DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 80, Issue 172 (September 4, 2015)

Page Range53509-53510
FR Document2015-21985

Federal Register, Volume 80 Issue 172 (Friday, September 4, 2015)
[Federal Register Volume 80, Number 172 (Friday, September 4, 2015)]
[Notices]
[Pages 53509-53510]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2015-21985]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 14655-000]


Cat Creek Energy, LLC; Notice of Preliminary Permit Application 
Accepted for Filing and Soliciting Comments, Motions To Intervene, and 
Competing Applications

    On December 12, 2014, Cat Creek Energy, LLC (Cat Creek) filed an 
application for a preliminary permit, pursuant to section 4(f) of the 
Federal Power Act, proposing to study the feasibility of the Cat Creek 
Energy Generation Facility Pumped Storage Hydroelectric Project (Cat 
Creek project). The project would be located at the US Bureau of 
Reclamation's (Reclamation) Anderson Ranch reservoir \1\ on the South 
Fork of the Boise River near Mountain Home in Elmore County, Idaho.
---------------------------------------------------------------------------

    \1\ On November 24, 2014, Owyhee Hydro, LLC also filed a 
preliminary permit to use the Anderson Ranch reservoir as a lower 
reservoir for the Anderson Ranch Pumped Storage Hydroelectric 
Project (P-14648), and thus may be competing for the same water 
resource.
---------------------------------------------------------------------------

    The sole purpose of a preliminary permit, if issued, is to grant 
the permit holder priority to file a license application during the 
permit term. A preliminary permit does not authorize the permit holder 
to perform any land-disturbing activities or otherwise enter upon lands 
or waters owned by others without the owners' express permission.
    On December 19, 2014, the Commission asked Reclamation to confirm 
that non-federal development is authorized at the Anderson Ranch site. 
On January 30, 2015, Reclamation responded stating that it retains 
jurisdiction over hydropower development at the Anderson Ranch dam, 
reservoir, and powerhouse, which are part of Reclamation's Boise 
Project. On June 8, 2015, the Commission responded and agreed with 
Reclamation's jurisdictional decision over hydropower development at 
the Boise Project's Anderson Ranch dam, powerhouse, and reservoir. 
However, the Commission would retain jurisdiction for hydropower 
facilities that would be located outside of Reclamation's development. 
Thus, an entity seeking to build a hydropower project that would use 
Reclamation's Boise Project facilities would need to obtain a lease of 
power privilege from Reclamation, but it also would need to obtain a 
license from the Commission for those facilities of the hydropower 
project that are not under Reclamation's jurisdiction.
    On August 21, 2015, Cat Creek filed minor revisions to the original 
Cat Creek project permit application. The revised Cat Creek project 
would use the existing Anderson Ranch reservoir, and would consist of 
the following new facilities: (1) A 3.4-mile-long, 80-foot-high earthen 
dam; (2) a 38,000-acre-foot impoundment as an upper reservoir; (3) two, 
5,600-foot-long, 22-foot-diameter steel penstocks; (4) two, 100-foot-
diameter concrete silos; (5) two, 200-megawatt vertical Francis 
turbines/generators; (6) an 8.0-mile-long, 230- kilovolt transmission 
line interconnecting with the existing Bonneville Power Administration 
Dixie Substation; (7) an approximately 3.6-mile-long access road; and 
(8) appurtenant facilities. The estimated annual generation of the Cat 
Creek project would be 1,401.6 gigawatt-hours.
    Applicant Contact for the Cat Creek project: Nicholas Josten, Cat 
Creek Energy, LLC, 1989 South 1875 East, Gooding, ID 83330; phone: 
(208) 954-5090.
    FERC Contact: Karen Sughrue; phone: (202) 502-8556.
    Deadline for filing comments, motions to intervene, competing 
applications (without notices of intent), or notices of intent to file 
competing applications: 60 days from the issuance of this notice. 
Competing applications and notices of intent must meet the requirements 
of 18 CFR 4.36.

[[Page 53510]]

    The Commission strongly encourages electronic filing. Please file 
comments, motions to intervene, notices of intent, and competing 
applications using the Commission's eFiling system at http://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief 
comments up to 6,000 characters, without prior registration, using the 
eComment system at http://www.ferc.gov/docs-filing/ecomment.asp. You 
must include your name and contact information at the end of your 
comments. For assistance, please contact FERC Online Support at 
[email protected], (866) 208-3676 (toll free), or (202) 502-
8659 (TTY). In lieu of electronic filing, please send a paper copy to: 
Secretary, Federal Energy Regulatory Commission, 888 First Street NE., 
Washington, DC 20426. The first page of any filing should include 
docket number P-14655-000.
    More information about this project, including a copy of the 
application, can be viewed or printed on the ``eLibrary'' link of 
Commission's Web site at http://www.ferc.gov/docs-filing/elibrary.asp. 
Enter the docket number (P-14655) in the docket number field to access 
the document. For assistance, contact FERC Online Support.

