80_FR_30169 80 FR 30069 - Florida Gas Transmission Company, LLC; Notice of Intent To Prepare an Environmental Assessment for the Proposed Jacksonville Expansion Project, and Request for Comments On Environmental Issues

80 FR 30069 - Florida Gas Transmission Company, LLC; Notice of Intent To Prepare an Environmental Assessment for the Proposed Jacksonville Expansion Project, and Request for Comments On Environmental Issues

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 80, Issue 100 (May 26, 2015)

Page Range30069-30071
FR Document2015-12615

Federal Register, Volume 80 Issue 100 (Tuesday, May 26, 2015)
[Federal Register Volume 80, Number 100 (Tuesday, May 26, 2015)]
[Notices]
[Pages 30069-30071]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2015-12615]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP15-144-000]


Florida Gas Transmission Company, LLC; Notice of Intent To 
Prepare an Environmental Assessment for the Proposed Jacksonville 
Expansion Project, and Request for Comments On Environmental Issues

    The staff of the Federal Energy Regulatory Commission (FERC or 
Commission) will prepare an environmental assessment (EA) that will 
discuss the environmental impacts of the Jacksonville Expansion Project 
(Project). The Project would involve constructing and operating 
interstate natural gas transmission facilities by the Florida Gas 
Transmission Company, LLC (FGT) in Bradford, Clay, Columbia, and 
Suwannee Counties, Florida. Specifically, FGT would construct: (1) 
About 3 miles of pipeline in Suwannee and Columbia Counties; (2) about 
5.7 miles of pipeline in Bradford County; and (3) a new compressor unit 
and regulation station in Bradford County. The Commission will use this 
EA in its decision-making process to determine whether the project is 
in the public convenience and necessity.
    This notice announces the opening of the scoping process the 
Commission will use to gather input from the public and interested 
agencies on the Project. You can make a difference by providing us with 
your specific comments or concerns about the Project. Your comments 
should focus on the potential environmental impacts, reasonable 
alternatives, and measures to avoid or minimize environmental impacts. 
Your input will help the Commission staff determine what issues they 
need to evaluate in the EA. To ensure that your comments are timely and 
properly recorded, please send your comments so that the Commission 
receives them in Washington, DC on or before June 15, 2015.
    If you sent comments on this Project to the Commission before the 
opening of this docket on March 31, 2015, you will need to file those 
comments in Docket No. CP15-144-000 to ensure they are considered as 
part of this proceeding.
    This notice is being sent to the Commission's current environmental 
mailing list for this project. State and local government 
representatives should notify their constituents of this proposed 
project and encourage them to comment on their areas of concern.
    If you are a landowner receiving this notice, an FGT representative 
may contact you about the acquisition of an easement to construct, 
operate, and maintain the proposed facilities. The company would seek 
to negotiate a mutually acceptable agreement. However, if the 
Commission approves the Project, that approval conveys with it the 
right of eminent domain. Therefore, if easement negotiations fail to 
produce an agreement, the pipeline company could initiate condemnation 
proceedings where compensation would be determined in accordance with 
state law.
    The ``For Citizens'' section of the FERC Web site (www.ferc.gov) 
provides more information about the FERC and the environmental review 
process. This section also includes information about getting involved 
in FERC jurisdictional projects, and a citizens' guide entitled ``An 
Interstate Natural Gas Facility On My Land? What Do I Need to Know?'' 
This guide addresses a number of frequently asked questions, including 
the use of eminent domain and how to participate in the Commission's 
proceedings.

Public Participation

    For your convenience, there are three methods you can use to submit 
your comments to the Commission. The Commission encourages electronic 
filing of comments and has expert staff available to assist you at 
(202) 502-8258 or efiling@ferc.gov. Please carefully

[[Page 30070]]

follow these instructions so that your comments are properly recorded.
    (1) You can file your comments electronically using the eComment 
feature on the Commission's Web site (www.ferc.gov) under the link to 
Documents and Filings. This is an easy method for submitting brief, 
text-only comments on a project;
    (2) You can file your comments electronically by using the eFiling 
feature on the Commission's Web site (www.ferc.gov) under the link to 
Documents and Filings. With eFiling, you can provide comments in a 
variety of formats by attaching them as a file with your submission. 
New eFiling users must first create an account by clicking on 
``eRegister.'' If you are filing a comment on a particular project, 
please select ``Comment on a Filing'' as the filing type; or
    (3) You can file a paper copy of your comments by mailing them to 
the following address. Be sure to reference the project docket number 
(CP15-144-000) with your submission: Kimberly D. Bose, Secretary, 
Federal Energy Regulatory Commission, 888 First Street NE., Room 1A, 
Washington, DC 20426.

