparation 
of the environmental document cannot also intervene. See 94 FERC ] 
61,076 (2001).
    k. With this notice, we are initiating informal consultation with: 
(1) the U.S. Fish and Wildlife Service and/or the National Marine 
Fisheries Service under section 7 of the Endangered Species Act and the 
joint agency regulations thereunder at 50 CFR, Part 402; and (2) the 
State Historic Preservation Officer, as required by section 106 of the 
National Historical Preservation Act, and the implementing regulations 
of the Advisory Council on Historic Preservation at 36 CFR 800.2.
    l. With this notice, we are designating Georgia Power as the 
Commission's non-federal representative for carrying out informal 
consultation, pursuant to section 7 of the Endangered Species Act and 
section 106 of the National Historic Preservation Act.
    m. Georgia Power filed with the Commission a Pre-Application 
Document (PAD; including a proposed process plan and schedule), 
pursuant to 18 CFR 5.6 of the Commission's regulations.
    n. A copy of the PAD is available for review at the Commission in 
the Public Reference Room, or may be viewed on the Commission's Web 
site (http://www.ferc.gov) using the ``eLibrary'' link. Enter the 
docket number, excluding the last three digits in the docket number 
field, to access the document. For assistance, contact FERC Online 
Support at [email protected], or toll free at 1-866-208-3676, 
or for TTY, (202) 502-8659. A copy is also available for inspection and 
reproduction at http://www.georgipower.com/about-energy/energy-sources/hydro-power/hydro-projects/wallace/home.cshtml, or the address in 
paragraph h.
    Register online at http://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances 
related to this or other pending projects. For assistance, contact FERC 
Online Support.
    o. With this notice, we are soliciting comments on the PAD and 
Commission staff's Scoping Document 1 (SD1), as well as study requests. 
All comments on the PAD and SD1, as well as study requests should be 
sent to the address above in paragraph h. In addition, all comments on 
the PAD and SD1, study requests, requests for cooperating agency 
status, and all communications to and from Commission staff related to 
the merits of the potential application must be filed with the 
Commission. Documents may be filed electronically via the Internet. See 
18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission's Web 
site http://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit 
brief comments up to 6,000 characters, without prior registration, 
using the eComment system at http://www.ferc.gov/docs-filing/ecomment.asp. You must include your name and contact information at the 
end of your comments. For assistance, please contact FERC Online 
Support. Although the Commission strongly encourages electronic filing, 
documents may also be paper-filed. To paper-file, mail an original and 
five copies to: Kimberly D. Bose, Secretary, Federal Energy Regulatory 
Commission, 888 First Street NE., Washington, DC 20426.
    All filings with the Commission must include on the first page, the 
project name and number (i.e., Wallace Dam Pumped Storage Project, P-
2413-117), and bear the appropriate heading: ``Comments on Pre-
Application Document,'' ``Study Requests,'' ``Comments on Scoping 
Document 1,'' ``Request for Cooperating Agency Status,'' or 
``Communications to and from Commission Staff.'' Any individual or 
entity interested in submitting study requests, commenting on the PAD 
or SD1, and any agency requesting cooperating status must do so by June 
19, 2015.
    p. Although our current intent is to prepare an environmental 
assessment (EA), there is the possibility that an Environmental Impact 
Statement (EIS) will be required. Nevertheless, this meeting will 
satisfy the NEPA scoping requirements, irrespective of whether an EA or 
EIS is issued by the Commission.

Scoping Meetings

    Commission staff will hold two scoping meetings in the vicinity of 
the project at the time and place noted below. The daytime meeting will 
focus on resource agency, Indian tribes, and non-governmental 
organization concerns, while the evening meeting is primarily for 
receiving input from the public. We invite all interested individuals, 
organizations, and agencies to attend one or both of the meetings, and 
to assist staff in identifying particular study needs, as well as the 
scope of environmental issues to be addressed in the environmental 
document. The times and locations of these meetings are as follows:

Daytime Scoping Meeting

    Date: Wednesday, May 20, 2015.
    Time: 1:00 p.m.
    Location: Rock Eagle 4-H Center, Sutton Hall, 350 Rock Eagle Road, 
Eatonton, Georgia 31024.
    Phone: (706) 484-2868.

