80_FR_43213 80 FR 43074 - Natural Gas Pipeline Company of America, LLC; Notice of Intent To Prepare an Environmental Assessment for the Proposed Chicago Market Expansion Project, and Request for Comments on Environmental Issues

80 FR 43074 - Natural Gas Pipeline Company of America, LLC; Notice of Intent To Prepare an Environmental Assessment for the Proposed Chicago Market Expansion Project, and Request for Comments on Environmental Issues

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 80, Issue 139 (July 21, 2015)

Page Range43074-43076
FR Document2015-17806

Federal Register, Volume 80 Issue 139 (Tuesday, July 21, 2015)
[Federal Register Volume 80, Number 139 (Tuesday, July 21, 2015)]
[Notices]
[Pages 43074-43076]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2015-17806]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP15-505-000]


Natural Gas Pipeline Company of America, LLC; Notice of Intent To 
Prepare an Environmental Assessment for the Proposed Chicago Market 
Expansion Project, and Request for Comments on Environmental Issues

    The staff of the Federal Energy Regulatory Commission (FERC or 
Commission) will prepare an environmental assessment (EA) that will 
discuss the environmental impacts of the Chicago Market Expansion 
Project (Project) involving construction and operation of facilities by 
Natural Gas Pipeline Company of America, LLC (Natural) in Livingston 
County, Illinois. The Commission will use this EA in its decision-
making process to determine whether the project is in the public 
convenience and necessity.
    This notice announces the opening of the scoping process the 
Commission will use to gather input from the public and interested 
agencies on the Project. You can make a difference by providing us with 
your specific comments or concerns about the Project. Your comments 
should focus on the potential environmental effects, reasonable 
alternatives, and measures to avoid or lessen environmental impacts. 
Your input will help the Commission staff determine what issues they 
need to evaluate in the EA. To ensure that your comments are timely and 
properly recorded, please send your comments so that the Commission 
receives them in Washington, DC on or before August 9, 2015.
    If you sent comments on this Project to the Commission before the 
opening of this docket on June 1, 2015, you will need to file those 
comments in Docket No. CP15-505-000 to ensure they are considered as 
part of this proceeding.
    This notice is being sent to the Commission's current environmental 
mailing list for this Project. State and local government 
representatives should notify their constituents of this proposed 
Project and encourage them to comment on their areas of concern.
    If you are a landowner receiving this notice, a Natural 
representative may contact you about the acquisition of an easement to 
construct, operate, and maintain the proposed facilities. The company 
would seek to negotiate a mutually acceptable agreement. However, if 
the Commission approves the Project, that approval conveys with it the 
right of eminent domain. Therefore, if easement negotiations fail to 
produce an agreement, the pipeline company could initiate condemnation 
proceedings where compensation would be determined in accordance with 
state law.
    Natural provided landowners with a fact sheet prepared by the FERC 
entitled ``An Interstate Natural Gas Facility On My Land? What Do I 
Need To Know?'' This fact sheet addresses a number of typically asked 
questions, including the use of eminent domain and how to participate 
in the Commission's proceedings. It is also available for viewing on 
the FERC Web site (www.ferc.gov).

Public Participation

    For your convenience, there are three methods you can use to submit 
your comments to the Commission. The Commission encourages electronic 
filing of comments and has expert staff available to assist you at 
(202) 502-8258 or efiling@ferc.gov. Please carefully follow these 
instructions so that your comments are properly recorded.
    (1) You can file your comments electronically using the eComment 
feature on the Commission's Web site (www.ferc.gov) under the link to 
Documents and Filings. This is an easy method for submitting brief, 
text-only comments on a project;
    (2) You can file your comments electronically by using the eFiling 
feature on the Commission's Web site (www.ferc.gov) under the link to 
Documents and Filings. With eFiling, you can provide comments in a 
variety of formats by attaching them as a file with your submission. 
New eFiling users must first create an account by clicking on 
``eRegister.'' If you are filing a comment on a particular project, 
please select ``Comment on a Filing'' as the filing type; or
    (3) You can file a paper copy of your comments by mailing them to 
the

[[Page 43075]]

following address. Be sure to reference the Project docket number 
(CP15-505-000) with your submission:
    Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 
888 First Street NE., Room 1A, Washington, DC 20426.