Summary of the Proposed Project

    According to FGT, the purpose of the Project is to provide a total 
of approximately 75,000 MMBtu/d of natural gas capacity to be delivered 
at various amounts at several points throughout Florida. To accomplish 
this, FGT proposes to:
     Construct approximately 3.0 miles of 30-inch-diameter 
looping pipeline and associated facilities \1\ in Suwannee and Columbia 
Counties;
---------------------------------------------------------------------------

    \1\ Associated facilities include new or relocated pig launchers 
and receivers, valves, and cathodic protection equipment.
---------------------------------------------------------------------------

     install one new compressor unit, re-wheel an existing 
turbine compressor unit, and construct and modify piping and valves at 
Compressor Station 16 in Bradford County;
     construct approximately 5.7 miles of 20-inch-diameter 
looping pipeline and associated facilities in Bradford County; and
     construct a new regulation station in Bradford County.
    FGT would also own, operate, and maintain these interstate natural 
gas transmission facilities. The general location of the project 
facilities is shown in Appendix 1.\2\
---------------------------------------------------------------------------

    \2\ The appendices referenced in this notice will not appear in 
the Federal Register. Copies of appendices were sent to all those 
receiving this notice in the mail and are available at www.ferc.gov 
using the link called ``eLibrary'' or from the Commission's Public 
Reference Room, 888 First Street NE., Washington, DC 20426, or call 
(202) 502-8371. For instructions on connecting to eLibrary, refer to 
the last page of this notice.
---------------------------------------------------------------------------

Land Requirements for Construction

    Construction of the proposed facilities would disturb about 140 
acres of land. Following construction, FGT would maintain about 50 
acres of land; the remaining land would be restored/stabilized and 
allowed to revert to former uses. Where feasible, FGT proposes to use 
existing rights-of-way for construction and operation of the proposed 
facilities. Both of the proposed pipelines would be 100% collocated 
with other existing FGT pipelines.

The EA Process

    The National Environmental Policy Act (NEPA) requires the 
Commission to take into account the potential environmental impacts of 
a proposed project whenever it considers the issuance of a Certificate 
of Public Convenience and Necessity. NEPA also requires us \3\ to 
discover and address concerns the public may have about proposals. This 
process is referred to as ``scoping.'' The main goal of the scoping 
process is to focus the analysis in the EA on the important 
environmental issues. By this notice, the Commission requests public 
comments on the scope of the issues to address in the EA. We will 
consider all filed comments during the preparation of the EA.
---------------------------------------------------------------------------

    \3\ ``We,'' ``us,'' and ``our'' refer to the environmental staff 
of the Commission's Office of Energy Projects.
---------------------------------------------------------------------------

    In the EA we will discuss impacts that could occur as a result of 
the construction and operation of the proposed project under these 
general headings:
     Geology and soils;
     land use;
     water resources, fisheries, and wetlands;
     cultural resources;
     vegetation and wildlife;
     air quality and noise;
     endangered and threatened species;
     public safety; and
     cumulative impacts.
    We will also evaluate reasonable alternatives to the proposed 
project or portions of the project, and make recommendations on how to 
lessen or avoid impacts on the various resource areas.
    The EA will present our independent analysis of the issues. The EA 
will be available in the public record through eLibrary and depending 
on the comments received during the scoping process we may also publish 
and distribute the EA to the public for an allotted comment period. We 
will consider all comments on the EA before making our recommendations 
to the Commission. To ensure we have the opportunity to consider and 
address your comments, please carefully follow the instructions in the 
Public Participation section below.
    With this notice, we are asking agencies with jurisdiction by law 
and/or special expertise with respect to the environmental issues of 
this project to formally cooperate with us in the preparation of the 
EA.\4\ Agencies that would like to request cooperating agency status 
should follow the instructions for filing comments provided under the 
Public Participation section of this notice.
---------------------------------------------------------------------------

    \4\ The Council on Environmental Quality regulations addressing 
cooperating agency responsibilities are at Title 40, Code of Federal 
Regulations, Part 1501.6.
---------------------------------------------------------------------------

Consultations Under Section 106 of the National Historic Preservation 
Act

    In accordance with the Advisory Council on Historic Preservation's 
implementing regulations for section 106 of the National Historic 
Preservation Act, we are using this notice to initiate consultation 
with the applicable State Historic Preservation Office (SHPO), and to 
solicit their views and those of other government agencies, interested 
Indian tribes, and the public on the project's potential effects on 
historic properties.\5\ We will define the project-specific Area of 
Potential Effects (APE) in consultation with the SHPO as the project 
develops. On natural gas facility projects, the APE at a minimum 
encompasses all areas subject to ground disturbance (examples include 
construction right-of-way, contractor/pipe storage yards, compressor 
stations, and access roads). Our EA for this project will document our 
findings on the impacts on historic properties and summarize the status 
of consultations under section 106.
---------------------------------------------------------------------------

