80_FR_32209 80 FR 32101 - Dominion Transmission, Inc.; Notice of Application

80 FR 32101 - Dominion Transmission, Inc.; Notice of Application

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 80, Issue 108 (June 5, 2015)

Page Range32101-32102
FR Document2015-13733

Federal Register, Volume 80 Issue 108 (Friday, June 5, 2015)
[Federal Register Volume 80, Number 108 (Friday, June 5, 2015)]
[Notices]
[Pages 32101-32102]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2015-13733]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket Nos. CP15-492-000]


Dominion Transmission, Inc.; Notice of Application

    Take notice that on May 15, 2015, Dominion Transmission, Inc. 
(DTI), filed an application pursuant to section 7(c) of the Natural Gas 
Act (NGA) and part 157 of the Commission's Regulations, for a 
certificate of public convenience and necessity to construct and 
operate the Leidy South Project (the ``Project''). The various parts of 
the Project will be located in Clinton, Franklin, and Centre Counties, 
Pennsylvania; Frederick County, Maryland; and Loudoun and Fauquier 
Counties, Virginia. The filing may be viewed on the Web at http://www.ferc.gov using the ``eLibrary'' link. Enter the docket number 
excluding the last three digits in the docket number field to access 
the document. For assistance, contact FERC at 
[email protected] or call toll-free, (886) 208-3676 or TYY, 
(202) 502-8659.
    Any questions regarding this application should be directed to 
Matthew R. Bley, Director Gas Transmission Certificates, Dominion 
Transmission, Inc., 701 E. Cary Street, Richmond, VA 23219, call at 
(804) 771-4399, or email [email protected].
    Specifically, DTI proposes to replace two 1,100 horsepower (hp) 
compressor units with one 10,915 hp unit at the Finnefrock Compressor 
Station in Clinton County, PA; install one suction filter/separator at 
the Centre Compressor Station in Centre County, PA; install one 13,220 
hp unit at the Chambersburg Compressor Station in Franklin County, PA; 
install one 15,900 hp unit at the Myersville Compressor Station in 
Frederick County, MD; install one 8,000 hp unit at the Leesburg 
Compressor Station in Loudoun County, VA; install a new cooler and 
filter separator at the Quantico Compressor Station in Fauquier County, 
VA; and construct a new meter station at the Panda Stonewall Power 
Project in Loudoun County, VA. The Project will allow DTI to provide an 
incremental 155 MMcf per day of firm transportation service to three 
electric power generation facilities. The total cost of the Project 
will be approximately $209,657,857.
    Pursuant to section 157.9 of the Commission's rules, 18 CFR 157.9, 
within 90 days of this Notice the Commission staff will either: 
Complete its environmental assessment (EA) and place it into the 
Commission's public record (eLibrary) for this proceeding, or issue a 
Notice of Schedule for Environmental Review. If a Notice of Schedule 
for Environmental Review is issued, it will indicate, among other 
milestones, the anticipated date for the Commission staff's issuance of 
the final environmental impact statement (FEIS) or EA for this 
proposal. The filing of the EA in the Commission's public record for 
this proceeding or the issuance of a Notice of Schedule will serve to 
notify federal and state agencies of the timing for the completion of 
all necessary reviews, and the subsequent need to complete all federal 
authorizations within 90 days of the date of issuance of the Commission 
staff's FEIS or EA.
    There are two ways to become involved in the Commission's review of 
this project. First, any person wishing to obtain legal status by 
becoming a party to the proceedings for this project should, on or 
before the comment date stated below, file with the Federal Energy 
Regulatory Commission, 888 First Street NE., Washington, DC 20426, a 
motion to intervene in accordance with the requirements of the 
Commission's Rules of Practice and Procedure (18 CFR 385.214 or 
385.211) and the Regulations under the NGA (18 CFR 157.10). A person 
obtaining party status will be placed on the service list maintained by 
the Secretary of the Commission and will receive copies of all 
documents filed by the applicant and by all other parties. A party must 
submit 5 copies of filings made with the Commission and must mail a 
copy to the applicant and to every other party in the proceeding. Only 
parties to the proceeding can ask for court review of Commission orders 
in the proceeding.
    However, a person does not have to intervene in order to have 
comments considered. The second way to participate is by filing with 
the Secretary of the Commission, as soon as possible, an original and 
two copies of comments in support of or in opposition to this project. 
The Commission will consider these comments in determining the 
appropriate action to be taken, but the filing of a comment alone will 
not serve to make the filer a party to the proceeding. The Commission's 
rules require that persons filing comments in opposition to the project 
provide copies of their protests only to the party or parties directly 
involved in the protest.
    Persons who wish to comment only on the environmental review of 
this project should submit an original and two copies of their comments 
to the Secretary of the Commission. Environmental commenters will be 
placed on the Commission's environmental mailing list, will receive 
copies of the environmental documents, and will be notified of meetings 
associated with the Commission's environmental review process. 
Environmental commenters will not be required to serve copies of filed 
documents on all other parties. However, the non-party commenters will 
not receive copies of all documents filed by other parties or issued by 
the Commission (except for the mailing of environmental documents 
issued by the Commission) and will not have the right to seek court 
review of the Commission's final order.
    Motions to intervene, protests and comments may be filed 
electronically via the internet in lieu of paper; see, 18 CFR 
385.2001(a)(1)(iii) and the instructions on the Commission's Web site 
under the ``e-Filing'' link. The Commission strongly encourages 
electronic filings.
    Comment Date: 5 p.m. Eastern Time on June 17, 2015.