Summary of the Proposed Project

    Natural proposes to construct and operate a new compressor station 
and associated facilities in Livingston County, Illinois. Specifically, 
Natural proposes to construct and operate one new 30,000 horsepower 
compressor station with suction and discharge station interconnect 
piping; and ancillary facilities. The Project would provide about 
238,000 dekatherms of incremental northbound firm transportation 
capacity to the city of Chicago, Illinois and neighboring areas.
    The general location of the project facilities is shown in appendix 
1.\1\
---------------------------------------------------------------------------

    \1\ The appendices referenced in this notice will not appear in 
the Federal Register. Copies of appendices were sent to all those 
receiving this notice in the mail and are available at www.ferc.gov 
using the link called ``eLibrary'' or from the Commission's Public 
Reference Room, 888 First Street NE., Washington, DC 20426, or call 
(202) 502-8371. For instructions on connecting to eLibrary, refer to 
the last page of this notice.
---------------------------------------------------------------------------

Land Requirements for Construction

    Construction of the proposed facilities would disturb about 21 
acres of land of which 19.2 acres would remain as the permanent 
facility following construction. The remaining 1.8 acres consists of 
temporary workspace necessary to accommodate construction of the 
Project. The temporary workspace would be restored to its previous land 
use and maintained in its pre-construction condition.

The EA Process

    The National Environmental Policy Act (NEPA) requires the 
Commission to take into account the environmental impacts that could 
result from an action whenever it considers the issuance of a 
Certificate of Public Convenience and Necessity. The NEPA also requires 
us \2\ to discover and address concerns the public may have about 
proposals. This process is referred to as ``scoping.'' The main goal of 
the scoping process is to focus the analysis in the EA on the important 
environmental issues. By this notice, the Commission requests public 
comments on the scope of the issues to address in the EA. We will 
consider all filed comments during the preparation of the EA.
---------------------------------------------------------------------------

    \2\ ``We,'' ``us,'' and ``our'' refer to the environmental staff 
of the Commission's Office of Energy Projects.
---------------------------------------------------------------------------

    In the EA we will discuss impacts that could occur as a result of 
the construction and operation of the proposed Project under these 
general headings:
 Geology and soils;
 land use;
 water resources, fisheries, and wetlands;
 cultural resources;
 vegetation and wildlife;
 air quality and noise;
 endangered and threatened species;
 public safety; and
 cumulative impacts.
    We will also evaluate reasonable alternatives to the proposed 
Project or portions of the Project, and make recommendations on how to 
lessen or avoid impacts on the various resource areas.
    The EA will present our independent analysis of the issues. The EA 
will be available in the public record through eLibrary (for directions 
on the use of eLibrary, please see the additional Information Section 
on page 6). Depending on the comments received during the scoping 
process, we may also publish and distribute the EA to the public for an 
allotted comment period. We will consider all comments on the EA before 
making our recommendations to the Commission. To ensure we have the 
opportunity to consider and address your comments, please carefully 
follow the instructions in the Public Participation section, beginning 
on page 2.
    With this notice, we are asking agencies with jurisdiction by law 
and/or special expertise with respect to the environmental issues of 
this Project to formally cooperate with us in the preparation of the 
EA.\3\ Agencies that would like to request cooperating agency status 
should follow the instructions for filing comments provided under the 
Public Participation section of this notice.
---------------------------------------------------------------------------

    \3\ The Council on Environmental Quality regulations addressing 
cooperating agency responsibilities are at Title 40, Code of Federal 
Regulations, part 1501.6.
---------------------------------------------------------------------------

Consultations Under Section 106 of the National Historic Preservation 
Act

    In accordance with the Advisory Council on Historic Preservation's 
implementing regulations for section 106 of the National Historic 
Preservation Act, we are using this notice to initiate consultations 
with the Illinois State Historic Preservation Office (SHPO), and to 
solicit its views and those of other government agencies, interested 
Indian tribes, and the public on the Project's potential effects on 
historic properties.\4\ We will define the Project-specific Area of 
Potential Effects (APE) in consultation with the SHPO as the Project 
develops. On natural gas facility projects, the APE at a minimum 
encompasses all areas subject to ground disturbance (examples include 
construction right-of-way, contractor/pipe storage yards, compressor 
stations, and access roads). Our EA for this Project will document our 
findings on the impacts on historic properties and summarize the status 
of consultations under section 106.
---------------------------------------------------------------------------

    \4\ The Advisory Council on Historic Preservation's regulations 
are at Title 36, Code of Federal Regulations, part 800. Those 
regulations define historic properties as any prehistoric or 
historic district, site, building, structure, or object included in 
or eligible for inclusion in the National Register of Historic 
Places.
---------------------------------------------------------------------------

