80_FR_50783 80 FR 50622 - Notice of Availability of the Final Environmental Impact Statement for the Proposed Lake Charles Liquefaction Project

80 FR 50622 - Notice of Availability of the Final Environmental Impact Statement for the Proposed Lake Charles Liquefaction Project

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 80, Issue 161 (August 20, 2015)

Page Range50622-50623
FR Document2015-20574

Federal Register, Volume 80 Issue 161 (Thursday, August 20, 2015)
[Federal Register Volume 80, Number 161 (Thursday, August 20, 2015)]
[Notices]
[Pages 50622-50623]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2015-20574]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission


Notice of Availability of the Final Environmental Impact 
Statement for the Proposed Lake Charles Liquefaction Project

------------------------------------------------------------------------
                                                     Docket No.
------------------------------------------------------------------------
Trunkline Gas Company, LLC................  CP14-119-000
Lake Charles LNG Company, LLC.............  CP14-120-000
 Lake Charles LNG Export Company, LLC.....  CP14-122-000
------------------------------------------------------------------------
 

    The staff of the Federal Energy Regulatory Commission (FERC or 
Commission) has prepared a final environmental impact statement (EIS) 
for the Lake Charles Liquefaction Project, proposed by Trunkline Gas 
Company, LLC (Trunkline), Lake Charles LNG Company, LLC, and Lake 
Charles LNG Export Company, LLC in the above-referenced dockets. 
Trunkline requests authorization to construct, install, and operate new 
natural gas pipeline facilities; modify certain existing pipeline 
facilities; and abandon one compressor unit in the states of Arkansas, 
Mississippi, and Louisiana (collectively referred to as the Non-
Liquefaction Facilities). Lake Charles LNG Company, LLC and Lake 
Charles LNG Export Company, LLC (collectively referred to as Lake 
Charles LNG) request authorization to site, construct, and operate new 
liquefaction facilities adjacent to an existing liquefied natural gas 
(LNG) terminal located in Calcasieu Parish, Louisiana, and to construct 
and operate certain facility modifications at the existing LNG 
terminal. The new liquefaction facilities would have a design 
production capacity of 16.45 million metric tons of LNG per annum, 
which would provide an LNG export capacity equivalent to about 2 
billion cubic feet per day of natural gas.
    Lake Charles LNG also requests authorization to abandon certain 
terminal facilities previously certificated under the Natural Gas Act 
(NGA) section 7; and convert such certificated facilities so that the 
entirety of the company's facilities and operations are authorized 
solely under NGA section 3.
    The final EIS assesses the potential environmental effects of 
construction and operation of the Lake Charles Liquefaction Project in 
accordance with the requirements of the National Environmental Policy 
Act. The FERC staff concludes that approval of the

[[Page 50623]]

