80_FR_23613 80 FR 23532 - Bison Peak Pumped Storage, LLC; Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications

80 FR 23532 - Bison Peak Pumped Storage, LLC; Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 80, Issue 81 (April 28, 2015)

Page Range23532-23533
FR Document2015-09840

Federal Register, Volume 80 Issue 81 (Tuesday, April 28, 2015)
[Federal Register Volume 80, Number 81 (Tuesday, April 28, 2015)]
[Notices]
[Pages 23532-23533]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2015-09840]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 14201-001]


Bison Peak Pumped Storage, LLC; Notice of Preliminary Permit 
Application Accepted for Filing and Soliciting Comments, Motions To 
Intervene, and Competing Applications

    On January 2, 2015, the Bison Peak Pumped Storage, LLC., filed an 
application for a successive preliminary permit, pursuant to section 
4(f) of the Federal Power Act (FPA), proposing to study the feasibility 
of the Bison Peak Pumped Storage Project (Bison Peak Project or 
project) to be located in the Tehachapi Mountains south of Tehachapi, 
Kern County, California. The sole purpose of a preliminary permit, if 
issued, is to grant the permit holder priority to file a license 
application during the permit term. A preliminary permit does not 
authorize the permit holder to perform any land-disturbing activities 
or otherwise enter upon lands or waters owned by others without the 
owners' express permission.
    The proposed project would be a closed-loop pumped storage project 
with an upper reservoir and the applicant has proposed three 
alternatives for the placement of a lower reservoir, termed ``West,'' 
``South,'' and ``East''. Water for the initial fill of each of the 
alternatives would be obtained from local water agency infrastructure 
via a route that would be identified during studies.
    A ring dam of varying heights and a perimeter of 6,000 feet would 
form the project's upper reservoir. The upper reservoir would have a 
total storage capacity of 4,196 acre-feet and a surface area of 45.4 
acres at an elevation of 7,800 feet mean sea level (msl) and a concrete 
lined intake/tailrace facility. The upper reservoir would be connected 
to one of the three proposed lower reservoir alternatives as described 
below.
    The West lower reservoir alternative would consist of the 
following: (1) The upper reservoir; (2) a 43-acre lower reservoir at 
5,380 feet msl created by a dam with a crest height of 250 feet, crest 
length of 1,435 feet, and a storage capacity of 5,347 acre-feet; (3) 
four 10-foot diameter, 5,890-foot-long penstocks from the concrete 
lined intake/tailrace facility at the upper reservoir; (4) an 
underground powerhouse with four 250-megawatt (MW) reversible pump-
turbines; (5) an intake/tailrace facility; and (6) appurtenant 
facilities. The estimated annual generation of the Bison Peak Pumped 
Storage Project West lower reservoir alternative would be about 2,190 
gigawatt-hours.
    The South lower reservoir alternative proposal would consist of the 
following: (1) The upper reservoir; (2) a 41.8-acre lower reservoir at 
4,875 feet msl created by a dam with a crest height of 260 feet, crest 
length of up to 1,285 feet, and a storage capacity of 4,616 acre-feet; 
(3) four 10-foot diameter, 9,420-foot-long penstocks from the concrete 
lined intake/tailrace facility at the upper reservoir to; (4) an 
underground powerhouse with four 250-megawatt (MW) reversible pump-
turbines; (5) an intake/tailrace facility; and (6) appurtenant 
facilities. The estimated annual generation of the Bison Peak Pumped 
Storage Project South lower reservoir alternative would be about 2,190 
gigawatt-hours.
    The East lower reservoir alternative would consist of the 
following: (1) The upper reservoir; (2) a 47-acre lower reservoir at 
5,800 feet msl created by a dam with a crest height of 320 feet, crest 
length of 1,150 feet, and a storage capacity of 5,724 acre-feet; (3) 
three 12-foot diameter, 5,890-foot-long penstocks from the concrete 
lined intake/tailrace facility at the upper reservoir to; (4) an 
underground powerhouse with three 250-megawatt (MW) reversible pump-
turbines; (5) an intake/tailrace facility; and (6) appurtenant 
facilities. The estimated annual generation of the Bison Peak Pumped 
Storage Project East lower reservoir alternative would be about 1,642 
gigawatt-hours.
    Applicant Contact: Mario Lucchese, Bison Peak Pumped Storage, LLC. 
9795 Cabrini Dr., Ste. 206, Burbank, CA 91504; phone: (818) 767-5552.
    FERC Contact: Matt Buhyoff; phone: (202) 502-6824.
    Deadline for filing comments, motions to intervene, competing 
applications (without notices of intent), or notices of intent to file 
competing applications: 60 days from the issuance of this notice. 
Competing applications and notices of intent must meet the requirements 
of 18 CFR 4.36.
    The Commission strongly encourages electronic filing. Please file 
comments, motions to intervene, notices of intent, and competing 
applications using the Commission's eFiling system at http://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief 
comments up to 6,000 characters, without prior registration, using the 
eComment system at http://www.ferc.gov/docs-filing/ecomment.asp. You 
must include your name and contact information at the end of your 
comments. For assistance, please contact FERC Online Support at 
[email protected], (866)