Environmental Mailing List

    The environmental mailing list includes federal, state, and local 
government representatives and agencies; elected officials; 
environmental and public interest groups; Indian tribes; other 
interested parties; and local libraries and newspapers. This list also 
includes all affected landowners (as defined in the Commission's 
regulations) who are potential right-of-way grantors, whose property 
may be used temporarily for Project purposes, or who own homes within 
certain distances of aboveground facilities, and anyone who submits 
comments on the project. We will update the environmental mailing list 
as the analysis proceeds to ensure that we send the information related 
to this environmental review to all individuals, organizations, and 
government entities interested in and/or potentially affected by the 
proposed Project.
    Copies of the EA will be sent to the environmental mailing list for 
public review and comment. If you would prefer to receive a paper copy 
of the document instead of the CD version or would like to remove your 
name from the mailing list, please return the attached Information 
Request (appendix 2).

Becoming an Intervenor

    In addition to involvement in the EA scoping process, you may want 
to become an ``intervenor'' which is an official party to the 
Commission's proceeding. Intervenors play a more formal role in the 
process and are able to file briefs, appear at hearings, and be heard 
by the courts if they choose to appeal the Commission's final ruling. 
An intervenor formally participates in the proceeding by filing a 
request to intervene. Instructions for becoming an

[[Page 43076]]

intervenor are in the User's Guide under the ``e-filing'' link on the 
Commission's Web site.

Additional Information

    Additional information about the project is available from the 
Commission's Office of External Affairs, at (866) 208-FERC, or on the 
FERC Web site at www.ferc.gov using the ``Document's & Filings'' link. 
Click on the eLibrary link, click on General Search and enter the 
docket number, excluding the last three digits in the Docket Number 
field (i.e., CP15-505). Be sure you have selected an appropriate date 
range. For assistance, please contact FERC Online Support at 
FercOnlineSupport@ferc.gov or toll free at (866) 208-3676, or for TTY, 
contact (202) 502-8659. The eLibrary link also provides access to the 
texts of formal documents issued by the Commission, such as orders, 
notices, and rulemakings.
    In addition, the Commission offers a free service called 
eSubscription which allows you to keep track of all formal issuances 
and submittals in specific dockets. This can reduce the amount of time 
you spend researching proceedings by automatically providing you with 
notification of these filings, document summaries, and direct links to 
the documents. Go to www.ferc.gov/docs-filing/esubscription.asp.
    Finally, public meetings or site visits will be posted on the 
Commission's calendar located at www.ferc.gov/EventCalendar/EventsList.aspx along with other related information.

    Dated: July 9, 2015.
Kimberly D. Bose,
Secretary.
[FR Doc. 2015-17806 Filed 7-20-15; 8:45 am]
 BILLING CODE 6717-01-P