proposed project would have some adverse environmental impacts; 
however, most of these impacts would be reduced to less-than-
significant levels with the implementation of Lake Charles LNG's and 
Trunkline's proposed mitigation and the additional measures recommended 
in the final EIS.
    The U.S. Army Corps of Engineers, U.S. Coast Guard, U.S. Department 
of Energy, U.S. Fish and Wildlife Service, and U.S. Department of 
Transportation participated as cooperating agencies in the preparation 
of the final EIS. Cooperating agencies have jurisdiction by law or 
special expertise with respect to resources potentially affected by a 
proposal and participate in the National Environmental Policy Act 
analysis. Although the cooperating agencies provided input on the 
conclusions and recommendations presented in the final EIS, the 
agencies will present their own conclusions and recommendations in 
their respective records of decision or determinations for the project.
    The Lake Charles Liquefaction Project includes:
     Three liquefaction trains, each with a production capacity 
sufficient to produce 5.48 million metric tons per annum of LNG for 
export (each train would contain metering and gas treatment facilities, 
liquefaction and refrigerant units, safety and control systems, and 
associated infrastructure);
     modifications and upgrades at the existing Trunkline LNG 
terminal;
     about 0.5 mile of 48-inch-diameter feed gas line to supply 
natural gas to the liquefaction facility from existing gas transmission 
pipelines;
     approximately 17.9 miles of 24- and 42-inch-diameter 
natural gas pipeline;
     a new compressor station with a manufacturer's rating of 
103,175 horsepower (hp), which equates to a site-specific rating of 
98,685 hp (based on relative humidity and elevation);
     abandonment of a 3,000-hp compressor unit, installation of 
a unit with a manufacturer's rating of 15,900 hp and site-specific 
rating of 15,002-hp unit, and piping modifications at one existing 
compressor station;
     modification of station piping at three other existing 
compressor stations;
     five new meter stations and modifications and upgrades of 
five existing meter stations;
     modification of certain existing pipeline facilities; and
     construction of miscellaneous auxiliary and appurtenant 
facilities.
    The FERC staff mailed copies of the final EIS to federal, state, 
and local government representatives and agencies; elected officials; 
environmental and public interest groups; Native American tribes; 
potentially affected landowners; other interested individuals and non-
governmental organizations; newspapers and libraries in the project 
area; and parties to this proceeding. Paper copy versions of this EIS 
were mailed to those specifically requesting them; all others received 
a compact disk version. In addition, the final EIS is available for 
public viewing on the FERC's Web site (www.ferc.gov) using the eLibrary 
link. A limited number of hardcopies are available for distribution and 
public inspection at: Federal Energy Regulatory Commission, Public 
Reference Room, 888 First Street NE., Room 2A, Washington, DC 20426, 
(202) 502-8371.
    Additional information about the project is available from the 
Commission's Office of External Affairs, at (866) 208-FERC, or on the 
FERC Web site (www.ferc.gov) using the eLibrary link. Click on the 
eLibrary link, click on ``General Search,'' and enter the docket 
number(s) excluding the last three digits in the Docket Number field 
(i.e., CP14-119, CP14-120, and CP14-122). Be sure you have selected an 
appropriate date range. For assistance, please contact FERC Online 
Support at [email protected] or toll free at (866) 208-3676; 
for TTY, contact (202) 502-8659. The eLibrary link also provides access 
to the texts of formal documents issued by the Commission, such as 
orders, notices, and rulemakings.
    In addition, the Commission offers a free service called 
eSubscription that allows you to keep track of all formal issuances and 
submittals in specific dockets. This can reduce the amount of time you 
spend researching proceedings by automatically providing you with 
notification of these filings, document summaries, and direct links to 
the documents. Go to www.ferc.gov/docs-filing/esubscription.asp.

    Dated: August 14, 2015.
Kimberly D. Bose,
Secretary.
[FR Doc. 2015-20574 Filed 8-19-15; 8:45 am]
BILLING CODE 6717-01-P