[[Page 23533]]

208-3676 (toll free), or (202) 502-8659 (TTY). In lieu of electronic 
filing, please send a paper copy to: Kimberly D. Bose, Secretary, 
Federal Energy Regulatory Commission, 888 First Street NE., Washington, 
DC 20426. The first page of any filing should include docket number P-
14201-001.
    More information about this project, including a copy of the 
application, can be viewed or printed on the ``eLibrary'' link of 
Commission's Web site at http://www.ferc.gov/docs-filing/elibrary.asp. 
Enter the docket number (P-14201) in the docket number field to access 
the document. For assistance, contact FERC Online Support.

    Dated: April 14, 2015.
 Kimberly D. Bose,
 Secretary.
[FR Doc. 2015-09840 Filed 4-27-15; 8:45 am]
 BILLING CODE 6717-01-P



                                                    23532                          Federal Register / Vol. 80, No. 81 / Tuesday, April 28, 2015 / Notices

                                                      If we publish and distribute the EA,                  DEPARTMENT OF ENERGY                                  Bison Peak Pumped Storage Project
                                                    copies will be sent to the environmental                                                                      West lower reservoir alternative would
                                                    mailing list for public review and                      Federal Energy Regulatory                             be about 2,190 gigawatt-hours.
                                                    comment. If you would prefer to receive                 Commission                                               The South lower reservoir alternative
                                                    a paper copy of the document instead of                 [Project No. 14201–001]
                                                                                                                                                                  proposal would consist of the following:
                                                    the CD version or would like to remove                                                                        (1) The upper reservoir; (2) a 41.8-acre
                                                    your name from the mailing list, please                 Bison Peak Pumped Storage, LLC;                       lower reservoir at 4,875 feet msl created
                                                    return the attached Information Request                 Notice of Preliminary Permit                          by a dam with a crest height of 260 feet,
                                                    (appendix 2).                                           Application Accepted for Filing and                   crest length of up to 1,285 feet, and a
                                                                                                            Soliciting Comments, Motions To                       storage capacity of 4,616 acre-feet; (3)
                                                    Becoming an Intervenor                                                                                        four 10-foot diameter, 9,420-foot-long
                                                                                                            Intervene, and Competing Applications
                                                      In addition to involvement in the EA                                                                        penstocks from the concrete lined
                                                    scoping process, you may want to                           On January 2, 2015, the Bison Peak                 intake/tailrace facility at the upper
                                                    become an ‘‘intervenor’’ which is an                    Pumped Storage, LLC., filed an                        reservoir to; (4) an underground
                                                    official party to the Commission’s                      application for a successive preliminary              powerhouse with four 250-megawatt
                                                    proceeding. Intervenors play a more                     permit, pursuant to section 4(f) of the               (MW) reversible pump-turbines; (5) an
                                                    formal role in the process and are able                 Federal Power Act (FPA), proposing to                 intake/tailrace facility; and (6)
                                                    to file briefs, appear at hearings, and be              study the feasibility of the Bison Peak               appurtenant facilities. The estimated
                                                    heard by the courts if they choose to                   Pumped Storage Project (Bison Peak                    annual generation of the Bison Peak
                                                    appeal the Commission’s final ruling.                   Project or project) to be located in the              Pumped Storage Project South lower
                                                    An intervenor formally participates in                  Tehachapi Mountains south of                          reservoir alternative would be about
                                                    the proceeding by filing a request to                   Tehachapi, Kern County, California. The               2,190 gigawatt-hours.
                                                    intervene. Instructions for becoming an                 sole purpose of a preliminary permit, if                 The East lower reservoir alternative
                                                    intervenor are in the User’s Guide under                issued, is to grant the permit holder                 would consist of the following: (1) The
                                                    the ‘‘e-filing’’ link on the Commission’s               priority to file a license application                upper reservoir; (2) a 47-acre lower
                                                    Web site.                                               during the permit term. A preliminary                 reservoir at 5,800 feet msl created by a
                                                                                                            permit does not authorize the permit                  dam with a crest height of 320 feet, crest
                                                    Additional Information                                  holder to perform any land-disturbing                 length of 1,150 feet, and a storage
