80_FR_30842 80 FR 30739 - Preparation and Evaluation of Radiological Emergency Response Plans and Preparedness

80 FR 30739 - Preparation and Evaluation of Radiological Emergency Response Plans and Preparedness

NUCLEAR REGULATORY COMMISSION

Federal Register Volume 80, Issue 103 (May 29, 2015)

Page Range30739-30740
FR Document2015-13079

The U.S. Nuclear Regulatory Commission (NRC) is issuing for public comment draft NUREG-0654/FEMA-REP-1, Revision 2, ``Criteria for Preparation and Evaluation of Radiological Emergency Response Plans and Preparedness in Support of Nuclear Power Plants.'' This guidance document was originally issued in December 1980 by the NRC in conjunction with the Federal Emergency Management Agency (FEMA). Both agencies use the document to evaluate the adequacy of the emergency plans and preparedness of commercial nuclear power plant (NPP) licensees and applicants, as well as those of State, local, and Tribal governments within the emergency planning zones (EPZs) surrounding commercial NPPs. This revision reflects changes to the NRC's and FEMA's regulations, guidance, and policies, as well as advances in technology and methods for responding to radiological incidents that have occurred since the document was originally issued. It also incorporates the four supplemental documents and addenda to NUREG-0654/FEMA-REP-1, Revision 1, that have been issued in the intervening years, and is intended to modernize the guidance while lessening administrative burden on users.

Federal Register, Volume 80 Issue 103 (Friday, May 29, 2015)
[Federal Register Volume 80, Number 103 (Friday, May 29, 2015)]
[Notices]
[Pages 30739-30740]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2015-13079]


=======================================================================
-----------------------------------------------------------------------

NUCLEAR REGULATORY COMMISSION

[FEMA-2012-0026, NRC-2015-0133]


Preparation and Evaluation of Radiological Emergency Response 
Plans and Preparedness

AGENCY: Nuclear Regulatory Commission.

ACTION: Draft NUREG; request for comment.

-----------------------------------------------------------------------

SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) is issuing for 
public comment draft NUREG-0654/FEMA-REP-1, Revision 2, ``Criteria for 
Preparation and Evaluation of Radiological Emergency Response Plans and 
Preparedness in Support of Nuclear Power Plants.'' This guidance 
document was originally issued in December 1980 by the NRC in 
conjunction with the Federal Emergency Management Agency (FEMA). Both 
agencies use the document to evaluate the adequacy of the emergency 
plans and preparedness of commercial nuclear power plant (NPP) 
licensees and applicants, as well as those of State, local, and Tribal 
governments within the emergency planning zones (EPZs) surrounding 
commercial NPPs. This revision reflects changes to the NRC's and FEMA's 
regulations, guidance, and policies, as well as advances in technology 
and methods for responding to radiological incidents that have occurred 
since the document was originally issued. It also incorporates the four 
supplemental documents and addenda to NUREG-0654/FEMA-REP-1, Revision 
1, that have been issued in the intervening years, and is intended to 
modernize the guidance while lessening administrative burden on users.

DATES: Submit comments by August 27, 2015. Comments received after this 
date will be considered if it is practical to do so, but the NRC is 
able to assure consideration only for comments received on or before 
this date.

ADDRESSES: In order to avoid the receipt and review of duplicate 
submissions, please submit your comments and any supporting material by 
only one of the following means:
     Federal Rulemaking Web site: Go to http://www.regulations.gov and search for Docket ID FEMA-2012-0026. For 
technical questions, contact the individual listed in the FOR FURTHER 
INFORMATION CONTACT section of this document.
     Mail comments to: Regulatory Affairs Division, Office of 
Chief Counsel, Federal Emergency Management Agency, 500 C Street SW., 
Washington, DC 20472-3100.
    For additional direction on obtaining information and submitting 
comments, see ``Obtaining Information and Submitting Comments'' in the 
SUPPLEMENTARY INFORMATION section of this document.

FOR FURTHER INFORMATION CONTACT: Don Tailleart, Office of Nuclear 
Security and Incident Response, U.S. Nuclear Regulatory Commission, 
Washington, DC 20555-0001; telephone: 301-287-9257; email: 
[email protected] or William Eberst, Technological Hazards 
Division, National Preparedness Directorate, Federal Emergency 
Management Agency; Washington, DC 20472-3100; telephone: 202-341-4917; 
email: [email protected].