    Dated: August 28, 2015.
Kimberly D. Bose,
Secretary.
[FR Doc. 2015-21985 Filed 9-3-15; 8:45 am]
BILLING CODE 6717-01-P



                                                                               Federal Register / Vol. 80, No. 172 / Friday, September 4, 2015 / Notices                                          53509

                                                  comments in Washington, DC on or                        137). Be sure you have selected an                    upon lands or waters owned by others
                                                  before September 30, 2015.                              appropriate date range. For assistance,               without the owners’ express permission.
                                                     For your convenience, there are three                please contact FERC Online Support at                   On December 19, 2014, the
                                                  methods you can use to file your                        FercOnlineSupport@ferc.gov or toll free               Commission asked Reclamation to
                                                  comments to the Commission. In all                      at (866) 208–3676, or for TTY, contact                confirm that non-federal development is
                                                  instances, please reference the project                 (202) 502–8659. The eLibrary link also                authorized at the Anderson Ranch site.
                                                  docket number (CP15–137–000) with                       provides access to the texts of formal                On January 30, 2015, Reclamation
                                                  your submission. The Commission                         documents issued by the Commission,                   responded stating that it retains
                                                  encourages electronic filing of                         such as orders, notices, and                          jurisdiction over hydropower
                                                  comments and has expert staff available                 rulemakings.                                          development at the Anderson Ranch
                                                  to assist you at (202) 502–8258 or                         In addition, the Commission offers a               dam, reservoir, and powerhouse, which
                                                  efiling@ferc.gov.                                       free service called eSubscription which               are part of Reclamation’s Boise Project.
                                                     (1) You can file your comments                       allows you to keep track of all formal                On June 8, 2015, the Commission
                                                  electronically using the eComment                       issuances and submittals in specific                  responded and agreed with
                                                  feature on the Commission’s Web site                    dockets. This can reduce the amount of                Reclamation’s jurisdictional decision
                                                  (www.ferc.gov) under the link to                        time you spend researching proceedings                over hydropower development at the
                                                  Documents and Filings. This is an easy                  by automatically providing you with                   Boise Project’s Anderson Ranch dam,
                                                  method for submitting brief, text-only                  notification of these filings, document               powerhouse, and reservoir. However,
                                                  comments on a project;                                  summaries, and direct links to the                    the Commission would retain
                                                     (2) You can also file your comments                  documents. Go to www.ferc.gov/docs-                   jurisdiction for hydropower facilities
                                                  electronically using the eFiling feature                filing/esubscription.asp.                             that would be located outside of
                                                  on the Commission’s Web site                                                                                  Reclamation’s development. Thus, an
                                                  (www.ferc.gov) under the link to                          Dated: August 31, 2015.
                                                                                                          Kimberly D. Bose,                                     entity seeking to build a hydropower
                                                  Documents and Filings. With eFiling,                                                                          project that would use Reclamation’s
                                                  you can provide comments in a variety                   Secretary.
                                                                                                                                                                Boise Project facilities would need to
                                                  of formats by attaching them as a file                  [FR Doc. 2015–21988 Filed 9–3–15; 8:45 am]
                                                                                                                                                                obtain a lease of power privilege from
                                                  with your submission. New eFiling                       BILLING CODE 6717–01–P
                                                                                                                                                                Reclamation, but it also would need to
                                                  users must first create an account by                                                                         obtain a license from the Commission
                                                  clicking on ‘‘eRegister.’’ You must select                                                                    for those facilities of the hydropower
                                                  the type of filing you are making. If you               DEPARTMENT OF ENERGY
                                                                                                                                                                project that are not under Reclamation’s
                                                  are filing a comment on a particular                                                                          jurisdiction.
                                                  project, please select ‘‘Comment on a                   Federal Energy Regulatory
                                                                                                          Commission                                              On August 21, 2015, Cat Creek filed
                                                  Filing’’; or                                                                                                  minor revisions to the original Cat Creek