[[Page 32102]]


    Dated: May 27, 2015.
Kimberly D. Bose,
Secretary.
[FR Doc. 2015-13733 Filed 6-4-15; 8:45 am]
BILLING CODE 6717-01-P



                                                                                     Federal Register / Vol. 80, No. 108 / Friday, June 5, 2015 / Notices                                            32101

                                                    or call toll free 1–866–208–3372 (voice)                   Any questions regarding this                        Procedure (18 CFR 385.214 or 385.211)
                                                    or 202–502–8659 (TTY), or send a FAX                    application should be directed to                      and the Regulations under the NGA (18
                                                    to 202–208–2106 with the required                       Matthew R. Bley, Director Gas                          CFR 157.10). A person obtaining party
                                                    accommodations.                                         Transmission Certificates, Dominion                    status will be placed on the service list
                                                       Prior to the conference, Commission                  Transmission, Inc., 701 E. Cary Street,                maintained by the Secretary of the
                                                    staff will post conference materials on                 Richmond, VA 23219, call at (804) 771–                 Commission and will receive copies of
                                                    the Commission’s Web site,                              4399, or email Matthew.R.Bley@                         all documents filed by the applicant and
                                                    www.ferc.gov (navigate to Documents &                   dom.com.                                               by all other parties. A party must submit
                                                    Filings, then Forms, then eForms                           Specifically, DTI proposes to replace
                                                                                                                                                                   5 copies of filings made with the
                                                    Refresh). The conference will also be                   two 1,100 horsepower (hp) compressor
                                                                                                                                                                   Commission and must mail a copy to
                                                    webcast and transcribed. The webcast                    units with one 10,915 hp unit at the
                                                                                                            Finnefrock Compressor Station in                       the applicant and to every other party in
                                                    will be available through a link on the                                                                        the proceeding. Only parties to the
                                                    Commission’s Calendar of Events,                        Clinton County, PA; install one suction
                                                                                                            filter/separator at the Centre Compressor              proceeding can ask for court review of
                                                    available at http://www.ferc.gov. An
                                                                                                            Station in Centre County, PA; install                  Commission orders in the proceeding.
                                                    email account has been created for off-
                                                    site participants to submit questions for               one 13,220 hp unit at the Chambersburg                    However, a person does not have to
                                                    the question and answer session at the                  Compressor Station in Franklin County,                 intervene in order to have comments
                                                    technical conference. Please email                      PA; install one 15,900 hp unit at the                  considered. The second way to
                                                    questions at any time to                                Myersville Compressor Station in                       participate is by filing with the
                                                    eForms.Refresh@ferc.gov.                                Frederick County, MD; install one 8,000                Secretary of the Commission, as soon as
                                                       For more information about this                      hp unit at the Leesburg Compressor                     possible, an original and two copies of
                                                    conference please contact Robert                        Station in Loudoun County, VA; install                 comments in support of or in opposition
                                                    Hudson (Technical Information), Office                  a new cooler and filter separator at the               to this project. The Commission will
                                                    of Enforcement, at (202) 502–6620 or                    Quantico Compressor Station in                         consider these comments in
                                                    Robert.Hudson@ferc.gov or Sarah                         Fauquier County, VA; and construct a                   determining the appropriate action to be
                                                    McKinley (Logistical Information),                      new meter station at the Panda                         taken, but the filing of a comment alone
                                                    Office of External Affairs at (202) 502–                Stonewall Power Project in Loudoun
                                                                                                                                                                   will not serve to make the filer a party
                                                    8368 or Sarah.McKinley@ferc.gov.                        County, VA. The Project will allow DTI
                                                                                                                                                                   to the proceeding. The Commission’s
                                                                                                            to provide an incremental 155 MMcf per
                                                      Dated: May 29, 2015.                                  day of firm transportation service to                  rules require that persons filing
                                                    Nathaniel J. Davis, Sr.,                                three electric power generation                        comments in opposition to the project
                                                    Deputy Secretary.                                       facilities. The total cost of the Project              provide copies of their protests only to
                                                    [FR Doc. 2015–13725 Filed 6–4–15; 8:45 am]              will be approximately $209,657,857.                    the party or parties directly involved in
                                                    BILLING CODE 6717–01–P                                     Pursuant to section 157.9 of the                    the protest.