                                                    43074                           Federal Register / Vol. 80, No. 139 / Tuesday, July 21, 2015 / Notices

                                                    near the City of Easton, Northampton                     The first page of any filing should                   No. CP15–505–000 to ensure they are
                                                    County, Pennsylvania. The sole purpose                   include docket number P–14675–000.                    considered as part of this proceeding.
                                                    of a preliminary permit, if issued, is to                   More information about this project,                  This notice is being sent to the
                                                    grant the permit holder priority to file                 including a copy of the application, can              Commission’s current environmental
                                                    a license application during the permit                  be viewed or printed on the ‘‘eLibrary’’              mailing list for this Project. State and
                                                    term. A preliminary permit does not                      link of the Commission’s Web site at                  local government representatives should
                                                    authorize the permit holder to perform                   http://www.ferc.gov/docs-filing/                      notify their constituents of this
                                                    any land-disturbing activities or                        elibrary.asp. Enter the docket number                 proposed Project and encourage them to
                                                    otherwise enter upon lands or waters                     (P–14675) in the docket number field to               comment on their areas of concern.
                                                    owned by others without the owners’                      access the document. For assistance,                     If you are a landowner receiving this
                                                    express permission.                                      contact FERC Online Support.                          notice, a Natural representative may
                                                       The proposed Chain Dam                                                                                      contact you about the acquisition of an
                                                                                                               Dated: July 14, 2015.
                                                    Hydroelectric Project would consist of                                                                         easement to construct, operate, and
                                                    the following: (1) An existing 20-foot-                  Kimberly D. Bose,                                     maintain the proposed facilities. The
                                                    high concrete gravity dam with a 690-                    Secretary.                                            company would seek to negotiate a
                                                    foot-long spillway; (2) an existing                      [FR Doc. 2015–17790 Filed 7–20–15; 8:45 am]           mutually acceptable agreement.
                                                    impoundment having a surface area of                     BILLING CODE 6717–01–P                                However, if the Commission approves
                                                    approximately 300 acres and a storage                                                                          the Project, that approval conveys with
                                                    capacity of 1,200 acre-feet at an                                                                              it the right of eminent domain.
                                                    elevation of 190 feet mean sea level                     DEPARTMENT OF ENERGY                                  Therefore, if easement negotiations fail
                                                    (msl); (2) three channels, each with a                                                                         to produce an agreement, the pipeline
                                                    very low head (VLH) 500-kilowatt (kW)                    Federal Energy Regulatory                             company could initiate condemnation
                                                    turbine-generator unit, with a maximum                   Commission                                            proceedings where compensation would
                                                    generating capacity of 1,500 kW, with a                  [Docket No. CP15–505–000]                             be determined in accordance with state
                                                    maximum hydraulic capacity of 2,300                                                                            law.
                                                    cubic feet per second under a net head                   Natural Gas Pipeline Company of                          Natural provided landowners with a
                                                    of 13.5 feet, (3) three new, heavy flotsam               America, LLC; Notice of Intent To                     fact sheet prepared by the FERC entitled
                                                    racks; (4) a crest-mounted walkway                       Prepare an Environmental Assessment                   ‘‘An Interstate Natural Gas Facility On
                                                    carrying hydraulic and electrical                        for the Proposed Chicago Market                       My Land? What Do I Need To Know?’’
                                                    conduits from the VLH turbines to a                      Expansion Project, and Request for                    This fact sheet addresses a number of
                                                    new powerhouse; and (5) a 280-foot-                      Comments on Environmental Issues                      typically asked questions, including the
                                                    long 12.42/7.2 kilovolt primary                                                                                use of eminent domain and how to
                                                    transmission line. The estimated annual                     The staff of the Federal Energy                    participate in the Commission’s
                                                    generation of the proposed project                       Regulatory Commission (FERC or                        proceedings. It is also available for
                                                    would be 7,880,000 kilowatt-hours.                       Commission) will prepare an                           viewing on the FERC Web site
                                                       Applicant Contact: Mr. Ralph J. Jones,                environmental assessment (EA) that will               (www.ferc.gov).
                                                    Siting Renewables, LLC, 1800 Rt. 34,                     discuss the environmental impacts of
                                                    Suite 101, Wall, NJ 07719; phone: (855)                  the Chicago Market Expansion Project                  Public Participation
                                                    946–7652.                                                (Project) involving construction and                    For your convenience, there are three
                                                       FERC Contact: Monir Chowdhury;                        operation of facilities by Natural Gas                methods you can use to submit your
                                                    phone: (202) 502–6736.                                   Pipeline Company of America, LLC                      comments to the Commission. The
                                                       Deadline for filing comments, motions                 (Natural) in Livingston County, Illinois.             Commission encourages electronic filing
                                                    to intervene, competing applications                     The Commission will use this EA in its                of comments and has expert staff
                                                    (without notices of intent), or notices of               decision-making process to determine                  available to assist you at (202) 502–8258
                                                    intent to file competing applications: 60                whether the project is in the public                  or efiling@ferc.gov. Please carefully
                                                    days from the issuance of this notice.                   convenience and necessity.                            follow these instructions so that your
                                                    Competing applications and notices of                       This notice announces the opening of               comments are properly recorded.
                                                    intent must meet the requirements of 18                  the scoping process the Commission                       (1) You can file your comments
                                                    CFR 4.36.                                                will use to gather input from the public              electronically using the eComment
                                                       The Commission strongly encourages                    and interested agencies on the Project.               feature on the Commission’s Web site
                                                    electronic filing. Please file comments,                 You can make a difference by providing                (www.ferc.gov) under the link to
                                                    motions to intervene, notices of intent,                 us with your specific comments or                     Documents and Filings. This is an easy
                                                    and competing applications using the                     concerns about the Project. Your                      method for submitting brief, text-only
                                                    Commission’s eFiling system at http://                   comments should focus on the potential                comments on a project;
                                                    www.ferc.gov/docs-filing/efiling.asp.                    environmental effects, reasonable                        (2) You can file your comments
                                                    Commenters can submit brief comments                     alternatives, and measures to avoid or                electronically by using the eFiling
                                                    up to 6,000 characters, without prior                    lessen environmental impacts. Your                    feature on the Commission’s Web site
                                                    registration, using the eComment system                  input will help the Commission staff                  (www.ferc.gov) under the link to
                                                    at http://www.ferc.gov/docs-filing/                      determine what issues they need to                    Documents and Filings. With eFiling,
                                                    ecomment.asp. You must include your                      evaluate in the EA. To ensure that your               you can provide comments in a variety
                                                    name and contact information at the end                  comments are timely and properly                      of formats by attaching them as a file
asabaliauskas on DSK5VPTVN1PROD with NOTICES