SUPPLEMENTARY INFORMATION:

I. Obtaining Information and Submitting Comments

A. Obtaining Information

    Please refer to Docket ID FEMA-2012-0026 when contacting the NRC 
about the availability of information for this action. You may obtain 
publicly available information related to this action by any of the 
following methods:
     Federal Rulemaking Web site: Go to http://www.regulations.gov and search for Docket ID FEMA-2012-0026.
     NRC's Agencywide Documents Access and Management System 
(ADAMS): You may obtain publicly available documents online in the 
ADAMS Public Documents collection at http://www.nrc.gov/reading-rm/adams.html. To begin the search, select ``ADAMS Public Documents'' and 
then select ``Begin Web-based ADAMS Search.'' For problems with ADAMS, 
please contact the NRC's Public Document Room (PDR) reference staff at 
1-800-397-4209, 301-415-4737, or by email to [email protected]. The 
draft guidance document is available in ADAMS under Accession No. 
ML14246A519.
     NRC's PDR: You may examine and purchase copies of public 
documents at the NRC's PDR, Room O1-F21, One White Flint North, 11555 
Rockville Pike, Rockville, Maryland 20852.
    Submitted comments may also be inspected at FEMA, Office of Chief 
Counsel, 500 C Street SW., Washington, DC 20472-3100.

B. Submitting Comments

    Please include Docket ID FEMA-2012-0026 in the subject line of your 
comment submission, in order to ensure that FEMA is able to make your 
comment submission available to the public in this docket.
    All submissions received must include the agency name (FEMA) and 
docket ID. Regardless of the method used for submitting comments or 
material, FEMA will post all submissions, without change, to 
www.regulations.gov and will include any personal information that you 
provide. Therefore, submitting this information makes it public. You 
may wish to read the Privacy Act notice, which can be viewed by 
clicking on the ``Privacy Notice'' link on the homepage of 
www.regulations.gov.

II. Discussion

    In December 1980, the NRC issued NUREG-0654/FEMA-REP-1, Revision 1, 
``Criteria for Preparation and Evaluation of Radiological Emergency 
Response Plans and Preparedness in Support of Nuclear Power Plants,'' 
in conjunction with FEMA (45 FR 85862; December 30, 1980).
    Revision 1 of NUREG-0654/FEMA-REP-1 provides guidance on meeting 
the 16 planning standards for NPP emergency response plans found in the 
NRC's regulations in paragraph 50.47(b) of Title 10 of the Code of 
Federal Regulations (10 CFR) and FEMA's regulations set forth in 44 CFR 
350.5(a). Both agencies use the guidance in determining compliance with 
these planning standards and evaluating the overall adequacy of the 
emergency plans and preparedness of commercial NPP licensees and 
applicants, as well as State, local, and Tribal governments within the 
EPZs surrounding commercial NPPs, for responding to a radiological 
incident at an NPP.

[[Page 30740]]

    Since the publication of NUREG-0654/FEMA-REP-1, Revision 1, in 
1980, four supplemental documents and one set of addenda have been 
issued that update and modify specific planning and procedural 
elements. These documents are available online at the Federal 
rulemaking Web site, www.regulations.gov, under Docket ID FEMA-2012-
0026. There have also been changes to the NRC's and FEMA's regulations, 
guidance, and policies, as well as advances in technology and methods 
for responding to radiological incidents. The NRC and FEMA are revising 
NUREG-0654/FEMA-REP-1, Revision 1, to incorporate information from the 
supplements and addenda; address regulatory, guidance, and policy 
changes; and include various emergency planning and preparedness 
lessons learned since its initial publication.
    The NRC is developing an emergency preparedness handbook (a NUREG 
document) in conjunction with the revision of NUREG-0654/FEMA-REP-1. 
The handbook will provide amplifying guidance on meeting the intent of 
the NUREG-0654/FEMA-REP-1, Revision 2 evaluation criteria applicable to 
commercial NPP applicants and licensees, and the level of detail that 
applicant and licensee emergency plans should provide regarding each 
evaluation criterion. A preliminary draft version of the handbook will 
be available for viewing in ADAMS under Accession No. ML15140A415 
during the public comment period for NUREG-0654/FEMA-REP-1, Revision 2; 
a final draft version of the handbook will be issued at a later time.
    The NRC and FEMA held two public meetings on August 22, 2012, and 
September 13, 2012, as well as two public stakeholder engagement 
sessions on October 29-31, 2013, and June 25, 2014. The public meetings 
were conducted in order to: (1) solicit input from stakeholders and 
interested members of the public on the scope of future revisions to 
NUREG-0654/FEMA-REP-1, Revision 1; (2) describe the proposed timeline 
for the revisions to NUREG-0654/FEMA-REP-1, Revision 1; (3) promote 
transparency, public participation, and collaboration during the NUREG-
0654/FEMA-REP-1, Revision 1, revision process; and (4) allow direct 
input from stakeholders and the public on changes being made during the 
initial writing process. Presentation material and meeting notes are 
available for review on the Federal rulemaking Web site, 
www.regulations.gov, under Docket ID FEMA-2012-0026.

