80_FR_32478 80 FR 32369 - Dominion Transmission, Inc.; Notice of Availability of the Environmental Assessment for the Proposed Lebanon West II Project

80 FR 32369 - Dominion Transmission, Inc.; Notice of Availability of the Environmental Assessment for the Proposed Lebanon West II Project

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 80, Issue 109 (June 8, 2015)

Page Range32369-32370
FR Document2015-13897

Federal Register, Volume 80 Issue 109 (Monday, June 8, 2015)
[Federal Register Volume 80, Number 109 (Monday, June 8, 2015)]
[Notices]
[Pages 32369-32370]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2015-13897]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP14-555-000]


Dominion Transmission, Inc.; Notice of Availability of the 
Environmental Assessment for the Proposed Lebanon West II Project

    The staff of the Federal Energy Regulatory Commission (FERC or 
Commission) has prepared an environmental assessment (EA) for the 
Lebanon West II Project, proposed by Dominion Transmission, Inc. 
(Dominion) in the above-referenced docket. Dominion requests 
authorization to replace 11 non-contiguous segments of its 26- and 30-
inch-diameter TL-400 Pipeline totaling about 10.2 miles, add a 10,915-
horsepower compressor unit to an existing compressor station, and 
install other compressor station and gate assembly facilities. Dominion 
also proposes to increase the maximum allowable operating pressure 
(MAOP) of these pipeline segments from 745 pounds per square inch gauge 
(psig) to 848 psig. The project would allow Dominion to transport an 
additional 130,000 dekatherms per day from Dominion's MarkWest Liberty 
Bluestone Interconnect in Butler County, Pennsylvania to Dominion's 
Lebanon-Texas Gas Interconnect in Warren County, Ohio.
    The EA assesses the potential environmental effects of the 
activities associated with the project in accordance with the 
requirements of the National Environmental Policy Act. The FERC staff 
concludes that approval of the proposed project, with appropriate 
mitigating measures, would not constitute a major federal action 
significantly affecting the quality of the human environment.
    The FERC staff mailed copies of the EA to federal, state, and local 
government representatives and agencies; elected officials; Native 
American tribes; potentially affected landowners; newspapers and 
libraries in the project area; and parties to this proceeding. In 
addition, the EA is available for public viewing on the FERC's Web site 
(www.ferc.gov) using the eLibrary link. A limited number of copies of 
the EA are available for distribution and public inspection at: Federal 
Energy Regulatory Commission, Public Reference Room, 888 First Street 
NE., Room 2A, Washington, DC 20426, (202) 502-8371.
    Any person wishing to comment on the EA may do so. Your comments 
should focus on the potential environmental effects, reasonable 
alternatives, and measures to avoid or lessen environmental impacts. 
The more specific your comments, the more useful they will be. To 
ensure that the Commission has the opportunity to consider your 
comments prior to making its decision on this project, it is important 
that we receive your comments in Washington, DC on or before July 2, 
2015.
    For your convenience, there are three methods you can use to file 
your comments with the Commission. In all instances please reference 
the project docket number (CP14-555-000) with your submission. The 
Commission encourages electronic filing of comments and has expert 
staff available to assist you at 202-502-8258 or [email protected].
    (1) You can file your comments electronically using the eComment 
feature located on the Commission's Web site (www.ferc.gov) under the 
link to Documents and Filings. This is an easy method for submitting 
brief, text-only comments on a project;
    (2) You can also file your comments electronically using the 
eFiling feature on the Commission's Web site (www.ferc.gov) under the 
link to Documents and Filings. With eFiling, you can provide comments 
in a variety of formats by attaching them as a file with your 
submission. New eFiling users must first create an account by clicking 
on ``eRegister.'' You must select the type of filing you are making. If 
you are filing a comment on a particular project, please select 
``Comment on a Filing''; or
    (3) You can file a paper copy of your comments by mailing them to 
the following address: Kimberly D. Bose, Secretary, Federal Energy 
Regulatory Commission, 888 First Street NE., Room 1A, Washington, DC 
20426.
    Any person seeking to become a party to the proceeding must file a 
motion to intervene pursuant to Rule 214 of the

[[Page 32370]]

Commission's Rules of Practice and Procedures (18 CFR 385.214).\1\ Only 
intervenors have the right to seek rehearing of the Commission's 
decision. The Commission grants affected landowners and others with 
environmental concerns intervenor status upon showing good cause by 
stating that they have a clear and direct interest in this proceeding 
which no other party can adequately represent. Simply filing 
environmental comments will not give you intervenor status, but you do 
not need intervenor status to have your comments considered.
---------------------------------------------------------------------------