                                              50622                       Federal Register / Vol. 80, No. 161 / Thursday, August 20, 2015 / Notices

                                              comment date for the particular                            The above-referenced meeting is open               DEPARTMENT OF ENERGY
                                              application.                                            to the public.
                                                 o. Filing and Service of Responsive                                                                        Federal Energy Regulatory
                                                                                                         Further information may be found at
                                              Documents: Any filing must (1) bear in                                                                        Commission
                                                                                                      www.pjm.com.
                                              all capital letters the title
                                                                                                         The discussions at the meeting                     Notice of Availability of the Final
                                              ‘‘COMMENTS’’; ‘‘PROTESTS’’, or
                                                                                                      described above may address matters at                Environmental Impact Statement for
                                              ‘‘MOTION TO INTERVENE’’ as
                                                                                                      issue in the following proceedings:                   the Proposed Lake Charles
                                              applicable; (2) set forth in the heading
                                                                                                                                                            Liquefaction Project
                                              the name of the applicant and the                       Docket No. EL13–88, Northern Indiana
                                              project number of the application to                      Public Service Company v.                                                         Docket No.
                                              which the filing responds; (3) furnish                    Midcontinent Independent System
                                              the name, address, and telephone                          Operator, Inc. and PJM                              Trunkline Gas Company,      CP14–119–000
                                              number of the person protesting or                        Interconnection, L.L.C.                               LLC.
                                              intervening; and (4) otherwise comply                                                                         Lake Charles LNG Com-       CP14–120–000
                                              with the requirements of 18 CFR                         Docket No. EL11–34, Midcontinent                        pany, LLC.
                                              385.2001 through 385.2005. All                            Independent System Operator, Inc.                   Lake Charles LNG Export     CP14–122–000
                                                                                                                                                              Company, LLC.
                                              comments, motions to intervene, or                      Docket No. EL14–21, Southwest Power
                                              protests must set forth their evidentiary                 Pool, Inc. v. Midcontinent
                                              basis and otherwise comply with the                       Independent System Operator, Inc.                      The staff of the Federal Energy
                                              requirements of 18 CFR 4.34(b).                         Docket No. EL14–30, Midcontinent                      Regulatory Commission (FERC or
                                              Agencies may obtain copies of the                         Independent System Operator, Inc. v.                Commission) has prepared a final
                                              application directly from the applicant.                                                                      environmental impact statement (EIS)
                                                                                                        Southwest Power Pool, Inc.
                                              A copy of any protest or motion to                                                                            for the Lake Charles Liquefaction
                                              intervene must be served upon each                      Docket No. ER11–1844, Midwest                         Project, proposed by Trunkline Gas
                                              representative of the applicant specified                 Independent Transmission System                     Company, LLC (Trunkline), Lake
                                              in the particular application. If an                      Operator, Inc.                                      Charles LNG Company, LLC, and Lake
                                              intervener files comments or documents                  Docket No. ER13–1864, Southwest                       Charles LNG Export Company, LLC in
                                              with the Commission relating to the                       Power Pool, Inc.                                    the above-referenced dockets. Trunkline
                                              merits of an issue that may affect the                                                                        requests authorization to construct,
                                              responsibilities of a particular resource               Docket No. ER10–1791, Midwest
                                                                                                        Independent Transmission System                     install, and operate new natural gas
                                              agency, they must also serve a copy of                                                                        pipeline facilities; modify certain
                                              the document on that resource agency.                     Operator, Inc.
                                                                                                                                                            existing pipeline facilities; and abandon
