80_FR_38808 80 FR 38679 - Kingfisher Wind, LLC; Order Granting Market-Based Rate Authorization and Request for Waivers and Providing Guidance on Vertical Market Power Representations

80 FR 38679 - Kingfisher Wind, LLC; Order Granting Market-Based Rate Authorization and Request for Waivers and Providing Guidance on Vertical Market Power Representations

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 80, Issue 129 (July 7, 2015)

Page Range38679-38684
FR Document2015-16589

Federal Register, Volume 80 Issue 129 (Tuesday, July 7, 2015)
[Federal Register Volume 80, Number 129 (Tuesday, July 7, 2015)]
[Notices]
[Pages 38679-38684]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2015-16589]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket Nos. ER15-1308-000; ER15-1308-001]


Kingfisher Wind, LLC; Order Granting Market-Based Rate 
Authorization and Request for Waivers and Providing Guidance on 
Vertical Market Power Representations

Before Commissioners: Norman C. Bay, Chairman; Philip D. Moeller, 
Cheryl A. LaFleur, Tony Clark, and Colette D. Honorable.

    1. In this order, we grant Kingfisher Wind, LLC (Kingfisher Wind) 
authority to make wholesale sales of electric energy, capacity, and 
ancillary services at market-based rates, effective June 30, 2015, as 
requested. Also, as discussed below, we grant Kingfisher Wind's request 
for waiver of the Commission's requirements to file an Open Access 
Transmission Tariff (OATT), to establish and maintain an Open Access 
Same-Time Information System (OASIS), and to comply with the 
Commission's Standards of Conduct. In addition, as discussed below, we 
provide guidance with regard to interconnection facilities that qualify 
for the blanket OATT waiver provided in Order No. 807.\1\ We also grant 
Kingfisher Wind's request for other waivers commonly granted to market-
based rate sellers, except as noted herein.
---------------------------------------------------------------------------

    \1\ Subsequent to the filing of this application, the Commission 
issued Order No. 807, which will be effective June 30, 2015. In 
Order No. 807, the Commission amended its regulations to waive the 
OATT requirements of 18 CFR 35.28, the OASIS requirements of part 
37, and the Standards of Conduct requirements of part 358, under 
certain conditions, for entities that own interconnection 
facilities. See Open Access and Priority Rights on Interconnection 
Customer's Interconnection Facilities, Order No. 807, FERC Stats. & 
Regs. ] 31,367 (2015).
---------------------------------------------------------------------------

    2. Additionally, we find that Kingfisher Wind meets the criteria 
for a Category 1 seller in the Northwest, Northeast, Southwest, 
Southeast, and Central regions and a Category 2 seller in the Southwest 
Power Pool (SPP) region, and is so designated. Kingfisher Wind must 
file updated market power analyses for the SPP region in compliance 
with the regional reporting schedule adopted in Order No. 697.\2\
---------------------------------------------------------------------------

    \2\ See Market-Based Rates for Wholesale Sales of Electric 
Energy, Capacity and Ancillary Services by Public Utilities, Order 
No. 697, FERC Stats. & Regs. ] 31,252, at PP 848-850, clarified, 121 
FERC ] 61,260 (2007) (Clarification Order), order on reh'g, Order 
No. 697-A, FERC Stats. & Regs. ] 31,268, clarified, 124 FERC ] 
61,055, order on reh'g, Order No. 697-B, FERC Stats. & Regs. ] 
31,285 (2008), order on reh'g, Order No. 697-C, FERC Stats. & Regs. 
] 31,291 (2009), order on reh'g, Order No. 697-D, FERC Stats. & 
Regs. ] 31,305 (2010), aff'd sub nom. Mont. Consumer Counsel v. 
FERC, 659 F.3d 910 (9th Cir. 2011), cert. denied, 133 S. Ct. 26 
(2012).

---------------------------------------------------------------------------

[[Page 38680]]

I. Background

    3. On March 17, 2015, as amended May 18, 2015, pursuant to section 
205 of the Federal Power Act (FPA),\3\ Kingfisher Wind filed an 
application for market-based rate authority with an accompanying tariff 
providing for the sale of electric energy, capacity, and ancillary 
services at market-based rates.\4\
---------------------------------------------------------------------------

    \3\ 16 U.S.C. 824d (2012).
    \4\ Kingfisher Wind requests authorization to sell ancillary 
services in the markets administered by PJM Interconnection, L.L.C., 
New York Independent System Operator, Inc., ISO New England Inc., 
California Independent System Operator Corp., Midcontinent 
Independent System Operator, Inc. (MISO), and SPP, as well as 
authorization to engage in the sale of certain ancillary services as 
a third-party provider in other markets.
---------------------------------------------------------------------------

    4. Kingfisher Wind states that it owns a 298 megawatt (MW) wind 
generation facility located in Canadian and Kingfisher Counties, 
Oklahoma (the Project), within the SPP market.
    5. Kingfisher Wind states that it will also own limited 
interconnection facilities which will consist of 34.5 kilovolt (kV) 
collection lines and related facilities, including a collection 
substation, transformers and disconnect switches, and a share of a 25-
mile, 345 kV generator tie line and related equipment and facilities 
(Shared Facilities) \5\ that are necessary to interconnect the Project 
to the 345 kV Cimarron substation owned by OG&E and the transmission 
system operated by SPP.
---------------------------------------------------------------------------

    \5\ Kingfisher Wind states that it will acquire 30 percent 
tenancy-in-common interests of the Shared Facilities from Canadian 
Hills Wind, LLC (Canadian Hills). Kingfisher adds that Canadian 
Hills is an exempt wholesale generator which owns and operates a 
wind generation facility that is interconnected with the Oklahoma 
Gas and Electric Company (OG&E) transmission system via the Shared 
Facilities. Kingfisher Wind states that the Commission granted 
Canadian Hills waiver of the OATT requirement. See Canadian Hills 
Wind, LLC, 143 FERC ] 61,261 (2013); see also Canadian Hills Wind, 
LLC, Docket No. ER15-1372-000 (May 14, 2015) (delegated letter 
order).
---------------------------------------------------------------------------

    6. Kingfisher Wind states that it will utilize the interconnection 
facilities solely to interconnect the Project to the transmission 
system operated by SPP. Kingfisher Wind states that the interconnection 
facilities do not comprise an integrated transmission system and are 
limited and discrete. Kingfisher Wind requests that the Commission 
waive the requirements under Order Nos. 888,\6\ 889,\7\ 890,\8\ 
2004,\9\ and 717,\10\ and section 35.28,\11\ and Parts 37 \12\ and 358 
\13\ of the Commission's regulations for all of the limited 
interconnection facilities, including but not limited to, the Shared 
Facilities.
---------------------------------------------------------------------------

    \6\ Promoting Wholesale Competition Through Open Access Non-
Discriminatory Transmission Services by Public Utilities; Recovery 
of Stranded Costs by Public Utilities and Transmitting Utilities, 
Order No. 888, FERC Stats. & Regs. ] 31,036 (1996), order on reh'g, 
Order No. 888-A, FERC Stats. & Regs. ] 31,048, order on reh'g, Order 
No. 888-B, 81 FERC ] 61,248 (1997), order on reh'g, Order No. 888-C, 
82 FERC ] 61,046 (1998), aff'd in relevant part sub nom. 
Transmission Access Policy Study Group v. FERC, 225 F.3d 667 (D.C. 
Cir. 2000), aff'd sub nom. New York v. FERC, 535 U.S. 1 (2002).
    \7\ Open Access Same-Time Information System and Standards of 
Conduct, Order No. 889, FERC Stats. & Regs. ] 31,035 (1996), order 
on reh'g, Order No. 889-A, FERC Stats. & Regs. ] 31,049, reh'g 
denied, Order No. 889-B, 81 FERC ] 61,253 (1997).
    \8\ Preventing Undue Discrimination and Preference in 
Transmission Service, Order No. 890, FERC Stats. & Regs. ] 31,241, 
order on reh'g, Order No. 890-A, FERC Stats. & Regs. ] 31,261 
(2007), order on reh'g, Order No. 890-B, 123 FERC ] 61,299 (2008), 
order on reh'g, Order No. 890-C, 126 FERC ] 61,228, order on 
clarification, Order No. 890-D, 129 FERC ] 61,126 (2009).
    \9\ Standards of Conduct for Transmission Providers, Order No. 
2004, FERC Stats. & Regs. ] 31,155 (2003), order on reh'g, Order No. 
2004-A, FERC Stats. & Regs. ] 31,161, order on reh'g, Order No. 
2004-B, FERC Stats. & Regs. ] 31,166, order on reh'g, Order No. 
2004-C, FERC Stats. & Regs. ] 31,172 (2004), order on reh'g, Order 
No. 2004-D, 110 FERC ] 61,320 (2005), vacated and remanded as it 
applies to natural gas pipelines sub nom. National Fuel Gas Supply 
Corp. v. FERC, 468 F.3d 831 (D.C. Cir. 2006); see Standards of 
Conduct for Transmission Providers, Order No. 690, FERC Stats. & 
Regs. ] 31,237, order on reh'g, Order No. 690-A, FERC Stats. & Regs. 
] 31,243 (2007).
    \10\ Standards of Conduct for Transmission Providers, Order No. 
717, FERC Stats. & Regs. ] 31,280 (2008), order on reh'g, Order No. 
717-A, FERC Stats. & Regs. ] 31,297, order on reh'g, Order No. 717-
B, 129 FERC ] 61,123 (2009), order on reh'g, Order No. 717-C, 131 
FERC ] 61,045 (2010), order on reh'g, Order No. 717-D, 135 FERC ] 
61,017 (2011).
    \11\ 18 CFR 35.28 (2014).
    \12\ 18 CFR 37 (2014).
    \13\ 18 CFR 358 (2014).
---------------------------------------------------------------------------

    7. Kingfisher Wind states that it is a wholly-owned subsidiary of 
FR Kingfisher Holdings II LLC, which is an indirect subsidiary of First 
Reserve Energy Infrastructure Fund II, L.P. (Fund II), which is 
controlled by senior officers of First Reserve, a global private equity 
firm focused on the energy industry. Kingfisher Wind states that Fund 
II is managed and controlled by its general partner, First Reserve 
Energy Infrastructure GP II, L.P., which in turn, is managed and 
controlled by its general partner, First Reserve Energy Infrastructure 
G.P. II Limited (First Reserve GP II). Kingfisher Wind states that its 
affiliates that own or control generation facilities in the United 
States are either exempt wholesale generators or owners of qualifying 
facilities under the Public Utility Regulatory Policies Act of 
1978.\14\ Kingfisher Wind represents that it is affiliated with 
approximately 918 MW of generation capacity in the SPP market, all of 
which is fully committed under long-term power purchase agreements.


