Section 101(c) of the Federal Mine Safety and Health Act of 1977 and 30 CFR part 44 govern the application, processing, and disposition of petitions for modification. This Federal Register Notice notifies the public that MSHA has investigated and issued a final decision on certain mine operator petitions to modify a safety standard.

Federal Register, Volume 80 Issue 83 (Thursday, April 30, 2015)
[Federal Register Volume 80, Number 83 (Thursday, April 30, 2015)]
[Notices]
[Pages 24286-24287]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2015-10092]


-----------------------------------------------------------------------

DEPARTMENT OF LABOR

Mine Safety and Health Administration


Affirmative Decisions on Petitions for Modification Granted in 
Whole or in Part

AGENCY: Mine Safety and Health Administration (MSHA), Labor.

ACTION: Notice.

-----------------------------------------------------------------------

SUMMARY: Section 101(c) of the Federal Mine Safety and Health Act of 
1977 and 30 CFR part 44 govern the application, processing, and 
disposition of petitions for modification. This Federal Register Notice 
notifies the public that MSHA has investigated and issued a final 
decision on certain mine operator petitions to modify a safety 
standard.

ADDRESSES: Copies of the final decisions are posted on MSHA's Web site 
at http://www.msha.gov/indexes/petition.htm. The public may inspect the 
petitions and final decisions during normal business hours in MSHA's 
Office of Standards, Regulations, and Variances, 1100 Wilson Boulevard, 
Room 2349, Arlington, Virginia 22209. All visitors must first stop at 
the receptionist desk on the 21st Floor to sign-in.

FOR FURTHER INFORMATION CONTACT: Roslyn B. Fontaine, Office of 
Standards, Regulations, and Variances at 202-693-9475 (Voice), 
[email protected] (Email), or 202-693-9441 (Telefax), or Barbara 
Barron at 202-693-9447 (Voice), [email protected] (Email), or 202-
693-9441 (Telefax). [These are not toll-free numbers].

SUPPLEMENTARY INFORMATION: 

I. Introduction

    Under section 101 of the Federal Mine Safety and Health Act of 
1977, a mine operator may petition and the Secretary of Labor 
(Secretary) may modify the application of a mandatory safety standard 
to that mine if the Secretary determines that: (1) An alternative 
method exists that will guarantee no

[[Page 24287]]

less protection for the miners affected than that provided by the 
standard; or (2) that the application of the standard will result in a 
diminution of safety to the affected miners.
    MSHA bases the final decision on the petitioner's statements, any 
comments and information submitted by interested persons, and a field 
investigation of the conditions at the mine. In some instances, MSHA 
may approve a petition for modification on the condition that the mine 
operator complies with other requirements noted in the decision.

II. Granted Petitions for Modification

    On the basis of the findings of MSHA's investigation, and as 
designee of the Secretary, MSHA has granted or partially granted the 
following petitions for modification:
     Docket Number: M-2014-026-C.
    FR Notice: 79 FR 48256 (8/15/2014).
    Petitioner: Covol Fuels No. 3, LLC, 10156 US Hwy 25 E, Pineville, 
Kentucky 40977.
    Mine: Crockett, MSHA I.D. No. 15-12682, located in Bell County, 
Kentucky; Coarse Coal Refuse Fill #5, Site I.D. No. KY07-12682-05.
    Regulation Affected: 30 CFR 77.214(a) (Refuse piles; general).

     Docket Number: M-2014-031-C.
    FR Notice: 79 FR 64623 (10/30/2014).
    Petitioner: Sunrise Coal LLC, 12661 Agricare Road, Oaktown, Indiana 
47561.
    Mine: Oaktown Fuels Mine No. 1, MSHA I.D. No. 12-02394, located in 
Knox County, Indiana.
    Regulation Affected: 30 CFR 75.1700 (Oil and gas wells).

     Docket Number: M-2014-032-C.
    FR Notice: 79 FR 64623 (10/30/2014).
    Petitioner: Sunrise Coal LLC, 12661 Agricare Road, Oaktown, Indiana 
47561.
    Mine: Oaktown Fuels Mine No. 2, MSHA I.D. No. 12-02418, located in 
Knox County, Indiana.
    Regulation Affected: 30 CFR 75.1700 (Oil and gas wells).