III. Backfitting and Issue Finality

    Issuance of NUREG-0654/FEMA-REP-1, Revision 2, in final form, would 
not constitute backfitting under 10 CFR 50.109 and would not otherwise 
be inconsistent with the issue finality provisions in 10 CFR part 52. 
As discussed in section I.B., ``Scope,'' under the subsection titled 
``Use by NRC,'' of NUREG-0654/FEMA-REP-1, Revision 2, the NRC has no 
current intention to impose NUREG-0654/FEMA-REP-1, Revision 2, on 
current holders of a construction permit, operating license, early site 
permit, or combined license.
    NUREG-0654/FEMA-REP-1, Revision 2, if finalized, could be applied 
to applications for certain 10 CFR part 50 operating licenses or 
construction permits and 10 CFR part 52 combined licenses and early 
site permits. Such action would not constitute backfitting as defined 
in 10 CFR 50.109 or be otherwise inconsistent with the applicable issue 
finality provision in 10 CFR part 52, inasmuch as such applicants are 
not, with certain exceptions, within the scope of entities protected by 
10 CFR 50.109 or the relevant issue finality provisions in 10 CFR part 
52. This is because neither the Backfit Rule nor the issue finality 
provisions under 10 CFR part 52--with certain exclusions discussed 
below--was intended to apply to every NRC action that substantially 
changes the expectations of current and future applicants. The 
exceptions to the general principle are applicable whenever an 
applicant references a 10 CFR part 52 license (e.g., an early site 
permit), NRC regulatory approval (e.g., a design certification rule), 
or both, with specified issue finality provisions. The staff does not, 
at this time, intend to impose the positions represented in the draft 
NUREG (if finalized) in a manner that is inconsistent with any issue 
finality provisions. If, in the future, the staff seeks to impose a 
position in the draft NUREG (if finalized) in a manner that does not 
provide issue finality as described in the applicable issue finality 
provision, then the staff must address the criteria for avoiding issue 
finality as described in the applicable issue finality provision.

    Dated at Rockville, Maryland, this 20th day of May, 2015.

    For the U.S. Nuclear Regulatory Commission.
Brian E. Holian,
Director, Office of Nuclear Security and Incident Response.
[FR Doc. 2015-13079 Filed 5-28-15; 8:45 am]
 BILLING CODE 7590-01-P



                                                                             Federal Register / Vol. 80, No. 103 / Friday, May 29, 2015 / Notices                                           30739