---------------------------------------------------------------------------

    \14\ 16 U.S.C. 2601 et seq. (2012).
---------------------------------------------------------------------------

II. Notice of Filings

    8. Notices of Kingfisher Wind's filings were published in the 
Federal Register,\15\ with interventions and protests due on or before 
June 9, 2015. None was filed.
---------------------------------------------------------------------------

    \15\ 80 FR 15,779 (2015); 80 FR 30,223 (2015).
---------------------------------------------------------------------------

    9. Notice of Kingfisher Wind's request for blanket authorization 
under part 34 of the Commission's regulations was separately published 
in the Federal Register,\16\ with interventions or protests due on or 
before April 7, 2015. None was filed.
---------------------------------------------------------------------------

    \16\ 80 FR 15,784 (2015).
---------------------------------------------------------------------------

III. Discussion

    10. As discussed below, we will grant Kingfisher Wind's request for 
authorization to make wholesale sales of electric energy, capacity, and 
ancillary services at market-based rates and we will accept its market-
based rate tariff, effective June 30, 2015, as requested.\17\ We will 
also grant Kingfisher Wind's request for certain waivers.
---------------------------------------------------------------------------

    \17\ We note that Kingfisher Wind is not being granted authority 
to make third-party sales of operating reserves to a public utility 
that is purchasing ancillary services to satisfy its own open access 
transmission tariff requirements to offer ancillary services to its 
own customers. If Kingfisher Wind seeks such authority, it must make 
the required showing and receive Commission authorization prior to 
making such sales. See Third-Party Provision of Ancillary Services; 
Accounting and Financial Reporting for New Electric Storage 
Technologies, Order No. 784, FERC Stats. & Regs. ] 31,349, at PP 
200-202 (2013), order on clarification, Order No. 784-A, 146 FERC ] 
61,114 (2014).
---------------------------------------------------------------------------

A. Market-Based Rate Authorization

    11. The Commission allows power sales at market-based rates if the 
seller and its affiliates do not have, or have adequately mitigated, 
horizontal and vertical market power.\18\
---------------------------------------------------------------------------

    \18\ Order No. 697, FERC Stats. & Regs. ] 31,252 at PP 62, 399, 
408, 440.
---------------------------------------------------------------------------

1. Horizontal Market Power

    12. The Commission has adopted two indicative screens for assessing 
horizontal market power: the pivotal supplier screen and the wholesale 
market share screen.\19\ The Commission has stated that passage of both 
screens establishes a rebuttable presumption that the applicant does 
not possess

[[Page 38681]]

horizontal market power, while failure of either screen creates a 
rebuttable presumption that the applicant has horizontal market 
power.\20\
---------------------------------------------------------------------------

    \19\ Id. P 62.
    \20\ Id. PP 33, 62-63.
---------------------------------------------------------------------------

    13. Kingfisher Wind represents that it relies on Westar Energy, 
Inc.'s recently accepted market power analysis to demonstrate that 
Kingfisher Wind passes both the pivotal supplier and the wholesale 
market share screens for the SPP market.\21\
---------------------------------------------------------------------------

    \21\ See Westar Energy, Inc., Docket No. ER14-724-000 (Feb. 28, 
2014) (delegated letter order). Kingfisher Wind relies on historical 
data for the SPP market for the study period of December 2011 
through November 2012 contained in the Westar pivotal supplier and 
market share screens study. Kingfisher Wind states that the use of 
more recent data (i.e., December 2012 through November 2013) would 
not result in significantly higher market shares because conditions 
would not change materially over one year. See Clarification Order, 
121 FERC ] 61,260 at P 12.d.
---------------------------------------------------------------------------

    14. Based on Kingfisher Wind's representations, we find that 
Kingfisher Wind satisfies the Commission's requirements for market-
based rates regarding horizontal market power.

2. Vertical Market Power

    15. In cases where a public utility, or any of its affiliates, 
owns, operates, or controls transmission facilities, the Commission 
requires that there be a Commission-approved OATT on file or that the 
seller has received waiver of the OATT requirement before granting a 
seller market-based rate authorization.\22\ Kingfisher Wind states that 
neither Kingfisher Wind nor its affiliates owns transmission facilities 
other than those limited and discrete facilities that are necessary to 
interconnect generation facilities to the transmission grid. As 
discussed more fully below, the Commission will grant Kingfisher Wind's 
request for waiver of the requirement to have an OATT on file for the 
interconnection facilities.
---------------------------------------------------------------------------

    \22\ Order No. 697, FERC Stats. & Regs. ] 31,252 at P 408.
---------------------------------------------------------------------------

    16. The Commission also considers a seller's ability to erect other 
barriers to entry as part of the vertical market power analysis.\23\ 
The Commission requires a seller to provide a description of its 
ownership or control of, or affiliation with an entity that owns or 
controls, intrastate natural gas transportation, intrastate natural gas 
storage or distribution facilities; sites for new generation capacity 
development; and physical coal supply sources and ownership of or 
control over who may access transportation of coal supplies 
(collectively, inputs to electric power production).\24\ The Commission 
also requires sellers to make an affirmative statement that they have 
not erected barriers to entry into the relevant market and will not 
erect barriers to entry into the relevant market.\25\ The Commission 
adopted a rebuttable presumption that the ownership or control of, or 
affiliation with any entity that owns or controls, inputs to electric 
power production does not allow a seller to raise entry barriers but 
will allow intervenors to demonstrate otherwise.\26\
---------------------------------------------------------------------------

    \23\ Id. P 440.
    \24\ Order No. 697-A, FERC Stats. & Regs. ] 31,268 at P 176.
    \25\ Order No. 697, FERC Stats. & Regs. ] 31,252 at P 447.
    \26\ Id. P 446.
---------------------------------------------------------------------------

    17. Regarding other barriers to entry, Kingfisher Wind states that 
neither it nor any of its affiliates owns or controls physical coal 
supply sources, entities that may access transportation of coal 
supplies, or sites to develop new generation capacity. Kingfisher Wind 
states that it has affiliates that own or control intrastate natural 
gas transportation, storage or distribution facilities, but that these 
assets will not allow Kingfisher Wind to erect barriers to entry.\27\
---------------------------------------------------------------------------

    \27\ Kingfisher Wind states that it is affiliated with: (1) 
Crestwood Midstream Partners, LP, which owns gathering pipelines and 
natural gas storage facilities located in a number of geographic 
regions, including some gathering pipelines located in or near SPP; 
(2) the Arthur C. Nielsen Pipeline System and Clearfield Pipeline 
System, intrastate natural gas pipelines located within 
Pennsylvania; and (3) FREIF Caliber Holdings, which owns gathering 
pipelines located in MISO. See Kingfisher Wind May 18 Supplement at 
2-3.
---------------------------------------------------------------------------

    18. Finally, consistent with Order No. 697, Kingfisher Wind 
affirmatively states that it and its affiliates have not erected, and 
will not erect, barriers to entry in SPP.
    19. Based on Kingfisher Wind's representations, we find that 
Kingfisher Wind satisfies the Commission's requirements for market-
based rates regarding vertical market power.

B. Waiver Requests

1. OATT, OASIS, and Standards of Conduct
    20. Kingfisher Wind seeks waiver of the requirements to file an 
OATT, establish and maintain an OASIS, and abide by the Standards of 
Conduct with respect to the interconnection facilities that it 
owns.\28\ In support, Kingfisher Wind represents that the 
interconnection facilities are limited and discrete and that it will 
utilize them solely to interconnect the Project to the transmission 
system operated by SPP. Kingfisher Wind further states that the 
interconnection facilities do not comprise an integrated transmission 
system.
---------------------------------------------------------------------------

    \28\ Notwithstanding the issuance of Order No. 807, Kingfisher 
Wind requests that the Commission rule on its requested waiver 
herein. Kingfisher Wind May 18 Supplement at n.5.
---------------------------------------------------------------------------

    21. Order Nos. 888 and 890 and section 35.28 of the Commission's 
regulations require public utilities that own, operate, or control 
facilities used for the transmission of electric energy in interstate 
commerce to file an OATT. Order No. 889 and part 37 of the Commission's 
regulations require public utilities to establish and maintain an 
OASIS. Order Nos. 889, 2004, and 717 and Part 358 of the Commission's 
regulations require public utilities to abide by certain Standards of 
Conduct.\29\ In prior orders, the Commission has enunciated the 
standards for exemption from some or all of the requirements of Order 
Nos. 888, 889, and 890.\30\ The Commission has stated that the criteria 
for waiver of the requirements of Order No. 890 and Order No. 2004 are 
unchanged from those used to evaluate requests for waiver under Order 
Nos. 888 and 889.\31\ Order No. 717 did not change those criteria.\32\
---------------------------------------------------------------------------

    \29\ Order No. 889, FERC Stats. & Regs. ] 31,035 at 31,590; 
Order No. 2004, FERC Stats. & Regs. ] 31,155 at P 16; Order No. 717, 
FERC Stats. & Regs. ] 31,280 at P 313.
    \30\ See, e.g., Black Creek Hydro, Inc., 77 FERC ] 61,232, at 
61,941 (1996) (Black Creek); Entergy Mississippi, Inc., 112 FERC ] 
61,228, at P 22 (2005) (Entergy).
    \31\ See Alcoa Power Generating Inc., 120 FERC ] 61,035, at P 3 
(2007); Alcoa Power Generating Inc., 108 FERC ] 61,243, at P 27 
(2004).
    \32\ See Order No. 717, FERC Stats. & Regs. ] 31,280 at PP 31-
33.
---------------------------------------------------------------------------

    22. The Commission may grant requests for waiver of the obligation 
to file an OATT to public utilities that can show that they own, 
operate, or control only limited and discrete transmission facilities 
(facilities that do not form an integrated transmission grid), until 
such time as the public utility receives a request for transmission 
service. Should the public utility receive such a request, the 
Commission has determined that the public utility must file with the 
Commission a pro forma tariff within 60 days of the date of the 
request, and must comply with any additional requirements that are 
effective on the date of the request.\33\
---------------------------------------------------------------------------

    \33\ Black Creek, 77 FERC at 61,941.
---------------------------------------------------------------------------

    23. The Commission has also determined that waiver of the 
requirement to establish an OASIS and abide by the Standards of Conduct 
would be appropriate for a public utility if the applicant: (1) Owns, 
operates, or controls only limited and discrete transmission facilities 
(rather than an integrated transmission grid); or (2) is a small public 
utility that owns, operates, or controls an integrated transmission 
grid, unless other circumstances are

[[Page 38682]]

present that indicate that a waiver would not be justified.\34\ The 
Commission has held that waiver of Order No. 889 will remain in effect 
until the Commission takes action in response to a complaint to the 
Commission that an entity evaluating its transmission needs could not 
get the information necessary to complete its evaluation (for OASIS 
waivers) or an entity complains that the public utility has unfairly 
used its access to information about transmission to benefit the 
utility or its affiliate (for Standards of Conduct waivers).\35\
---------------------------------------------------------------------------

    \34\ Id. Although the Commission originally precluded waiver of 
the requirements for OASIS and the Standards of Conduct for a small 
public utility that is a member of a tight power pool, in Black 
Hills Power, Inc., 135 FERC ] 61,058, at PP 2-3 (2011) (Black 
Hills), the Commission explained that membership in a tight power 
pool is no longer a factor in the determination for waiver of 
Standards of Conduct. Moreover, Black Hills did not affect waivers 
based on a public utility disposing of no more than 4 million 
megawatt-hours annually.
    \35\ Entergy, 112 FERC ] 61,228 at P 23 (citing Cent. Minn. Mun. 
Power Agency, 79 FERC ] 61,260, at 62,127 (1997) (Central 
Minnesota); Easton Utils. Comm'n, 83 FERC ] 61,334, at 62,343 (1998) 
(Easton)).
---------------------------------------------------------------------------

    24. Based on the statements in Kingfisher Wind's application, we 
find that its interconnection facilities qualify as limited and 
discrete. Kingfisher Wind will use the facilities solely to 
interconnect the Project to the transmission grid. Accordingly, we will 
grant Kingfisher Wind waiver of the requirements of Order Nos. 888 and 
890 and section 35.28 of the Commission's regulations to have an OATT 
on file with respect to the interconnection facilities. However, if 
Kingfisher Wind receives a request for transmission service, it must 
file with the Commission a pro forma OATT within 60 days of the date of 
the request.\36\
---------------------------------------------------------------------------

    \36\ Black Creek, 77 FERC at 61,941.
---------------------------------------------------------------------------