    Dated: April 27, 2015.
Sheila McConnell,
Acting Director, Office of Standards, Regulations, and Variances.
[FR Doc. 2015-10092 Filed 4-29-15; 8:45 am]
 BILLING CODE 4510-43-P



                                                  24286                         Federal Register / Vol. 80, No. 83 / Thursday, April 30, 2015 / Notices

                                                     (2) Major maintenance requiring the                     (8) The ground fault and ground                    all circuits are in their normal state. At
                                                  raising/lowering of the boom/mast                       check circuits will be disabled                       this time normal work procedures can
                                                  would only be performed on an as                        provided:                                             begin.
                                                  needed basis, which could span long                        (a) The internal grounding conductor                  The petitioner asserts that this
                                                  periods of time. Therefore, training and                of the trailing cable has been tested and             proposed alternative method of the
                                                  review of the procedure would only be                   is continuous from the frame of the                   existing standard will not result in a
                                                  conducted prior to this need. At such                   dragline to the grounding resistor                    diminution of safety to the miners
                                                  time, all persons involved in the process               located at the substation. Utilizing the              affected.
                                                  would be trained and retrained.                         ground check circuit and disconnecting                  Dated: April 27, 2015.
                                                     The petitioner states that:                          the pilot circuit at the machine frame,               Sheila McConnell,
                                                     (1) Coyote Creek employees, its                      and verifying the circuit breaker cannot
                                                                                                                                                                Acting Director, Office of Standards,
                                                  contractors, and affected persons will be               be closed, will be an acceptable test.                Regulations, and Variances.
                                                  trained on the requirements of the                      Resistance measurements will also be
                                                                                                                                                                [FR Doc. 2015–10093 Filed 4–29–15; 8:45 am]
                                                  procedure at the mine.                                  used to assure the ground conductor is
                                                                                                                                                                BILLING CODE 4510–43–P
                                                     (2) The procedure will be coordinated                continuous. The grounding resistor will
                                                  by a Coyote Creek Mine maintenance                      be tested to assure it is properly
                                                  supervisor and, if present, the                         connected, is not open, or is not                     DEPARTMENT OF LABOR
                                                  contractor’s representative will assist.                shorted.
                                                  At least two MSHA qualified                                (b) Normal short circuit protection                Mine Safety and Health Administration
                                                  electricians will be present at all times               will be provided at all times. The over
                                                  during the procedure.                                   current relay setting may be increased                Affirmative Decisions on Petitions for
                                                                                                          up to 100 percent above its normal                    Modification Granted in Whole or in
                                                     (3) The number of persons required
                                                                                                          setting.                                              Part
                                                  on board the machine will be limited.                      (9) During the boom raising/lowering
                                                  An MSHA qualified electrician, dragline                 procedure an MSHA qualified                           AGENCY: Mine Safety and Health
                                                  operator, and the dragline oiler will be                electrician will be positioned at the                 Administration (MSHA), Labor.
                                                  permitted on the machine. The Coyote                    substation dedicated to monitor the                   ACTION: Notice.
                                                  Creek maintenance supervisor and                        grounding circuit. The MSHA qualified
                                                  contractor’s representative may either be                                                                     SUMMARY:   Section 101(c) of the Federal
                                                                                                          electrician will be able to detect a
                                                  on board or at a location on the ground                                                                       Mine Safety and Health Act of 1977 and
                                                                                                          grounded phase condition or an open
                                                  to assist in the coordination.                          ground wire condition. The MSHA                       30 CFR part 44 govern the application,
                                                     (4) The affected area under the boom                 qualified electrician at the substation               processing, and disposition of petitions
                                                  will be secured to prevent persons from                 will at all times maintain                            for modification. This Federal Register
                                                  entering and/or contacting the frame of                 communications with an MSHA                           Notice notifies the public that MSHA
                                                  the machine during the ‘‘boom raising/                  qualified electrician at the dragline. If a           has investigated and issued a final
                                                  lowering’’. The area will be secured and                grounded phase condition or an open                   decision on certain mine operator
                                                  only those persons identified in Item #3                ground wire should occur during the                   petitions to modify a safety standard.
                                                  will be permitted inside the secured                    process, the MSHA qualified electrician               ADDRESSES: Copies of the final decisions
                                                  area. At no time will anyone be                         at the substation will notify the MSHA                are posted on MSHA’s Web site at
                                                  permitted under the boom or close to                    qualified electrician at the dragline. All            http://www.msha.gov/indexes/
                                                  the boom.                                               persons on board the machine must be                  petition.htm. The public may inspect
                                                     (5) Communication between the                        aware of the condition and must remain                the petitions and final decisions during
                                                  dragline operator, the MSHA qualified                   on board the machine. The boom must                   normal business hours in MSHA’s
                                                  electrician at the dragline, the MSHA                   be lowered to the ground or controlled                Office of Standards, Regulations, and
                                                  qualified electrician at the substation,                and electrical circuit deenergized,                   Variances, 1100 Wilson Boulevard,
                                                  the Coyote Creek maintenance                            locked and tagged out. The circuit must               Room 2349, Arlington, Virginia 22209.
                                                  supervisor, and the contractor’s                        remain deenergized until the condition                All visitors must first stop at the
                                                  representative, if present, will be a                   is corrected. The ground fault and                    receptionist desk on the 21st Floor to
                                                  dedicated channel on the company’s                      ground check circuits will be reinstalled             sign-in.
                                                  two-way radio.                                          prior to reenergizing and testing the                 FOR FURTHER INFORMATION CONTACT:
                                                     (6) An MSHA qualified electrician                    machine. Once circuits have been tested               Roslyn B. Fontaine, Office of Standards,
                                                  will complete an examination of all                     and no adverse conditions are present,                Regulations, and Variances at 202–693–
                                                  electrical components that will be                      the boom raising/lowering procedure, as               9475 (Voice), fontaine.roslyn@dol.gov
                                                  energized. The examination will be                      outlined above, will be resumed.                      (Email), or 202–693–9441 (Telefax), or
                                                  done within two hours prior to the                         (10) During the construction/                      Barbara Barron at 202–693–9447
                                                  boom raising/lowering process. A record                 maintenance procedure, persons cannot                 (Voice), barron.barbara@dol.gov
                                                  of this examination will be made                        get on or off the dragline while the                  (Email), or 202–693–9441 (Telefax).
                                                  available to interested parties. The                    ground check ground fault circuits are                [These are not toll-free numbers].
                                                  machine will be deenergized to perform                  disabled unless the circuit is                        SUPPLEMENTARY INFORMATION:
                                                  this examination.                                       deenergized, locked and tagged out as
                                                     (7) After the examination is                         verified by the MSHA qualified                        I. Introduction
mstockstill on DSK4VPTVN1PROD with NOTICES