                                                       Additional information about the                     activities or otherwise enter upon lands              capacity of 5,724 acre-feet; (3) three 12-
                                                    project is available from the                           or waters owned by others without the                 foot diameter, 5,890-foot-long penstocks
                                                    Commission’s Office of External Affairs,                owners’ express permission.                           from the concrete lined intake/tailrace
                                                    at (866) 208–FERC, or on the FERC Web                      The proposed project would be a                    facility at the upper reservoir to; (4) an
                                                    site at www.ferc.gov using the                          closed-loop pumped storage project                    underground powerhouse with three
                                                    ‘‘eLibrary’’ link. Click on the eLibrary                with an upper reservoir and the                       250-megawatt (MW) reversible pump-
                                                    link, click on ‘‘General Search’’ and                   applicant has proposed three                          turbines; (5) an intake/tailrace facility;
                                                    enter the docket number, excluding the                  alternatives for the placement of a lower             and (6) appurtenant facilities. The
                                                    last three digits in the Docket Number                  reservoir, termed ‘‘West,’’ ‘‘South,’’ and            estimated annual generation of the
                                                    field (i.e., CP15–88). Be sure you have                 ‘‘East’’. Water for the initial fill of each          Bison Peak Pumped Storage Project East
                                                    selected an appropriate date range. For                 of the alternatives would be obtained                 lower reservoir alternative would be
                                                    assistance, please contact FERC Online                  from local water agency infrastructure                about 1,642 gigawatt-hours.
                                                    Support at FercOnlineSupport@ferc.gov                   via a route that would be identified                     Applicant Contact: Mario Lucchese,
                                                    or toll free at (866) 208–3676, or for                  during studies.                                       Bison Peak Pumped Storage, LLC. 9795
                                                    TTY, contact (202) 502–8659. The                           A ring dam of varying heights and a                Cabrini Dr., Ste. 206, Burbank, CA
                                                    eLibrary link also provides access to the               perimeter of 6,000 feet would form the                91504; phone: (818) 767–5552.
                                                    texts of formal documents issued by the                 project’s upper reservoir. The upper                     FERC Contact: Matt Buhyoff; phone:
                                                    Commission, such as orders, notices,                    reservoir would have a total storage                  (202) 502–6824.
                                                    and rulemakings.                                        capacity of 4,196 acre-feet and a surface                Deadline for filing comments, motions
                                                       In addition, the Commission now                      area of 45.4 acres at an elevation of                 to intervene, competing applications
                                                    offers a free service called eSubscription              7,800 feet mean sea level (msl) and a                 (without notices of intent), or notices of
                                                    which allows you to keep track of all                   concrete lined intake/tailrace facility.              intent to file competing applications: 60
                                                    formal issuances and submittals in                      The upper reservoir would be connected                days from the issuance of this notice.
                                                    specific dockets. This can reduce the                   to one of the three proposed lower                    Competing applications and notices of
                                                    amount of time you spend researching                    reservoir alternatives as described                   intent must meet the requirements of 18
                                                    proceedings by automatically providing                  below.                                                CFR 4.36.
                                                    you with notification of these filings,                    The West lower reservoir alternative                  The Commission strongly encourages
                                                    document summaries, and direct links                    would consist of the following: (1) The               electronic filing. Please file comments,
                                                    to the documents. Go to www.ferc.gov/                   upper reservoir; (2) a 43-acre lower                  motions to intervene, notices of intent,
                                                    docs-filing/esubscription.asp.                          reservoir at 5,380 feet msl created by a              and competing applications using the
                                                       Finally, public meetings or site visits              dam with a crest height of 250 feet, crest            Commission’s eFiling system at http://
                                                    will be posted on the Commission’s                      length of 1,435 feet, and a storage                   www.ferc.gov/docs-filing/efiling.asp.
                                                                                                            capacity of 5,347 acre-feet; (3) four 10-             Commenters can submit brief comments
asabaliauskas on DSK5VPTVN1PROD with NOTICES




