80_FR_53683 80 FR 53511 - Blue River Hydro Power, LLC; Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications

80 FR 53511 - Blue River Hydro Power, LLC; Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 80, Issue 172 (September 4, 2015)

Page Range53511-53512
FR Document2015-21987

Federal Register, Volume 80 Issue 172 (Friday, September 4, 2015)
[Federal Register Volume 80, Number 172 (Friday, September 4, 2015)]
[Notices]
[Pages 53511-53512]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2015-21987]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 14690-000]


Blue River Hydro Power, LLC; Notice of Preliminary Permit 
Application Accepted for Filing and Soliciting Comments, Motions To 
Intervene, and Competing Applications

    On July 1, 2015, Blue River Hydro Power, LLC filed an application 
for a preliminary permit, pursuant to section 4(f) of the Federal Power 
Act (FPA), proposing to study the feasibility of the Blue River 
Hydroelectric Project (Blue River Project or project) to be located at 
Blue River Dam near the Town of Blue River in Lane County, Oregon. The 
sole purpose of a preliminary permit, if issued, is to grant the permit 
holder priority to file a license application during the permit term. A 
preliminary permit does not authorize the permit holder to perform any 
land-disturbing activities or otherwise enter upon lands or waters 
owned by others without the owners' express permission.
    The proposed project would utilize flows at the existing Blue River 
Dam, and would consist of the following new features: (1) A 12-foot-
diameter, 500-foot-long steel liner pipe installed in the downstream 
portion of the existing dam outlet tunnel, (2) a gatehouse containing 
two 7-foot-wide, 8-foot-high steel slidegates to regulate pipe pressure 
and release excess water, (3) a 9-foot- to 12-foot-diameter, 600-foot-
long steel penstock, (4) a 70-foot-wide, 55-foot-long reinforced 
concrete powerhouse, (5) two 10 megawatt vertical-shaft Francis 
turbine/generators, (6) an approximately 40-foot-wide, 40-foot-long 
concrete tailrace returning flows to the Blue River, (7) a switchyard 
and a 2.5-mile-long, 12.5-kilovolt buried transmission line 
interconnecting with Lane Electric Cooperative's existing Blue River 
substation, and (8) appurtenant facilities. The estimated annual 
generation of the Blue River Project would be 50 gigawatt-hours.
    Applicant Contact: Mr. Rett Hubbard, Blue River Hydro Power, LLC, 
285 East Oregon Avenue, Suite 7, Creswell, Oregon 97426; phone: (541) 
632-4706.
    FERC Contact: Sean O'Neill; phone: (202) 502-6462.
    Deadline for filing comments, motions to intervene, competing 
applications (without notices of intent), or notices of intent to file 
competing applications: 60 days from the issuance of this notice. 
Competing applications and notices of intent must meet the requirements 
of 18 CFR 4.36.
    The Commission strongly encourages electronic filing. Please file 
comments, motions to intervene, notices of intent, and competing 
applications using the Commission's eFiling system at http://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief 
comments up to 6,000 characters, without prior registration, using the 
eComment system at http://www.ferc.gov/docs-filing/ecomment.asp. You 
must include your name and contact information at the end of your 
comments. For assistance, please contact FERC Online Support at 
FERCOnlineSupport@ferc.gov, (866) 208-3676 (toll free), or (202) 502-
8659 (TTY). In lieu of electronic filing, please send a paper copy to: 
Secretary, Federal Energy Regulatory Commission, 888 First Street NE., 
Washington, DC 20426. The first page of any filing should include 
docket number P-14690-000.
    More information about this project, including a copy of the 
application, can

[[Page 53512]]

be viewed or printed on the ``eLibrary'' link of Commission's Web site 
at http://www.ferc.gov/docs-filing/elibrary.asp. Enter the docket 
number (P-14690) in the docket number field to access the document. For 
assistance, contact FERC Online Support.