    25. The Commission will also grant Kingfisher Wind waiver of the 
requirements of Order No. 889 and part 37 of the Commission's 
regulations with respect to OASIS and Order Nos. 889, 2004, and 717 and 
Part 358 with respect to the Standards of Conduct. We note that 
Kingfisher Wind's waiver of the requirement to establish an OASIS will 
remain in effect until the Commission takes action in response to a 
complaint to the Commission that an entity evaluating its transmission 
needs could not get the information necessary to complete its 
evaluation.\37\ Likewise, Kingfisher Wind's waiver of the Standards of 
Conduct will remain in effect unless and until the Commission takes 
action on a complaint by an entity that Kingfisher Wind has unfairly 
used its access to information to unfairly benefit itself or its 
affiliates.\38\
---------------------------------------------------------------------------

    \37\ Entergy, 112 FERC ] 61,228 at P 23 (citing Central 
Minnesota, 79 FERC at 62,127; Easton, 83 FERC at 62,343).
    \38\ Id. Kingfisher Wind must notify the Commission if there is 
a material change in facts that affects its waiver within 30 days of 
the date of such change. Material Changes in Facts Underlying Waiver 
of Order No. 889 and Part 358 of the Commission's Regulations, 127 
FERC ] 61,141, at P 5 (2009).
---------------------------------------------------------------------------

    26. Given that Order No. 807 will be effective June 30, 2015, we 
take this opportunity to explain how market-based rate applicants and 
sellers may demonstrate a lack of vertical market power once the 
blanket waiver provided for in 18 CFR 35.28(d)(2) takes effect. In 
Order No. 807, the Commission modified its policy to provide an 
additional method for obtaining waiver of the OATT requirements. 
Specifically, the Commission stated that a market-based rate seller or 
any of its affiliates that own, operate, or control transmission 
facilities may satisfy the vertical market power requirements in 18 CFR 
35.37(d) by one of the following: (1) Have a Commission-approved OATT 
on file; (2) receive waiver of the OATT requirement under 18 CFR 
35.28(d)(1); or (3) satisfy the requirements for a blanket waiver under 
18 CFR 35.28(d)(2).\39\
---------------------------------------------------------------------------

    \39\ Order No. 807, FERC Stats. & Regs. ] 31,367 at P 57.
---------------------------------------------------------------------------

    27. We provide guidance herein that an applicant that qualifies for 
the blanket OATT waiver under 18 CFR 35.28(d)(2) should affirm in its 
market-based rate application that it qualifies for the blanket OATT 
waiver. As the Commission stated in Order No. 807, ``[s]uch a waiver is 
justified because the usually limited and discrete nature of 
[Interconnection Customer's Interconnection Facilities (ICIF)] and 
ICIF's dedicated interconnection purpose means that such facilities do 
not typically present the concerns about discriminatory conduct that 
the Commission's OATT, OASIS, and Standards of Conduct requirements 
were intended to address.'' \40\ In accordance with Order No. 807, the 
waivers referenced in 18 CFR 35.28(d)(2) shall be deemed in effect 
unless revoked as of the date the public utility ceases to satisfy the 
qualifications of 18 CFR 35.28(d)(2), and also may be revoked by the 
Commission if the Commission determines that it is in the public 
interest to do so.\41\ Thus, applicants who attest that they qualify 
for the blanket authorization do not need to request, nor should they 
request, a waiver of the OATT, OASIS and Standards of Conduct 
requirements. We also note that the Commission stated in Order No. 807 
that an entity that has already been issued a waiver of the OATT, OASIS 
and Standards of Conduct requirements and that is eligible for the 
blanket waiver under Order No. 807 will be deemed to be operating under 
the blanket waiver without further filings necessary with respect to 
the previously-issued waiver.\42\
---------------------------------------------------------------------------

    \40\ Id. P 55.
    \41\ Id. P 101 (``the [blanket] waiver would be deemed to be 
revoked as of the date the public utility ceases to satisfy the 
qualifications for such waiver. . . . [I]f the ICIF that are covered 
by a blanket waiver become integrated into a transmission system 
such that they can no longer be considered ICIF, the blanket waiver 
would be deemed to be revoked.''). After revocation of its waivers, 
the public utility must comply with the requirements that had been 
waived within 60 days of revocation. Id. at regulatory text (to be 
codified at 18 CFR 35.28(d)(2)(i)).
    \42\ Id. P 176 (referencing P 89, which states, in part, that 
``if an entity has previously received a specific waiver of the OATT 
and related obligations pursuant to the Commission's `limited and 
discrete' or `small entity' standards, the blanket waiver will 
supersede the existing waiver'').
---------------------------------------------------------------------------

    28. As stated above, Kingfisher Wind specifically requests that the 
Commission rule on its requested OATT waiver, and we hereby grant this 
waiver.
2. Other Waivers and Authorizations
    29. Kingfisher Wind also requests the following waivers and 
authorizations: (1) Waiver of the filing requirements of subparts B and 
C of part 35 of the Commission's regulations, except sections 35.12(a), 
35.13(b), 35.15, and 35.16; (2) waiver of the accounting and other 
requirements of parts 41, 101, and 141 of the Commission's regulations, 
except sections 141.14 and 141.15; and (3) blanket authorization under 
section 204 of the FPA \43\ and Part 34 of the Commission's regulations 
for all future issuances of securities and assumptions of liability.
---------------------------------------------------------------------------

    \43\ 16 U.S.C. 824c (2012).
---------------------------------------------------------------------------

    30. The Commission will grant the requested waivers and 
authorizations consistent with those granted to other entities with 
market-based rate authorizations.\44\ Notwithstanding the

[[Page 38683]]

waiver of the accounting and reporting requirements, the Commission 
expects Kingfisher Wind to keep its accounting records in accordance 
with generally accepted accounting principles.
---------------------------------------------------------------------------

    \44\ We note that the Commission has examined and approved the 
continued applicability of the waiver of its accounting and 
reporting requirements in parts 41, 101, and 141 of the Commission's 
regulations, as well as the continued applicability of the blanket 
authorization for the issuance of securities and the assumption of 
liabilities in part 34 of the Commission's regulations. See Order 
No. 697, FERC Stats. & Regs. ] 31,252 at PP 984-985 (regarding 
waiver of parts 41, 101, and 141) and PP 999-1000 (regarding blanket 
approval under part 34). However, waiver of the provisions of part 
101 that apply to hydropower licensees is not granted with respect 
to licensed hydropower projects. Hydropower licensees are required 
to comply with the requirements of the Uniform System of Accounts 
pursuant to 18 CFR part 101 to the extent necessary to carry out 
their responsibilities under part I of the FPA. We further note that 
a licensee's status as a market-based rate seller under part II of 
the FPA does not exempt it from its accounting responsibilities as a 
licensee under part I of the FPA. See Seneca Gen., LLC, 145 FERC ] 
61,096, at P 23 n.20 (2013) (citing Trafalgar Power Inc., 87 FERC ] 
61,207, at 61,798 (1999) (noting that ``all licensees are required 
to comply with the requirements of the Uniform System of Accounts to 
the extent necessary to carry out their responsibilities under 
[s]ections 4(b), 10(d) and 14 of the FPA'')).
---------------------------------------------------------------------------

C. Reporting Requirements

    31. An entity with market-based rate authorization must file an 
Electric Quarterly Report (EQR) with the Commission, consistent with 
Order Nos. 2001 \45\ and 768,\46\ to fulfill its responsibility under 
FPA section 205(c) \47\ to have rates on file in a convenient form and 
place.\48\ Kingfisher Wind must file EQRs electronically with the 
Commission consistent with the procedures set forth in Order No. 
770.\49\ Failure to timely and accurately file an EQR is a violation of 
the Commission's regulations for which Kingfisher Wind may be subject 
to refund, civil penalties, and/or revocation of market-based rate 
authority.\50\
---------------------------------------------------------------------------

    \45\ Revised Public Utility Filing Requirements, Order No. 2001, 
FERC Stats. & Regs. ] 31,127, reh'g denied, Order No. 2001-A, 100 
FERC ] 61,074, reh'g denied, Order No. 2001-B, 100 FERC ] 61,342, 
order directing filing, Order No. 2001-C, 101 FERC ] 61,314 (2002), 
order directing filing, Order No. 2001-D, 102 FERC ] 61,334, order 
refining filing requirements, Order No. 2001-E, 105 FERC ] 61,352 
(2003), order on clarification, Order No. 2001-F, 106 FERC ] 61,060 
(2004), order revising filing requirements, Order No. 2001-G, 120 
FERC ] 61,270, order on reh'g and clarification, Order No. 2001-H, 
121 FERC ] 61,289 (2007), order revising filing requirements, Order 
No. 2001-I, FERC Stats. & Regs. ] 31,282 (2008).
    \46\ Electricity Mkt. Transparency Provisions of Section 220 of 
the Fed. Power Act, Order No. 768, FERC Stats. & Regs. ] 31,336 
(2012), order on reh'g, Order No. 768-A, 143 FERC ] 61,054 (2013).
    \47\ 16 U.S.C. 824d(c) (2012).
    \48\ See Revisions to Electric Quarterly Report Filing Process, 
Order No. 770, FERC Stats. & Regs. ] 31,338, at P 3 (2012) (citing 
Order No. 2001, FERC Stats. & Regs. ] 31,127 at P 31).
    \49\ Order No. 770, FERC Stats. & Regs. ] 31,338.
    \50\ The exact filing dates for these reports are prescribed in 
18 CFR 35.10b (2014). Forfeiture of market-based rate authority may 
require a new application for market-based rate authority if the 
applicant wishes to resume making sales at market-based rates.
---------------------------------------------------------------------------

    32. Additionally, Kingfisher Wind must timely report to the 
Commission any change in status that would reflect a departure from the 
characteristics the Commission relied upon in granting market-based 
rate authority.\51\
---------------------------------------------------------------------------

    \51\ Reporting Requirement for Changes in Status for Public 
Utilities with Market-Based Rate Authority, Order No. 652, FERC 
Stats. & Regs. ] 31,175, order on reh'g, 111 FERC ] 61,413 (2005); 
18 CFR 35.42 (2014).
---------------------------------------------------------------------------

    33. In Order No. 697, the Commission created two categories of 
sellers.\52\ Category 1 sellers are not required to file regularly 
scheduled updated market power analyses. Category 1 sellers are 
wholesale power marketers and wholesale power producers that own or 
control 500 MW or less of generation in aggregate per region; that do 
not own, operate, or control transmission facilities other than limited 
equipment necessary to connect individual generation facilities to the 
transmission grid (or have been granted waiver of the requirements of 
Order No. 888); that are not affiliated with anyone that owns, 
operates, or controls transmission facilities in the same region as the 
seller's generation assets; that are not affiliated with a franchised 
public utility in the same region as the seller's generation assets; 
and that do not raise other vertical market power issues.\53\ Sellers 
that do not fall into Category 1 are designated as Category 2 sellers 
and are required to file updated market power analyses.\54\
---------------------------------------------------------------------------

    \52\ Order No. 697, FERC Stats. & Regs. ] 31,252 at P 848.
    \53\ 18 CFR 35.36(a) (2014).
    \54\ Order No. 697, FERC Stats. & Regs. ] 31,252 at P 850.
---------------------------------------------------------------------------

    34. Kingfisher Wind requests Category 1 seller status in the 
Northwest, Northeast, Southwest, Southeast, and Central regions, and 
Category 2 seller status in the SPP region. Kingfisher Wind states that 
it is located in the SPP region, where it and its affiliates own or 
control more than 500 MW of generation capacity. Kingfisher Wind 
represents that it does not own or control generation in any other 
region. Kingfisher Wind further represents that neither it nor its 
affiliates own, operate or control transmission facilities other than 
limited facilities necessary to connect individual generating 
facilities to the transmission grid. Kingfisher Wind also represents 
that it is not affiliated with any entity that owns, operates or 
controls transmission facilities in the same region as its generation 
assets nor with a franchised public utility in the same region as its 
generation assets. Finally, Kingfisher Wind represents that neither it 
nor its affiliates raise other vertical market power concerns.
    35. Based on Kingfisher Wind's representations, we grant Kingfisher 
Wind Category 1 seller status in the Northwest, Northeast, Southwest, 
Southeast and Central regions and Category 2 seller status in the SPP 
region. Kingfisher Wind must file an updated market power analysis for 
the SPP region in compliance with the regional reporting schedule 
adopted in Order No. 697.\55\ The Commission also reserves the right to 
require such an analysis at any time for any region.\56\
---------------------------------------------------------------------------