    \5\ The Advisory Council on Historic Preservation's regulations 
are at Title 36, Code of Federal Regulations, Part 800. Those 
regulations define historic properties as any prehistoric or 
historic district, site, building, structure, or object included in 
or eligible for inclusion in the National Register of Historic 
Places.
---------------------------------------------------------------------------

Environmental Mailing List

    The environmental mailing list includes federal, state, and local 
government representatives and agencies; elected officials; 
environmental and public interest groups; Native American Tribes; other 
interested parties; and local libraries and newspapers. This list also 
includes all affected landowners (as defined in the Commission's 
regulations) who are potential right-of-way grantors, whose property 
may be used temporarily for

[[Page 30071]]

project purposes, or who own homes within certain distances of 
aboveground facilities, and anyone who submits comments on the project. 
We will update the environmental mailing list as the analysis proceeds 
to ensure that we send the information related to this environmental 
review to all individuals, organizations, and government entities 
interested in and/or potentially affected by the proposed project.
    If we publish and distribute the EA, copies of the EA will be sent 
to the environmental mailing list for public review and comment. If you 
would prefer to receive a paper copy of the document instead of the CD 
version or would like to remove your name from the mailing list, please 
return the attached Information Request (Appendix 2).

Becoming an Intervenor

    In addition to involvement in the EA scoping process, you may want 
to become an ``intervenor'' which is an official party to the 
Commission's proceeding. Intervenors play a more formal role in the 
process and are able to file briefs, appear at hearings, and be heard 
by the courts if they choose to appeal the Commission's final ruling. 
An intervenor formally participates in the proceeding by filing a 
request to intervene. Instructions for becoming an intervenor are in 
the User's Guide under the ``e-filing'' link on the Commission's Web 
site.

Additional Information

    Additional information about the project is available from the 
Commission's Office of External Affairs, at (866) 208-FERC, or on the 
FERC Web site at www.ferc.gov using the ``eLibrary'' link. Click on the 
eLibrary link, click on ``General Search'' and enter the docket number 
CP15-144 (note: the last three digits are excluded). Be sure you have 
selected an appropriate date range. For assistance, please contact FERC 
Online Support at FercOnlineSupport@ferc.gov or toll free at (866) 208-
3676, or for TTY, contact (202) 502-8659. The eLibrary link also 
provides access to the texts of formal documents issued by the 
Commission, such as orders, notices, and rulemakings.
    In addition, the Commission offers a free service called 
eSubscription which allows you to keep track of all formal issuances 
and submittals in specific dockets. This can reduce the amount of time 
you spend researching proceedings by automatically providing you with 
notification of these filings, document summaries, and direct links to 
the documents. Go to www.ferc.gov/docs-filing/esubscription.asp.
    Finally, public meetings or site visits will be posted on the 
Commission's calendar located at www.ferc.gov/EventCalendar/EventsList.aspx along with other related information.

    Dated: May 19, 2015.
Kimberly D. Bose,
 Secretary.
[FR Doc. 2015-12615 Filed 5-22-15; 8:45 am]
 BILLING CODE 6717-01-P



                                                                                 Federal Register / Vol. 80, No. 100 / Tuesday, May 26, 2015 / Notices                                           30069