                                              A copy of all other filings in reference                Docket Nos. ER13–1923, ER13–1938,                     one compressor unit in the states of
                                              to this application must be accompanied                   ER13–1943, ER13–1945, Midcontinent                  Arkansas, Mississippi, and Louisiana
                                              by proof of service on all persons listed                 Independent System Operator, Inc.                   (collectively referred to as the Non-
                                              in the service list prepared by the                     Docket Nos. ER13–1924, ER13–1926,                     Liquefaction Facilities). Lake Charles
                                              Commission in this proceeding, in                         ER13–1927, ER13–1936, ER13–1944,                    LNG Company, LLC and Lake Charles
                                              accordance with 18 CFR 4.34(b) and                                                                            LNG Export Company, LLC (collectively
                                                                                                        ER13–1947, PJM Interconnection,
                                              385.2010.                                                                                                     referred to as Lake Charles LNG) request
                                                                                                        L.L.C.
                                                Dated: August 14, 2015.                                                                                     authorization to site, construct, and
                                                                                                      Docket Nos. ER13–1937, ER13–1939,                     operate new liquefaction facilities
                                              Kimberly D. Bose,
                                                                                                        Southwest Power Pool, Inc.                          adjacent to an existing liquefied natural
                                              Secretary.
                                              [FR Doc. 2015–20577 Filed 8–19–15; 8:45 am]
                                                                                                      Docket No. ER14–1174, Southwest                       gas (LNG) terminal located in Calcasieu
                                                                                                        Power Pool, Inc.                                    Parish, Louisiana, and to construct and
                                              BILLING CODE 6717–01–P
                                                                                                      Docket No. ER14–1736, Midcontinent                    operate certain facility modifications at
                                                                                                        Independent System Operator, Inc.                   the existing LNG terminal. The new
                                              DEPARTMENT OF ENERGY                                                                                          liquefaction facilities would have a
                                                                                                      Docket No. ER14–2022, Midcontinent                    design production capacity of 16.45
                                              Federal Energy Regulatory                                 Independent System Operator, Inc.                   million metric tons of LNG per annum,
                                              Commission                                              Docket No. ER14–2445, Midcontinent                    which would provide an LNG export
                                                                                                        Independent System Operator, Inc.                   capacity equivalent to about 2 billion
                                              Notice of Commission Staff                                                                                    cubic feet per day of natural gas.
                                                                                                      Docket No. ER15–1874, PJM
                                              Attendance                                                                                                       Lake Charles LNG also requests
                                                                                                        Interconnection, L.L.C.                             authorization to abandon certain
                                                 The Federal Energy Regulatory                        Docket No. ER15–1890, Midcontinent                    terminal facilities previously
                                              Commission hereby gives notice that                       Independent System Operator, Inc.                   certificated under the Natural Gas Act
                                              members of the Commission’s staff will                                                                        (NGA) section 7; and convert such
                                              attend the following meeting related to                   For more information, contact Valerie
                                                                                                                                                            certificated facilities so that the entirety
                                              the Midcontinent Independent System                     Teeter, Office of Energy Policy and
                                                                                                                                                            of the company’s facilities and
                                              Operator, Inc. (MISO)—PJM                               Innovation, Federal Energy Regulatory
                                                                                                                                                            operations are authorized solely under
                                              Interconnection, L.L.C. (PJM) Joint and                 Commission at (202) 502–8538 or                       NGA section 3.
                                                                                                      Valerie.Teeter@ferc.gov.
tkelley on DSK3SPTVN1PROD with NOTICES