                                                     (3) You can file a paper copy of your
                                                                                                          [Project No. 14655–000]
                                                                                                                                                                project permit application. The revised
                                                  comments by mailing them to the
                                                                                                                                                                Cat Creek project would use the existing
                                                  following address: Kimberly D. Bose,
                                                                                                          Cat Creek Energy, LLC; Notice of                      Anderson Ranch reservoir, and would
                                                  Secretary, Federal Energy Regulatory
                                                                                                          Preliminary Permit Application                        consist of the following new facilities:
                                                  Commission, 888 First Street NE., Room
                                                                                                          Accepted for Filing and Soliciting                    (1) A 3.4-mile-long, 80-foot-high earthen
                                                  1A, Washington, DC 20426.
                                                                                                          Comments, Motions To Intervene, and                   dam; (2) a 38,000-acre-foot
                                                     Any person seeking to become a party
                                                                                                          Competing Applications                                impoundment as an upper reservoir; (3)
                                                  to the proceeding must file a motion to
                                                                                                                                                                two, 5,600-foot-long, 22-foot-diameter
                                                  intervene pursuant to Rule 214 of the
                                                                                                            On December 12, 2014, Cat Creek                     steel penstocks; (4) two, 100-foot-
                                                  Commission’s Rules of Practice and
                                                                                                          Energy, LLC (Cat Creek) filed an                      diameter concrete silos; (5) two, 200-
                                                  Procedures (18 CFR 385.214).1 Only
                                                                                                          application for a preliminary permit,                 megawatt vertical Francis turbines/
                                                  intervenors have the right to seek
                                                                                                          pursuant to section 4(f) of the Federal               generators; (6) an 8.0-mile-long, 230-
                                                  rehearing of the Commission’s decision.
                                                                                                          Power Act, proposing to study the                     kilovolt transmission line
                                                  The Commission grants affected
                                                                                                          feasibility of the Cat Creek Energy                   interconnecting with the existing
                                                  landowners and others with
                                                                                                          Generation Facility Pumped Storage                    Bonneville Power Administration Dixie
                                                  environmental concerns intervenor
                                                                                                          Hydroelectric Project (Cat Creek                      Substation; (7) an approximately 3.6-
                                                  status upon showing good cause by
                                                                                                          project). The project would be located at             mile-long access road; and (8)
                                                  stating that they have a clear and direct
                                                                                                          the US Bureau of Reclamation’s                        appurtenant facilities. The estimated
                                                  interest in this proceeding which no
                                                                                                          (Reclamation) Anderson Ranch                          annual generation of the Cat Creek
                                                  other party can adequately represent.
                                                                                                          reservoir 1 on the South Fork of the                  project would be 1,401.6 gigawatt-hours.
                                                  Simply filing environmental comments
                                                  will not give you intervenor status, but                Boise River near Mountain Home in                       Applicant Contact for the Cat Creek
                                                  you do not need intervenor status to                    Elmore County, Idaho.                                 project: Nicholas Josten, Cat Creek
                                                  have your comments considered.                            The sole purpose of a preliminary                   Energy, LLC, 1989 South 1875 East,
                                                     Additional information about the                     permit, if issued, is to grant the permit             Gooding, ID 83330; phone: (208) 954–
                                                  project is available from the                           holder priority to file a license                     5090.
                                                  Commission’s Office of External Affairs,                application during the permit term. A                   FERC Contact: Karen Sughrue; phone:
                                                  at (866) 208–FERC, or on the FERC Web                   preliminary permit does not authorize                 (202) 502–8556.
                                                                                                          the permit holder to perform any land-
mstockstill on DSK4VPTVN1PROD with NOTICES