                                                    calendar located at www.ferc.gov/
                                                    EventCalendar/EventsList.aspx along                     foot diameter, 5,890-foot-long penstocks              up to 6,000 characters, without prior
                                                    with other related information.                         from the concrete lined intake/tailrace               registration, using the eComment system
                                                                                                            facility at the upper reservoir; (4) an               at http://www.ferc.gov/docs-filing/
                                                      Dated: April 17, 2015.                                underground powerhouse with four                      ecomment.asp. You must include your
                                                    Kimberly D. Bose,                                       250-megawatt (MW) reversible pump-                    name and contact information at the end
                                                    Secretary.                                              turbines; (5) an intake/tailrace facility;            of your comments. For assistance,
                                                    [FR Doc. 2015–09746 Filed 4–27–15; 8:45 am]             and (6) appurtenant facilities. The                   please contact FERC Online Support at
                                                    BILLING CODE 6717–01–P                                  estimated annual generation of the                    FERCOnlineSupport@ferc.gov, (866)


                                               VerDate Sep<11>2014   18:18 Apr 27, 2015   Jkt 235001   PO 00000   Frm 00037   Fmt 4703   Sfmt 4703   E:\FR\FM\28APN1.SGM   28APN1


                                                                                   Federal Register / Vol. 80, No. 81 / Tuesday, April 28, 2015 / Notices                                                  23533

                                                    208–3676 (toll free), or (202) 502–8659                 DEPARTMENT OF ENERGY                                     Applicant Contact: Paul Maselbas,
                                                    (TTY). In lieu of electronic filing, please                                                                    Los Angeles County Public Works,
                                                    send a paper copy to: Kimberly D. Bose,                 Federal Energy Regulatory                              Waterworks Division, 900 S. Freemont
                                                    Secretary, Federal Energy Regulatory                    Commission                                             Ave., Alhambra, CA 91803, (626) 300–
                                                    Commission, 888 First Street NE.,                                                                              3302.
                                                    Washington, DC 20426. The first page of                 [Docket No., CD15–23–000]                                FERC Contact: Robert Bell, Phone No.
                                                    any filing should include docket                                                                               (202) 502–6062, email:
                                                    number P–14201–001.                                     Los Angeles County Public Works;                       robert.bell@ferc.gov.
                                                                                                            Notice of Preliminary Determination of                   Qualifying Conduit Hydropower
                                                       More information about this project,                                                                        Facility Description: The proposed
                                                                                                            a Qualifying Conduit Hydropower
                                                    including a copy of the application, can                Facility and Soliciting Comments and                   project would consist of: (1) an existing
                                                    be viewed or printed on the ‘‘eLibrary’’                Motions To Intervene                                   51-foot by 38-foot building, which will
                                                    link of Commission’s Web site at                                                                               serve as the powerhouse; (2) an existing
                                                    http://www.ferc.gov/docs-filing/                          On April 14, 2015, Los Angeles                       30-inch-diameter pipe to the treatment
                                                    elibrary.asp. Enter the docket number                   County Public Works filed a notice of                  plant; (3) one proposed turbine-
                                                    (P–14201) in the docket number field to                 intent to construct a qualifying conduit               generator unit with an installed capacity
                                                    access the document. For assistance,                    hydropower facility, pursuant to section               of 215 kW, which will replace pressure
                                                    contact FERC Online Support.                            30 of the Federal Power Act (FPA), as                  reducing valve CV5; (4) an existing 125-
                                                      Dated: April 14, 2015.                                amended by section 4 of the                            foot-long, 30-inch-diameter discharge
                                                                                                            Hydropower Regulatory Efficiency Act                   pipe that delivers potable water to
                                                    Kimberly D. Bose,
                                                                                                            of 2013 (HREA). The proposed M7W                       storage tanks for distribution to parts of
                                                    Secretary.                                              Pressure Reducing Station Hydroelectric                the City of Palmdale, California and (5)
                                                    [FR Doc. 2015–09840 Filed 4–27–15; 8:45 am]             Project would have an installed capacity               appurtenant facilities. The proposed
                                                    BILLING CODE 6717–01–P                                  of 215 kilowatts (kW) and would be                     project would have an estimated annual
                                                                                                            located at the Quartz Hill Water                       generating capacity of 730 megawatt-
                                                                                                            Treatment Plant, which treats water for                hours.
                                                                                                            municipal consumption. The project                       A qualifying conduit hydropower
                                                                                                            would be located near the Town of                      facility is one that is determined or
                                                                                                            Palmdale in Los Angeles County,                        deemed to meet all of the criteria shown
                                                                                                            California.                                            in the table below.