                                                                                                            Commission’s rules, 18 CFR 157.9,                         Persons who wish to comment only
                                                                                                            within 90 days of this Notice the                      on the environmental review of this
                                                    DEPARTMENT OF ENERGY                                    Commission staff will either: Complete                 project should submit an original and
                                                                                                            its environmental assessment (EA) and                  two copies of their comments to the
                                                    Federal Energy Regulatory                               place it into the Commission’s public                  Secretary of the Commission.
                                                    Commission                                              record (eLibrary) for this proceeding, or              Environmental commenters will be
                                                                                                            issue a Notice of Schedule for                         placed on the Commission’s
                                                    [Docket Nos. CP15–492–000]                              Environmental Review. If a Notice of                   environmental mailing list, will receive
                                                                                                            Schedule for Environmental Review is
                                                                                                                                                                   copies of the environmental documents,
                                                    Dominion Transmission, Inc.; Notice of                  issued, it will indicate, among other
                                                                                                                                                                   and will be notified of meetings
                                                    Application                                             milestones, the anticipated date for the
                                                                                                                                                                   associated with the Commission’s
                                                                                                            Commission staff’s issuance of the final
                                                       Take notice that on May 15, 2015,                    environmental impact statement (FEIS)                  environmental review process.
                                                    Dominion Transmission, Inc. (DTI),                      or EA for this proposal. The filing of the             Environmental commenters will not be
                                                    filed an application pursuant to section                EA in the Commission’s public record                   required to serve copies of filed
                                                    7(c) of the Natural Gas Act (NGA) and                   for this proceeding or the issuance of a               documents on all other parties.
                                                    part 157 of the Commission’s                            Notice of Schedule will serve to notify                However, the non-party commenters
                                                    Regulations, for a certificate of public                federal and state agencies of the timing               will not receive copies of all documents
                                                    convenience and necessity to construct                  for the completion of all necessary                    filed by other parties or issued by the
                                                    and operate the Leidy South Project (the                reviews, and the subsequent need to                    Commission (except for the mailing of
                                                    ‘‘Project’’). The various parts of the                  complete all federal authorizations                    environmental documents issued by the
                                                    Project will be located in Clinton,                     within 90 days of the date of issuance                 Commission) and will not have the right
                                                    Franklin, and Centre Counties,                          of the Commission staff’s FEIS or EA.                  to seek court review of the
                                                    Pennsylvania; Frederick County,                            There are two ways to become                        Commission’s final order.
                                                    Maryland; and Loudoun and Fauquier                      involved in the Commission’s review of                    Motions to intervene, protests and
                                                    Counties, Virginia. The filing may be                   this project. First, any person wishing to
                                                                                                                                                                   comments may be filed electronically
                                                    viewed on the Web at http://                            obtain legal status by becoming a party
asabaliauskas on DSK5VPTVN1PROD with NOTICES




                                                                                                                                                                   via the internet in lieu of paper; see, 18
                                                    www.ferc.gov using the ‘‘eLibrary’’ link.               to the proceedings for this project
                                                                                                                                                                   CFR 385.2001(a)(1)(iii) and the
                                                    Enter the docket number excluding the                   should, on or before the comment date
                                                                                                                                                                   instructions on the Commission’s Web
                                                    last three digits in the docket number                  stated below, file with the Federal
                                                    field to access the document. For                       Energy Regulatory Commission, 888                      site under the ‘‘e-Filing’’ link. The
                                                    assistance, contact FERC at                             First Street NE., Washington, DC 20426,                Commission strongly encourages
                                                    FERCOnlineSupport@ferc.gov or call                      a motion to intervene in accordance                    electronic filings.
                                                    toll-free, (886) 208–3676 or TYY, (202)                 with the requirements of the                              Comment Date: 5 p.m. Eastern Time
                                                    502–8659.                                               Commission’s Rules of Practice and                     on June 17, 2015.