                                                  site (www.ferc.gov) using the eLibrary                                                                          Deadline for filing comments, motions
                                                  link. Click on the eLibrary link, click on              disturbing activities or otherwise enter              to intervene, competing applications
                                                  ‘‘General Search,’’ and enter the docket                                                                      (without notices of intent), or notices of
                                                  number excluding the last three digits in                 1 On November 24, 2014, Owyhee Hydro, LLC           intent to file competing applications: 60
                                                                                                          also filed a preliminary permit to use the Anderson   days from the issuance of this notice.
                                                  the Docket Number field (i.e., CP15–                    Ranch reservoir as a lower reservoir for the
                                                                                                          Anderson Ranch Pumped Storage Hydroelectric
                                                                                                                                                                Competing applications and notices of
                                                     1 See the previous discussion on the methods for     Project (P–14648), and thus may be competing for      intent must meet the requirements of 18
                                                  filing comments.                                        the same water resource.                              CFR 4.36.


                                             VerDate Sep<11>2014   16:57 Sep 03, 2015   Jkt 235001   PO 00000   Frm 00025   Fmt 4703   Sfmt 4703   E:\FR\FM\04SEN1.SGM   04SEN1


                                                  53510                       Federal Register / Vol. 80, No. 172 / Friday, September 4, 2015 / Notices

                                                     The Commission strongly encourages                      The proposed project consists of the                  More information about this project,
                                                  electronic filing. Please file comments,                Boardman Dam Development located at                   including a copy of the application, can
                                                  motions to intervene, notices of intent,                River Mile 6.1 and the Sabin Dam                      be viewed or printed on the ‘‘eLibrary’’
                                                  and competing applications using the                    Development located at River Mile 5.3.                link of Commission’s Web site at http://
                                                  Commission’s eFiling system at http://                  The Boardman Dam Development                          www.ferc.gov/docs-filing/elibrary.asp.
                                                  www.ferc.gov/docs-filing/efiling.asp.                   would consist of: (1) A 103-acre                      Enter the docket number (P–14681) in
                                                  Commenters can submit brief comments                    Boardman Pond; (2) a 650-foot-long                    the docket number field to access the
                                                  up to 6,000 characters, without prior                   west earth-filled abutment, a 20-foot-                document. For assistance, contact FERC
                                                  registration, using the eComment system                 wide emergency spillway, a 40-foot-long               Online Support.
                                                  at http://www.ferc.gov/docs-filing/                     intake structure containing twin 10-foot-               Dated: August 28, 2015.
                                                  ecomment.asp. You must include your                     diameter by 73-foot-long steel penstocks              Kimberly D. Bose,
                                                  name and contact information at the end                 leading to the powerhouse, and an
                                                                                                                                                                Secretary.
                                                  of your comments. For assistance,                       approximately 150-foot-long earth-filled
                                                                                                                                                                [FR Doc. 2015–21986 Filed 9–3–15; 8:45 am]
                                                  please contact FERC Online Support at                   east abutment; (3) a 70-foot-long, 20-
                                                  FERCOnlineSupport@ferc.gov, (866)                       foot-wide reinforced concrete                         BILLING CODE 6717–01–P