    \55\ Id.
    \56\ Id. P 853.
---------------------------------------------------------------------------

    The Commission orders:
    (A) Kingfisher Wind's market-based rate tariff is hereby accepted 
for filing, effective June 30, 2015, as requested, as discussed in the 
body of this order.
    (B) Kingfisher Wind's request for waiver of the requirements to 
file an OATT, to establish and maintain an OASIS, and to comply with 
the Standards of Conduct is hereby granted, as discussed in the body of 
this order.
    (C) Waiver of the provisions of subparts B and C of part 35 of the 
Commission's regulations, with the exception of sections 35.12(a), 
35.13(b), 35.15, and 35.16, is hereby granted.
    (D) Waiver of part 101 of the Commission's regulations is hereby 
granted, with the exception that waiver of the provisions of Part 101 
that apply to hydropower licensees is not granted with respect to 
licensed hydropower projects. Waiver of parts 41 and 141 of the 
Commission's regulations is hereby granted, with the exception of 
sections 141.14 and 141.15.
    (E) Blanket authorization under part 34 of the Commission's 
regulations for all future issuances of securities and assumptions of 
liability is hereby granted. Kingfisher Wind is hereby authorized to 
issue securities and assume obligations or liabilities as guarantor, 
indorser, surety, or otherwise in respect of any security of another 
person; provided that such issue or assumption is for some lawful 
object within the corporate purposes of Kingfisher Wind, compatible 
with the public interest, and reasonably necessary or appropriate for 
such purposes.
    (F) The Commission reserves the right to modify this order to 
require a further showing that neither the public nor private interests 
will be adversely affected by continued Commission approval of 
Kingfisher Wind's issuance of securities or assumptions of liability.
    (G) Kingfisher Wind is hereby required to file EQRs in compliance 
with Order Nos. 2001 and 768. If the effective date of Kingfisher 
Wind's market-based rate tariff falls within a quarter of the year that 
has already expired, Kingfisher Wind's EQRs for the expired quarter are 
due within 30 days of the date of this order.
    (H) The Secretary is hereby directed to publish a copy of this 
order in the Federal Register.

    By the Commission.


[[Page 38684]]


    Issued: June 30, 2015.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2015-16589 Filed 7-6-15; 8:45 am]
BILLING CODE 6717-01-P



                                                                               Federal Register / Vol. 80, No. 129 / Tuesday, July 7, 2015 / Notices                                                     38679

                                                 Docket Numbers: ER15–2082–000.                          Applicants: Cameron Interstate                      DEPARTMENT OF ENERGY
                                                 Applicants: ExxonMobil Baton Rouge                    Pipeline, L.L.C.
                                              Complex.                                                   Description: Annual Report of                       Federal Energy Regulatory
                                                 Description: Compliance filing:                       Transportation Imbalances and Cash                    Commission
                                              Compliance to be effective 7/1/2015.                     Out Activity.                                         [Docket Nos. ER15–1308–000; ER15–1308–
                                                 Filed Date: 6/30/15.                                    Filed Date: 4/27/12.                                001]
                                                 Accession Number: 20150630–5266.                        Accession Number: 20120427–5145.
                                                 Comments Due: 5 p.m. ET 7/21/15.                        Comments Due: 5 p.m. ET 7/6/15.                     Kingfisher Wind, LLC; Order Granting
                                                 Docket Numbers: ER15–2083–000.                          Docket Numbers: RP15–171–000.                       Market-Based Rate Authorization and
                                                 Applicants: New York Independent                        Applicants: Destin Pipeline Company,                Request for Waivers and Providing
                                              System Operator, Inc.                                    L.L.C.                                                Guidance on Vertical Market Power
                                                 Description: Section 205(d) Rate                        Description: Report Filing: Notice of               Representations
                                              Filing: NYISO 205 filing EPC agreement                   Auxiliary Installation Reimbursement
                                              among NYISO, Central Hudson and CPV                                                                            Before Commissioners: Norman C. Bay,
                                                                                                       Fee Effective Date.                                     Chairman; Philip D. Moeller, Cheryl A.
                                              Valley to be effective 6/3/2015.                           Filed Date: 6/22/15.
                                                 Filed Date: 6/30/15.                                                                                          LaFleur, Tony Clark, and Colette D.
                                                                                                         Accession Number: 20150622–5154.                      Honorable.
                                                 Accession Number: 20150630–5269.                        Comments Due: 5 p.m. ET 7/6/15.
                                                 Comments Due: 5 p.m. ET 7/21/15.                                                                               1. In this order, we grant Kingfisher
                                                                                                         Docket Numbers: RP15–23–007.                        Wind, LLC (Kingfisher Wind) authority
                                                 Docket Numbers: ER15–2084–000.                          Applicants: Transwestern Pipeline
                                                 Applicants: LG&E Energy Marketing                                                                           to make wholesale sales of electric
                                                                                                       Company, LLC.                                         energy, capacity, and ancillary services
                                              Inc.                                                       Description: Settlement Agreement.
                                                 Description: Section 205(d) Rate                                                                            at market-based rates, effective June 30,
                                                                                                         Filed Date: 6/22/15.                                2015, as requested. Also, as discussed
                                              Filing: Amendment to Market Based
                                                                                                         Accession Number: 20150622–5000.
                                              Rate Tariff to be effective 7/1/2015.                                                                          below, we grant Kingfisher Wind’s
                                                                                                         Comments Due: 5 p.m. ET 7/13/15.
                                                 Filed Date: 6/30/15.                                                                                        request for waiver of the Commission’s
                                                 Accession Number: 20150630–5272.                        Any person desiring to intervene or                 requirements to file an Open Access
                                                 Comments Due: 5 p.m. ET 7/21/15.                      protest in any of the above proceedings               Transmission Tariff (OATT), to establish
                                                 The filings are accessible in the                     must file in accordance with Rules 211                and maintain an Open Access Same-
                                              Commission’s eLibrary system by                          and 214 of the Commission’s                           Time Information System (OASIS), and
                                              clicking on the links or querying the                    Regulations (18 CFR 385.211 and                       to comply with the Commission’s
                                              docket number.                                           385.214) on or before 5:00 p.m. Eastern               Standards of Conduct. In addition, as
                                                 Any person desiring to intervene or                   time on the specified comment date.                   discussed below, we provide guidance
                                              protest in any of the above proceedings                  Protests may be considered, but                       with regard to interconnection facilities
                                              must file in accordance with Rules 211                   intervention is necessary to become a                 that qualify for the blanket OATT
                                              and 214 of the Commission’s                              party to the proceeding.                              waiver provided in Order No. 807.1 We
                                              Regulations (18 CFR 385.211 and                          Filings in Existing Proceedings                       also grant Kingfisher Wind’s request for
                                              385.214) on or before 5:00 p.m. Eastern                                                                        other waivers commonly granted to
                                                                                                          Docket Numbers: RP14–1195–003.                     market-based rate sellers, except as
                                              time on the specified comment date.
                                                                                                          Applicants: Sierrita Gas Pipeline LLC.             noted herein.
                                              Protests may be considered, but
                                                                                                          Description: Compliance filing Tariff                 2. Additionally, we find that
                                              intervention is necessary to become a
                                                                                                       Record Correction Compliance to be                    Kingfisher Wind meets the criteria for a
                                              party to the proceeding.
                                                 eFiling is encouraged. More detailed                  effective 10/31/2014.                                 Category 1 seller in the Northwest,
                                                                                                          Filed Date: 6/18/15.                               Northeast, Southwest, Southeast, and
                                              information relating to filing
                                                                                                          Accession Number: 20150618–5095                    Central regions and a Category 2 seller
                                              requirements, interventions, protests,
                                                                                                          Comments Due: 5 p.m. ET 6/30/15.                   in the Southwest Power Pool (SPP)
                                              service, and qualifying facilities filings
                                              can be found at: http://www.ferc.gov/                       Any person desiring to protest in any              region, and is so designated. Kingfisher
                                              docs-filing/efiling/filing-req.pdf. For                  of the above proceedings must file in                 Wind must file updated market power
                                              other information, call (866) 208–3676                   accordance with Rule 211 of the                       analyses for the SPP region in
                                              (toll free). For TTY, call (202) 502–8659.               Commission’s Regulations (18 CFR                      compliance with the regional reporting
                                                                                                       385.211) on or before 5:00 p.m. Eastern               schedule adopted in Order No. 697.2
                                                Dated: June 30, 2015.
                                                                                                       time on the specified comment date.
                                              Nathaniel J. Davis, Sr.,                                                                                          1 Subsequent to the filing of this application, the
                                                                                                          The filings are accessible in the
                                              Deputy Secretary.                                                                                              Commission issued Order No. 807, which will be
                                                                                                       Commission’s eLibrary system by                       effective June 30, 2015. In Order No. 807, the
                                              [FR Doc. 2015–16603 Filed 7–6–15; 8:45 am]               clicking on the links or querying the                 Commission amended its regulations to waive the
                                              BILLING CODE 6717–01–P                                   docket number.                                        OATT requirements of 18 CFR 35.28, the OASIS
                                                                                                          eFiling is encouraged. More detailed               requirements of part 37, and the Standards of
                                                                                                                                                             Conduct requirements of part 358, under certain
                                                                                                       information relating to filing                        conditions, for entities that own interconnection
                                              DEPARTMENT OF ENERGY                                     requirements, interventions, protests,                facilities. See Open Access and Priority Rights on
                                                                                                       service, and qualifying facilities filings            Interconnection Customer’s Interconnection
                                              Federal Energy Regulatory                                                                                      Facilities, Order No. 807, FERC Stats. & Regs.
                                                                                                       can be found at: http://www.ferc.gov/
                                              Commission                                                                                                     ¶ 31,367 (2015).
                                                                                                       docs-filing/efiling/filing-req.pdf. For                  2 See Market-Based Rates for Wholesale Sales of

                                              Combined Notice of Filings                               other information, call (866) 208–3676                Electric Energy, Capacity and Ancillary Services by
tkelley on DSK3SPTVN1PROD with NOTICES




                                                                                                       (toll free). For TTY, call (202) 502–8659.            Public Utilities, Order No. 697, FERC Stats. & Regs.
                                                Take notice that the Commission has                                                                          ¶ 31,252, at PP 848–850, clarified, 121 FERC
                                                                                                         Dated: June 29, 2015.                               ¶ 61,260 (2007) (Clarification Order), order on reh’g,
                                              received the following Natural Gas
                                                                                                       Nathaniel J. Davis, Sr.,                              Order No. 697–A, FERC Stats. & Regs. ¶ 31,268,
                                              Pipeline Rate and Refund Report filings:                                                                       clarified, 124 FERC ¶ 61,055, order on reh’g, Order
                                                                                                       Deputy Secretary.
                                              Filings Instituting Proceedings                                                                                No. 697–B, FERC Stats. & Regs. ¶ 31,285 (2008),
                                                                                                       [FR Doc. 2015–16588 Filed 7–6–15; 8:45 am]            order on reh’g, Order No. 697–C, FERC Stats. &
                                                Docket Numbers: RP12–1136–000.                         BILLING CODE 6717–01–P                                                                            Continued