                                              Common Market Initiative (Docket No.                                                                             The final EIS assesses the potential
                                              AD14–3–000): MISO/PJM Joint                               Dated: August 13, 2015.                             environmental effects of construction
                                              Stakeholder Meeting—August 20, 2015.                    Kimberly D. Bose,                                     and operation of the Lake Charles
                                                 The above-referenced meeting will be                 Secretary.
                                                                                                                                                            Liquefaction Project in accordance with
                                              held at: PJM Conference & Training                                                                            the requirements of the National
                                                                                                      [FR Doc. 2015–20463 Filed 8–19–15; 8:45 am]
                                              Center, 2750 Monroe Boulevard,                                                                                Environmental Policy Act. The FERC
                                                                                                      BILLING CODE 6717–01–P                                staff concludes that approval of the
                                              Audubon, PA 19403.


                                         VerDate Sep<11>2014   17:31 Aug 19, 2015   Jkt 235001   PO 00000   Frm 00028   Fmt 4703   Sfmt 4703   E:\FR\FM\20AUN1.SGM   20AUN1


                                                                          Federal Register / Vol. 80, No. 161 / Thursday, August 20, 2015 / Notices                                          50623

                                              proposed project would have some                        groups; Native American tribes;                       requesting public comment to revise
                                              adverse environmental impacts;                          potentially affected landowners; other                and extend the Banking Organization
                                              however, most of these impacts would                    interested individuals and non-                       Systemic Risk Report (FR Y–15; OMB
                                              be reduced to less-than-significant                     governmental organizations;                           No. 7100–0352). The July 9 proposal
                                              levels with the implementation of Lake                  newspapers and libraries in the project               would, among other revisions, collect
                                              Charles LNG’s and Trunkline’s                           area; and parties to this proceeding.                 information on short-term wholesale
                                              proposed mitigation and the additional                  Paper copy versions of this EIS were                  funding.
                                              measures recommended in the final EIS.                  mailed to those specifically requesting                  On July 20, 2015, the Board adopted
                                                 The U.S. Army Corps of Engineers,                    them; all others received a compact disk              a final rule establishing a capital
                                              U.S. Coast Guard, U.S. Department of                    version. In addition, the final EIS is                surcharge for the largest, most
                                              Energy, U.S. Fish and Wildlife Service,                 available for public viewing on the                   interconnected banks. In that final rule,
                                              and U.S. Department of Transportation                   FERC’s Web site (www.ferc.gov) using                  the Board amended the July 9 proposal
                                              participated as cooperating agencies in                 the eLibrary link. A limited number of                to conform the definition of short-term
                                              the preparation of the final EIS.                       hardcopies are available for distribution             wholesale funding with the definition in
                                              Cooperating agencies have jurisdiction                  and public inspection at: Federal Energy              the final rule. To allow interested
                                              by law or special expertise with respect                Regulatory Commission, Public                         persons to comment on the entire
                                              to resources potentially affected by a                  Reference Room, 888 First Street NE.,                 notice, the Board is extending the
                                              proposal and participate in the National                Room 2A, Washington, DC 20426, (202)                  comment period of the July 9 proposal,
                                              Environmental Policy Act analysis.                      502–8371.                                             to include the July 20 amendments to
                                              Although the cooperating agencies                          Additional information about the                   the proposed short-term wholesale
                                              provided input on the conclusions and                   project is available from the                         funding collection, until October 19,
                                              recommendations presented in the final                  Commission’s Office of External Affairs,              2015.
                                              EIS, the agencies will present their own                at (866) 208–FERC, or on the FERC Web                 DATES:  Comments must be submitted on
                                              conclusions and recommendations in                      site (www.ferc.gov) using the eLibrary                or before October 19, 2015. The
                                              their respective records of decision or                 link. Click on the eLibrary link, click on            comment period for the proposed
                                              determinations for the project.                         ‘‘General Search,’’ and enter the docket              revisions and extension of the FR Y–15
                                                 The Lake Charles Liquefaction Project                number(s) excluding the last three digits             published July 9, 2015 (80 FR 39433) is
                                              includes:                                               in the Docket Number field (i.e., CP14–               extended from September 8, 2015 to
                                                 • Three liquefaction trains, each with               119, CP14–120, and CP14–122). Be sure                 October 19, 2015.
                                              a production capacity sufficient to                     you have selected an appropriate date
                                              produce 5.48 million metric tons per                                                                          ADDRESSES: You may submit comments,
                                                                                                      range. For assistance, please contact
                                              annum of LNG for export (each train                                                                           identified by FR Y–15, by any of the
                                                                                                      FERC Online Support at
                                              would contain metering and gas                                                                                following methods:
                                                                                                      FercOnlineSupport@ferc.gov or toll free
                                              treatment facilities, liquefaction and                                                                          • Agency Web site: http://
                                                                                                      at (866) 208–3676; for TTY, contact
                                              refrigerant units, safety and control                                                                         www.federalreserve.gov. Follow the