    \1\ See the previous discussion on the methods for filing 
comments.
---------------------------------------------------------------------------

    Additional information about the Project is available from the 
Commission's Office of External Affairs, at (866) 208-FERC, or on the 
FERC Web site (www.ferc.gov) using the eLibrary link. Click on the 
eLibrary link, click on ``General Search,'' and enter the docket number 
excluding the last three digits in the Docket Number field (i.e., CP14-
555). Be sure you have selected an appropriate date range. For 
assistance, please contact FERC Online Support at 
[email protected] or toll free at (866) 208-3676, or for TTY, 
contact (202) 502-8659. The eLibrary link also provides access to the 
texts of formal documents issued by the Commission, such as orders, 
notices, and rulemakings.
    In addition, the Commission offers a free service called 
eSubscription which allows you to keep track of all formal issuances 
and submittals in specific dockets. This can reduce the amount of time 
you spend researching proceedings by automatically providing you with 
notification of these filings, document summaries, and direct links to 
the documents. Go to www.ferc.gov/docs-filing/esubscription.asp.

    Dated: June 2, 2015.
Kimberly D. Bose,
Secretary.
[FR Doc. 2015-13897 Filed 6-5-15; 8:45 am]
 BILLING CODE 6717-17-P



                                                                                  Federal Register / Vol. 80, No. 109 / Monday, June 8, 2015 / Notices                                             32369