                                         VerDate Sep<11>2014   20:31 Jul 06, 2015   Jkt 235001   PO 00000   Frm 00019   Fmt 4703   Sfmt 4703   E:\FR\FM\07JYN1.SGM   07JYN1


                                              38680                            Federal Register / Vol. 80, No. 129 / Tuesday, July 7, 2015 / Notices

                                              I. Background                                            under Order Nos. 888,6 889,7 890,8                      the Public Utility Regulatory Policies
                                                                                                       2004,9 and 717,10 and section 35.28,11                  Act of 1978.14 Kingfisher Wind
                                                 3. On March 17, 2015, as amended                      and Parts 37 12 and 358 13 of the                       represents that it is affiliated with
                                              May 18, 2015, pursuant to section 205                    Commission’s regulations for all of the                 approximately 918 MW of generation
                                              of the Federal Power Act (FPA),3                         limited interconnection facilities,                     capacity in the SPP market, all of which
                                              Kingfisher Wind filed an application for                 including but not limited to, the Shared                is fully committed under long-term
                                              market-based rate authority with an                      Facilities.                                             power purchase agreements.
                                              accompanying tariff providing for the                       7. Kingfisher Wind states that it is a
                                              sale of electric energy, capacity, and                   wholly-owned subsidiary of FR
                                              ancillary services at market-based rates.4               Kingfisher Holdings II LLC, which is an                 II. Notice of Filings
                                                                                                       indirect subsidiary of First Reserve                       8. Notices of Kingfisher Wind’s filings
                                                 4. Kingfisher Wind states that it owns
                                                                                                       Energy Infrastructure Fund II, L.P.                     were published in the Federal
                                              a 298 megawatt (MW) wind generation                      (Fund II), which is controlled by senior
                                              facility located in Canadian and                                                                                 Register,15 with interventions and
                                                                                                       officers of First Reserve, a global private
                                              Kingfisher Counties, Oklahoma (the                                                                               protests due on or before June 9, 2015.
                                                                                                       equity firm focused on the energy
                                              Project), within the SPP market.                                                                                 None was filed.
                                                                                                       industry. Kingfisher Wind states that                      9. Notice of Kingfisher Wind’s request
                                                 5. Kingfisher Wind states that it will                Fund II is managed and controlled by its                for blanket authorization under part 34
                                              also own limited interconnection                         general partner, First Reserve Energy                   of the Commission’s regulations was
                                              facilities which will consist of 34.5                    Infrastructure GP II, L.P., which in turn,
                                                                                                                                                               separately published in the Federal
                                              kilovolt (kV) collection lines and related               is managed and controlled by its general
                                                                                                                                                               Register,16 with interventions or
                                              facilities, including a collection                       partner, First Reserve Energy
                                                                                                                                                               protests due on or before April 7, 2015.
                                              substation, transformers and disconnect                  Infrastructure G.P. II Limited (First
                                                                                                                                                               None was filed.
                                              switches, and a share of a 25-mile, 345                  Reserve GP II). Kingfisher Wind states
                                              kV generator tie line and related                        that its affiliates that own or control                 III. Discussion
                                              equipment and facilities (Shared                         generation facilities in the United States                 10. As discussed below, we will grant
                                                                                                       are either exempt wholesale generators                  Kingfisher Wind’s request for
                                              Facilities) 5 that are necessary to
                                                                                                       or owners of qualifying facilities under                authorization to make wholesale sales of
                                              interconnect the Project to the 345 kV
                                              Cimarron substation owned by OG&E                          6 Promoting Wholesale Competition Through
                                                                                                                                                               electric energy, capacity, and ancillary
                                              and the transmission system operated                     Open Access Non-Discriminatory Transmission
                                                                                                                                                               services at market-based rates and we
                                              by SPP.                                                  Services by Public Utilities; Recovery of Stranded      will accept its market-based rate tariff,
                                                                                                       Costs by Public Utilities and Transmitting Utilities,   effective June 30, 2015, as requested.17
                                                 6. Kingfisher Wind states that it will                Order No. 888, FERC Stats. & Regs. ¶ 31,036 (1996),     We will also grant Kingfisher Wind’s
                                              utilize the interconnection facilities                   order on reh’g, Order No. 888–A, FERC Stats. &
                                                                                                                                                               request for certain waivers.
                                                                                                       Regs. ¶ 31,048, order on reh’g, Order No. 888–B, 81
                                              solely to interconnect the Project to the                FERC ¶ 61,248 (1997), order on reh’g, Order No.
                                              transmission system operated by SPP.                     888–C, 82 FERC ¶ 61,046 (1998), aff’d in relevant
                                                                                                                                                               A. Market-Based Rate Authorization
                                              Kingfisher Wind states that the                          part sub nom. Transmission Access Policy Study            11. The Commission allows power
                                              interconnection facilities do not                        Group v. FERC, 225 F.3d 667 (D.C. Cir. 2000), aff’d
                                                                                                       sub nom. New York v. FERC, 535 U.S. 1 (2002).
                                                                                                                                                               sales at market-based rates if the seller
                                              comprise an integrated transmission                        7 Open Access Same-Time Information System            and its affiliates do not have, or have
                                              system and are limited and discrete.                     and Standards of Conduct, Order No. 889, FERC           adequately mitigated, horizontal and
                                              Kingfisher Wind requests that the                        Stats. & Regs. ¶ 31,035 (1996), order on reh’g, Order   vertical market power.18
                                                                                                       No. 889–A, FERC Stats. & Regs. ¶ 31,049, reh’g
                                              Commission waive the requirements                        denied, Order No. 889–B, 81 FERC ¶ 61,253 (1997).       1. Horizontal Market Power
                                                                                                         8 Preventing Undue Discrimination and

                                                                                                       Preference in Transmission Service, Order No. 890,         12. The Commission has adopted two
                                              Regs. ¶ 31,291 (2009), order on reh’g, Order No.
                                              697–D, FERC Stats. & Regs. ¶ 31,305 (2010), aff’d        FERC Stats. & Regs. ¶ 31,241, order on reh’g, Order     indicative screens for assessing
                                              sub nom. Mont. Consumer Counsel v. FERC, 659
                                                                                                       No. 890–A, FERC Stats. & Regs. ¶ 31,261 (2007),         horizontal market power: the pivotal
                                                                                                       order on reh’g, Order No. 890–B, 123 FERC ¶ 61,299      supplier screen and the wholesale
                                              F.3d 910 (9th Cir. 2011), cert. denied, 133 S. Ct. 26    (2008), order on reh’g, Order No. 890–C, 126 FERC
                                              (2012).                                                  ¶ 61,228, order on clarification, Order No. 890–D,      market share screen.19 The Commission
                                                3 16 U.S.C. 824d (2012).                               129 FERC ¶ 61,126 (2009).                               has stated that passage of both screens
                                                4 Kingfisher Wind requests authorization to sell         9 Standards of Conduct for Transmission
                                                                                                                                                               establishes a rebuttable presumption
                                              ancillary services in the markets administered by        Providers, Order No. 2004, FERC Stats. & Regs.          that the applicant does not possess
                                              PJM Interconnection, L.L.C., New York Independent        ¶ 31,155 (2003), order on reh’g, Order No. 2004–A,
                                              System Operator, Inc., ISO New England Inc.,             FERC Stats. & Regs. ¶ 31,161, order on reh’g, Order
                                                                                                                                                                 14 16  U.S.C. 2601 et seq. (2012).
                                                                                                       No. 2004–B, FERC Stats. & Regs. ¶ 31,166, order on
                                              California Independent System Operator Corp.,                                                                      15 80  FR 15,779 (2015); 80 FR 30,223 (2015).
                                                                                                       reh’g, Order No. 2004–C, FERC Stats. & Regs.
                                              Midcontinent Independent System Operator, Inc.           ¶ 31,172 (2004), order on reh’g, Order No. 2004–D,        16 80 FR 15,784 (2015).
                                              (MISO), and SPP, as well as authorization to engage      110 FERC ¶ 61,320 (2005), vacated and remanded            17 We note that Kingfisher Wind is not being
                                              in the sale of certain ancillary services as a third-    as it applies to natural gas pipelines sub nom.         granted authority to make third-party sales of
                                              party provider in other markets.                         National Fuel Gas Supply Corp. v. FERC, 468 F.3d        operating reserves to a public utility that is
                                                5 Kingfisher Wind states that it will acquire 30       831 (D.C. Cir. 2006); see Standards of Conduct for      purchasing ancillary services to satisfy its own open
                                              percent tenancy-in-common interests of the Shared        Transmission Providers, Order No. 690, FERC Stats.      access transmission tariff requirements to offer
                                              Facilities from Canadian Hills Wind, LLC (Canadian       & Regs. ¶ 31,237, order on reh’g, Order No. 690–A,      ancillary services to its own customers. If
                                                                                                       FERC Stats. & Regs. ¶ 31,243 (2007).                    Kingfisher Wind seeks such authority, it must make
                                              Hills). Kingfisher adds that Canadian Hills is an          10 Standards of Conduct for Transmission
                                              exempt wholesale generator which owns and                                                                        the required showing and receive Commission
                                                                                                       Providers, Order No. 717, FERC Stats. & Regs.           authorization prior to making such sales. See Third-
                                              operates a wind generation facility that is              ¶ 31,280 (2008), order on reh’g, Order No. 717–A,       Party Provision of Ancillary Services; Accounting
tkelley on DSK3SPTVN1PROD with NOTICES




                                              interconnected with the Oklahoma Gas and Electric        FERC Stats. & Regs. ¶ 31,297, order on reh’g, Order     and Financial Reporting for New Electric Storage
                                              Company (OG&E) transmission system via the               No. 717–B, 129 FERC ¶ 61,123 (2009), order on           Technologies, Order No. 784, FERC Stats. & Regs.
                                              Shared Facilities. Kingfisher Wind states that the       reh’g, Order No. 717–C, 131 FERC ¶ 61,045 (2010),       ¶ 31,349, at PP 200–202 (2013), order on
                                              Commission granted Canadian Hills waiver of the          order on reh’g, Order No. 717–D, 135 FERC ¶ 61,017      clarification, Order No. 784–A, 146 FERC ¶ 61,114
                                              OATT requirement. See Canadian Hills Wind, LLC,          (2011).                                                 (2014).
                                              143 FERC ¶ 61,261 (2013); see also Canadian Hills          11 18 CFR 35.28 (2014).                                 18 Order No. 697, FERC Stats. & Regs. ¶ 31,252 at

                                              Wind, LLC, Docket No. ER15–1372–000 (May 14,               12 18 CFR 37 (2014).                                  PP 62, 399, 408, 440.
                                              2015) (delegated letter order).                            13 18 CFR 358 (2014).                                   19 Id. P 62.