                                                  completed, the electrical components                    electrician at the substation.                           Under section 101 of the Federal Mine
                                                  necessary to complete the boom raising/                    (11) After the boom raising/lowering               Safety and Health Act of 1977, a mine
                                                  lowering process will be energized to                   is completed, the MSHA qualified                      operator may petition and the Secretary
                                                  assure they are operating properly as                   electrician at the substation will restore            of Labor (Secretary) may modify the
                                                  determined by an MSHA qualified                         all the protective devices to their normal            application of a mandatory safety
                                                  electrician. When completed, the                        state. When this has been completed,                  standard to that mine if the Secretary
                                                  machine will be deenergized and locked                  the MSHA qualified electrician at the                 determines that: (1) An alternative
                                                  out.                                                    substation will notify the dragline that              method exists that will guarantee no


                                             VerDate Sep<11>2014   17:01 Apr 29, 2015   Jkt 235001   PO 00000   Frm 00057   Fmt 4703   Sfmt 4703   E:\FR\FM\30APN1.SGM   30APN1


                                                                                Federal Register / Vol. 80, No. 83 / Thursday, April 30, 2015 / Notices                                           24287

                                                  less protection for the miners affected                 U.S.C. 552b), hereby gives notice of the              Tuesday, May 5, 2015
                                                  than that provided by the standard; or                  scheduling of meetings for the
                                                                                                                                                                Committee on Audit & Oversight (AO)
                                                  (2) that the application of the standard                transaction of National Science Board
                                                  will result in a diminution of safety to                business, as follows:                                 Open Session: 8:05–9:05 a.m.
                                                  the affected miners.                                    AGENCY: National Science Board, NSF.                  • Approval of February 2015 open
                                                    MSHA bases the final decision on the
                                                                                                          DATE AND TIME: May 5, 2015 from 8:00                    meeting minutes
                                                  petitioner’s statements, any comments
                                                  and information submitted by interested                 a.m. to 3:45 p.m. and May 6, 2015 from                • Committee Chairman’s opening
                                                  persons, and a field investigation of the               8:00 a.m. to 3:00 p.m. (EDT).                           remarks
                                                  conditions at the mine. In some                         PLACE: These meetings will be held at                 • Approval of OIG Semiannual Report
                                                  instances, MSHA may approve a                           the National Science Foundation, 4201                   materials
                                                  petition for modification on the                        Wilson Blvd., Rooms 1235, Arlington,                  • NSF FY 2014 Merit Review Report
                                                  condition that the mine operator                        VA 22230. All visitors must contact the               • Inspector General’s update, including
                                                  complies with other requirements noted                  Board Office (call 703–292–7000 or send                 FY 2015 Financial Statement audit
                                                  in the decision.                                        an email message to                                     plans
                                                                                                          nationalsciencebrd@nsf.gov) at least 24               • Chief Financial Officer’s update
                                                  II. Granted Petitions for Modification
                                                                                                          hours prior to the meeting and provide                • Committee Chairman’s closing
                                                    On the basis of the findings of                       name and organizational affiliation.                    remarks
                                                  MSHA’s investigation, and as designee                   Visitors must report to the NSF visitor
                                                  of the Secretary, MSHA has granted or                                                                         Audit and Oversight Committee
                                                                                                          desk located in the lobby at the 9th and
                                                  partially granted the following petitions               N. Stuart Streets entrance to receive a               Closed Session: 9:05–9:35 a.m.
                                                  for modification:                                       visitor’s badge.
                                                    • Docket Number: M–2014–026–C.                                                                              • Approval of February 2015 closed
                                                                                                          WEBCAST INFORMATION: Public meetings                    meeting minutes
                                                    FR Notice: 79 FR 48256 (8/15/2014).
                                                                                                          and public portions of meetings will be               • Committee Chairman’s opening
                                                    Petitioner: Covol Fuels No. 3, LLC,
                                                                                                          webcast. To view the meetings, go to                    remarks
                                                  10156 US Hwy 25 E, Pineville,