                                                  Minnesota. The Upper St. Anthony Lock                      More information about this project,                government representatives and
                                                  and Dam is owned and operated by U.S.                   including a copy of the application, can               agencies; elected officials; Native
                                                  Army Corps of Engineers. The sole                       be viewed or printed on the ‘‘eLibrary’’               American tribes; potentially affected
                                                  purpose of a preliminary permit, if                     link of Commission’s Web site at                       landowners; newspapers and libraries in
                                                  issued, is to grant the permit holder                   http://www.ferc.gov/docs-filing/                       the project area; and parties to this
                                                  priority to file a license application                  elibrary.asp. Enter the docket number                  proceeding. In addition, the EA is
                                                  during the permit term. A preliminary                   (P–14671) in the docket number field to                available for public viewing on the
                                                  permit does not authorize the permit                    access the document. For assistance,                   FERC’s Web site (www.ferc.gov) using
                                                  holder to perform any land-disturbing                   contact FERC Online Support.                           the eLibrary link. A limited number of
                                                  activities or otherwise enter upon lands                  Dated: June 2, 2015.                                 copies of the EA are available for
                                                  or waters owned by others without the                                                                          distribution and public inspection at:
                                                                                                          Kimberly D. Bose,
                                                  owners’ express permission.                                                                                    Federal Energy Regulatory Commission,
                                                     The proposed project would be                        Secretary.                                             Public Reference Room, 888 First Street
                                                  located completely within lands owned                   [FR Doc. 2015–13902 Filed 6–5–15; 8:45 am]             NE., Room 2A, Washington, DC 20426,
                                                  by the United States and consist of: (1)                BILLING CODE 6717–01–P                                 (202) 502–8371.
                                                  The existing 400-foot-long by 56-foot-                                                                            Any person wishing to comment on
                                                  wide by 77-foot-high lock (2) two new                                                                          the EA may do so. Your comments
                                                  56-foot-wide by 70-foot high vertical lift              DEPARTMENT OF ENERGY                                   should focus on the potential
                                                  steel gates; (3) two new submersible                                                                           environmental effects, reasonable
                                                  1700-kilowatt axial flow Kaplan turbine-                Federal Energy Regulatory                              alternatives, and measures to avoid or
                                                  generator units having a combined                       Commission                                             lessen environmental impacts. The more
                                                  capacity of 3.4 megawatts; (4) two new                  [Docket No. CP14–555–000]                              specific your comments, the more useful
                                                  6-foot-long by 6-foot-wide by 4-foot-high                                                                      they will be. To ensure that the
                                                  pad mounted metal boxes containing                      Dominion Transmission, Inc.; Notice of                 Commission has the opportunity to
                                                  plant controls, communications and                      Availability of the Environmental                      consider your comments prior to
                                                  inverter equipment, and a step-up                       Assessment for the Proposed Lebanon                    making its decision on this project, it is
                                                  distribution transformer; (5) a new 400                 West II Project                                        important that we receive your
                                                  to 500-foot-long, 13.8 kilovolt,                                                                               comments in Washington, DC on or
                                                  underground transmission line that                         The staff of the Federal Energy                     before July 2, 2015.
                                                  would connect to Xcel Energy’s                          Regulatory Commission (FERC or                            For your convenience, there are three
                                                  distribution system; and (6) appurtenant                Commission) has prepared an                            methods you can use to file your
                                                  facilities. The project would have an                   environmental assessment (EA) for the                  comments with the Commission. In all
                                                  estimated annual generation of 18,500                   Lebanon West II Project, proposed by                   instances please reference the project
                                                  megawatt-hours.                                         Dominion Transmission, Inc.                            docket number (CP14–555–000) with
                                                     Applicant Contact: Robert H. Schulte,                (Dominion) in the above-referenced                     your submission. The Commission
                                                  2236 Coley Forest Place, Raleigh, NC                    docket. Dominion requests                              encourages electronic filing of
                                                  27607, (952) 949–2676.                                  authorization to replace 11 non-                       comments and has expert staff available
                                                     FERC Contact: Tyrone A. Williams,                    contiguous segments of its 26- and 30-                 to assist you at 202–502–8258 or
                                                  (202) 502–6331.                                         inch-diameter TL–400 Pipeline totaling                 efiling@ferc.gov.
                                                     Deadline for filing comments, motions                about 10.2 miles, add a 10,915-                           (1) You can file your comments
                                                  to intervene, competing applications                    horsepower compressor unit to an                       electronically using the eComment
                                                  (without notices of intent), or notices of              existing compressor station, and install               feature located on the Commission’s
                                                  intent to file competing applications: 60               other compressor station and gate                      Web site (www.ferc.gov) under the link
                                                  days from the issuance of this notice.                  assembly facilities. Dominion also                     to Documents and Filings. This is an
                                                  Competing applications and notices of                   proposes to increase the maximum                       easy method for submitting brief, text-
                                                  intent must meet the requirements of 18                 allowable operating pressure (MAOP) of                 only comments on a project;
                                                  CFR 4.36. The Commission strongly                       these pipeline segments from 745                          (2) You can also file your comments
                                                  encourages electronic filing. Please file               pounds per square inch gauge (psig) to                 electronically using the eFiling feature
                                                  comments, motions to intervene, notices                 848 psig. The project would allow                      on the Commission’s Web site
                                                  of intent, and competing applications                   Dominion to transport an additional                    (www.ferc.gov) under the link to
                                                  using the Commission’s eFiling system                   130,000 dekatherms per day from                        Documents and Filings. With eFiling,
                                                  at http://www.ferc.gov/docs-filing/                     Dominion’s MarkWest Liberty Bluestone                  you can provide comments in a variety
                                                  efiling.asp. Commenters can submit                      Interconnect in Butler County,                         of formats by attaching them as a file
                                                  brief comments up to 6,000 characters,                  Pennsylvania to Dominion’s Lebanon-                    with your submission. New eFiling
                                                  without prior registration, using the                   Texas Gas Interconnect in Warren                       users must first create an account by
                                                  eComment system at http://                              County, Ohio.                                          clicking on ‘‘eRegister.’’ You must select
                                                  www.ferc.gov/docs-filing/                                  The EA assesses the potential                       the type of filing you are making. If you
                                                  ecomment.asp. You must include your                     environmental effects of the activities                are filing a comment on a particular
                                                  name and contact information at the end                 associated with the project in                         project, please select ‘‘Comment on a
                                                  of your comments. For assistance,                       accordance with the requirements of the                Filing’’; or
                                                  please contact FERC Online Support at                   National Environmental Policy Act. The                    (3) You can file a paper copy of your
mstockstill on DSK4VPTVN1PROD with NOTICES




                                                  FERCOnlineSupport@ferc.gov, (866)                       FERC staff concludes that approval of                  comments by mailing them to the
                                                  208–3676 (toll free), or (202) 502–8659                 the proposed project, with appropriate                 following address: Kimberly D. Bose,
                                                  (TTY). In lieu of electronic filing, please             mitigating measures, would not                         Secretary, Federal Energy Regulatory
                                                  send a paper copy to: Secretary, Federal                constitute a major federal action                      Commission, 888 First Street NE., Room
                                                  Energy Regulatory Commission, 888                       significantly affecting the quality of the             1A, Washington, DC 20426.
                                                  First Street NE., Washington, DC 20426.                 human environment.                                        Any person seeking to become a party
                                                  The first page of any filing should                        The FERC staff mailed copies of the                 to the proceeding must file a motion to
                                                  include docket number P–14671–000.                      EA to federal, state, and local                        intervene pursuant to Rule 214 of the