                                         VerDate Sep<11>2014   20:31 Jul 06, 2015   Jkt 235001   PO 00000   Frm 00020   Fmt 4703   Sfmt 4703   E:\FR\FM\07JYN1.SGM       07JYN1


                                                                               Federal Register / Vol. 80, No. 129 / Tuesday, July 7, 2015 / Notices                                                        38681

                                              horizontal market power, while failure                   requires sellers to make an affirmative                   comprise an integrated transmission
                                              of either screen creates a rebuttable                    statement that they have not erected                      system.
                                              presumption that the applicant has                       barriers to entry into the relevant market                   21. Order Nos. 888 and 890 and
                                              horizontal market power.20                               and will not erect barriers to entry into                 section 35.28 of the Commission’s
                                                13. Kingfisher Wind represents that it                 the relevant market.25 The Commission                     regulations require public utilities that
                                              relies on Westar Energy, Inc.’s recently                 adopted a rebuttable presumption that                     own, operate, or control facilities used
                                              accepted market power analysis to                        the ownership or control of, or                           for the transmission of electric energy in
                                              demonstrate that Kingfisher Wind                         affiliation with any entity that owns or                  interstate commerce to file an OATT.
                                              passes both the pivotal supplier and the                 controls, inputs to electric power                        Order No. 889 and part 37 of the
                                              wholesale market share screens for the                   production does not allow a seller to                     Commission’s regulations require public
                                              SPP market.21                                            raise entry barriers but will allow                       utilities to establish and maintain an
                                                14. Based on Kingfisher Wind’s                         intervenors to demonstrate otherwise.26                   OASIS. Order Nos. 889, 2004, and 717
                                              representations, we find that Kingfisher                    17. Regarding other barriers to entry,                 and Part 358 of the Commission’s
                                              Wind satisfies the Commission’s                          Kingfisher Wind states that neither it                    regulations require public utilities to
                                              requirements for market-based rates                      nor any of its affiliates owns or controls                abide by certain Standards of
                                              regarding horizontal market power.                       physical coal supply sources, entities                    Conduct.29 In prior orders, the
                                              2. Vertical Market Power                                 that may access transportation of coal                    Commission has enunciated the
                                                                                                       supplies, or sites to develop new                         standards for exemption from some or
                                                 15. In cases where a public utility, or                                                                         all of the requirements of Order Nos.
                                                                                                       generation capacity. Kingfisher Wind
                                              any of its affiliates, owns, operates, or                                                                          888, 889, and 890.30 The Commission
                                                                                                       states that it has affiliates that own or
                                              controls transmission facilities, the                                                                              has stated that the criteria for waiver of
                                                                                                       control intrastate natural gas
                                              Commission requires that there be a                                                                                the requirements of Order No. 890 and
                                                                                                       transportation, storage or distribution
                                              Commission-approved OATT on file or                                                                                Order No. 2004 are unchanged from
                                                                                                       facilities, but that these assets will not
                                              that the seller has received waiver of the                                                                         those used to evaluate requests for
                                                                                                       allow Kingfisher Wind to erect barriers
                                              OATT requirement before granting a                                                                                 waiver under Order Nos. 888 and 889.31
                                              seller market-based rate authorization.22                to entry.27
                                                                                                          18. Finally, consistent with Order No.                 Order No. 717 did not change those
                                              Kingfisher Wind states that neither                                                                                criteria.32
                                              Kingfisher Wind nor its affiliates owns                  697, Kingfisher Wind affirmatively
                                                                                                       states that it and its affiliates have not                   22. The Commission may grant
                                              transmission facilities other than those                                                                           requests for waiver of the obligation to
                                              limited and discrete facilities that are                 erected, and will not erect, barriers to
                                                                                                       entry in SPP.                                             file an OATT to public utilities that can
                                              necessary to interconnect generation                                                                               show that they own, operate, or control
                                              facilities to the transmission grid. As                     19. Based on Kingfisher Wind’s
                                                                                                       representations, we find that Kingfisher                  only limited and discrete transmission
                                              discussed more fully below, the                                                                                    facilities (facilities that do not form an
                                              Commission will grant Kingfisher                         Wind satisfies the Commission’s
                                                                                                                                                                 integrated transmission grid), until such
                                              Wind’s request for waiver of the                         requirements for market-based rates
                                                                                                                                                                 time as the public utility receives a
                                              requirement to have an OATT on file for                  regarding vertical market power.
                                                                                                                                                                 request for transmission service. Should
                                              the interconnection facilities.                          B. Waiver Requests                                        the public utility receive such a request,
                                                 16. The Commission also considers a                                                                             the Commission has determined that the
                                              seller’s ability to erect other barriers to              1. OATT, OASIS, and Standards of
                                                                                                                                                                 public utility must file with the
                                              entry as part of the vertical market                     Conduct
                                                                                                                                                                 Commission a pro forma tariff within 60
                                              power analysis.23 The Commission                            20. Kingfisher Wind seeks waiver of                    days of the date of the request, and must
                                              requires a seller to provide a description               the requirements to file an OATT,                         comply with any additional
                                              of its ownership or control of, or                       establish and maintain an OASIS, and                      requirements that are effective on the
                                              affiliation with an entity that owns or                  abide by the Standards of Conduct with                    date of the request.33
                                              controls, intrastate natural gas                         respect to the interconnection facilities                    23. The Commission has also
                                              transportation, intrastate natural gas                   that it owns.28 In support, Kingfisher                    determined that waiver of the
                                              storage or distribution facilities; sites for            Wind represents that the                                  requirement to establish an OASIS and
                                              new generation capacity development;                     interconnection facilities are limited                    abide by the Standards of Conduct
                                              and physical coal supply sources and                     and discrete and that it will utilize them                would be appropriate for a public utility
                                              ownership of or control over who may                     solely to interconnect the Project to the                 if the applicant: (1) Owns, operates, or
                                              access transportation of coal supplies                   transmission system operated by SPP.                      controls only limited and discrete
                                              (collectively, inputs to electric power                  Kingfisher Wind further states that the                   transmission facilities (rather than an
                                              production).24 The Commission also                       interconnection facilities do not                         integrated transmission grid); or (2) is a
                                                                                                                                                                 small public utility that owns, operates,
                                                20 Id.  PP 33, 62–63.                                    25 Order No. 697, FERC Stats. & Regs. ¶ 31,252 at
                                                                                                                                                                 or controls an integrated transmission
                                                21 See   Westar Energy, Inc., Docket No. ER14–724–     P 447.
                                              000 (Feb. 28, 2014) (delegated letter order).              26 Id. P 446.
                                                                                                                                                                 grid, unless other circumstances are
                                              Kingfisher Wind relies on historical data for the          27 Kingfisher Wind states that it is affiliated with:
                                                                                                                                                                   29 Order No. 889, FERC Stats. & Regs. ¶ 31,035 at
                                              SPP market for the study period of December 2011         (1) Crestwood Midstream Partners, LP, which owns
                                              through November 2012 contained in the Westar            gathering pipelines and natural gas storage facilities    31,590; Order No. 2004, FERC Stats. &
                                              pivotal supplier and market share screens study.         located in a number of geographic regions,                Regs. ¶ 31,155 at P 16; Order No. 717, FERC Stats.
                                              Kingfisher Wind states that the use of more recent       including some gathering pipelines located in or          & Regs. ¶ 31,280 at P 313.
                                              data (i.e., December 2012 through November 2013)         near SPP; (2) the Arthur C. Nielsen Pipeline System
                                                                                                                                                                   30 See, e.g., Black Creek Hydro, Inc., 77 FERC

                                              would not result in significantly higher market          and Clearfield Pipeline System, intrastate natural        ¶ 61,232, at 61,941 (1996) (Black Creek); Entergy
tkelley on DSK3SPTVN1PROD with NOTICES




                                              shares because conditions would not change               gas pipelines located within Pennsylvania; and (3)        Mississippi, Inc., 112 FERC ¶ 61,228, at P 22 (2005)
                                              materially over one year. See Clarification Order,       FREIF Caliber Holdings, which owns gathering              (Entergy).
                                              121 FERC ¶ 61,260 at P 12.d.                             pipelines located in MISO. See Kingfisher Wind              31 See Alcoa Power Generating Inc., 120 FERC
                                                 22 Order No. 697, FERC Stats. & Regs. ¶ 31,252 at                                                               ¶ 61,035, at P 3 (2007); Alcoa Power Generating
                                                                                                       May 18 Supplement at 2–3.
                                              P 408.                                                     28 Notwithstanding the issuance of Order No. 807,       Inc., 108 FERC ¶ 61,243, at P 27 (2004).
                                                 23 Id. P 440.                                                                                                     32 See Order No. 717, FERC Stats. & Regs.
                                                                                                       Kingfisher Wind requests that the Commission rule
                                                 24 Order No. 697–A, FERC Stats. & Regs. ¶ 31,268      on its requested waiver herein. Kingfisher Wind           ¶ 31,280 at PP 31–33.
                                              at P 176.                                                May 18 Supplement at n.5.                                   33 Black Creek, 77 FERC at 61,941.




                                         VerDate Sep<11>2014   20:31 Jul 06, 2015   Jkt 235001   PO 00000   Frm 00021   Fmt 4703   Sfmt 4703   E:\FR\FM\07JYN1.SGM      07JYN1


                                              38682                            Federal Register / Vol. 80, No. 129 / Tuesday, July 7, 2015 / Notices

                                              present that indicate that a waiver                      takes action on a complaint by an entity                applicants who attest that they qualify
                                              would not be justified.34 The                            that Kingfisher Wind has unfairly used                  for the blanket authorization do not
                                              Commission has held that waiver of                       its access to information to unfairly                   need to request, nor should they
                                              Order No. 889 will remain in effect until                benefit itself or its affiliates.38                     request, a waiver of the OATT, OASIS
                                              the Commission takes action in                              26. Given that Order No. 807 will be                 and Standards of Conduct requirements.
                                              response to a complaint to the                           effective June 30, 2015, we take this                   We also note that the Commission stated
                                              Commission that an entity evaluating its                 opportunity to explain how market-                      in Order No. 807 that an entity that has
                                              transmission needs could not get the                     based rate applicants and sellers may                   already been issued a waiver of the
                                              information necessary to complete its                    demonstrate a lack of vertical market                   OATT, OASIS and Standards of
                                              evaluation (for OASIS waivers) or an                     power once the blanket waiver provided                  Conduct requirements and that is
                                              entity complains that the public utility                 for in 18 CFR 35.28(d)(2) takes effect. In              eligible for the blanket waiver under
                                              has unfairly used its access to                          Order No. 807, the Commission                           Order No. 807 will be deemed to be
                                              information about transmission to                        modified its policy to provide an                       operating under the blanket waiver
                                              benefit the utility or its affiliate (for                additional method for obtaining waiver                  without further filings necessary with
                                              Standards of Conduct waivers).35                         of the OATT requirements. Specifically,                 respect to the previously-issued
                                                 24. Based on the statements in                        the Commission stated that a market-                    waiver.42
                                              Kingfisher Wind’s application, we find                   based rate seller or any of its affiliates                 28. As stated above, Kingfisher Wind
                                              that its interconnection facilities qualify              that own, operate, or control                           specifically requests that the
                                              as limited and discrete. Kingfisher Wind                 transmission facilities may satisfy the                 Commission rule on its requested OATT
                                              will use the facilities solely to                        vertical market power requirements in                   waiver, and we hereby grant this waiver.
                                              interconnect the Project to the                          18 CFR 35.37(d) by one of the following:                2. Other Waivers and Authorizations
                                              transmission grid. Accordingly, we will                  (1) Have a Commission-approved OATT
                                                                                                                                                                  29. Kingfisher Wind also requests the
                                              grant Kingfisher Wind waiver of the                      on file; (2) receive waiver of the OATT
                                                                                                                                                               following waivers and authorizations:
                                              requirements of Order Nos. 888 and 890                   requirement under 18 CFR 35.28(d)(1);
                                                                                                                                                               (1) Waiver of the filing requirements of
                                              and section 35.28 of the Commission’s                    or (3) satisfy the requirements for a
                                                                                                                                                               subparts B and C of part 35 of the
                                              regulations to have an OATT on file                      blanket waiver under 18 CFR
                                                                                                                                                               Commission’s regulations, except
                                              with respect to the interconnection                      35.28(d)(2).39
                                                                                                                                                               sections 35.12(a), 35.13(b), 35.15, and
                                              facilities. However, if Kingfisher Wind                     27. We provide guidance herein that
                                                                                                                                                               35.16; (2) waiver of the accounting and
                                              receives a request for transmission                      an applicant that qualifies for the
                                                                                                                                                               other requirements of parts 41, 101, and
                                              service, it must file with the                           blanket OATT waiver under 18 CFR
                                                                                                                                                               141 of the Commission’s regulations,
                                              Commission a pro forma OATT within                       35.28(d)(2) should affirm in its market-
                                                                                                                                                               except sections 141.14 and 141.15; and
                                              60 days of the date of the request.36                    based rate application that it qualifies                (3) blanket authorization under section
                                                 25. The Commission will also grant                    for the blanket OATT waiver. As the                     204 of the FPA 43 and Part 34 of the
                                              Kingfisher Wind waiver of the                            Commission stated in Order No. 807,                     Commission’s regulations for all future
                                              requirements of Order No. 889 and part                   ‘‘[s]uch a waiver is justified because the              issuances of securities and assumptions
                                              37 of the Commission’s regulations with                  usually limited and discrete nature of                  of liability.
                                              respect to OASIS and Order Nos. 889,                     [Interconnection Customer’s                                30. The Commission will grant the
                                              2004, and 717 and Part 358 with respect                  Interconnection Facilities (ICIF)] and                  requested waivers and authorizations
                                              to the Standards of Conduct. We note                     ICIF’s dedicated interconnection                        consistent with those granted to other
                                              that Kingfisher Wind’s waiver of the                     purpose means that such facilities do                   entities with market-based rate
                                              requirement to establish an OASIS will                   not typically present the concerns about                authorizations.44 Notwithstanding the
                                              remain in effect until the Commission                    discriminatory conduct that the
                                              takes action in response to a complaint                  Commission’s OATT, OASIS, and                           be considered ICIF, the blanket waiver would be
                                              to the Commission that an entity                         Standards of Conduct requirements                       deemed to be revoked.’’). After revocation of its
                                              evaluating its transmission needs could                  were intended to address.’’ 40 In                       waivers, the public utility must comply with the
                                                                                                                                                               requirements that had been waived within 60 days
                                              not get the information necessary to                     accordance with Order No. 807, the                      of revocation. Id. at regulatory text (to be codified
                                              complete its evaluation.37 Likewise,                     waivers referenced in 18 CFR                            at 18 CFR 35.28(d)(2)(i)).
                                              Kingfisher Wind’s waiver of the                          35.28(d)(2) shall be deemed in effect                      42 Id. P 176 (referencing P 89, which states, in