                                                                                      TABLE 1—CRITERIA FOR QUALIFYING CONDUIT HYDROPOWER FACILITY
                                                                                                                                                                                                        Satisfies
                                                           Statutory provision                                                            Description                                                    (Y/N)

                                                    FPA 30(a)(3)(A), as amended            The conduit the facility uses is a tunnel, canal, pipeline, aqueduct, flume, ditch, or similar                  Y
                                                      by HREA.                               manmade water conveyance that is operated for the distribution of water for agricultural,
                                                                                             municipal, or industrial consumption and not primarily for the generation of electricity.
                                                    FPA 30(a)(3)(C)(i), as amended         The facility is constructed, operated, or maintained for the generation of electric power and                   Y
                                                      by HREA.                               uses for such generation only the hydroelectric potential of a non-federally owned conduit.
                                                    FPA 30(a)(3)(C)(ii), as amend-         The facility has an installed capacity that does not exceed 5 megawatts ..................................      Y
                                                      ed by HREA.
                                                    FPA 30(a)(3)(C)(iii), as amend-        On or before August 9, 2013, the facility is not licensed, or exempted from the licensing re-                   Y
                                                      ed by HREA.                           quirements of Part I of the FPA.



                                                      Preliminary Determination: Based                      deadline date for the particular                       facility meets the qualifying criteria
                                                    upon the above criteria, Commission                     proceeding.                                            must set forth their evidentiary basis.
                                                    staff preliminarily determines that the                    Filing and Service of Responsive                       The Commission strongly encourages
                                                    proposal satisfies the requirements for a               Documents: All filings must (1) bear in                electronic filing. Please file motions to
                                                    qualifying conduit hydropower facility,                 all capital letters the ‘‘COMMENTS                     intervene and comments using the
                                                    which is not required to be licensed or                 CONTESTING QUALIFICATION FOR A                         Commission’s eFiling system at http://
                                                    exempted from licensing.                                CONDUIT HYDROPOWER FACILITY’’                          www.ferc.gov/docs-filing/efiling.asp.
                                                      Comments and Motions to Intervene:                    or ‘‘MOTION TO INTERVENE,’’ as                         Commenters can submit brief comments
                                                    Deadline for filing comments contesting                 applicable; (2) state in the heading the               up to 6,000 characters, without prior
                                                    whether the facility meets the qualifying               name of the applicant and the project                  registration, using the eComment system
                                                    criteria is 45 days from the issuance                   number of the application to which the                 at http://www.ferc.gov/docs-filing/
                                                    date of this notice.                                    filing responds; (3) state the name,                   ecomment.asp. You must include your
                                                                                                            address, and telephone number of the                   name and contact information at the end
                                                      Deadline for filing motions to
                                                                                                                                                                   of your comments. For assistance,
asabaliauskas on DSK5VPTVN1PROD with NOTICES




                                                    intervene is 30 days from the issuance                  person filing; and (4) otherwise comply
                                                                                                            with the requirements of sections                      please contact FERC Online Support at
                                                    date of this notice.
                                                                                                            385.2001 through 385.2005 of the                       FERCOnlineSupport@ferc.gov, (866)
                                                      Anyone may submit comments or a                                                                              208–3676 (toll free), or (202) 502–8659
                                                    motion to intervene in accordance with                  Commission’s regulations.1 All
                                                                                                                                                                   (TTY). In lieu of electronic filing, please
                                                    the requirements of Rules of Practice                   comments contesting Commission staff’s
                                                                                                                                                                   send a paper copy to: Secretary, Federal
                                                    and Procedure, 18 CFR 385.210 and                       preliminary determination that the
                                                                                                                                                                   Energy Regulatory Commission, 888
                                                    385.214. Any motions to intervene must                                                                         First Street NE., Washington, DC 20426.
                                                    be received on or before the specified                    1 18   CFR 385.2001–2005 (2014).                     A copy of all other filings in reference


                                               VerDate Sep<11>2014   18:18 Apr 27, 2015   Jkt 235001   PO 00000   Frm 00038   Fmt 4703   Sfmt 4703   E:\FR\FM\28APN1.SGM   28APN1



Document Created: 2015-12-16 08:36:09
Document Modified: 2015-12-16 08:36:09
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation80 FR 23532 

2025 Federal Register | Disclaimer | Privacy Policy
USC | CFR | eCFR