    Dated: August 28, 2015.
Kimberly D. Bose,
Secretary.
[FR Doc. 2015-21987 Filed 9-3-15; 8:45 am]
BILLING CODE 6717-01-P



                                                                              Federal Register / Vol. 80, No. 172 / Friday, September 4, 2015 / Notices                                            53511

                                                  responded and agreed with                               (without notices of intent), or notices of            during the permit term. A preliminary
                                                  Reclamation’s jurisdictional decision                   intent to file competing applications: 60             permit does not authorize the permit
                                                  over hydropower development at the                      days from the issuance of this notice.                holder to perform any land-disturbing
                                                  Boise Project’s Anderson Ranch dam,                     Competing applications and notices of                 activities or otherwise enter upon lands
                                                  powerhouse, and reservoir. However,                     intent must meet the requirements of 18               or waters owned by others without the
                                                  the Commission would retain                             CFR 4.36.                                             owners’ express permission.
                                                  jurisdiction for hydropower facilities                     The Commission strongly encourages                    The proposed project would utilize
                                                  that would be located outside of                        electronic filing. Please file comments,              flows at the existing Blue River Dam,
                                                  Reclamation’s development. Thus, an                     motions to intervene, notices of intent,              and would consist of the following new
                                                  entity seeking to build a hydropower                    and competing applications using the                  features: (1) A 12-foot-diameter, 500-
                                                  project that would use Reclamation’s                    Commission’s eFiling system at http://                foot-long steel liner pipe installed in the
                                                  Boise Project facilities would need to                  www.ferc.gov/docs-filing/efiling.asp.                 downstream portion of the existing dam
                                                  obtain a lease of power privilege from                  Commenters can submit brief comments                  outlet tunnel, (2) a gatehouse containing
                                                  Reclamation, but it also would need to                  up to 6,000 characters, without prior                 two 7-foot-wide, 8-foot-high steel
                                                  obtain a license from the Commission                    registration, using the eComment system               slidegates to regulate pipe pressure and
                                                  for those facilities of the hydropower                  at http://www.ferc.gov/docs-filing/                   release excess water, (3) a 9-foot- to 12-
                                                  project that are not under Reclamation’s                ecomment.asp. You must include your                   foot-diameter, 600-foot-long steel
                                                  jurisdiction.                                           name and contact information at the end               penstock, (4) a 70-foot-wide, 55-foot-
                                                     On July 27, 2015, Owyhee Hydro filed                 of your comments. For assistance,                     long reinforced concrete powerhouse,
                                                  a revised application providing an                      please contact FERC Online Support at                 (5) two 10 megawatt vertical-shaft
                                                  additional alternative to the proposed                  FERCOnlineSupport@ferc.gov, (866)                     Francis turbine/generators, (6) an
                                                  Anderson Ranch project. The revised                     208–3676 (toll free), or (202) 502–8659               approximately 40-foot-wide, 40-foot-
                                                  Anderson Ranch project has three                        (TTY). In lieu of electronic filing, please           long concrete tailrace returning flows to
                                                  alternatives: Alternatives A, B, and C.                 send a paper copy to: Secretary, Federal              the Blue River, (7) a switchyard and a
                                                  Alternatives A and B would use the                      Energy Regulatory Commission, 888                     2.5-mile-long, 12.5-kilovolt buried
                                                  existing Anderson Ranch dam,                            First Street NE., Washington, DC 20426.               transmission line interconnecting with
                                                  reservoir, powerhouse, tailrace, and                    The first page of any filing should                   Lane Electric Cooperative’s existing
                                                  transmission lines, and would consist of                include docket number P–14648–000.                    Blue River substation, and (8)
                                                  the following new facilities: (1) A 1,060-                 More information about this project,               appurtenant facilities. The estimated
                                                  foot-long, 65-foot-high zoned earth or                  including a copy of the application, can              annual generation of the Blue River
                                                  concrete faced rockfill dam; (2) a 900-                 be viewed or printed on the ‘‘eLibrary’’              Project would be 50 gigawatt-hours.
                                                  acre-foot impoundment as an upper                       link of Commission’s Web site at                         Applicant Contact: Mr. Rett Hubbard,
                                                  reservoir; (3) a 4,180-foot-long, 9.1-foot-             http://www.ferc.gov/docs-filing/                      Blue River Hydro Power, LLC, 285 East
                                                  diameter single steel penstock (6.5-foot-               elibrary.asp. Enter the docket number                 Oregon Avenue, Suite 7, Creswell,
                                                  diameter if twin conduit); (4) a single                 (P–14648) in the docket number field to               Oregon 97426; phone: (541) 632–4706.
                                                  80-megawatt (MW) reversible pump                        access the document. For assistance,                     FERC Contact: Sean O’Neill; phone:
                                                  turbine/generator to be located within                  contact FERC Online Support.                          (202) 502–6462.
                                                  the third bay of the existing                                                                                    Deadline for filing comments, motions
                                                  powerhouse; and (5) appurtenant                           Dated: August 28, 2015.                             to intervene, competing applications
                                                  facilities. Alternative C would use the                 Kimberly D. Bose,                                     (without notices of intent), or notices of
                                                  existing Anderson Ranch dam,                            Secretary.                                            intent to file competing applications: 60
                                                  reservoir, and powerhouse, and would                    [FR Doc. 2015–21984 Filed 9–3–15; 8:45 am]            days from the issuance of this notice.
                                                  consist of the same new facilities as in                BILLING CODE 6717–0–1P                                Competing applications and notices of
                                                  Alternatives A and B except it would                                                                          intent must meet the requirements of 18
                                                  have: (1) A 4,180-foot-long, 9.1-foot-                                                                        CFR 4.36.
                                                  diameter single steel penstock (6.5-foot-               DEPARTMENT OF ENERGY                                     The Commission strongly encourages
                                                  diameter if twin conduit) and a 3,440-                                                                        electronic filing. Please file comments,
                                                  foot-long, 9.1-foot-diameter single steel               Federal Energy Regulatory                             motions to intervene, notices of intent,
                                                  penstock (6.5-foot-diameter if twin                     Commission                                            and competing applications using the
                                                  conduit); (2) a 250-foot-long, 90-foot-                 [Project No. 14690–000]                               Commission’s eFiling system at http://
                                                  wide concrete powerhouse located                                                                              www.ferc.gov/docs-filing/efiling.asp.
                                                  adjacent to the existing Anderson Ranch                 Blue River Hydro Power, LLC; Notice                   Commenters can submit brief comments
                                                  reservoir; (3) a single 80–MW Pelton                    of Preliminary Permit Application                     up to 6,000 characters, without prior
                                                  turbine/generator; and (4) a 3,400-foot-                Accepted for Filing and Soliciting                    registration, using the eComment system
                                                  long, 69 or 115-kilovolt transmission                   Comments, Motions To Intervene, and                   at http://www.ferc.gov/docs-filing/
                                                  line interconnecting with the existing                  Competing Applications                                ecomment.asp. You must include your
                                                  Bonneville Power Administration Dixie                                                                         name and contact information at the end
                                                  Substation. The estimated annual                           On July 1, 2015, Blue River Hydro                  of your comments. For assistance,
                                                  generation for the Anderson Ranch                       Power, LLC filed an application for a                 please contact FERC Online Support at
                                                  project would be 175.2 gigawatt-hours.                  preliminary permit, pursuant to section               FERCOnlineSupport@ferc.gov, (866)
                                                     Applicant Contact for the Anderson                   4(f) of the Federal Power Act (FPA),                  208–3676 (toll free), or (202) 502–8659
mstockstill on DSK4VPTVN1PROD with NOTICES