                                               Comments submitted in response to                     have been issued in the intervening                   select ‘‘Begin Web-based ADAMS
                                             this Notice will be summarized and                      years, and is intended to modernize the               Search.’’ For problems with ADAMS,
                                             included in the request for Office of                   guidance while lessening administrative               please contact the NRC’s Public
                                             Management and Budget approval of the                   burden on users.                                      Document Room (PDR) reference staff at
                                             ICR; they will also become a matter of                  DATES: Submit comments by August 27,                  1–800–397–4209, 301–415–4737, or by
                                             public record.                                          2015. Comments received after this date               email to pdr.resource@nrc.gov. The draft
                                                                                                     will be considered if it is practical to do           guidance document is available in
                                             II. Current Actions
                                                                                                     so, but the NRC is able to assure                     ADAMS under Accession No.
                                               Affected Public: Grant recipients of                  consideration only for comments                       ML14246A519.
                                             NSF SEES and comparable non-SEES                        received on or before this date.                        • NRC’s PDR: You may examine and
                                             Programs.                                                                                                     purchase copies of public documents at
                                                                                                     ADDRESSES: In order to avoid the receipt
                                               Total Respondents: 950.                                                                                     the NRC’s PDR, Room O1–F21, One
                                               Frequency: One-time collection.                       and review of duplicate submissions,
                                                                                                     please submit your comments and any                   White Flint North, 11555 Rockville
                                               Total responses: 760.                                                                                       Pike, Rockville, Maryland 20852.
                                               Average Time per response: 45                         supporting material by only one of the
                                                                                                     following means:                                        Submitted comments may also be
                                             minutes.                                                                                                      inspected at FEMA, Office of Chief
                                               Estimated Total Burden Hours: 576.3                     • Federal Rulemaking Web site: Go to
                                                                                                     http://www.regulations.gov and search                 Counsel, 500 C Street SW., Washington,
                                             hours.                                                                                                        DC 20472–3100.
                                                                                                     for Docket ID FEMA–2012–0026. For
                                               Dated: May 26, 2015.                                  technical questions, contact the                      B. Submitting Comments
                                             Suzanne H. Plimpton,                                    individual listed in the FOR FURTHER
                                             Reports Clearance Officer, National Science             INFORMATION CONTACT section of this                      Please include Docket ID FEMA–
                                             Foundation.                                             document.                                             2012–0026 in the subject line of your
                                             [FR Doc. 2015–13041 Filed 5–28–15; 8:45 am]               • Mail comments to: Regulatory                      comment submission, in order to ensure
                                             BILLING CODE 7555–01–P                                  Affairs Division, Office of Chief                     that FEMA is able to make your
                                                                                                     Counsel, Federal Emergency                            comment submission available to the
                                                                                                     Management Agency, 500 C Street SW.,                  public in this docket.
                                             NUCLEAR REGULATORY                                      Washington, DC 20472–3100.                               All submissions received must
                                             COMMISSION                                                For additional direction on obtaining               include the agency name (FEMA) and
                                                                                                     information and submitting comments,                  docket ID. Regardless of the method
                                             [FEMA–2012–0026, NRC–2015–0133]                                                                               used for submitting comments or
                                                                                                     see ‘‘Obtaining Information and
                                                                                                     Submitting Comments’’ in the                          material, FEMA will post all
                                             Preparation and Evaluation of
                                                                                                     SUPPLEMENTARY INFORMATION section of                  submissions, without change, to
                                             Radiological Emergency Response
                                                                                                     this document.                                        www.regulations.gov and will include
                                             Plans and Preparedness
                                                                                                     FOR FURTHER INFORMATION CONTACT: Don
                                                                                                                                                           any personal information that you
                                             AGENCY: Nuclear Regulatory                              Tailleart, Office of Nuclear Security and             provide. Therefore, submitting this
                                             Commission.                                             Incident Response, U.S. Nuclear                       information makes it public. You may
                                             ACTION: Draft NUREG; request for                        Regulatory Commission, Washington,                    wish to read the Privacy Act notice,
                                             comment.                                                DC 20555–0001; telephone: 301–287–                    which can be viewed by clicking on the
                                                                                                     9257; email: Don.Tailleart@nrc.gov or                 ‘‘Privacy Notice’’ link on the homepage
                                             SUMMARY:   The U.S. Nuclear Regulatory                  William Eberst, Technological Hazards                 of www.regulations.gov.
                                             Commission (NRC) is issuing for public                  Division, National Preparedness                       II. Discussion
                                             comment draft NUREG–0654/FEMA–                          Directorate, Federal Emergency
                                             REP–1, Revision 2, ‘‘Criteria for                                                                                In December 1980, the NRC issued
                                                                                                     Management Agency; Washington, DC
                                             Preparation and Evaluation of                                                                                 NUREG–0654/FEMA–REP–1, Revision
                                                                                                     20472–3100; telephone: 202–341–4917;
                                             Radiological Emergency Response Plans                                                                         1, ‘‘Criteria for Preparation and
                                                                                                     email: William.Eberst@fema.dhs.gov.
                                             and Preparedness in Support of Nuclear                                                                        Evaluation of Radiological Emergency
                                                                                                     SUPPLEMENTARY INFORMATION:                            Response Plans and Preparedness in
                                             Power Plants.’’ This guidance document
                                             was originally issued in December 1980                  I. Obtaining Information and                          Support of Nuclear Power Plants,’’ in
                                             by the NRC in conjunction with the                      Submitting Comments                                   conjunction with FEMA (45 FR 85862;
                                             Federal Emergency Management Agency                                                                           December 30, 1980).
                                             (FEMA). Both agencies use the                           A. Obtaining Information                                 Revision 1 of NUREG–0654/FEMA–
                                             document to evaluate the adequacy of                       Please refer to Docket ID FEMA–                    REP–1 provides guidance on meeting
                                             the emergency plans and preparedness                    2012–0026 when contacting the NRC                     the 16 planning standards for NPP
                                             of commercial nuclear power plant                       about the availability of information for             emergency response plans found in the
                                             (NPP) licensees and applicants, as well                 this action. You may obtain publicly                  NRC’s regulations in paragraph 50.47(b)
                                             as those of State, local, and Tribal                    available information related to this                 of Title 10 of the Code of Federal
                                             governments within the emergency                        action by any of the following methods:               Regulations (10 CFR) and FEMA’s
                                             planning zones (EPZs) surrounding                          • Federal Rulemaking Web site: Go to               regulations set forth in 44 CFR 350.5(a).
                                             commercial NPPs. This revision reflects                 http://www.regulations.gov and search                 Both agencies use the guidance in
                                             changes to the NRC’s and FEMA’s                         for Docket ID FEMA–2012–0026.                         determining compliance with these
                                             regulations, guidance, and policies, as                    • NRC’s Agencywide Documents                       planning standards and evaluating the
Lhorne on DSK2VPTVN1PROD with NOTICES