                                                  208–3676 (toll free), or (202) 502–8659                 powerhouse containing a 1,000 kilowatt
                                                  (TTY). In lieu of electronic filing, please             turbine-generator; and (4) appurtenant
                                                                                                                                                                DEPARTMENT OF ENERGY
                                                  send a paper copy to: Secretary, Federal                facilities.
                                                  Energy Regulatory Commission, 888                          The Sabin Dam Development would                    Federal Energy Regulatory
                                                  First Street NE., Washington, DC 20426.                 consist of: (1) A 40-acre Sabin Pond; (2)             Commission
                                                  The first page of any filing should                     a 60-foot-long earth west embankment,
                                                  include docket number P–14655–000.                      a 70-foot-long by 20-foot-wide                        [Project No. 14648–000]
                                                     More information about this project,                 reinforced concrete powerhouse integral
                                                  including a copy of the application, can                                                                      Owyhee Hydro, LLC; Notice of
                                                                                                          with the dam containing a 500 kilowatt
                                                  be viewed or printed on the ‘‘eLibrary’’                                                                      Preliminary Permit Application
                                                                                                          turbine-generator, a 52-foot-long
                                                  link of Commission’s Web site at http://                                                                      Accepted for Filing and Soliciting
                                                                                                          intermediate earth embankment, a 32-
                                                  www.ferc.gov/docs-filing/elibrary.asp.                                                                        Comments, Motions To Intervene, and
                                                                                                          foot-long stop wide spillway section, an
                                                  Enter the docket number (P–14655) in                                                                          Competing Applications
                                                                                                          18-foot wide tainter gate spillway
                                                  the docket number field to access the                   section, and a 330-foot-long earth east                 On November 24, 2014, Owyhee
                                                  document. For assistance, contact FERC                  embankment; and (3) appurtenant                       Hydro, LLC (Owyhee Hydro) filed an
                                                  Online Support.                                         facilities. The project would generate an             application for preliminary permit,
                                                    Dated: August 28, 2015.                               estimated 7,600 megawatt hours                        pursuant to section 4(f) of the Federal
                                                  Kimberly D. Bose,                                       annually.                                             Power Act, proposing to study the
                                                  Secretary.                                                 Applicant Contact: Charles R.                      feasibility of the Anderson Ranch
                                                  [FR Doc. 2015–21985 Filed 9–3–15; 8:45 am]
                                                                                                          Peterson, 9627 Seth Road, Northport, MI               Pumped Storage Hydroelectric Project
                                                                                                          49670; phone: 231–649–8706.                           (Anderson Ranch project). The project
                                                  BILLING CODE 6717–01–P
                                                                                                             FERC Contact: Sergiu Serban, (202)                 would be located at the U.S. Bureau of
                                                                                                          502–6211.                                             Reclamation’s (Reclamation) Anderson
                                                  DEPARTMENT OF ENERGY                                       Deadline for filing comments, motions              Ranch dam and reservoir 1 on the South
                                                                                                          to intervene, competing applications                  Fork of the Boise River near Mountain
                                                  Federal Energy Regulatory                               (without notices of intent), or notices of            Home in Elmore County, Idaho.
                                                  Commission                                              intent to file competing applications: 60               The sole purpose of a preliminary
                                                                                                          days from the issuance of this notice.                permit, if issued, is to grant the permit
                                                  [Project No. 14681–000]
                                                                                                          Competing applications and notices of                 holder priority to file a license
                                                  Peterson Machinery Sales; Notice of                     intent must meet the requirements of 18               application during the permit term. A
                                                  Preliminary Permit Application                          CFR 4.36. The Commission strongly                     preliminary permit does not authorize
                                                  Accepted for Filing and Soliciting                      encourages electronic filing. Please file             the permit holder to perform any land-
                                                  Comments, Motions To Intervene, and                     comments, motions to intervene, notices               disturbing activities or otherwise enter
                                                  Competing Applications                                  of intent, and competing applications                 upon lands or waters owned by others
                                                                                                          using the Commission’s eFiling system                 without the owners’ express permission.
                                                     On June 3, 2015, Peterson Machinery                  at http://www.ferc.gov/docs-filing/                     On December 4, 2014, the
                                                  Sales filed an application for a                        efiling.asp. Commenters can submit                    Commission asked Reclamation to
                                                  preliminary permit under section 4(f) of                brief comments up to 6,000 characters,                confirm that non-federal development is
                                                  the Federal Power Act proposing to                      without prior registration, using the                 authorized at the Anderson Ranch site.
                                                  study the feasibility of the proposed                   eComment system at http://                            On January 30, 2015, Reclamation
                                                  Boardman River Hydro-Electric Project                   www.ferc.gov/docs-filing/                             responded stating that it retains
                                                  No. 14681–000, to be located on the                     ecomment.asp. You must include your                   jurisdiction over hydropower
                                                  Boardman River near Traverse City,                      name and contact information at the end               development at the Anderson Ranch
                                                  Grand Traverse County, Michigan. The                    of your comments. For assistance,                     dam, reservoir, and powerhouse, which
                                                  sole purpose of a preliminary permit, if                please contact FERC Online Support at                 are part of Reclamation’s Boise Project.
mstockstill on DSK4VPTVN1PROD with NOTICES




                                                  issued, is to grant the permit holder                   FERCOnlineSupport@ferc.gov, (866)                     On June 8, 2015, the Commission
                                                  priority to file a license application                  208–3676 (toll free), or (202) 502–8659
                                                  during the permit term. A preliminary                   (TTY). In lieu of electronic filing, please
                                                  permit does not authorize the permit                    send a paper copy to: Secretary, Federal                1 On December 12, 2014, Cat Creek Energy, LLC

                                                  holder to perform any land-disturbing                   Energy Regulatory Commission, 888                     also filed for a preliminary permit to use the
                                                                                                                                                                Anderson Ranch reservoir as a lower reservoir for
                                                  activities or otherwise enter upon lands                First Street NE., Washington, DC 20426.               the Cat Creek Energy Generation Facility Pumped
                                                  or waters owned by others without the                   The first page of any filing should                   Storage Hydroelectric Project (P–14655), and thus
                                                  owners’ express permission.                             include docket number P–14681–000.                    may be competing for the same water resource.



                                             VerDate Sep<11>2014   16:57 Sep 03, 2015   Jkt 235001   PO 00000   Frm 00026   Fmt 4703   Sfmt 4703   E:\FR\FM\04SEN1.SGM   04SEN1



Document Created: 2015-12-15 09:58:12
Document Modified: 2015-12-15 09:58:12
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation80 FR 53509 