Evening Scoping Meeting

    Date: Wednesday, May 20, 2015.
    Time: 6:30 p.m.
    Location: Rock Eagle 4-H Center, Sutton Hall, 350 Rock Eagle Road, 
Eatonton, Georgia 31024.
    Phone: (706) 484-2868.
    SD1, which outlines the subject areas to be addressed in the 
environmental

[[Page 23525]]

document, was mailed to the individuals and entities on the 
Commission's mailing list. Copies of SD1 will be available at the 
scoping meetings, or may be viewed on the web at http://www.ferc.gov, 
using the ``eLibrary'' link. Follow the directions for accessing 
information in paragraph n. Based on all oral and written comments, a 
Scoping Document 2 (SD2) may be issued. SD2 may include a revised 
process plan and schedule, as well as a list of issues, identified 
through the scoping process.

Environmental Site Review

    The potential applicant and Commission staff will conduct an 
Environmental Site Review of the project on Tuesday, May 19, 2015, 
starting at 9:00 a.m. All participants should meet at Georgia Power's 
Old Salem Park, located at 1530 Old Salem Road, Greensboro, Georgia 
30642. Anyone with questions about the site visit should contact Ms. 
Courtenay O'Mara, Southern Company Generation, at (404) 506-7219, or at 
[email protected], on or before May 5, 2015. Participants of 
the tour must provide identification, sign a liability waiver, and wear 
appropriate clothing and closed toed shoes. If any participant 
attending any part of the site visit is disabled or has special needs, 
please send an email to Oconee Relicensing at 
[email protected].

Meeting Objectives

    At the scoping meetings, Commission staff will: (1) Initiate 
scoping of the issues; (2) review and discuss existing conditions and 
resource management objectives; (3) review and discuss existing 
information and identify preliminary information and study needs; (4) 
review and discuss the process plan and schedule for pre-filing 
activities that incorporates the time frames provided for in Part 5 of 
the Commission's regulations and, to the extent possible, maximizes 
coordination of federal, state, and tribal permitting and certification 
processes; and (5) discuss the appropriateness of any federal or state 
agency or Indian tribe acting as a cooperating agency for development 
of an environmental document.
    Meeting participants should come prepared to discuss their issues 
and/or concerns. Please review the PAD in preparation for the scoping 
meetings. Directions on how to obtain a copy of the PAD and SD1 are 
included in item n. of this document.

Meeting Procedures

    The meetings will be recorded by a stenographer. The transcripts 
will be placed in the public record for the project.

    Dated: April 17, 2015.
Kimberly D. Bose,
Secretary.
[FR Doc. 2015-09747 Filed 4-27-15; 8:45 am]
 BILLING CODE 6717-01-P