                                                                                                          http://www.nsf.gov/nsb/notices/ and                   • Discussion of two-month grantee
                                                  Kentucky 40977.
                                                                                                          follow the instructions.                                salary policy
                                                    Mine: Crockett, MSHA I.D. No. 15–
                                                  12682, located in Bell County,                          UPDATES: Please refer to the National                 • Chairman’s closing remarks
                                                  Kentucky; Coarse Coal Refuse Fill #5,                   Science Board Web site for additional
                                                                                                          information. Meeting information and                  Committee on Strategy and Budget
                                                  Site I.D. No. KY07–12682–05.                                                                                  (CSB)
                                                    Regulation Affected: 30 CFR 77.214(a)                 schedule updates (time, place, subject
                                                  (Refuse piles; general).                                matter or status of meeting) may be                   Closed Session: 9:35–10:20 a.m.
                                                    • Docket Number: M–2014–031–C.                        found at http://www.nsf.gov/nsb/
                                                                                                          notices/.                                             • Committee Chairman’s remarks
                                                    FR Notice: 79 FR 64623 (10/30/2014).                                                                        • Approval of CSB closed minutes for
                                                    Petitioner: Sunrise Coal LLC, 12661                   AGENCY CONTACT: Jennie L. Moehlmann,                    the February 2015 meeting and March
                                                  Agricare Road, Oaktown, Indiana 47561.                  jmoehlma@nsf.gov, (703) 292–7000.                       2015 teleconference
                                                    Mine: Oaktown Fuels Mine No. 1,                       PUBLIC AFFAIRS CONTACT: Nadine Lymn,                  • NSF FY 2017 budget development
                                                  MSHA I.D. No. 12–02394, located in                      nlymn@nsf.gov, (703) 292–2490.                        • Performance Improvement Officer
                                                  Knox County, Indiana.
                                                                                                          STATUS: Portions open; portions closed.                 update on FY 2015–2017 strategic
                                                    Regulation Affected: 30 CFR 75.1700
                                                                                                                                                                  reviews
                                                  (Oil and gas wells).                                    Open Sessions
                                                    • Docket Number: M–2014–032–C.                                                                              Committee on Strategy and Budget
                                                                                                          May 5, 2015                                           (CSB)
                                                    FR Notice: 79 FR 64623 (10/30/2014).
                                                    Petitioner: Sunrise Coal LLC, 12661                   8:00–8:05 a.m. (Chairman’s                            Open Session: 10:30–10:45 a.m.
                                                  Agricare Road, Oaktown, Indiana 47561.                      introduction)
                                                    Mine: Oaktown Fuels Mine No. 2,                       8:05–9:05 a.m. (AO)                                   • Approval of CSB open minutes for
                                                  MSHA I.D. No. 12–02418, located in                                                                              February 2015 meeting and open joint
                                                                                                          10:30–10:45 a.m. (CSB)
                                                  Knox County, Indiana.                                                                                           CPP/CSB minutes for February 2015
                                                                                                          10:45–11:15 a.m. (CPP)                                • NSF FY 2016 budget update
                                                    Regulation Affected: 30 CFR 75.1700
                                                  (Oil and gas wells).                                    11:15–11:55 a.m. (Plenary)
                                                                                                                                                                Committee on Programs and Plans
                                                    Dated: April 27, 2015.                                May 6, 2015                                           (CPP)
                                                  Sheila McConnell,                                       10:45–11:25 a.m. (Plenary)                            Open Session: 10:45–11:15 a.m.
                                                  Acting Director, Office of Standards,                   12:30–1:15 p.m. (Plenary)
                                                  Regulations, and Variances.                                                                                   • Approval of open minutes of the
                                                                                                          1:15–3:00 p.m. (SEI)
                                                  [FR Doc. 2015–10092 Filed 4–29–15; 8:45 am]                                                                     February 2015 meeting
                                                  BILLING CODE 4510–43–P                                  Closed Sessions                                       • Committee Chairman’s remarks
                                                                                                          May 5, 2015                                           • Information item: Cornell High Energy
                                                                                                                                                                  Synchrotron Source (CHESS)
                                                  NATIONAL SCIENCE FOUNDATION                             9:05–9:35 a.m. (AO)                                   • Information item: Advanced LIGO
mstockstill on DSK4VPTVN1PROD with NOTICES




