The Acting Administrator, Southwestern Power Administration (Southwestern), has prepared Current and Revised 2015 Power Repayment Studies for the Sam Rayburn Dam project which show the need for an increase in annual revenues to meet cost recovery criteria. Such increased revenues are needed primarily to cover the costs associated with increased operations and maintenance costs and increased interest expense associated with investments and replacements in the hydroelectric generating facilities. The Acting Administrator of Southwestern has developed a proposed Sam Rayburn Dam Rate Schedule, which is supported by power repayment studies, to recover the required revenues. The Revised 2015 Power Repayment Study indicates that the proposed Rate Schedule would increase annual revenues approximately 7.9 percent from $4,230,120 to $4,563,792 effective January 1, 2016 through September 30, 2019.

Federal Register, Volume 80 Issue 196 (Friday, October 9, 2015)
[Federal Register Volume 80, Number 196 (Friday, October 9, 2015)]
[Notices]
[Pages 61206-61207]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2015-25765]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Southwestern Power Administration


Sam Rayburn Dam Power Rate

AGENCY: Southwestern Power Administration, DOE.

ACTION: Notice of public review and comment.

-----------------------------------------------------------------------

SUMMARY: The Acting Administrator, Southwestern Power Administration 
(Southwestern), has prepared Current and Revised 2015 Power Repayment 
Studies for the Sam Rayburn Dam project which show the need for an 
increase in annual revenues to meet cost recovery criteria. Such 
increased revenues are needed primarily to cover the costs associated 
with increased operations and maintenance costs and increased interest 
expense associated with investments and replacements in the 
hydroelectric generating facilities. The Acting Administrator of 
Southwestern has developed a proposed Sam Rayburn Dam Rate Schedule, 
which is supported by power repayment studies, to recover the required 
revenues. The Revised 2015 Power Repayment Study indicates that the 
proposed Rate Schedule would increase annual revenues approximately 7.9 
percent from $4,230,120 to $4,563,792 effective January 1, 2016 through 
September 30, 2019.

DATES: The consultation and comment period will end on November 9, 
2015. If requested, a combined Public Information and Comment Forum 
(Forum) will be held in Tulsa, Oklahoma at 9:00 a.m. on October 22, 
2015. Persons desiring the Forum to be held must send a written request 
for such Forum to the Senior Vice President, Chief Operating Officer 
(see FOR FURTHER INFORMATION CONTACT) by October 16, 2015. If no 
request is received, the Forum will not be held.

ADDRESSES: If requested, the Forum will be held in Southwestern's 
offices, Room 1460, Williams Center Tower I, One West Third Street, 
Tulsa, Oklahoma 74103.

FOR FURTHER INFORMATION CONTACT: Marshall Boyken, Senior Vice 
President, Chief Operating Officer, Office of Corporate Operations, 
Southwestern Power Administration, U.S. Department of Energy, One West 
Third Street, Tulsa, Oklahoma 74103, (918) 595-6646, 
[email protected].

SUPPLEMENTARY INFORMATION: Originally established by Secretarial Order 
No. 1865 dated August 31, 1943, Southwestern is an agency within the 
U.S. Department of Energy created by the Department of Energy 
Organization Act, Public Law 95-91, dated August 4, 1977.
    Southwestern markets power from 24 multi-purpose reservoir projects 
with hydroelectric power facilities constructed and operated by the 
U.S. Army Corps of Engineers (Corps). These projects are located in the 
states of Arkansas, Missouri, Oklahoma, and Texas. Southwestern's 
marketing area includes these states plus Kansas and Louisiana. The 
costs associated with the hydropower facilities of 22 of the 24 
projects are repaid via revenues received under the Integrated System 
rates, as are the costs associated with Southwestern's transmission 
facilities that consist of 1,380 miles of high-voltage transmission 
lines, 25 substations, and 46 microwave and VHF radio sites. Costs 
associated with the Sam Rayburn and Robert D. Willis Dams, two Corps 
projects that are isolated hydraulically, electrically, and financially 
from the Integrated System, are repaid by separate rate schedules.