                                               VerDate Sep<11>2014   18:31 Jun 04, 2015   Jkt 235001   PO 00000   Frm 00020   Fmt 4703   Sfmt 4703   E:\FR\FM\05JNN1.SGM   05JNN1


                                                    32102                            Federal Register / Vol. 80, No. 108 / Friday, June 5, 2015 / Notices

                                                      Dated: May 27, 2015.                                  2790 Notice of Termination ATC-Alliant                    Docket Numbers: RR15–10–000.
                                                    Kimberly D. Bose,                                       OA to be effective 7/29/2015.                             Applicants: North American Electric
                                                    Secretary.                                                 Filed Date: 5/29/15.                                Reliability Corp.
                                                    [FR Doc. 2015–13733 Filed 6–4–15; 8:45 am]                 Accession Number: 20150529–5315.                       Description: North American Electric
                                                    BILLING CODE 6717–01–P
                                                                                                               Comments Due: 5 p.m. ET 6/19/15.                    Reliability Corporation’s Report of
                                                                                                               Docket Numbers: ER15–1815–000.                      Budgeted to Actual Costs for 2014 for
                                                                                                               Applicants: Public Service Company                  NERC and the Regional Entities.
                                                    DEPARTMENT OF ENERGY                                    of New Hampshire.                                         Filed Date: 5/29/15.
                                                                                                               Description: Section 205(d) rate filing                Accession Number: 20150529–5246.
                                                    Federal Energy Regulatory                               per 35.13(a)(2)(iii): Joint Market Based                  Comments Due: 5 p.m. ET 6/19/15.
                                                    Commission                                              Tariff to be effective 5/30/2015.                         The filings are accessible in the
                                                                                                               Filed Date: 5/29/15.                                Commission’s eLibrary system by
                                                    Combined Notice of Filings #2                              Accession Number: 20150529–5316.                    clicking on the links or querying the
                                                       Take notice that the Commission                         Comments Due: 5 p.m. ET 6/19/15.                    docket number.
                                                    received the following electric corporate                  Docket Numbers: ER15–1816–000.                         Any person desiring to intervene or
                                                    filings:                                                   Applicants: Western Massachusetts                   protest in any of the above proceedings
                                                       Docket Numbers: EC15–149–000.                        Electric Company.                                      must file in accordance with Rules 211
                                                       Applicants: American Transmission                       Description: Section 205(d) rate filing             and 214 of the Commission’s
                                                    Company LLC.                                            per 35.13(a)(2)(iii): Joint Market Based               Regulations (18 CFR 385.211 and
                                                       Description: Application for                         Tariff to be effective 5/30/2015.                      385.214) on or before 5:00 p.m. Eastern
                                                    Authority to Acquire Transmission                          Filed Date: 5/29/15.                                time on the specified comment date.
                                                                                                               Accession Number: 20150529–5322.                    Protests may be considered, but
                                                    Facilities Under Section 203 of the FPA
                                                                                                               Comments Due: 5 p.m. ET 6/19/15.                    intervention is necessary to become a
                                                    of American Transmission Company
                                                    LLC.                                                       Docket Numbers: ER15–1817–000.                      party to the proceeding.
                                                       Filed Date: 5/29/15.                                    Applicants: San Diego Gas & Electric                   eFiling is encouraged. More detailed
                                                       Accession Number: 20150529–5347.                     Company.                                               information relating to filing
                                                       Comments Due: 5 p.m. ET 6/19/15.                        Description: Fourth Annual                          requirements, interventions, protests,
                                                                                                            Informational Filing [Cycle 4] of Fourth               service, and qualifying facilities filings
                                                       Take notice that the Commission                      Transmission Owner Rate Formula rate                   can be found at: http://www.ferc.gov/
                                                    received the following electric rate                    mechanism of San Diego Gas & Electric                  docs-filing/efiling/filing-req.pdf. For
                                                    filings:                                                Company.                                               other information, call (866) 208–3676
                                                       Docket Numbers: ER13–136–003;                           Filed Date: 5/29/15.                                (toll free). For TTY, call (202) 502–8659.
                                                    ER13–135–003; ER13–137–003; ER13–                          Accession Number: 20150529–5344.                      Dated: May 29, 2015.
                                                    138–003; ER13–141–003; ER13–142–                           Comments Due: 5 p.m. ET 6/19/15.
                                                    003.                                                                                                           Nathaniel J. Davis, Sr.,
                                                                                                               Docket Numbers: ER15–1818–000.                      Deputy Secretary.
                                                       Applicants: Georgia-Pacific Brewton                     Applicants: Southern Company
                                                    LLC.                                                    Services, Inc.
                                                                                                                                                                   [FR Doc. 2015–13727 Filed 6–4–15; 8:45 am]
                                                       Description: Supplement to December                     Description: Notice of Termination of               BILLING CODE 6717–01–P
                                                    30, 2014 Updated Market Power                           Service Agreement for Network
                                                    Analysis in Southeast Region of the                     Integration Transmission Service and
                                                    Georgia-Pacific Entities.                                                                                      DEPARTMENT OF ENERGY
                                                                                                            Network Operating Agreement between
                                                       Filed Date: 5/29/15.                                 City of Seneca, South Carolina and
                                                       Accession Number: 20150529–5284.                                                                            Federal Energy Regulatory
                                                                                                            Southern Company Services, Inc., as                    Commission
                                                       Comments Due: 5 p.m. ET 6/19/15.                     agent for Southern Companies.
                                                       Docket Numbers: ER15–1812–000.                          Filed Date: 5/29/15.                                [Docket No. CP15–493–000]
                                                       Applicants: Midcontinent                                Accession Number: 20150529–5346.
                                                    Independent System Operator, Inc.                          Comments Due: 5 p.m. ET 6/19/15.                    Notice of Application; El Paso Natural
                                                       Description: Section 205(d) rate filing                                                                     Gas Company, LLC
                                                                                                               Docket Numbers: ER15–1819–000.
                                                    per 35.13(a)(2)(iii): 2015–05–29_SA                        Applicants: CED Atwell Island West,                    Take notice that on May 19, 2015, El
                                                    2790 ATC-Alliant Energy Operating                       LLC.                                                   Paso Natural Gas Company, L.L.C. (El
                                                    Agreement to be effective 7/29/2015.                       Description: Initial rate filing per                Paso), P.O. Box 1087, Colorado Springs,
                                                       Filed Date: 5/29/15.                                 35.12 CED Atwell West LLC Co-Tenancy                   Colorado 80944, filed an application
                                                       Accession Number: 20150529–5245.                     Filing to be effective 5/31/2015.                      pursuant to section 3 of the Natural Gas
                                                       Comments Due: 5 p.m. ET 6/19/15.                        Filed Date: 5/29/15.                                Act (NGA) and Part 153 of the
                                                       Docket Numbers: ER15–1813–000.                          Accession Number: 20150529–5359.                    Commission’s regulations to amend its
                                                       Applicants: The Connecticut Light                       Comments Due: 5 p.m. ET 6/19/15.                    Monument 90 Presidential Permit to
                                                    and Power Company.                                         Docket Numbers: ER15–1820–000.                      establish a maximum export capacity of
                                                       Description: Section 205(d) rate filing                 Applicants: SPS Atwell Island, LLC.                 56.9 million cubic feet per day at its
                                                    per 35.13(a)(2)(iii): Joint Market Based                   Description: Initial rate filing per                existing international border crossing
                                                    Tariff to be effective 5/30/2015.                       35.12 Filing of Co-Tenancy and                         from the United States into Mexico
asabaliauskas on DSK5VPTVN1PROD with NOTICES