                                                  Ranch project: Mr. Matthew Shapiro,                     proposing to study the feasibility of the             (TTY). In lieu of electronic filing, please
                                                  Owyhee Hydro, LLC, 1210 W. Franklin                     Blue River Hydroelectric Project (Blue                send a paper copy to: Secretary, Federal
                                                  St., Ste. 2, Boise, ID 83702; phone: (208)              River Project or project) to be located at            Energy Regulatory Commission, 888
                                                  246–9925.                                               Blue River Dam near the Town of Blue                  First Street NE., Washington, DC 20426.
                                                     FERC Contact: Karen Sughrue; phone:                  River in Lane County, Oregon. The sole                The first page of any filing should
                                                  (202) 502–8556.                                         purpose of a preliminary permit, if                   include docket number P–14690–000.
                                                     Deadline for filing comments, motions                issued, is to grant the permit holder                    More information about this project,
                                                  to intervene, competing applications                    priority to file a license application                including a copy of the application, can


                                             VerDate Sep<11>2014   16:57 Sep 03, 2015   Jkt 235001   PO 00000   Frm 00027   Fmt 4703   Sfmt 4703   E:\FR\FM\04SEN1.SGM   04SEN1


                                                  53512                       Federal Register / Vol. 80, No. 172 / Friday, September 4, 2015 / Notices

                                                  be viewed or printed on the ‘‘eLibrary’’                not serve to make protestants parties to              necessary, execute and record a
                                                  link of Commission’s Web site at                        the proceeding. Any person wishing to                 Declaration of Restrictive Covenant. The
                                                  http://www.ferc.gov/docs-filing/                        become a party must file a notice of                  settlement includes a covenant not to
                                                  elibrary.asp. Enter the docket number                   intervention or motion to intervene, as               sue the Settling Party pursuant to the
                                                  (P–14690) in the docket number field to                 appropriate. Such notices, motions, or                Comprehensive Environmental
                                                  access the document. For assistance,                    protests must be filed on or before the               Response, Compensation, and Liability
                                                  contact FERC Online Support.                            comment date. Anyone filing a motion                  Act or the Resource Conservation and
                                                    Dated: August 28, 2015.                               to intervene or protest must serve a copy             Recovery Act with respect to the
                                                                                                          of that document on the Petitioner.                   Existing Contamination. Existing
                                                  Kimberly D. Bose,
                                                                                                             The Commission encourages                          Contamination is defined as any
                                                  Secretary.                                                                                                    hazardous substances, pollutants, or
                                                                                                          electronic submission of protests and
                                                  [FR Doc. 2015–21987 Filed 9–3–15; 8:45 am]              interventions in lieu of paper using the              contaminants or Waste Material present
                                                  BILLING CODE 6717–01–P                                  ‘‘eFiling’’ link at http://www.ferc.gov.              or existing on or under the Property as
                                                                                                          Persons unable to file electronically                 of the Effective Date of the Settlement
                                                                                                          should submit an original and 5 copies                Agreement; any hazardous substances,
                                                  DEPARTMENT OF ENERGY                                    of the protest or intervention to the                 pollutants, or contaminants or Waste
                                                                                                          Federal Energy Regulatory Commission,                 Material that migrated from the Property
                                                  Federal Energy Regulatory
                                                                                                          888 First Street NE., Washington, DC                  prior to the Effective Date of the
                                                  Commission
                                                                                                          20426.                                                Settlement Agreement; and any
                                                  [Docket No. EL15–96–000]                                   This filing is accessible on-line at               hazardous substances, pollutants, or
                                                                                                          http://www.ferc.gov, using the                        contaminants or Waste Material
                                                  Backyard Farms Energy LLC,                              ‘‘eLibrary’’ link and is available for                presently at the Site that migrates onto,
                                                  Devonshire Energy LLC: Notice of                        review in the Commission’s Public                     on, under, or from the Property after the
                                                  Petition for Declaratory Order                          Reference Room in Washington, DC.                     Effective Date of the Settlement
                                                     Take notice that on August 27, 2015,                 There is an ‘‘eSubscription’’ link on the             Agreement.
                                                  in accordance with section 35.42(a)(2) of               Web site that enables subscribers to                     For thirty (30) days following the date
                                                  the regulations of the Federal Energy                   receive email notification when a                     of publication of this notice, the Agency
                                                  Regulatory Commission (Commission),                     document is added to a subscribed                     will receive written comments relating