                                                  DEPARTMENT OF ENERGY                                    that the exemption from licensing for                 and interested agencies on the Project.
                                                                                                          the Number 3 Mill Project, FERC No.                   You can make a difference by providing
                                                  Federal Energy Regulatory                               5633, originally issued July 14, 1982,3               us with your specific comments or
                                                  Commission                                              has been transferred to Hydro                         concerns about the Project. Your
                                                  [Project No. 7141–002]                                  Development Group Acquisition, LLC,                   comments should focus on the potential
                                                                                                          an affiliate of Enel Green Power. The                 environmental impacts, reasonable
                                                  Mill Shoals Hydro Company, Inc.; Mill                   project is located on the South Branch                alternatives, and measures to avoid or
                                                  Shoals Hydro Company, LLC; Notice of                    Oswegatchie River in St. Lawrence                     minimize environmental impacts. Your
                                                  Transfer of Exemption                                   County, New York. The transfer of an                  input will help the Commission staff
                                                                                                          exemption does not require Commission                 determine what issues they need to
                                                     1. By letter filed April 24, 2015,1                  approval.                                             evaluate in the EA. To ensure that your
                                                  William B. Conway, Jr., Counsel for Enel                  2. Hydro Development Group                          comments are timely and properly
                                                  Green Power North America, Inc.                         Acquisition, LLC is now the exemptee                  recorded, please send your comments so
                                                  (EGPNA),2 informed the Commission                       of the Number 3 Mill Project, FERC No.                that the Commission receives them in
                                                  that the exemption from licensing for                   5633. All correspondence should be                    Washington, DC on or before June 15,
                                                  the Milstead Dam Project, FERC No.                      forwarded to: Hydro Development                       2015.
                                                  7141, originally issued April 15, 1983,3                Group Acquisition, LLC, c/o Enel Green                   If you sent comments on this Project
                                                  has been transferred to Mill Shoals                     Power North America, Inc., Attn:                      to the Commission before the opening of
                                                  Hydro Company, LLC, an affiliate of                     General Counsel, 1 Tech Drive, Suite
                                                  Enel Green Power. The project is located                                                                      this docket on March 31, 2015, you will
                                                                                                          220, Andover, MA 01810.                               need to file those comments in Docket
                                                  on the Yellow River in Rockdale
                                                  County, Georgia. The transfer of an
                                                                                                            Dated: May 19, 2015.                                No. CP15–144–000 to ensure they are
                                                  exemption does not require Commission                   Kimberly D. Bose,                                     considered as part of this proceeding.
                                                  approval.                                               Secretary.                                               This notice is being sent to the
                                                     2. Mill Shoals Hydro Company, LLC                    [FR Doc. 2015–12605 Filed 5–22–15; 8:45 am]           Commission’s current environmental
                                                  is now the exemptee of the Milstead                     BILLING CODE 6717–01–P                                mailing list for this project. State and
                                                  Dam Project, FERC No. 7141. All                                                                               local government representatives should
                                                  correspondence should be forwarded to:                                                                        notify their constituents of this
                                                  Mill Shoals Hydro Company, LLC, c/o                     DEPARTMENT OF ENERGY                                  proposed project and encourage them to
                                                  Enel Green Power North America, Inc.,                                                                         comment on their areas of concern.
                                                  Attn: General Counsel, 1 Tech Drive,                    Federal Energy Regulatory                                If you are a landowner receiving this
                                                  Suite 220, Andover, MA 01810.                           Commission                                            notice, an FGT representative may
                                                    Dated: May 19, 2015.                                  [Docket No. CP15–144–000]                             contact you about the acquisition of an
                                                                                                                                                                easement to construct, operate, and
                                                  Kimberly D. Bose,
                                                                                                          Florida Gas Transmission Company,                     maintain the proposed facilities. The
                                                  Secretary.                                              LLC; Notice of Intent To Prepare an                   company would seek to negotiate a
                                                  [FR Doc. 2015–12609 Filed 5–22–15; 8:45 am]             Environmental Assessment for the                      mutually acceptable agreement.
                                                  BILLING CODE 6717–01P                                   Proposed Jacksonville Expansion                       However, if the Commission approves
                                                                                                          Project, and Request for Comments On                  the Project, that approval conveys with
                                                                                                          Environmental Issues                                  it the right of eminent domain.
                                                  DEPARTMENT OF ENERGY                                                                                          Therefore, if easement negotiations fail
                                                                                                            The staff of the Federal Energy                     to produce an agreement, the pipeline
                                                  Federal Energy Regulatory                               Regulatory Commission (FERC or
                                                  Commission                                                                                                    company could initiate condemnation
                                                                                                          Commission) will prepare an                           proceedings where compensation would
                                                  [Project No. 5633–011]                                  environmental assessment (EA) that will               be determined in accordance with state
                                                                                                          discuss the environmental impacts of                  law.
                                                  Hydro Development Group, Inc., Hydro                    the Jacksonville Expansion Project
                                                                                                                                                                   The ‘‘For Citizens’’ section of the
                                                  Development Group Acquisition, LLC;                     (Project). The Project would involve
                                                                                                                                                                FERC Web site (www.ferc.gov) provides
                                                  Notice of Transfer of Exemption                         constructing and operating interstate
                                                                                                                                                                more information about the FERC and
                                                                                                          natural gas transmission facilities by the
                                                    1. By letter filed April 24, 2015,1                                                                         the environmental review process. This
                                                                                                          Florida Gas Transmission Company,
                                                  William B. Conway, Jr., Counsel for Enel                                                                      section also includes information about
                                                                                                          LLC (FGT) in Bradford, Clay, Columbia,
                                                  Green Power North America, Inc.                                                                               getting involved in FERC jurisdictional
                                                                                                          and Suwannee Counties, Florida.
                                                  (EGPNA),2 informed the Commission                                                                             projects, and a citizens’ guide entitled
                                                                                                          Specifically, FGT would construct: (1)
                                                                                                                                                                ‘‘An Interstate Natural Gas Facility On
                                                                                                          About 3 miles of pipeline in Suwannee
                                                     1 Seventeen other exempted projects which are to                                                           My Land? What Do I Need to Know?’’
                                                  be transferred were included in the April 24, 2015      and Columbia Counties; (2) about 5.7
                                                                                                                                                                This guide addresses a number of
                                                  letter. These exemptions will be handled under          miles of pipeline in Bradford County;
                                                                                                                                                                frequently asked questions, including
                                                  separate proceedings.                                   and (3) a new compressor unit and
                                                     2 Enel Green Power North America, Inc. is a                                                                the use of eminent domain and how to
                                                                                                          regulation station in Bradford County.
                                                  wholly owned subsidiary of Enel Green Power. Enel                                                             participate in the Commission’s
                                                                                                          The Commission will use this EA in its
                                                  Green Power is a well-capitalized publicly traded                                                             proceedings.
                                                  company.                                                decision-making process to determine
                                                     3 23 FERC ¶ 62,045, Notice of Exemption From         whether the project is in the public                  Public Participation
mstockstill on DSK4VPTVN1PROD with NOTICES