                                             well as advances in technology and                      Access and Management System                          overall adequacy of the emergency plans
                                             methods for responding to radiological                  (ADAMS): You may obtain publicly                      and preparedness of commercial NPP
                                             incidents that have occurred since the                  available documents online in the                     licensees and applicants, as well as
                                             document was originally issued. It also                 ADAMS Public Documents collection at                  State, local, and Tribal governments
                                             incorporates the four supplemental                      http://www.nrc.gov/reading-rm/                        within the EPZs surrounding
                                             documents and addenda to NUREG–                         adams.html. To begin the search, select               commercial NPPs, for responding to a
                                             0654/FEMA–REP–1, Revision 1, that                       ‘‘ADAMS Public Documents’’ and then                   radiological incident at an NPP.


                                        VerDate Sep<11>2014   15:17 May 28, 2015   Jkt 235001   PO 00000   Frm 00089   Fmt 4703   Sfmt 4703   E:\FR\FM\29MYN1.SGM   29MYN1


                                             30740                           Federal Register / Vol. 80, No. 103 / Friday, May 29, 2015 / Notices

                                                Since the publication of NUREG–                      III. Backfitting and Issue Finality                   SECURITIES AND EXCHANGE
                                             0654/FEMA–REP–1, Revision 1, in                                                                               COMMISSION
                                                                                                        Issuance of NUREG–0654/FEMA–
                                             1980, four supplemental documents and
                                                                                                     REP–1, Revision 2, in final form, would               [Release No. 34–75036; File No. SR–FINRA–
                                             one set of addenda have been issued
                                                                                                     not constitute backfitting under 10 CFR               2015–003]
                                             that update and modify specific
                                                                                                     50.109 and would not otherwise be
                                             planning and procedural elements.                                                                             Self-Regulatory Organizations;
                                                                                                     inconsistent with the issue finality
                                             These documents are available online at                                                                       Financial Industry Regulatory
                                                                                                     provisions in 10 CFR part 52. As
                                             the Federal rulemaking Web site,                                                                              Authority, Inc.; Order Approving
                                                                                                     discussed in section I.B., ‘‘Scope,’’
                                             www.regulations.gov, under Docket ID                                                                          Proposed Rule Change To Amend the
                                                                                                     under the subsection titled ‘‘Use by
                                             FEMA–2012–0026. There have also                         NRC,’’ of NUREG–0654/FEMA–REP–1,                      Code of Arbitration Procedure for
                                             been changes to the NRC’s and FEMA’s                    Revision 2, the NRC has no current                    Customer Disputes and the Code of
                                             regulations, guidance, and policies, as                 intention to impose NUREG–0654/                       Arbitration Procedure for Industry
                                             well as advances in technology and                      FEMA–REP–1, Revision 2, on current                    Disputes To Increase a Fee for the Late
                                             methods for responding to radiological                  holders of a construction permit,                     Cancellation of a Scheduled Hearing,
                                             incidents. The NRC and FEMA are                         operating license, early site permit, or              Lengthen the Notice Period for
                                             revising NUREG–0654/FEMA–REP–1,                         combined license.                                     Cancelling a Scheduled Hearing, and
                                             Revision 1, to incorporate information                                                                        Increase the Amount of Honoraria Paid
                                                                                                        NUREG–0654/FEMA–REP–1,
                                             from the supplements and addenda;                                                                             to Arbitrators Affected by a Late
                                                                                                     Revision 2, if finalized, could be applied
                                             address regulatory, guidance, and policy                                                                      Cancellation of a Scheduled Hearing
                                                                                                     to applications for certain 10 CFR part