                                                       Filed Date: 5/29/15.                                 Common Facilities Agreement to be                      located in Cochise County, Arizona, all
                                                       Accession Number: 20150529–5294.                     effective 5/29/2015.                                   as more fully set forth in the application
                                                       Comments Due: 5 p.m. ET 6/19/15.                        Filed Date: 5/29/15.                                which is on file with the Commission
                                                       Docket Numbers: ER15–1814–000.                          Accession Number: 20150529–5424.                    and open to public inspection. The
                                                       Applicants: Midcontinent                                Comments Due: 5 p.m. ET 6/19/15.                    filing may also be viewed on the web at
                                                    Independent System Operator, Inc.                          Take notice that the Commission                     http://www.ferc.gov using the
                                                       Description: Section 205(d) rate filing              received the following electric                        ‘‘eLibrary’’ link. Enter the docket
                                                    per 35.13(a)(2)(iii): 2015–05–29_SA                     reliability filings:                                   number excluding the last three digits in


                                               VerDate Sep<11>2014   18:31 Jun 04, 2015   Jkt 235001   PO 00000   Frm 00021   Fmt 4703   Sfmt 4703   E:\FR\FM\05JNN1.SGM   05JNN1



Document Created: 2015-12-15 15:20:38
Document Modified: 2015-12-15 15:20:38
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
Dates5 p.m. Eastern Time on June 17, 2015.
FR Citation80 FR 32101 

2025 Federal Register | Disclaimer | Privacy Policy
USC | CFR | eCFR