                                                  Licensing (1983).                                       convenience and necessity.
                                                     1 Seventeen other exempted projects which are to                                                             For your convenience, there are three
                                                                                                            This notice announces the opening of
                                                  be transferred were included in the April 24, 2015                                                            methods you can use to submit your
                                                                                                          the scoping process the Commission
                                                  letter. These exemptions will be handled under                                                                comments to the Commission. The
                                                  separate proceedings.                                   will use to gather input from the public
                                                     2 Enel Green Power North America, Inc. is a
                                                                                                                                                                Commission encourages electronic filing
                                                  wholly owned subsidiary of Enel Green Power. Enel         3 20 FERC ¶ 62,054, Order Granting Exemption        of comments and has expert staff
                                                  Green Power is a well-capitalized publicly traded       from Licensing of a Small Hydroelectric Project of    available to assist you at (202) 502–8258
                                                  company.                                                5 Megawatts or Less (1982).                           or efiling@ferc.gov. Please carefully


                                             VerDate Sep<11>2014   17:50 May 22, 2015   Jkt 235001   PO 00000   Frm 00033   Fmt 4703   Sfmt 4703   E:\FR\FM\26MYN1.SGM   26MYN1


                                                  30070                          Federal Register / Vol. 80, No. 100 / Tuesday, May 26, 2015 / Notices

                                                  follow these instructions so that your                  Land Requirements for Construction                    making our recommendations to the
                                                  comments are properly recorded.                           Construction of the proposed facilities             Commission. To ensure we have the
                                                     (1) You can file your comments                       would disturb about 140 acres of land.                opportunity to consider and address
                                                  electronically using the eComment                       Following construction, FGT would                     your comments, please carefully follow
                                                  feature on the Commission’s Web site                    maintain about 50 acres of land; the                  the instructions in the Public
                                                  (www.ferc.gov) under the link to                        remaining land would be restored/                     Participation section below.
                                                  Documents and Filings. This is an easy                                                                          With this notice, we are asking
                                                                                                          stabilized and allowed to revert to
                                                  method for submitting brief, text-only                                                                        agencies with jurisdiction by law and/
                                                                                                          former uses. Where feasible, FGT
                                                  comments on a project;                                                                                        or special expertise with respect to the
                                                                                                          proposes to use existing rights-of-way
                                                     (2) You can file your comments                                                                             environmental issues of this project to
                                                                                                          for construction and operation of the
                                                  electronically by using the eFiling                                                                           formally cooperate with us in the
                                                                                                          proposed facilities. Both of the proposed             preparation of the EA.4 Agencies that
                                                  feature on the Commission’s Web site                    pipelines would be 100% collocated
                                                  (www.ferc.gov) under the link to                                                                              would like to request cooperating
                                                                                                          with other existing FGT pipelines.                    agency status should follow the
                                                  Documents and Filings. With eFiling,
                                                  you can provide comments in a variety                   The EA Process                                        instructions for filing comments
                                                  of formats by attaching them as a file                                                                        provided under the Public Participation
                                                                                                             The National Environmental Policy
                                                  with your submission. New eFiling                                                                             section of this notice.
                                                                                                          Act (NEPA) requires the Commission to
                                                  users must first create an account by                   take into account the potential                       Consultations Under Section 106 of the
                                                  clicking on ‘‘eRegister.’’ If you are filing            environmental impacts of a proposed                   National Historic Preservation Act
                                                  a comment on a particular project,                      project whenever it considers the                       In accordance with the Advisory
                                                  please select ‘‘Comment on a Filing’’ as                issuance of a Certificate of Public                   Council on Historic Preservation’s
                                                  the filing type; or                                     Convenience and Necessity. NEPA also                  implementing regulations for section
                                                     (3) You can file a paper copy of your                requires us 3 to discover and address                 106 of the National Historic