                                                    23524                          Federal Register / Vol. 80, No. 81 / Tuesday, April 28, 2015 / Notices

                                                      Dated: April 22, 2015.                                thereunder at 50 CFR, Part 402; and (2)               of your comments. For assistance,
                                                    Nathaniel J. Davis, Sr.,                                the State Historic Preservation Officer,              please contact FERC Online Support.
                                                    Deputy Secretary.                                       as required by section 106 of the                     Although the Commission strongly
                                                    [FR Doc. 2015–09808 Filed 4–27–15; 8:45 am]             National Historical Preservation Act,                 encourages electronic filing, documents
                                                    BILLING CODE 6717–01–P
                                                                                                            and the implementing regulations of the               may also be paper-filed. To paper-file,
                                                                                                            Advisory Council on Historic                          mail an original and five copies to:
                                                                                                            Preservation at 36 CFR 800.2.                         Kimberly D. Bose, Secretary, Federal
                                                    DEPARTMENT OF ENERGY                                       l. With this notice, we are designating            Energy Regulatory Commission, 888
                                                                                                            Georgia Power as the Commission’s                     First Street NE., Washington, DC 20426.
                                                    Federal Energy Regulatory                               non-federal representative for carrying                  All filings with the Commission must
                                                    Commission                                              out informal consultation, pursuant to                include on the first page, the project
                                                                                                            section 7 of the Endangered Species Act               name and number (i.e., Wallace Dam
                                                    [Project No. 2413–117]
                                                                                                            and section 106 of the National Historic              Pumped Storage Project, P–2413–117),
                                                    Georgia Power Company; Notice of                        Preservation Act.                                     and bear the appropriate heading:
                                                                                                               m. Georgia Power filed with the                    ‘‘Comments on Pre-Application
                                                    Intent To File License Application,
                                                                                                            Commission a Pre-Application                          Document,’’ ‘‘Study Requests,’’
                                                    Filing of Pre-Application Document
                                                                                                            Document (PAD; including a proposed                   ‘‘Comments on Scoping Document 1,’’
                                                    (Pad), Commencement of Pre-Filing
                                                                                                            process plan and schedule), pursuant to               ‘‘Request for Cooperating Agency
                                                    Process, and Scoping; Request for
                                                                                                            18 CFR 5.6 of the Commission’s                        Status,’’ or ‘‘Communications to and
                                                    Comments on the Pad and Scoping
                                                                                                            regulations.                                          from Commission Staff.’’ Any
                                                    Document, and Identification of Issues                     n. A copy of the PAD is available for
                                                    and Associated Study Requests                                                                                 individual or entity interested in
                                                                                                            review at the Commission in the Public                submitting study requests, commenting
                                                      a. Type of Filing: Notice of Intent to                Reference Room, or may be viewed on                   on the PAD or SD1, and any agency
                                                    File License Application for a New                      the Commission’s Web site (http://                    requesting cooperating status must do so
                                                    License and Commencing Pre-filing                       www.ferc.gov) using the ‘‘eLibrary’’ link.            by June 19, 2015.
                                                    Process.                                                Enter the docket number, excluding the                   p. Although our current intent is to
                                                      b. Project No.: 2413–117.                             last three digits in the docket number                prepare an environmental assessment
                                                      c. Dated Filed: February 18, 2015.                    field, to access the document. For                    (EA), there is the possibility that an
                                                      d. Submitted By: Georgia Power                        assistance, contact FERC Online                       Environmental Impact Statement (EIS)
                                                    Company (Georgia Power).                                Support at FERCONlineSupport@                         will be required. Nevertheless, this
                                                      e. Name of Project: Wallace Dam                       ferc.gov, or toll free at 1–866–208–3676,             meeting will satisfy the NEPA scoping
                                                    Pumped Storage Project.                                 or for TTY, (202) 502–8659. A copy is                 requirements, irrespective of whether an
                                                      f. Location: On the Oconee River, in                  also available for inspection and                     EA or EIS is issued by the Commission.
                                                    Hancock, Putnam, Green, and Morgan                      reproduction at http://
                                                    Counties, Georgia. The project occupies                 www.georgipower.com/about-energy/                     Scoping Meetings
                                                    about 370 acres of federal land                         energy-sources/hydro-power/hydro-                       Commission staff will hold two
                                                    administered by the U.S. Forest Service.                projects/wallace/home.cshtml, or the                  scoping meetings in the vicinity of the
                                                      g. Filed Pursuant to: 18 CFR part 5 of                address in paragraph h.                               project at the time and place noted
                                                    the Commission’s Regulations.                              Register online at http://                         below. The daytime meeting will focus
                                                      h. Potential Applicant Contact:                       www.ferc.gov/docs-filing/                             on resource agency, Indian tribes, and
                                                    Courtenay R. O’Mara, P.E., Wallace Dam                  esubscription.asp to be notified via                  non-governmental organization
                                                    Hydro Relicensing Manager, Southern                     email of new filings and issuances                    concerns, while the evening meeting is
                                                    Company Generation, BIN 10193, 241                      related to this or other pending projects.            primarily for receiving input from the
                                                    Ralph McGill Blvd. NE., Atlanta, GA                     For assistance, contact FERC Online                   public. We invite all interested
                                                    30308–3374; (404) 506–7219;                             Support.                                              individuals, organizations, and agencies
                                                    g2oconeerel@southernco.com.                                o. With this notice, we are soliciting             to attend one or both of the meetings,
                                                      i. FERC Contact: Allan Creamer at                     comments on the PAD and Commission                    and to assist staff in identifying
                                                    (202) 502–8365, or email at                             staff’s Scoping Document 1 (SD1), as                  particular study needs, as well as the
                                                    allan.creamer@ferc.gov.                                 well as study requests. All comments on               scope of environmental issues to be
                                                      j. Cooperating agencies: Federal, state,              the PAD and SD1, as well as study                     addressed in the environmental
                                                    local, and tribal agencies with                         requests should be sent to the address                document. The times and locations of
                                                    jurisdiction and/or special expertise                   above in paragraph h. In addition, all                these meetings are as follows:
                                                    with respect to environmental issues                    comments on the PAD and SD1, study
                                                                                                                                                                  Daytime Scoping Meeting
                                                    that wish to cooperate in the                           requests, requests for cooperating
                                                    preparation of the environmental                        agency status, and all communications                   Date: Wednesday, May 20, 2015.
                                                    document should follow the                              to and from Commission staff related to                 Time: 1:00 p.m.
                                                    instructions for filing such requests                   the merits of the potential application                 Location: Rock Eagle 4–H Center,
                                                    described in item o below. Cooperating                  must be filed with the Commission.                    Sutton Hall, 350 Rock Eagle Road,
                                                                                                            Documents may be filed electronically                 Eatonton, Georgia 31024.
                                                    agencies should note the Commission’s
                                                                                                                                                                    Phone: (706) 484–2868.
                                                    policy that agencies that cooperate in                  via the Internet. See 18 CFR
                                                    the preparation of the environmental                    385.2001(a)(1)(iii) and the instructions              Evening Scoping Meeting
asabaliauskas on DSK5VPTVN1PROD with NOTICES