                                                    of your comments. For assistance,                        recorded, please send your comments so                with your submission. New eFiling
                                                    please contact FERC Online Support at                    that the Commission receives them in                  users must first create an account by
                                                    FERCOnlineSupport@ferc.gov, (866)                        Washington, DC on or before August 9,                 clicking on ‘‘eRegister.’’ If you are filing
                                                    208–3676 (toll free), or (202) 502–8659                  2015.                                                 a comment on a particular project,
                                                    (TTY). In lieu of electronic filing, please                 If you sent comments on this Project               please select ‘‘Comment on a Filing’’ as
                                                    send a paper copy to: Secretary, Federal                 to the Commission before the opening of               the filing type; or
                                                    Energy Regulatory Commission, 888                        this docket on June 1, 2015, you will                    (3) You can file a paper copy of your
                                                    First Street NE., Washington, DC 20426.                  need to file those comments in Docket                 comments by mailing them to the


                                               VerDate Sep<11>2014   17:58 Jul 20, 2015   Jkt 235001   PO 00000   Frm 00024   Fmt 4703   Sfmt 4703   E:\FR\FM\21JYN1.SGM   21JYN1


                                                                                    Federal Register / Vol. 80, No. 139 / Tuesday, July 21, 2015 / Notices                                                      43075