                                                  18 CFR 35.42(a)(2), Order No. 652,1 and                 docket(s). For assistance with any FERC               to the settlement. The Agency will
                                                  Order No. 697,2 Backyard Farms Energy                   Online service, please email                          consider all comments received and
                                                  LLC and Devonshire Energy LLC (MBR                      FERCOnlineSupport@ferc.gov, or call                   may modify or withdraw its consent to
                                                  Entities), filed a petition for declaratory             (866) 208–3676 (toll free). For TTY, call             the settlement if comments received
                                                  order requesting that the Commission                    (202) 502–8659.                                       disclose facts or considerations which
                                                  find that the MBR Entities are not                         Comment Date: 5:00 p.m. Eastern time               indicate that the settlement is
                                                  affiliates of or under ‘‘common control’’               on September 28, 2015.                                inappropriate, improper, or inadequate.
                                                  with the Fidelity Accounts or FIL                         Dated: August 28, 2015.
                                                                                                                                                                The Agency’s response to any comments
                                                  Limited (FIL), or, in the alternative, that                                                                   received will be available for public
                                                                                                          Kimberly D. Bose,
                                                  even if such an affiliation is deemed to                                                                      inspection at the EPA, Region 5,
                                                                                                          Secretary.                                            Records Center, 77 W. Jackson Blvd.,
                                                  exist, investments by the Fidelity                      [FR Doc. 2015–21983 Filed 9–3–15; 8:45 am]
                                                  Accounts or FIL would not affect the                                                                          7th Fl., Chicago, Illinois 60604.
                                                                                                          BILLING CODE 6717–01–P
                                                  conditions relied upon by the                                                                                 DATES: Comments must be submitted on
                                                  Commission when granting market-                                                                              or before October 5, 2015.
                                                  based rate authorization to the extent                                                                        ADDRESSES: The proposed settlement is
                                                                                                          ENVIRONMENTAL PROTECTION                              available for public inspection at the
                                                  such investments are passive
                                                                                                          AGENCY                                                EPA, Region 5, Records Center, 77 W.
                                                  investments, as more fully described in
                                                  the petition.                                           [FRL–9933–59–Region 5]                                Jackson Blvd., 7th Fl., Chicago, Illinois
                                                     Any person desiring to intervene or to                                                                     60604. A copy of the proposed
                                                  protest this filing must file in                        Proposed Prospective Purchaser                        settlement may be obtained from Peter
                                                  accordance with Rules 211 and 214 of                    Agreement for the Delco Chassis                       Felitti, Assoc. Regional Counsel, EPA,
                                                  the Commission’s Rules of Practice and                  Industrial Land I & II Site in Livonia,               Office of Regional Counsel, Region 5, 77
                                                  Procedure (18 CFR 385.211, 385.214).                    Michigan                                              W. Jackson Blvd., Mail Code: C–14J,
                                                  Protests will be considered by the                      AGENCY: Environmental Protection                      Chicago, Illinois 60604. Comments
                                                  Commission in determining the                           Agency (EPA).                                         should reference the Delco Chassis
                                                  appropriate action to be taken, but will                                                                      Industrial Land I & II Site, Livonia,
                                                                                                          ACTION: Notice; request for public
                                                                                                                                                                Michigan and EPA Docket No. V–W–
                                                     1 Reporting Requirement for Changes in Status for
                                                                                                          comment.                                              15–C–024 and should be addressed to
                                                  Public Utilities With Market-Based Rate Authority,      SUMMARY:   In accordance with the                     Peter Felitti, Assoc. Regional Counsel,
                                                  Order No. 652, 70 FR 8253 (Feb. 18, 2005), reh’g,                                                             EPA, Office of Regional Counsel, Region
                                                  111 FERC ¶ 61,413 (2005).                               Prospective Purchaser Agreement,
                                                     2 Market-Based Rates for Wholesale Sales of          notice is hereby given of a proposed                  5, 77 W. Jackson Blvd., Mail Code: C–
                                                  Electric Energy, Capacity and Ancillary Services by     administrative settlement concerning a                14J, Chicago, Illinois 60604.
                                                  Public Utilities, Order No. 697, 72 FR 39904 (July                                                            FOR FURTHER INFORMATION CONTACT:
mstockstill on DSK4VPTVN1PROD with NOTICES