                                                    document cannot also intervene. See 94                  on the Commission’s Web site http://                    Date: Wednesday, May 20, 2015.
                                                    FERC ¶ 61,076 (2001).                                   www.ferc.gov/docs-filing/efiling.asp.                   Time: 6:30 p.m.
                                                      k. With this notice, we are initiating                Commenters can submit brief comments                    Location: Rock Eagle 4–H Center,
                                                    informal consultation with: (1) the U.S.                up to 6,000 characters, without prior                 Sutton Hall, 350 Rock Eagle Road,
                                                    Fish and Wildlife Service and/or the                    registration, using the eComment system               Eatonton, Georgia 31024.
                                                    National Marine Fisheries Service under                 at http://www.ferc.gov/docs-filing/                     Phone: (706) 484–2868.
                                                    section 7 of the Endangered Species Act                 ecomment.asp. You must include your                     SD1, which outlines the subject areas
                                                    and the joint agency regulations                        name and contact information at the end               to be addressed in the environmental


                                               VerDate Sep<11>2014   18:18 Apr 27, 2015   Jkt 235001   PO 00000   Frm 00029   Fmt 4703   Sfmt 4703   E:\FR\FM\28APN1.SGM   28APN1


                                                                                   Federal Register / Vol. 80, No. 81 / Tuesday, April 28, 2015 / Notices                                                 23525