                                              Standards of Conduct will remain in                      unless revoked as of the date the public                part, that ‘‘if an entity has previously received a
                                                                                                                                                               specific waiver of the OATT and related obligations
                                              effect unless and until the Commission                   utility ceases to satisfy the qualifications            pursuant to the Commission’s ‘limited and discrete’
                                                                                                       of 18 CFR 35.28(d)(2), and also may be                  or ‘small entity’ standards, the blanket waiver will
                                                 34 Id. Although the Commission originally
                                                                                                       revoked by the Commission if the                        supersede the existing waiver’’).
                                              precluded waiver of the requirements for OASIS           Commission determines that it is in the                    43 16 U.S.C. 824c (2012).
                                              and the Standards of Conduct for a small public                                                                     44 We note that the Commission has examined
                                              utility that is a member of a tight power pool, in       public interest to do so.41 Thus,
                                                                                                                                                               and approved the continued applicability of the
                                              Black Hills Power, Inc., 135 FERC ¶ 61,058, at PP                                                                waiver of its accounting and reporting requirements
                                              2–3 (2011) (Black Hills), the Commission explained          38 Id. Kingfisher Wind must notify the
                                                                                                                                                               in parts 41, 101, and 141 of the Commission’s
                                              that membership in a tight power pool is no longer       Commission if there is a material change in facts       regulations, as well as the continued applicability
                                              a factor in the determination for waiver of              that affects its waiver within 30 days of the date of   of the blanket authorization for the issuance of
                                              Standards of Conduct. Moreover, Black Hills did          such change. Material Changes in Facts Underlying       securities and the assumption of liabilities in part
                                              not affect waivers based on a public utility             Waiver of Order No. 889 and Part 358 of the             34 of the Commission’s regulations. See Order No.
                                              disposing of no more than 4 million megawatt-            Commission’s Regulations, 127 FERC ¶ 61,141, at         697, FERC Stats. & Regs. ¶ 31,252 at PP 984–985
                                              hours annually.                                          P 5 (2009).                                             (regarding waiver of parts 41, 101, and 141) and PP
                                                 35 Entergy, 112 FERC ¶ 61,228 at P 23 (citing            39 Order No. 807, FERC Stats. & Regs. ¶ 31,367 at
                                                                                                                                                               999–1000 (regarding blanket approval under part
tkelley on DSK3SPTVN1PROD with NOTICES




                                              Cent. Minn. Mun. Power Agency, 79 FERC ¶ 61,260,         P 57.                                                   34). However, waiver of the provisions of part 101
                                              at 62,127 (1997) (Central Minnesota); Easton Utils.         40 Id. P 55.
                                                                                                                                                               that apply to hydropower licensees is not granted
                                              Comm’n, 83 FERC ¶ 61,334, at 62,343 (1998)                  41 Id. P 101 (‘‘the [blanket] waiver would be        with respect to licensed hydropower projects.
                                              (Easton)).                                               deemed to be revoked as of the date the public          Hydropower licensees are required to comply with
                                                 36 Black Creek, 77 FERC at 61,941.
                                                                                                       utility ceases to satisfy the qualifications for such   the requirements of the Uniform System of
                                                 37 Entergy, 112 FERC ¶ 61,228 at P 23 (citing         waiver. . . . [I]f the ICIF that are covered by a       Accounts pursuant to 18 CFR part 101 to the extent
                                              Central Minnesota, 79 FERC at 62,127; Easton, 83         blanket waiver become integrated into a                 necessary to carry out their responsibilities under
                                              FERC at 62,343).                                         transmission system such that they can no longer        part I of the FPA. We further note that a licensee’s



                                         VerDate Sep<11>2014   20:31 Jul 06, 2015   Jkt 235001   PO 00000   Frm 00022   Fmt 4703   Sfmt 4703   E:\FR\FM\07JYN1.SGM    07JYN1


                                                                               Federal Register / Vol. 80, No. 129 / Tuesday, July 7, 2015 / Notices                                           38683

                                              waiver of the accounting and reporting                      33. In Order No. 697, the Commission               regional reporting schedule adopted in
                                              requirements, the Commission expects                     created two categories of sellers.52                  Order No. 697.55 The Commission also
                                              Kingfisher Wind to keep its accounting                   Category 1 sellers are not required to file           reserves the right to require such an
                                              records in accordance with generally                     regularly scheduled updated market                    analysis at any time for any region.56
                                              accepted accounting principles.                          power analyses. Category 1 sellers are                   The Commission orders:
                                                                                                       wholesale power marketers and                            (A) Kingfisher Wind’s market-based
                                              C. Reporting Requirements                                                                                      rate tariff is hereby accepted for filing,
                                                                                                       wholesale power producers that own or
                                                31. An entity with market-based rate                   control 500 MW or less of generation in               effective June 30, 2015, as requested, as
                                              authorization must file an Electric                      aggregate per region; that do not own,                discussed in the body of this order.
                                              Quarterly Report (EQR) with the                          operate, or control transmission                         (B) Kingfisher Wind’s request for
                                              Commission, consistent with Order Nos.                   facilities other than limited equipment               waiver of the requirements to file an
                                              2001 45 and 768,46 to fulfill its                        necessary to connect individual                       OATT, to establish and maintain an
                                              responsibility under FPA section                         generation facilities to the transmission             OASIS, and to comply with the
                                              205(c) 47 to have rates on file in a                     grid (or have been granted waiver of the              Standards of Conduct is hereby granted,
                                              convenient form and place.48 Kingfisher                  requirements of Order No. 888); that are              as discussed in the body of this order.
                                              Wind must file EQRs electronically with                  not affiliated with anyone that owns,                    (C) Waiver of the provisions of
                                              the Commission consistent with the                       operates, or controls transmission                    subparts B and C of part 35 of the
                                              procedures set forth in Order No. 770.49                 facilities in the same region as the                  Commission’s regulations, with the
                                              Failure to timely and accurately file an                                                                       exception of sections 35.12(a), 35.13(b),
                                                                                                       seller’s generation assets; that are not
                                              EQR is a violation of the Commission’s                                                                         35.15, and 35.16, is hereby granted.
                                                                                                       affiliated with a franchised public
                                              regulations for which Kingfisher Wind                                                                             (D) Waiver of part 101 of the
                                                                                                       utility in the same region as the seller’s            Commission’s regulations is hereby
                                              may be subject to refund, civil penalties,               generation assets; and that do not raise
                                              and/or revocation of market-based rate                                                                         granted, with the exception that waiver
                                                                                                       other vertical market power issues.53                 of the provisions of Part 101 that apply
                                              authority.50                                             Sellers that do not fall into Category 1
                                                32. Additionally, Kingfisher Wind                                                                            to hydropower licensees is not granted
                                                                                                       are designated as Category 2 sellers and              with respect to licensed hydropower
                                              must timely report to the Commission
                                                                                                       are required to file updated market                   projects. Waiver of parts 41 and 141 of
                                              any change in status that would reflect
                                                                                                       power analyses.54                                     the Commission’s regulations is hereby
                                              a departure from the characteristics the                    34. Kingfisher Wind requests Category
                                              Commission relied upon in granting                                                                             granted, with the exception of sections
                                                                                                       1 seller status in the Northwest,
                                              market-based rate authority.51                                                                                 141.14 and 141.15.
                                                                                                       Northeast, Southwest, Southeast, and                     (E) Blanket authorization under part
                                                                                                       Central regions, and Category 2 seller                34 of the Commission’s regulations for
                                              status as a market-based rate seller under part II of
                                              the FPA does not exempt it from its accounting           status in the SPP region. Kingfisher                  all future issuances of securities and
                                              responsibilities as a licensee under part I of the       Wind states that it is located in the SPP             assumptions of liability is hereby
                                              FPA. See Seneca Gen., LLC, 145 FERC ¶ 61,096, at         region, where it and its affiliates own or
                                              P 23 n.20 (2013) (citing Trafalgar Power Inc., 87                                                              granted. Kingfisher Wind is hereby
                                              FERC ¶ 61,207, at 61,798 (1999) (noting that ‘‘all
                                                                                                       control more than 500 MW of generation                authorized to issue securities and
                                              licensees are required to comply with the                capacity. Kingfisher Wind represents                  assume obligations or liabilities as
                                              requirements of the Uniform System of Accounts to        that it does not own or control                       guarantor, indorser, surety, or otherwise
                                              the extent necessary to carry out their                  generation in any other region.
                                              responsibilities under [s]ections 4(b), 10(d) and 14                                                           in respect of any security of another
                                              of the FPA’’)).                                          Kingfisher Wind further represents that               person; provided that such issue or
                                                 45 Revised Public Utility Filing Requirements,        neither it nor its affiliates own, operate            assumption is for some lawful object
                                              Order No. 2001, FERC Stats. & Regs. ¶ 31,127, reh’g      or control transmission facilities other              within the corporate purposes of
                                              denied, Order No. 2001–A, 100 FERC ¶ 61,074,             than limited facilities necessary to
                                              reh’g denied, Order No. 2001–B, 100 FERC ¶                                                                     Kingfisher Wind, compatible with the
                                              61,342, order directing filing, Order No. 2001–C,        connect individual generating facilities              public interest, and reasonably
                                              101 FERC ¶ 61,314 (2002), order directing filing,        to the transmission grid. Kingfisher                  necessary or appropriate for such
                                              Order No. 2001–D, 102 FERC ¶ 61,334, order               Wind also represents that it is not
                                              refining filing requirements, Order No. 2001–E, 105                                                            purposes.
                                              FERC ¶ 61,352 (2003), order on clarification, Order
                                                                                                       affiliated with any entity that owns,                    (F) The Commission reserves the right
                                              No. 2001–F, 106 FERC ¶ 61,060 (2004), order              operates or controls transmission                     to modify this order to require a further
                                              revising filing requirements, Order No. 2001–G, 120      facilities in the same region as its                  showing that neither the public nor
                                              FERC ¶ 61,270, order on reh’g and clarification,         generation assets nor with a franchised
                                              Order No. 2001–H, 121 FERC ¶ 61,289 (2007), order                                                              private interests will be adversely
                                              revising filing requirements, Order No. 2001–I,          public utility in the same region as its              affected by continued Commission
                                              FERC Stats. & Regs. ¶ 31,282 (2008).                     generation assets. Finally, Kingfisher                approval of Kingfisher Wind’s issuance
                                                 46 Electricity Mkt. Transparency Provisions of        Wind represents that neither it nor its               of securities or assumptions of liability.
                                              Section 220 of the Fed. Power Act, Order No. 768,        affiliates raise other vertical market
                                              FERC Stats. & Regs. ¶ 31,336 (2012), order on reh’g,                                                              (G) Kingfisher Wind is hereby
                                              Order No. 768–A, 143 FERC ¶ 61,054 (2013).               power concerns.                                       required to file EQRs in compliance
                                                 47 16 U.S.C. 824d(c) (2012).                             35. Based on Kingfisher Wind’s                     with Order Nos. 2001 and 768. If the
                                                 48 See Revisions to Electric Quarterly Report         representations, we grant Kingfisher                  effective date of Kingfisher Wind’s
                                              Filing Process, Order No. 770, FERC Stats. & Regs.       Wind Category 1 seller status in the                  market-based rate tariff falls within a
                                              ¶ 31,338, at P 3 (2012) (citing Order No. 2001, FERC     Northwest, Northeast, Southwest,
                                              Stats. & Regs. ¶ 31,127 at P 31).                                                                              quarter of the year that has already
                                                 49 Order No. 770, FERC Stats. & Regs. ¶ 31,338.
                                                                                                       Southeast and Central regions and                     expired, Kingfisher Wind’s EQRs for the
                                                 50 The exact filing dates for these reports are       Category 2 seller status in the SPP                   expired quarter are due within 30 days
                                              prescribed in 18 CFR 35.10b (2014). Forfeiture of        region. Kingfisher Wind must file an                  of the date of this order.
                                              market-based rate authority may require a new            updated market power analysis for the
tkelley on DSK3SPTVN1PROD with NOTICES