                                             VerDate Sep<11>2014   17:09 Jun 05, 2015   Jkt 235001   PO 00000   Frm 00032   Fmt 4703   Sfmt 4703   E:\FR\FM\08JNN1.SGM   08JNN1


                                                  32370                                      Federal Register / Vol. 80, No. 109 / Monday, June 8, 2015 / Notices

                                                  Commission’s Rules of Practice and                                       dockets. This can reduce the amount of                                    the MISO–PJM Joint Operating
                                                  Procedures (18 CFR 385.214).1 Only                                       time you spend researching proceedings                                    Agreement (JOA) and the MISO–PJM
                                                  intervenors have the right to seek                                       by automatically providing you with                                       seam. The conference will be held at the
                                                  rehearing of the Commission’s decision.                                  notification of these filings, document                                   Commission’s headquarters at 888 First
                                                  The Commission grants affected                                           summaries, and direct links to the                                        Street NE., Washington, DC 20426 in the
                                                  landowners and others with                                               documents. Go to www.ferc.gov/docs-                                       Commission Meeting Room. An updated
                                                  environmental concerns intervenor                                        filing/esubscription.asp.                                                 agenda identifying panelists for this
                                                  status upon showing good cause by                                          Dated: June 2, 2015.                                                    conference is attached.
                                                  stating that they have a clear and direct                                                                                                             The technical conference will not be
                                                                                                                           Kimberly D. Bose,
                                                  interest in this proceeding which no                                                                                                               transcribed. However, there will be a
                                                                                                                           Secretary.
                                                  other party can adequately represent.                                                                                                              free webcast of the conference. The
                                                  Simply filing environmental comments                                     [FR Doc. 2015–13897 Filed 6–5–15; 8:45 am]
                                                                                                                                                                                                     webcast will allow persons to listen to
                                                  will not give you intervenor status, but                                 BILLING CODE 6717–17–P
                                                                                                                                                                                                     the technical conference, but not
                                                  you do not need intervenor status to                                                                                                               participate. Anyone with internet access
                                                  have your comments considered.                                                                                                                     who wants to listen to the conference
                                                     Additional information about the                                      DEPARTMENT OF ENERGY
                                                                                                                                                                                                     can do so by navigating to the Calendar
                                                  Project is available from the
                                                                                                                           Federal Energy Regulatory                                                 of Events at www.ferc.gov and locating
                                                  Commission’s Office of External Affairs,
                                                                                                                           Commission                                                                the technical conference in the
                                                  at (866) 208–FERC, or on the FERC Web
                                                                                                                                                                                                     Calendar. The technical conference will
                                                  site (www.ferc.gov) using the eLibrary                                   [Docket No. EL13–88–000]                                                  contain a link to its webcast. The
                                                  link. Click on the eLibrary link, click on
                                                                                                                                                                                                     Capitol Connection provides technical
                                                  ‘‘General Search,’’ and enter the docket                                 Northern Indiana Public Service                                           support for the webcast and offers the
                                                  number excluding the last three digits in                                Company v. Midcontinent Independent                                       option of listening to the meeting via
                                                  the Docket Number field (i.e., CP14–                                     System Operator, Inc. and PJM
                                                  555). Be sure you have selected an                                                                                                                 phone-bridge for a fee. If you have any
                                                                                                                           Interconnection, LLC; Supplemental                                        questions, visit
                                                  appropriate date range. For assistance,                                  Notice of Technical Conference
                                                  please contact FERC Online Support at                                                                                                              www.CapitolConnection.org or call 703–
                                                  FercOnlineSupport@ferc.gov or toll free                                     As announced in the notice issued on                                   993–3100.1
                                                  at (866) 208–3676, or for TTY, contact                                   May 5, 2015, the Federal Energy                                              While the purpose of this conference
                                                  (202) 502–8659. The eLibrary link also                                   Regulatory Commission will hold a                                         is to discuss the matter pending before
                                                  provides access to the texts of formal                                   technical conference on June 15, 2015                                     the Commission in Docket No. EL13–88
                                                  documents issued by the Commission,                                      from 9:00 a.m. to 4:00 p.m. to explore                                    and is not for the purpose of discussing
                                                  such as orders, notices, and                                             issues raised in the complaint filed by                                   other specific cases, we note that the
                                                  rulemakings.                                                             Northern Indiana Public Service                                           discussions at the conference may
                                                     In addition, the Commission offers a                                  Company (NIPSCO) against                                                  address matters at issue in the following
                                                  free service called eSubscription which                                  Midcontinent Independent System                                           Commission proceedings that are either
                                                  allows you to keep track of all formal                                   Operator, Inc. (MISO) and PJM                                             pending or within their rehearing
                                                  issuances and submittals in specific                                     Interconnection, L.L.C. (PJM) related to                                  period:

                                                  •   PJM Interconnection, L.L.C ............................................................................................................................................        Docket   No.   ER13–1944
                                                  •   Midcontinent Independent System Operator, Inc ........................................................................................................                         Docket   No.   ER13–1943
                                                  •   PJM Interconnection, L.L.C ............................................................................................................................................        Docket   No.   ER13–1924
                                                  •   Midcontinent Independent System Operator, Inc ........................................................................................................                         Docket   No.   ER13–1945
                                                  •   Entergy Services, Inc ......................................................................................................................................................   Docket   No.   ER13–1955
                                                  •   Cleco Power LLC ............................................................................................................................................................   Docket   No.   ER13–1956
                                                  •   Southwest Power Pool, Inc ............................................................................................................................................         Docket   No.   ER14–1174
                                                  •   Midcontinent Independent System Operator, Inc ........................................................................................................                         Docket   No.   ER14–1736
                                                  •   Midcontinent Independent System Operator, Inc. .......................................................................................................                         Docket   No.   ER14–2445
                                                  •   Southwest Power Pool, Inc ............................................................................................................................................         Docket   No.   ER13–1864
                                                  •   Southwest Power Pool, Inc. v. Midcontinent Independent System Operator, Inc ....................................................                                               Docket   No.   EL14–21
                                                  •   Midcontinent Independent System Operator, Inc. v. Southwest Power Pool, Inc ....................................................                                               Docket   No.   EL14–30
                                                  •   Midwest Independent Transmission System Operator, Inc ........................................................................................                                 Docket   No.   EL11–34
                                                  •   Midwest Independent Transmission System Operator, Inc ........................................................................................                                 Docket   No.   ER11–1844


                                                     Advance registration is strongly                                      information on this event will be posted                                  202–208–2106 with the required
                                                  encouraged for all attendees. If you have                                on the Calendar of Events on the                                          accommodations.
                                                  not already done so, those who plan to                                   Commission’s Web site, www.ferc.gov,                                        Following the technical conference,
                                                  attend may register in advance at the                                    prior to the event.                                                       the Commission will consider post-
                                                  following Web page: https://                                                                                                                       technical conference comments
                                                                                                                             Commission conferences are                                              submitted on or before July 15, 2015.
                                                  www.ferc.gov/whats-new/registration/                                     accessible under section 508 of the
                                                  06-15-15-form.asp. Attendees should                                                                                                                Reply comments are due on or before
                                                                                                                           Rehabilitation Act of 1973. For                                           August 5, 2015. The written comments
                                                  allow time to pass through building
mstockstill on DSK4VPTVN1PROD with NOTICES




                                                                                                                           accessibility accommodations please                                       will be included in the formal record of
                                                  security procedures before the 9:00 a.m.                                 send an email to accessibility@ferc.gov                                   the proceeding, which, together with the
                                                  (Eastern Time) start time of the                                         or call toll free 1–866–208–3372 (voice)                                  record developed to date, will form the
                                                  technical conference. In addition,                                       or 202–502–8659 (TTY); or send a fax to                                   basis for further Commission action.

                                                     1 See the previous discussion on the methods for                        1 The webcast will be available on the Calendar

                                                  filing comments.                                                         of Events on the Commission’s Web site
                                                                                                                           www.ferc.gov for three months after the conference.


                                             VerDate Sep<11>2014         17:09 Jun 05, 2015        Jkt 235001      PO 00000       Frm 00033       Fmt 4703      Sfmt 4703      E:\FR\FM\08JNN1.SGM             08JNN1



Document Created: 2018-02-22 10:12:58
Document Modified: 2018-02-22 10:12:58
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation80 FR 32369 