                                                  comments by mailing them to the                         concerns the public may have about                    Preservation Act, we are using this
                                                  following address. Be sure to reference                 proposals. This process is referred to as             notice to initiate consultation with the
                                                  the project docket number (CP15–144–                    ‘‘scoping.’’ The main goal of the scoping             applicable State Historic Preservation
                                                  000) with your submission: Kimberly D.                  process is to focus the analysis in the               Office (SHPO), and to solicit their views
                                                  Bose, Secretary, Federal Energy                         EA on the important environmental                     and those of other government agencies,
                                                  Regulatory Commission, 888 First Street                 issues. By this notice, the Commission                interested Indian tribes, and the public
                                                  NE., Room 1A, Washington, DC 20426.                     requests public comments on the scope                 on the project’s potential effects on
                                                  Summary of the Proposed Project                         of the issues to address in the EA. We                historic properties.5 We will define the
                                                                                                          will consider all filed comments during               project-specific Area of Potential Effects
                                                     According to FGT, the purpose of the                 the preparation of the EA.                            (APE) in consultation with the SHPO as
                                                  Project is to provide a total of                           In the EA we will discuss impacts that             the project develops. On natural gas
                                                  approximately 75,000 MMBtu/d of                         could occur as a result of the                        facility projects, the APE at a minimum
                                                  natural gas capacity to be delivered at                 construction and operation of the                     encompasses all areas subject to ground
                                                  various amounts at several points                       proposed project under these general                  disturbance (examples include
                                                  throughout Florida. To accomplish this,                 headings:                                             construction right-of-way, contractor/
                                                  FGT proposes to:                                           • Geology and soils;                               pipe storage yards, compressor stations,
                                                     • Construct approximately 3.0 miles                     • land use;                                        and access roads). Our EA for this
                                                  of 30-inch-diameter looping pipeline                       • water resources, fisheries, and                  project will document our findings on
                                                  and associated facilities 1 in Suwannee                 wetlands;                                             the impacts on historic properties and
                                                  and Columbia Counties;                                     • cultural resources;                              summarize the status of consultations
                                                     • install one new compressor unit, re-                  • vegetation and wildlife;                         under section 106.
                                                  wheel an existing turbine compressor                       • air quality and noise;
                                                  unit, and construct and modify piping                      • endangered and threatened species;               Environmental Mailing List
                                                  and valves at Compressor Station 16 in                     • public safety; and                                  The environmental mailing list
                                                  Bradford County;                                           • cumulative impacts.                              includes federal, state, and local
                                                     • construct approximately 5.7 miles                     We will also evaluate reasonable                   government representatives and
                                                  of 20-inch-diameter looping pipeline                    alternatives to the proposed project or               agencies; elected officials;
                                                  and associated facilities in Bradford                   portions of the project, and make                     environmental and public interest
                                                  County; and                                             recommendations on how to lessen or                   groups; Native American Tribes; other
                                                     • construct a new regulation station                 avoid impacts on the various resource                 interested parties; and local libraries
                                                  in Bradford County.                                     areas.                                                and newspapers. This list also includes
                                                     FGT would also own, operate, and                        The EA will present our independent                all affected landowners (as defined in
                                                  maintain these interstate natural gas                   analysis of the issues. The EA will be                the Commission’s regulations) who are
                                                  transmission facilities. The general                    available in the public record through                potential right-of-way grantors, whose
                                                  location of the project facilities is shown             eLibrary and depending on the                         property may be used temporarily for
                                                  in Appendix 1.2                                         comments received during the scoping
                                                                                                          process we may also publish and                         4 The Council on Environmental Quality
                                                    1 Associated  facilities include new or relocated     distribute the EA to the public for an                regulations addressing cooperating agency
mstockstill on DSK4VPTVN1PROD with NOTICES




                                                  pig launchers and receivers, valves, and cathodic       allotted comment period. We will                      responsibilities are at Title 40, Code of Federal
                                                  protection equipment.                                                                                         Regulations, Part 1501.6.
                                                    2 The appendices referenced in this notice will
                                                                                                          consider all comments on the EA before                  5 The Advisory Council on Historic Preservation’s