                                                                                                                                                                (H) The Secretary is hereby directed
                                              application for market-based rate authority if the       SPP region in compliance with the
                                              applicant wishes to resume making sales at market-                                                             to publish a copy of this order in the
                                              based rates.                                                                                                   Federal Register.
                                                                                                         52 Order No. 697, FERC Stats. & Regs. ¶ 31,252 at
                                                 51 Reporting Requirement for Changes in Status
                                                                                                       P 848.                                                  By the Commission.
                                              for Public Utilities with Market-Based Rate
                                                                                                         53 18 CFR 35.36(a) (2014).
                                              Authority, Order No. 652, FERC Stats. & Regs. ¶
                                                                                                         54 Order No. 697, FERC Stats. & Regs. ¶ 31,252 at     55 Id.
                                              31,175, order on reh’g, 111 FERC ¶ 61,413 (2005);
                                              18 CFR 35.42 (2014).                                     P 850.                                                  56 Id.   P 853.



                                         VerDate Sep<11>2014   20:31 Jul 06, 2015   Jkt 235001   PO 00000   Frm 00023   Fmt 4703   Sfmt 4703   E:\FR\FM\07JYN1.SGM   07JYN1


                                              38684                            Federal Register / Vol. 80, No. 129 / Tuesday, July 7, 2015 / Notices

                                                Issued: June 30, 2015.                                 DC 20460; telephone number: 202–566–                  developing the section 303(d) lists,
                                              Nathaniel J. Davis, Sr.,                                 0399# ; fax number: 202–566–1331;                     States are required to consider various
                                              Deputy Secretary.                                        email address: Kovatch.charles@                       sources of water quality related data and
                                              [FR Doc. 2015–16589 Filed 7–6–15; 8:45 am]               epa.gov.                                              information, including the section
                                              BILLING CODE 6717–01–P                                   SUPPLEMENTARY INFORMATION:
                                                                                                                                                             305(b) State water quality reports.
                                                                                                       Supporting documents that explain in                  Section 106(e) requires that states
                                                                                                       detail the information that the EPA will              annually update monitoring data and
                                                                                                       be collecting are available in the public             use it in their section 305(b) report.
                                              ENVIRONMENTAL PROTECTION
                                                                                                       docket for this ICR. The docket can be                Section 314(a) requires states to report
                                              AGENCY
                                                                                                       viewed online at www.regulations.gov                  on the condition of their publicly-
                                              [EPA–HQ–OW–2003–0026; FRL–9930–14–
                                                                                                       or in person at the EPA Docket Center,                owned lakes within the section 305(b)
                                              OW]                                                                                                            report.
                                                                                                       WJC West, Room 3334, 1301
                                                                                                                                                                EPA’s Assessment and Watershed
                                              Proposed Information Collection                          Constitution Ave. NW., Washington,
                                                                                                                                                             Protection Division (AWPD) works with
                                              Request; Comment Request; National                       DC. The telephone number for the
                                                                                                                                                             its Regional counterparts to review and
                                              Water Quality Inventory Reports                          Docket Center is 202–566–1744. For                    approve or disapprove State section
                                              (Renewal)                                                additional information about EPA’s                    303(d) lists and TMDLs from 56
                                                                                                       public docket, visit http://www.epa.gov/              respondents (the 50 States, the District
                                              AGENCY: Environmental Protection                         dockets.
                                              Agency (EPA).                                                                                                  of Columbia, and the five Territories).
                                                                                                          Pursuant to section 3506(c)(2)(A) of
                                                                                                                                                             Section 303(d) specifically requires
                                              ACTION: Notice.                                          the PRA, EPA is soliciting comments
                                                                                                                                                             States to develop lists and TMDLs ‘‘from
                                                                                                       and information to enable it to: (i)
                                              SUMMARY:    The Environmental Protection                                                                       time to time,’’ and EPA to review and
                                                                                                       Evaluate whether the proposed                         approve or disapprove the lists and the
                                              Agency is planning to submit an                          collection of information is necessary
                                              information collection request (ICR),                                                                          TMDLs. EPA also collects State 305(b)
                                                                                                       for the proper performance of the                     reports from 59 respondents (the 50
                                              ‘‘National Water Quality Inventory                       functions of the Agency, including
                                              Reports (Renewal)’’ (EPA ICR No.                                                                               States, the District of Columbia, five
                                                                                                       whether the information will have                     Territories, and 3 River Basin
                                              1560.11, OMB Control No. 2040–0071)                      practical utility; (ii) evaluate the
                                              to the Office of Management and Budget                                                                         Commissions).
                                                                                                       accuracy of the Agency’s estimate of the                 Tribes are not required to submit
                                              (OMB) for review and approval in                         burden of the proposed collection of
                                              accordance with the Paperwork                                                                                  section 305(b) reports. However, to meet
                                                                                                       information, including the validity of                the needs of Tribes at all levels of
                                              Reduction Act (44 U.S.C. 3501 et seq.).                  the methodology and assumptions used;
                                              Before submitting the ICR to OMB, EPA                                                                          development, EPA has prepared
                                                                                                       (iii) enhance the quality, utility, and               guidance that presents the basic steps a
                                              is soliciting public comments on                         clarity of the information to be
                                              specific aspects of the proposed                                                                               Tribe should take to collect the water
                                                                                                       collected; and (iv) minimize the burden               quality information it needs to make
                                              information collection as described                      of the collection of information on those
                                              below. This is a request for renewal of                                                                        effective decisions about its program, its
                                                                                                       who are to respond, including through                 goals, and its future directions. Tribal
                                              an existing collection. An Agency may                    the use of appropriate automated
                                              not conduct or sponsor and a person is                                                                         water quality monitoring and reporting
                                                                                                       electronic, mechanical, or other                      activities are covered under the Section
                                              not required to respond to a collection                  technological collection techniques or
                                              of information unless it displays a                                                                            106 Tribal Grants Program and not
                                                                                                       other forms of information technology,                included in the burden estimates for
                                              currently valid OMB control number.                      e.g., permitting electronic submission of             this ICR.
                                              DATES: Comments must be submitted on                     responses. EPA will consider the                         During the period covered by this ICR
                                              or before September 8, 2015.                             comments received and amend the ICR                   renewal, respondents will: Complete
                                              ADDRESSES: Submit your comments,                         as appropriate. The final ICR package                 their 2016 section 305(b) reports and
                                              referencing Docket ID No. EPA–HQ–                        will then be submitted to OMB for                     2016 section 303(d) lists; complete their
                                              OW–2003–0026, online using                               review and approval. At that time, EPA                2018 section 305(b) reports and 2018
                                              www.regulations.gov (our preferred                       will issue another Federal Register                   section 303(d) lists; transmit annual
                                              method), by email to OW-Docket@                          notice to announce the submission of                  electronic updates of ambient
                                              epa.gov, or by mail to: EPA Docket                       the ICR to OMB and the opportunity to                 monitoring data via the Water Quality
                                              Center, Environmental Protection                         submit additional comments to OMB.                    Exchange; and continue to develop
                                              Agency, Mail Code 28221T, 1200                              Abstract: The Clean Water Act section              TMDLs according to their established
                                              Pennsylvania Ave. NW., Washington,                       305(b) reports contain information on                 schedules. EPA will prepare biennial
                                              DC 20460.                                                the water quality standards attainment                updates on assessed and impaired
                                                 EPA’s policy is that all comments                     status of assessed waters, and, when                  waters for Congress and the public for
                                              received will be included in the public                  waters are impaired, the pollutants and               the 2016 reporting cycle and for the
                                              docket without change including any                      potential sources affecting water quality.            2018 cycle, and EPA will review 303(d)
                                              personal information provided, unless                    This information helps track State                    list and TMDL submissions from
                                              the comment includes profanity, threats,                 progress in addressing water pollution.               respondents.
                                              information claimed to be Confidential                   Section 303(d) of the Clean Water Act                    The burdens of specific activities that
                                              Business Information (CBI) or other                      requires States to identify and rank                  States undertake as part of their section
                                              information whose disclosure is                          waters that cannot meet water quality                 305(b) and 303(d) programs are derived
tkelley on DSK3SPTVN1PROD with NOTICES




                                              restricted by statute.                                   standards (WQS) following the                         from a project among EPA, States and
                                              FOR FURTHER INFORMATION CONTACT:                         implementation of technology-based                    other interested stakeholders to develop
                                              Charles Kovatch, Assessment and                          controls. Under section 303(d), States                a tool for estimating the States’ resource
                                              Watershed Protection Division, Office of                 are also required to establish total                  needs for State water quality
                                              Water, Mail Code: 4503T,                                 maximum daily loads (TMDLs) for                       management programs. This project has
                                              Environmental Protection Agency, 1200                    listed waters not meeting standards as a              developed the State Water Quality
                                              Pennsylvania Ave. NW., Washington,                       result of pollutant discharges. In                    Management Workload Model


                                         VerDate Sep<11>2014   20:31 Jul 06, 2015   Jkt 235001   PO 00000   Frm 00024   Fmt 4703   Sfmt 4703   E:\FR\FM\07JYN1.SGM   07JYN1



Document Created: 2015-12-15 13:27:13
Document Modified: 2015-12-15 13:27:13
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation80 FR 38679 

2025 Federal Register | Disclaimer | Privacy Policy
USC | CFR | eCFR