                                             changes; and include various emergency
                                                                                                     50 operating licenses or construction                 May 22, 2015.
                                             planning and preparedness lessons
                                                                                                     permits and 10 CFR part 52 combined
                                             learned since its initial publication.                                                                        I. Introduction
                                                                                                     licenses and early site permits. Such
                                                The NRC is developing an emergency                   action would not constitute backfitting                  On February 5, 2015, the Financial
                                             preparedness handbook (a NUREG                          as defined in 10 CFR 50.109 or be                     Industry Regulatory Authority, Inc.
                                             document) in conjunction with the                       otherwise inconsistent with the                       (‘‘FINRA’’) filed with the Securities and
                                             revision of NUREG–0654/FEMA–REP–1.                      applicable issue finality provision in 10             Exchange Commission (‘‘Commission’’),
                                             The handbook will provide amplifying                    CFR part 52, inasmuch as such                         pursuant to Section 19(b)(1) of the
                                             guidance on meeting the intent of the                   applicants are not, with certain                      Securities Exchange Act of 1934 (‘‘Act’’
                                             NUREG–0654/FEMA–REP–1, Revision 2                       exceptions, within the scope of entities              or ‘‘Exchange Act’’) 1 and Rule 19b–4
                                             evaluation criteria applicable to                       protected by 10 CFR 50.109 or the                     thereunder,2 a proposed rule change to
                                             commercial NPP applicants and                           relevant issue finality provisions in 10              amend Rules 12214 and 12601 of
                                             licensees, and the level of detail that                 CFR part 52. This is because neither the              FINRA’s Code of Arbitration Procedure
                                             applicant and licensee emergency plans                  Backfit Rule nor the issue finality                   for Customer Disputes (‘‘Customer
                                             should provide regarding each                           provisions under 10 CFR part 52—with                  Code’’) and Rules 12214 and 12601 of
                                             evaluation criterion. A preliminary draft               certain exclusions discussed below—                   its Code of Arbitration Procedure for
                                             version of the handbook will be                         was intended to apply to every NRC                    Industry Disputes (‘‘Industry Code’’)
                                             available for viewing in ADAMS under                    action that substantially changes the                 (together, ‘‘Codes’’) to increase the fee
                                             Accession No. ML15140A415 during the                    expectations of current and future                    for the late cancellation or
                                             public comment period for NUREG–                        applicants. The exceptions to the                     postponement of a scheduled hearing,
                                             0654/FEMA–REP–1, Revision 2; a final                    general principle are applicable                      lengthen the notice period for cancelling
                                             draft version of the handbook will be                   whenever an applicant references a 10                 or postponing a scheduled hearing
                                             issued at a later time.                                 CFR part 52 license (e.g., an early site              session, and increase the amount of
                                                The NRC and FEMA held two public                     permit), NRC regulatory approval (e.g., a             honoraria paid to arbitrators affected by
                                             meetings on August 22, 2012, and                        design certification rule), or both, with             the late cancellation or postponement of
                                             September 13, 2012, as well as two                      specified issue finality provisions. The              a scheduled hearing session. The
                                             public stakeholder engagement sessions                  staff does not, at this time, intend to               proposed rule change was published for
                                             on October 29–31, 2013, and June 25,                    impose the positions represented in the               comment in the Federal Register on
                                             2014. The public meetings were                          draft NUREG (if finalized) in a manner                February 24, 2015.3 The Commission
                                             conducted in order to: (1) solicit input                that is inconsistent with any issue                   received twelve comment letters on the
                                             from stakeholders and interested                        finality provisions. If, in the future, the           proposal.4 On March 26, 2015, FINRA
                                             members of the public on the scope of                   staff seeks to impose a position in the
                                             future revisions to NUREG–0654/                         draft NUREG (if finalized) in a manner                  1 15  U.S.C. 78s(b)(1).