                                                  not appear in the Federal Register. Copies of                                                                 regulations are at Title 36, Code of Federal
                                                  appendices were sent to all those receiving this        8371. For instructions on connecting to eLibrary,     Regulations, Part 800. Those regulations define
                                                  notice in the mail and are available at www.ferc.gov    refer to the last page of this notice.                historic properties as any prehistoric or historic
                                                  using the link called ‘‘eLibrary’’ or from the            3 ‘‘We,’’ ‘‘us,’’ and ‘‘our’’ refer to the          district, site, building, structure, or object included
                                                  Commission’s Public Reference Room, 888 First           environmental staff of the Commission’s Office of     in or eligible for inclusion in the National Register
                                                  Street NE., Washington, DC 20426, or call (202) 502-    Energy Projects.                                      of Historic Places.



                                             VerDate Sep<11>2014   18:31 May 22, 2015   Jkt 235001   PO 00000   Frm 00034   Fmt 4703   Sfmt 4703   E:\FR\FM\26MYN1.SGM   26MYN1


                                                                                 Federal Register / Vol. 80, No. 100 / Tuesday, May 26, 2015 / Notices                                                   30071

                                                  project purposes, or who own homes                      documents. Go to www.ferc.gov/docs-                      The filings in the above-referenced
                                                  within certain distances of aboveground                 filing/esubscription.asp.                             proceeding are accessible in the
                                                  facilities, and anyone who submits                         Finally, public meetings or site visits            Commission’s eLibrary system by
                                                  comments on the project. We will                        will be posted on the Commission’s                    clicking on the appropriate link in the
                                                  update the environmental mailing list as                calendar located at www.ferc.gov/                     above list. They are also available for
                                                  the analysis proceeds to ensure that we                 EventCalendar/EventsList.aspx along                   electronic review in the Commission’s
                                                  send the information related to this                    with other related information.                       Public Reference Room in Washington,
                                                  environmental review to all individuals,                  Dated: May 19, 2015.                                DC. There is an eSubscription link on
                                                  organizations, and government entities                  Kimberly D. Bose,                                     the Web site that enables subscribers to
                                                  interested in and/or potentially affected               Secretary.                                            receive email notification when a
                                                  by the proposed project.                                [FR Doc. 2015–12615 Filed 5–22–15; 8:45 am]           document is added to a subscribed
                                                     If we publish and distribute the EA,                 BILLING CODE 6717–01–P                                docket(s). For assistance with any FERC
                                                  copies of the EA will be sent to the                                                                          Online service, please email
                                                  environmental mailing list for public                                                                         FERCOnlineSupport@ferc.gov. or call
                                                  review and comment. If you would                        DEPARTMENT OF ENERGY                                  (866) 208–3676 (toll free). For TTY, call
                                                  prefer to receive a paper copy of the
                                                                                                                                                                (202) 502–8659.
                                                  document instead of the CD version or                   Federal Energy Regulatory
                                                  would like to remove your name from                     Commission                                              Dated: May 19, 2015.
                                                  the mailing list, please return the                     [Docket No. ER15–1714–000]                            Kimberly D. Bose,
                                                  attached Information Request                                                                                  Secretary.
                                                  (Appendix 2).                                           Targray Americas Inc.; Supplemental                   [FR Doc. 2015–12616 Filed 5–22–15; 8:45 am]
                                                  Becoming an Intervenor                                  Notice That Initial Market-Based Rate                 BILLING CODE 6717–01–P
                                                                                                          Filing Includes Request for Blanket
                                                    In addition to involvement in the EA                  Section 204 Authorization
                                                  scoping process, you may want to                                                                              DEPARTMENT OF ENERGY
                                                  become an ‘‘intervenor’’ which is an                       This is a supplemental notice in the
                                                  official party to the Commission’s                      above-referenced proceeding of Targray
                                                                                                          Americas Inc.’s application for market-               Federal Energy Regulatory
                                                  proceeding. Intervenors play a more                                                                           Commission
                                                  formal role in the process and are able                 based rate authority, with an
                                                  to file briefs, appear at hearings, and be              accompanying rate tariff, noting that
                                                  heard by the courts if they choose to                   such application includes a request for               [Project No. 6756–008]
                                                  appeal the Commission’s final ruling.                   blanket authorization, under 18 CFR
                                                                                                          part 34, of future issuances of securities            Sweetwater Hydroelectric, Inc.; Lower
                                                  An intervenor formally participates in
                                                                                                          and assumptions of liability.                         Valley, LLC; Notice of Transfer of
                                                  the proceeding by filing a request to
                                                                                                             Any person desiring to intervene or to             Exemption
                                                  intervene. Instructions for becoming an
                                                                                                          protest should file with the Federal
                                                  intervenor are in the User’s Guide under
                                                                                                          Energy Regulatory Commission, 888                       1. By letter filed April 24, 2015,1
                                                  the ‘‘e-filing’’ link on the Commission’s
                                                                                                          First Street NE., Washington, DC 20426,               William B. Conway, Jr., Counsel for Enel
                                                  Web site.
                                                                                                          in accordance with Rules 211 and 214                  Green Power North America, Inc.
                                                  Additional Information                                  of the Commission’s Rules of Practice                 (EGPNA),2 informed the Commission
                                                                                                          and Procedure (18 CFR 385.211 and                     that the exemption from licensing for
                                                     Additional information about the
                                                                                                          385.214). Anyone filing a motion to                   the Lower Valley Project, FERC No.
                                                  project is available from the                           intervene or protest must serve a copy
                                                  Commission’s Office of External Affairs,                                                                      6756, originally issued November 9,
                                                                                                          of that document on the Applicant.                    1982,3 has been transferred to Lower
                                                  at (866) 208–FERC, or on the FERC Web                      Notice is hereby given that the
                                                  site at www.ferc.gov using the                                                                                Valley, LLC, an affiliate of Enel Green
                                                                                                          deadline for filing protests with regard
                                                  ‘‘eLibrary’’ link. Click on the eLibrary                                                                      Power. The project is located on the
                                                                                                          to the applicant’s request for blanket
                                                  link, click on ‘‘General Search’’ and                   authorization, under 18 CFR part 34, of               Sugar River in Sullivan County, New
                                                  enter the docket number CP15–144                        future issuances of securities and                    Hampshire. The transfer of an
                                                  (note: the last three digits are excluded).             assumptions of liability, is June 8, 2015.            exemption does not require Commission
                                                  Be sure you have selected an                               The Commission encourages                          approval.
                                                  appropriate date range. For assistance,                 electronic submission of protests and                   2. Lower Valley, LLC is now the
                                                  please contact FERC Online Support at                   interventions in lieu of paper, using the             exemptee of the Lower Valley Project,
                                                  FercOnlineSupport@ferc.gov or toll free                 FERC Online links at http://                          FERC No. 6756. All correspondence
                                                  at (866) 208–3676, or for TTY, contact                  www.ferc.gov. To facilitate electronic                should be forwarded to: Lower Valley,
                                                  (202) 502–8659. The eLibrary link also                  service, persons with Internet access                 LLC, c/o Enel Green Power North
                                                  provides access to the texts of formal                  who will eFile a document and/or be                   America, Inc., Attn: General Counsel, 1
                                                  documents issued by the Commission,                     listed as a contact for an intervenor
                                                  such as orders, notices, and                                                                                  Tech Drive, Suite 220, Andover, MA
                                                                                                          must create and validate an                           01810.
                                                  rulemakings.                                            eRegistration account using the
                                                     In addition, the Commission offers a                 eRegistration link. Select the eFiling                   1 Seventeen other exempted projects which are to
mstockstill on DSK4VPTVN1PROD with NOTICES