                                                    document, was mailed to the                             Meeting Procedures                                    of the protest or intervention to the
                                                    individuals and entities on the                           The meetings will be recorded by a                  Federal Energy Regulatory Commission,
                                                    Commission’s mailing list. Copies of                    stenographer. The transcripts will be                 888 First Street NE., Washington, DC
                                                    SD1 will be available at the scoping                    placed in the public record for the                   20426.
                                                    meetings, or may be viewed on the web                   project.                                                 This filing is accessible on-line at
                                                    at http://www.ferc.gov, using the                                                                             http://www.ferc.gov, using the
                                                                                                              Dated: April 17, 2015.                              ‘‘eLibrary’’ link and is available for
                                                    ‘‘eLibrary’’ link. Follow the directions
                                                                                                            Kimberly D. Bose,                                     review in the Commission’s Public
                                                    for accessing information in paragraph
                                                    n. Based on all oral and written                        Secretary.                                            Reference Room in Washington, DC.
                                                    comments, a Scoping Document 2 (SD2)                    [FR Doc. 2015–09747 Filed 4–27–15; 8:45 am]           There is an ‘‘eSubscription’’ link on the
                                                                                                            BILLING CODE 6717–01–P                                Web site that enables subscribers to
                                                    may be issued. SD2 may include a
                                                                                                                                                                  receive email notification when a
                                                    revised process plan and schedule, as
                                                                                                                                                                  document is added to a subscribed
                                                    well as a list of issues, identified                    DEPARTMENT OF ENERGY                                  docket(s). For assistance with any FERC
                                                    through the scoping process.
                                                                                                                                                                  Online service, please email
                                                    Environmental Site Review                               Federal Energy Regulatory                             FERCOnlineSupport@ferc.gov, or call
                                                                                                            Commission                                            (866) 208–3676 (toll free). For TTY, call
                                                       The potential applicant and                          [Docket No. EL15–61–000]                              (202) 502–8659.
                                                    Commission staff will conduct an                                                                                 Comment Date: 5:00 p.m. Eastern
                                                    Environmental Site Review of the                        Benjamin Riggs v. Rhode Island Public                 Time on May 12, 2015.
                                                    project on Tuesday, May 19, 2015,                       Utilities Commission Notice of Petition                 Dated: April 22, 2015.
                                                    starting at 9:00 a.m. All participants                  For Enforcement                                       Nathaniel J. Davis, Sr.,
                                                    should meet at Georgia Power’s Old                                                                            Deputy Secretary.
                                                    Salem Park, located at 1530 Old Salem                      Take notice that on April 21, 2015,
                                                                                                            Benjamin Riggs (Petitioner) filed a                   [FR Doc. 2015–09809 Filed 4–27–15; 8:45 am]
                                                    Road, Greensboro, Georgia 30642.
                                                                                                            Petition for Enforcement, pursuant to                 BILLING CODE 6717–01–P
                                                    Anyone with questions about the site
                                                                                                            section 210(h)(2) of the Public Utility
                                                    visit should contact Ms. Courtenay
                                                                                                            Regulatory Policies Act of 1978
                                                    O’Mara, Southern Company Generation,                                                                          DEPARTMENT OF ENERGY
                                                                                                            (PURPA), requesting the Federal Energy
                                                    at (404) 506–7219, or at g2oconeerel@
                                                                                                            Regulatory Commission (Commission)
                                                    southernco.com, on or before May 5,                     to exercise its authority and initiate                Federal Energy Regulatory
                                                    2015. Participants of the tour must                     enforcement action against the Rhode                  Commission
                                                    provide identification, sign a liability                Island Public Utilities Commission to                 [Project No. 4093–035]
                                                    waiver, and wear appropriate clothing                   ensure that PURPA regulations are
                                                    and closed toed shoes. If any participant               properly and lawfully implemented.                    McMahan Hydroelectric L.L.C.; Notice
                                                    attending any part of the site visit is                 Petitioner alleges that the Rhode Island              of Application Tendered for Filing With
                                                    disabled or has special needs, please                   Public Utility Commission on August                   the Commission and Soliciting
                                                    send an email to Oconee Relicensing at                  16, 2010, as directed by the Rhode                    Additional Study Requests and
                                                    g2oconeerel@southernco.com.                             Island General Assembly, approved a                   Establishing Procedural Schedule for
                                                                                                            20-year Purchase Power Agreement                      Relicensing and a Deadline for
                                                    Meeting Objectives
                                                                                                            between Deepwater Wind Block Island,                  Submission of Final Amendments
                                                       At the scoping meetings, Commission                  LLC and National Grid that appears to
                                                                                                            constitute a violation of the Federal                    Take notice that the following
                                                    staff will: (1) Initiate scoping of the
                                                                                                            Power Act, to include 16 U.S.C. 791 et                hydroelectric application has been filed
                                                    issues; (2) review and discuss existing
                                                                                                            seq., 16 U.S.C. 824, and the Supremacy                with the Commission and is available
                                                    conditions and resource management
                                                                                                            Clause of the U.S. Constitution.                      for public inspection.
                                                    objectives; (3) review and discuss                                                                               a. Type of Application: Subsequent
                                                    existing information and identify                          Any person desiring to intervene or to
                                                                                                            protest this filing must file in                      license.
                                                    preliminary information and study                                                                                b. Project No.: P–4093–035.
                                                    needs; (4) review and discuss the                       accordance with Rules 211 and 214 of                     c. Date filed: March 30, 2015.
                                                    process plan and schedule for pre-filing                the Commission’s Rules of Practice and                   d. Applicant: McMahan Hydroelectric
                                                    activities that incorporates the time                   Procedure (18 CFR 385.211, 385.214).                  L.L.C.
                                                    frames provided for in Part 5 of the                    Protests will be considered by the                       e. Name of Project: Bynum
                                                    Commission’s regulations and, to the                    Commission in determining the                         Hydroelectric Project.
                                                    extent possible, maximizes coordination                 appropriate action to be taken, but will                 f. Location: On the Haw River, in
                                                    of federal, state, and tribal permitting                not serve to make protestants parties to              Chatham County, North Carolina. No
                                                    and certification processes; and (5)                    the proceeding. Any person wishing to                 federal lands are occupied by the project
                                                    discuss the appropriateness of any                      become a party must file a notice of                  works or located within the project
                                                    federal or state agency or Indian tribe                 intervention or motion to intervene, as               boundary.
                                                    acting as a cooperating agency for                      appropriate. Such notices, motions, or                   g. Filed Pursuant to: Federal Power
                                                    development of an environmental                         protests must be filed on or before the               Act 16 U.S.C. 791(a)–825(r).
                                                                                                            comment date. Anyone filing a motion                     h. Applicant Contact: Andrew J.
asabaliauskas on DSK5VPTVN1PROD with NOTICES