                                                                                                          portion of the Delco Chassis Industrial
                                                  20, 2007), clarified, 72 FR 72239 (Dec. 20, 2007),                                                            Peter Felitti, Assoc. Regional Counsel,
                                                  reh’g, Order No. 697–A, 73 FR 25832 (May 7, 2008)
                                                                                                          Land I & II Site in Livonia, Michigan
                                                  (‘‘Order No. 697–A’’), reh’g, 124 FERC ¶ 61,055         with the following settling party:                    EPA, Office of Regional Counsel, Region
                                                  (2008), reh’g, Order No. 697–B, 73 FR 79610 (Dec.       Livonia West Commerce Center, LLC.                    5, 77 W. Jackson Blvd., Mail Code: C–
                                                  30, 2008), reh’g, Order No. 697–C, 74 FR 30924          The settlement requires the Settling                  14J, Chicago, Illinois 60604.
                                                  (June 29, 2009), reh’g, Order No. 697–D, 57 FR
                                                  14342 (March 25, 2010), clarified 131 FERC ¶
                                                                                                          Party to provide access to the Property,              SUPPLEMENTARY INFORMATION: The
                                                  61,021 (2010), reh’g denied, 134 FERC ¶ 61,046          exercise due care with respect to                     Settling Party proposes to acquire
                                                  (2011), reh’g denied, 143 FERC ¶ 61,126 (2013).         existing contamination, and, if                       ownership of a portion of the former


                                             VerDate Sep<11>2014   16:57 Sep 03, 2015   Jkt 235001   PO 00000   Frm 00028   Fmt 4703   Sfmt 4703   E:\FR\FM\04SEN1.SGM   04SEN1



Document Created: 2015-12-15 09:58:09
Document Modified: 2015-12-15 09:58:09
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation80 FR 53511 

2024 Federal Register | Disclaimer | Privacy Policy