                                                  free service called eSubscription which                 link to log on and submit the                         be transferred were included in the April 24, 2015
                                                  allows you to keep track of all formal                  intervention or protests.                             letter. These exemptions will be handled under
                                                  issuances and submittals in specific                       Persons unable to file electronically              separate proceedings.
                                                  dockets. This can reduce the amount of                  should submit an original and 5 copies                   2 Enel Green Power North America, Inc. is a

                                                  time you spend researching proceedings                  of the intervention or protest to the                 wholly owned subsidiary of Enel Green Power. Enel
                                                                                                                                                                Green Power is a well-capitalized publicly traded
                                                  by automatically providing you with                     Federal Energy Regulatory Commission,                 company.
                                                  notification of these filings, document                 888 First Street NE., Washington, DC                     3 21 FERC ¶ 62,216, Notice of Exemption from

                                                  summaries, and direct links to the                      20426.                                                Licensing (1982).



                                             VerDate Sep<11>2014   17:50 May 22, 2015   Jkt 235001   PO 00000   Frm 00035   Fmt 4703   Sfmt 4703   E:\FR\FM\26MYN1.SGM   26MYN1



Document Created: 2018-02-21 10:31:16
Document Modified: 2018-02-21 10:31:16
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation80 FR 30069 

2024 Federal Register | Disclaimer | Privacy Policy
USC | CFR | eCFR