                                                                                                          9:35–10:20 a.m. (CSB)
                                                  Sunshine Act Meeting                                                                                          Plenary Board Meeting
                                                                                                          1:00–3:45 p.m. (CPP)
                                                                                                                                                                Open Session: 11:15–11:35 a.m.
                                                    The National Science Board, pursuant                  May 6, 2015
                                                  to NSF regulations (45 CFR part 614),                                                                         • Presentation by the President of NSB’s
                                                  the National Science Foundation Act, as                 8:00–8:30 a.m. (Plenary executive)                      2015 Public Service Award recipient,
                                                  amended (42 U.S.C. 1862n–5), and the                    8:30–10:30 a.m. (Plenary)                               the American Museum of Natural
                                                  Government in the Sunshine Act (5                       MATTERS TO BE DISCUSSED:                                History


                                             VerDate Sep<11>2014   17:01 Apr 29, 2015   Jkt 235001   PO 00000   Frm 00058   Fmt 4703   Sfmt 4703   E:\FR\FM\30APN1.SGM   30APN1



Document Created: 2018-02-21 10:14:44
Document Modified: 2018-02-21 10:14:44
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
ActionNotice.
ContactRoslyn B. Fontaine, Office of Standards, Regulations, and Variances at 202-693-9475 (Voice), [email protected] (Email), or 202-693-9441 (Telefax), or Barbara Barron at 202-693-9447 (Voice), [email protected] (Email), or 202- 693-9441 (Telefax). [These are not toll-free numbers].
FR Citation80 FR 24286 