                                                    following address. Be sure to reference                     In the EA we will discuss impacts that             historic properties.4 We will define the
                                                    the Project docket number (CP15–505–                     could occur as a result of the                        Project-specific Area of Potential Effects
                                                    000) with your submission:                               construction and operation of the                     (APE) in consultation with the SHPO as
                                                      Kimberly D. Bose, Secretary, Federal                   proposed Project under these general                  the Project develops. On natural gas
                                                    Energy Regulatory Commission, 888                        headings:                                             facility projects, the APE at a minimum
                                                    First Street NE., Room 1A, Washington,                   • Geology and soils;                                  encompasses all areas subject to ground
                                                    DC 20426.                                                • land use;                                           disturbance (examples include
                                                                                                             • water resources, fisheries, and                     construction right-of-way, contractor/
                                                    Summary of the Proposed Project                               wetlands;                                        pipe storage yards, compressor stations,
                                                       Natural proposes to construct and                     • cultural resources;                                 and access roads). Our EA for this
                                                    operate a new compressor station and                     • vegetation and wildlife;                            Project will document our findings on
                                                    associated facilities in Livingston                      • air quality and noise;                              the impacts on historic properties and
                                                    County, Illinois. Specifically, Natural                  • endangered and threatened species;                  summarize the status of consultations
                                                    proposes to construct and operate one                    • public safety; and                                  under section 106.
                                                    new 30,000 horsepower compressor                         • cumulative impacts.                                 Environmental Mailing List
                                                    station with suction and discharge                          We will also evaluate reasonable
                                                    station interconnect piping; and                         alternatives to the proposed Project or                  The environmental mailing list
                                                    ancillary facilities. The Project would                  portions of the Project, and make                     includes federal, state, and local
                                                    provide about 238,000 dekatherms of                      recommendations on how to lessen or                   government representatives and
                                                    incremental northbound firm                              avoid impacts on the various resource                 agencies; elected officials;
                                                    transportation capacity to the city of                   areas.                                                environmental and public interest
                                                    Chicago, Illinois and neighboring areas.                    The EA will present our independent                groups; Indian tribes; other interested
                                                                                                             analysis of the issues. The EA will be                parties; and local libraries and
                                                       The general location of the project
                                                                                                             available in the public record through                newspapers. This list also includes all
                                                    facilities is shown in appendix 1.1
                                                                                                             eLibrary (for directions on the use of                affected landowners (as defined in the
                                                    Land Requirements for Construction                       eLibrary, please see the additional                   Commission’s regulations) who are
                                                                                                             Information Section on page 6).                       potential right-of-way grantors, whose
                                                      Construction of the proposed facilities
                                                                                                             Depending on the comments received                    property may be used temporarily for
                                                    would disturb about 21 acres of land of
                                                                                                             during the scoping process, we may also               Project purposes, or who own homes
                                                    which 19.2 acres would remain as the
                                                                                                             publish and distribute the EA to the                  within certain distances of aboveground
                                                    permanent facility following
                                                                                                             public for an allotted comment period.                facilities, and anyone who submits
                                                    construction. The remaining 1.8 acres
                                                                                                             We will consider all comments on the                  comments on the project. We will
                                                    consists of temporary workspace
                                                                                                             EA before making our recommendations                  update the environmental mailing list as
                                                    necessary to accommodate construction
                                                                                                             to the Commission. To ensure we have                  the analysis proceeds to ensure that we
                                                    of the Project. The temporary workspace
                                                                                                             the opportunity to consider and address               send the information related to this
                                                    would be restored to its previous land
                                                                                                             your comments, please carefully follow                environmental review to all individuals,
                                                    use and maintained in its pre-
                                                                                                             the instructions in the Public                        organizations, and government entities
                                                    construction condition.
                                                                                                             Participation section, beginning on page              interested in and/or potentially affected
                                                    The EA Process                                           2.                                                    by the proposed Project.
                                                                                                                With this notice, we are asking                       Copies of the EA will be sent to the
                                                       The National Environmental Policy                                                                           environmental mailing list for public
                                                    Act (NEPA) requires the Commission to                    agencies with jurisdiction by law and/
                                                                                                             or special expertise with respect to the              review and comment. If you would
                                                    take into account the environmental                                                                            prefer to receive a paper copy of the
                                                    impacts that could result from an action                 environmental issues of this Project to
                                                                                                             formally cooperate with us in the                     document instead of the CD version or
                                                    whenever it considers the issuance of a                                                                        would like to remove your name from
                                                    Certificate of Public Convenience and                    preparation of the EA.3 Agencies that
                                                                                                             would like to request cooperating                     the mailing list, please return the
                                                    Necessity. The NEPA also requires us 2                                                                         attached Information Request (appendix
                                                    to discover and address concerns the                     agency status should follow the
                                                                                                             instructions for filing comments                      2).
                                                    public may have about proposals. This
                                                    process is referred to as ‘‘scoping.’’ The               provided under the Public Participation               Becoming an Intervenor
                                                    main goal of the scoping process is to                   section of this notice.                                 In addition to involvement in the EA
                                                    focus the analysis in the EA on the                      Consultations Under Section 106 of the                scoping process, you may want to
                                                    important environmental issues. By this                  National Historic Preservation Act                    become an ‘‘intervenor’’ which is an
                                                    notice, the Commission requests public                                                                         official party to the Commission’s
                                                    comments on the scope of the issues to                      In accordance with the Advisory
                                                                                                                                                                   proceeding. Intervenors play a more
                                                    address in the EA. We will consider all                  Council on Historic Preservation’s
                                                                                                                                                                   formal role in the process and are able
                                                    filed comments during the preparation                    implementing regulations for section
                                                                                                                                                                   to file briefs, appear at hearings, and be
                                                    of the EA.                                               106 of the National Historic
                                                                                                                                                                   heard by the courts if they choose to
                                                                                                             Preservation Act, we are using this
                                                                                                                                                                   appeal the Commission’s final ruling.
                                                      1 The appendices referenced in this notice will        notice to initiate consultations with the
                                                                                                                                                                   An intervenor formally participates in
                                                    not appear in the Federal Register. Copies of            Illinois State Historic Preservation
asabaliauskas on DSK5VPTVN1PROD with NOTICES




                                                                                                                                                                   the proceeding by filing a request to
                                                    appendices were sent to all those receiving this         Office (SHPO), and to solicit its views
                                                    notice in the mail and are available at www.ferc.gov                                                           intervene. Instructions for becoming an
                                                                                                             and those of other government agencies,
                                                    using the link called ‘‘eLibrary’’ or from the
                                                    Commission’s Public Reference Room, 888 First
                                                                                                             interested Indian tribes, and the public                4 The Advisory Council on Historic Preservation’s
                                                    Street NE., Washington, DC 20426, or call (202)          on the Project’s potential effects on                 regulations are at Title 36, Code of Federal
                                                    502–8371. For instructions on connecting to                                                                    Regulations, part 800. Those regulations define
                                                    eLibrary, refer to the last page of this notice.           3 The Council on Environmental Quality              historic properties as any prehistoric or historic
                                                      2 ‘‘We,’’ ‘‘us,’’ and ‘‘our’’ refer to the             regulations addressing cooperating agency             district, site, building, structure, or object included
                                                    environmental staff of the Commission’s Office of        responsibilities are at Title 40, Code of Federal     in or eligible for inclusion in the National Register
                                                    Energy Projects.                                         Regulations, part 1501.6.                             of Historic Places.