                                                    document.
                                                                                                            to intervene or protest must serve a copy             McMahan, President, McMahan
                                                       Meeting participants should come                     of that document on the Petitioner.                   Hydroelectric L.L.C., 105 Durham
                                                    prepared to discuss their issues and/or                    The Commission encourages                          Eubanks Road, Pittsboro, NC 27312l;
                                                    concerns. Please review the PAD in                      electronic submission of protests and                 (336) 509–2148; email—
                                                    preparation for the scoping meetings.                   interventions in lieu of paper using the              mcmahanhydro@gmail.com.
                                                    Directions on how to obtain a copy of                   ‘‘eFiling’’ link at http://www.ferc.gov.                 i. FERC Contact: Sean Murphy at
                                                    the PAD and SD1 are included in item                    Persons unable to file electronically                 (202) 502–6145; or email at
                                                    n. of this document.                                    should submit an original and 5 copies                sean.murphy@ferc.gov.


                                               VerDate Sep<11>2014   18:18 Apr 27, 2015   Jkt 235001   PO 00000   Frm 00030   Fmt 4703   Sfmt 4703   E:\FR\FM\28APN1.SGM   28APN1



Document Created: 2015-12-16 08:35:19
Document Modified: 2015-12-16 08:35:19
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
DatesWednesday, May 20, 2015.
FR Citation80 FR 23524 

2025 Federal Register | Disclaimer | Privacy Policy