                                             FEMA–REP–1, Revision 1; (2) describe                    that does not provide issue finality as                 2 17  CFR 240.19b–4.
                                                                                                                                                              3 See Exchange Act Release No. 74289 (Feb. 18,
                                                                                                     described in the applicable issue finality
                                             the proposed timeline for the revisions                                                                       2015), 80 FR 9773 (Feb. 24, 2015) (‘‘Notice’’).
                                                                                                     provision, then the staff must address
                                             to NUREG–0654/FEMA–REP–1,                                                                                        4 See Letters from Steven B. Caruso, Esq., Maddox
                                                                                                     the criteria for avoiding issue finality as           Hargett & Caruso, P.C., dated February 20, 2015
                                             Revision 1; (3) promote transparency,
                                                                                                     described in the applicable issue finality            (‘‘Caruso Letter’’); Philip M. Aidikoff, Aidikoff, Uhl
                                             public participation, and collaboration
                                                                                                     provision.                                            & Bakhtiari, dated February 24, 2015 (‘‘Aidikoff
                                             during the NUREG–0654/FEMA–REP–1,                                                                             Letter’’); George H. Friedman, Esq., George H.
                                             Revision 1, revision process; and (4)                     Dated at Rockville, Maryland, this 20th day         Friedman Consulting, LLC, dated March 1, 2015
                                             allow direct input from stakeholders                    of May, 2015.                                         (‘‘Friedman Letter’’); Joseph C. Pfeiffer, President,
Lhorne on DSK2VPTVN1PROD with NOTICES




                                                                                                       For the U.S. Nuclear Regulatory                     Public Investors Arbitration Bar Association
                                             and the public on changes being made                                                                          (‘‘PIABA’’), dated March 9, 2015 (‘‘PIABA Letter’’);
                                             during the initial writing process.                     Commission.
                                                                                                                                                           Ryan K. Bakhtiari, Aidikoff, Uhl & Bakhtiari, dated
                                             Presentation material and meeting notes                 Brian E. Holian,                                      March 9, 2015 (‘‘Bakhtiari Letter’’); Jasmine Blake-
                                             are available for review on the Federal                 Director, Office of Nuclear Security and              Stewart, Francis Laryea, Jason Robinson, and Darius
                                                                                                     Incident Response.                                    Wood, Student Interns, and Nicole Iannarone,
                                             rulemaking Web site,                                                                                          Assistant Clinical Professor, Investor Advocacy
                                             www.regulations.gov, under Docket ID                    [FR Doc. 2015–13079 Filed 5–28–15; 8:45 am]           Clinic, Georgia State University College of Law,
                                             FEMA–2012–0026.                                         BILLING CODE 7590–01–P                                dated March 13, 2015 (‘‘GSU Letter’’); Mark R.



                                        VerDate Sep<11>2014   15:17 May 28, 2015   Jkt 235001   PO 00000   Frm 00090   Fmt 4703   Sfmt 4703   E:\FR\FM\29MYN1.SGM   29MYN1



Document Created: 2015-12-15 15:31:51
Document Modified: 2015-12-15 15:31:51
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
ActionDraft NUREG; request for comment.
DatesSubmit comments by August 27, 2015. Comments received after this date will be considered if it is practical to do so, but the NRC is able to assure consideration only for comments received on or before this date.
ContactDon Tailleart, Office of Nuclear Security and Incident Response, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001; telephone: 301-287-9257; email: [email protected] or William Eberst, Technological Hazards Division, National Preparedness Directorate, Federal Emergency Management Agency; Washington, DC 20472-3100; telephone: 202-341-4917; email: [email protected]
FR Citation80 FR 30739 