                                               VerDate Sep<11>2014   17:58 Jul 20, 2015   Jkt 235001   PO 00000   Frm 00025   Fmt 4703   Sfmt 4703   E:\FR\FM\21JYN1.SGM   21JYN1


                                                    43076                           Federal Register / Vol. 80, No. 139 / Tuesday, July 21, 2015 / Notices

                                                    intervenor are in the User’s Guide under                 Comments on Environmental Issues                      approves the Project, that approval
                                                    the ‘‘e-filing’’ link on the Commission’s                (NOI). Since its application in the                   conveys with it the right of eminent
                                                    Web site.                                                above-referenced docket, FERC staff has               domain. Therefore, if the easement
                                                                                                             requested information regarding the                   negotiations fail to produce an
                                                    Additional Information
                                                                                                             proposed facilities, as well as alternative           agreement, the pipeline company could
                                                       Additional information about the                      routes to the proposed Kemblesville                   initiate condemnation proceedings
                                                    project is available from the                            Loop 1 in Chester County, Pennsylvania.               where compensation would be
                                                    Commission’s Office of External Affairs,                 On June 2, 2015, FERC staff also                      determined in accordance with state
                                                    at (866) 208–FERC, or on the FERC Web                    conducted an onsite environmental                     law.
                                                    site at www.ferc.gov using the                           review of the proposed pipeline and                     A fact sheet prepared by the FERC
                                                    ‘‘Document’s & Filings’’ link. Click on                  several alternative routes. In response to            entitled ‘‘An Interstate Natural Gas
                                                    the eLibrary link, click on General                      data requested by FERC staff, Eastern                 Facility on My Land? What Do I Need
                                                    Search and enter the docket number,                      Shore Natural Gas Company (Eastern                    To Know?’’ is available for viewing on
                                                    excluding the last three digits in the                   Shore) provided information on four                   the FERC Web site (www.ferc.gov). This
                                                    Docket Number field (i.e., CP15–505).                    alternative pipeline routes. FERC staff is            fact sheet addresses a number of
                                                    Be sure you have selected an                             further evaluating Alternative Route 2 as             typically asked questions, including the
                                                    appropriate date range. For assistance,                  described in Eastern Shore’s April 21,                use of eminent domain and how to
                                                    please contact FERC Online Support at                    2015 response. This Supplemental                      participate in the Commission’s
                                                    FercOnlineSupport@ferc.gov or toll free                  Notice is being issued to seek comments               proceedings.
                                                    at (866) 208–3676, or for TTY, contact                   on Alternative Route 2 and opens a new                Public Participation
                                                    (202) 502–8659. The eLibrary link also                   scoping period for interested parties to
                                                    provides access to the texts of formal                   file comments on environmental issues                    For your convenience, there are three
                                                    documents issued by the Commission,                      specific to this alternative route.                   methods you can use to submit your
                                                    such as orders, notices, and                                The January 22, 2015 NOI announced                 comments to the Commission. The
                                                    rulemakings.                                             that the FERC staff will prepare an                   Commission will provide equal
                                                       In addition, the Commission offers a                  environmental assessment (EA) to                      consideration to all comments received,
                                                    free service called eSubscription which                  address the environmental impacts of                  whether filed in written form or
                                                    allows you to keep track of all formal                   the White Oak Mainline Expansion                      provided verbally. The Commission
                                                    issuances and submittals in specific                     Project (Project). Please refer to the NOI            encourages electronic filing of
                                                    dockets. This can reduce the amount of                   for more information about the overall                comments and has expert staff available
                                                    time you spend researching proceedings                   facilities proposed by Eastern Shore in               to assist you at (202) 502–8258 or
                                                    by automatically providing you with                      Pennsylvania and Delaware, and FERC                   efiling@ferc.gov. Please carefully follow
                                                    notification of these filings, document                  staff’s EA process. The Commission will               these instructions so that your
                                                    summaries, and direct links to the                       use the EA in its decision-making                     comments are properly recorded.
                                                    documents. Go to www.ferc.gov/docs-                      process to determine whether the                         (1) You can file your comments
                                                    filing/esubscription.asp.                                Project is in the public convenience and              electronically using the eComment
                                                       Finally, public meetings or site visits               necessity.                                            feature located on the Commission’s
                                                    will be posted on the Commission’s                          The Commission previously solicited                Web site (www.ferc.gov) under the link
                                                    calendar located at www.ferc.gov/                        public input on the Project in the                    to Documents and Filings. This is an
                                                    EventCalendar/EventsList.aspx along                      beginning of 2015. We 2 are now                       easy method for interested persons to
                                                    with other related information.                          specifically seeking comments on the                  submit brief, text-only comments on a
                                                                                                             Kemblesville Loop Alternative Route 2                 project;
                                                      Dated: July 9, 2015.                                                                                            (2) You can file your comments
                                                    Kimberly D. Bose,                                        to help the Commission staff evaluate
                                                                                                                                                                   electronically using the eFiling feature
                                                    Secretary.
                                                                                                             the environmental impact associated
                                                                                                                                                                   located on the Commission’s Web site
                                                                                                             with the alternative and how that
                                                    [FR Doc. 2015–17806 Filed 7–20–15; 8:45 am]                                                                    (www.ferc.gov) under the link to
                                                                                                             compares to the currently proposed
                                                    BILLING CODE 6717–01–P                                                                                         Documents and Filings. With eFiling,
                                                                                                             route. Please note that this special
                                                                                                                                                                   you can provide comments in a variety
                                                                                                             scoping period will close on August 8,
                                                                                                                                                                   of formats by attaching them as a file
                                                    DEPARTMENT OF ENERGY                                     2015.
                                                                                                                                                                   with your submission. New eFiling
                                                                                                                This Supplemental Notice is being
                                                                                                                                                                   users must first create an account by
                                                    Federal Energy Regulatory                                sent to the Commission’s current
                                                                                                                                                                   clicking on ‘‘eRegister.’’ You must select
                                                    Commission                                               environmental mailing list for this
                                                                                                                                                                   the type of filing you are making. If you
                                                                                                             Project, including new landowners that
                                                    [Docket No. CP15–18–000]                                                                                       are filing a comment on a particular
                                                                                                             would be affected by the alternative
                                                                                                                                                                   project, please select ‘‘Comment on a
                                                                                                             pipeline route.
                                                    Eastern Shore Natural Gas Company;                                                                             Filing;’’ or
                                                                                                                If you are a landowner receiving this                 (3) You can file a paper copy of your
                                                    Supplemental Notice of Intent To                         notice, a pipeline company
                                                    Prepare an Environmental Assessment                                                                            comments by mailing them to the
                                                                                                             representative may contact you about                  following address: Kimberly D. Bose,
                                                    for the Proposed White Oak Mainline                      the acquisition of an easement to
                                                    Expansion Project and Request for                                                                              Secretary, Federal Energy Regulatory
                                                                                                             construct, operate, and maintain the
asabaliauskas on DSK5VPTVN1PROD with NOTICES