                                                                                                      (202) 502–8659. The eLibrary link also
                                              systems, and associated infrastructure);                                                                      instructions for submitting comments at
                                                                                                      provides access to the texts of formal
                                                 • modifications and upgrades at the                                                                        http://www.federalreserve.gov/
                                                                                                      documents issued by the Commission,
                                              existing Trunkline LNG terminal;                                                                              generalinfo/foia/ProposedRegs.cfm.
                                                                                                      such as orders, notices, and
                                                 • about 0.5 mile of 48-inch-diameter                                                                         • Federal eRulemaking Portal: http://
                                                                                                      rulemakings.
                                              feed gas line to supply natural gas to the                                                                    www.regulations.gov. Follow the
                                                                                                         In addition, the Commission offers a
                                              liquefaction facility from existing gas                                                                       instructions for submitting comments.
                                                                                                      free service called eSubscription that
                                              transmission pipelines;                                                                                         • Email: regs.comments@
                                                                                                      allows you to keep track of all formal
                                                 • approximately 17.9 miles of 24- and                                                                      federalreserve.gov. Include OMB
                                                                                                      issuances and submittals in specific
                                              42-inch-diameter natural gas pipeline;                                                                        number in the subject line of the
                                                                                                      dockets. This can reduce the amount of
                                                 • a new compressor station with a                    time you spend researching proceedings
                                                                                                                                                            message.
                                              manufacturer’s rating of 103,175                                                                                • FAX: (202) 452–3819 or (202) 452–
                                                                                                      by automatically providing you with                   3102.
                                              horsepower (hp), which equates to a                     notification of these filings, document
                                              site-specific rating of 98,685 hp (based                                                                        • Mail: Robert deV. Frierson,
                                                                                                      summaries, and direct links to the                    Secretary, Board of Governors of the
                                              on relative humidity and elevation);                    documents. Go to www.ferc.gov/docs-
                                                 • abandonment of a 3,000-hp                          filing/esubscription.asp.
                                                                                                                                                            Federal Reserve System, 20th Street and
                                              compressor unit, installation of a unit                                                                       Constitution Avenue NW., Washington,
                                              with a manufacturer’s rating of 15,900                    Dated: August 14, 2015.                             DC 20551.
                                              hp and site-specific rating of 15,002-hp                Kimberly D. Bose,                                        All public comments are available
                                              unit, and piping modifications at one                   Secretary.                                            from the Board’s Web site at http://
                                              existing compressor station;                            [FR Doc. 2015–20574 Filed 8–19–15; 8:45 am]           www.federalreserve.gov/apps/foia/
                                                 • modification of station piping at                  BILLING CODE 6717–01–P
                                                                                                                                                            proposedregs.aspx as submitted, unless
                                              three other existing compressor stations;                                                                     modified for technical reasons.
                                                 • five new meter stations and                                                                              Accordingly, comments will not be
                                              modifications and upgrades of five                                                                            edited to remove any identifying or
                                                                                                      FEDERAL RESERVE SYSTEM
                                              existing meter stations;                                                                                      contact information. Public comments
                                                 • modification of certain existing                   Proposed Agency Information                           may also be viewed electronically or in
                                              pipeline facilities; and                                Collection Activities; Comment                        paper form in Room 3515, 1801 K Street
                                                 • construction of miscellaneous
tkelley on DSK3SPTVN1PROD with NOTICES




                                                                                                      Request                                               NW., (between 18th and 19th Street
                                              auxiliary and appurtenant facilities.                                                                         NW.), Washington, DC 20006 between
                                                 The FERC staff mailed copies of the                  AGENCY: Board of Governors of the                     9:00 a.m. and 5:00 p.m. on weekdays.
                                              final EIS to federal, state, and local                  Federal Reserve System (Board).                          Additionally, commenters may send a
                                              government representatives and                          SUMMARY: On July 9, 2015, the Federal                 copy of their comments to the OMB
                                              agencies; elected officials;                            Reserve published a notice in the                     Desk Officer, Shagufta Ahmed, Office of
                                              environmental and public interest                       Federal Register (80 FR 39433)                        Information and Regulatory Affairs,


                                         VerDate Sep<11>2014   17:31 Aug 19, 2015   Jkt 235001   PO 00000   Frm 00029   Fmt 4703   Sfmt 4703   E:\FR\FM\20AUN1.SGM   20AUN1



Document Created: 2015-12-15 11:08:19
Document Modified: 2015-12-15 11:08:19
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation80 FR 50622 