                                                    Comments on Environmental Issues                                                                               Commission, 888 First Street NE., Room
                                                                                                             proposed facilities. The company would                1A, Washington, DC 20426.
                                                      On January 22, 2015, the Federal                       seek to negotiate a mutually acceptable
                                                    Energy Regulatory Commission (FERC                       agreement. However, if the Commission                 Summary of Kemblesville Loop
                                                    or Commission) issued in Docket No.                                                                            Alternative Route 2
                                                                                                               1 A pipeline loop is constructed parallel to an
                                                    CP15–18–000 a Notice of Intent to                                                                                The Kemblesville Loop Alternative
                                                                                                             existing pipeline to increase capacity.
                                                    Prepare an Environmental Assessment                        2 ‘‘We,’’ ‘‘us,’’ and ‘‘our’’ refer to the          Route 2 would be collocated entirely
                                                    for the Proposed White Oak Mainline                      environmental staff of the Commission’s Office of     with the existing right-of-way for
                                                    Expansion Project and Request for                        Energy Projects.                                      Eastern Shore’s White Oak mainline


                                               VerDate Sep<11>2014   17:58 Jul 20, 2015   Jkt 235001   PO 00000   Frm 00026   Fmt 4703   Sfmt 4703   E:\FR\FM\21JYN1.SGM   21JYN1



Document Created: 2018-02-23 09:23:10
Document Modified: 2018-02-23 09:23:10
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation80 FR 43074 

2024 Federal Register | Disclaimer | Privacy Policy