[[Page 61207]]

    Guidelines for preparation of power repayment studies are included 
in DOE Order No. RA 6120.2 entitled Power Marketing Administration 
Financial Reporting. Following DOE guidelines, Southwestern prepared a 
2015 Current Power Repayment Study using the existing Sam Rayburn Dam 
Rate Schedule.\1\ This study indicates that Southwestern's legal 
requirement to repay the investment in the power generating facility 
for power and energy marketed by Southwestern will not be met without 
an increase in revenues. The need for increased revenues is primarily 
due to increased operations and maintenance costs and increased 
interest expense associated with investments and replacements in the 
Corps hydroelectric generating facilities. The 2015 Revised Power 
Repayment Study shows that additional annual revenues of $333,672 (a 
7.9 percent increase), beginning January 1, 2016, are needed to satisfy 
repayment criteria.
---------------------------------------------------------------------------

    \1\ FERC, on February 6, 2014, confirmed and approved the 
existing Sam Rayburn Dam rate schedule for the period October 1 2013 
through September 30, 2017. See 146 FERC ] 62,105 (FERC Docket No. 
EF14-2-000).
---------------------------------------------------------------------------

    Southwestern will continue to perform its Power Repayment Studies 
annually, and if the 2016 results should indicate the need for 
additional revenues, another rate filing will be conducted and updated 
revenue requirements implemented for fiscal year 2017 and thereafter.
    Procedures for public participation in power and transmission rate 
adjustments of the Power Marketing Administrations are found at title 
10, part 903, subpart A of the Code of Federal Regulations (10 CFR part 
903). Southwestern's customers and other interested parties may request 
copies of the 2015 Sam Rayburn Dam Power Repayment Studies and the 
proposed Rate Schedule. Submit requests to the Director, Division of 
Resources and Rates, Office of Corporate Operations, Southwestern Power 
Administration, One West Third, Tulsa, OK 74103, (918) 595-6684 or via 
email to [email protected].
    If requested a Public Information and Comment Forum (Forum) will be 
held on October 22, 2015, to explain to customers and interested 
parties the proposed Rate Schedule and supporting 2015 Power Repayment 
Studies, and to allow for comment. A chairman, who will be responsible 
for orderly procedure, will conduct the Forum if requested. Questions 
concerning the rates, studies, and information presented at the Forum 
will be answered, to the extent possible, at the Forum. Questions not 
answered at the Forum will be answered in writing. Questions involving 
voluminous data contained in Southwestern's records may best be 
answered by consultation and review of pertinent records at 
Southwestern's offices.
    Persons requesting that a Forum be held should indicate in writing 
to the Senior Vice President and Chief Operating Officer (see FOR 
FURTHER INFORMATION CONTACT) by letter, email, or facsimile 
transmission (918-595-6646) by October 16, 2015, their request for such 
a Forum. If no request is received, no such Forum will be held. Persons 
interested in speaking at the Forum, if held, should submit a request 
to the Senior Vice President and Chief Operating Officer, Southwestern, 
at least seven (7) calendar days prior to the Forum so that a list of 
forum participants can be developed. The chairman may allow others to 
speak if time permits.
    A transcript of the Forum, if held, will be made. Copies of the 
transcript and all documents introduced will be available for review at 
Southwestern's offices (see ADDRESSES) during normal business hours. 
Copies of the transcript and all documents introduced may also be 
obtained, for a fee, from the transcribing service. A copy of all 
written comments or an electronic copy in MS Word on the proposed Sam 
Rayburn Dam Rate Schedule is due on or before November 9, 2015. 
Comments should be submitted to the Senior Vice President and Chief 
Operating Officer, Southwestern, (see FOR FURTHER INFORMATION CONTACT).
    Procedures for the confirmation and approval of rates for the 
Federal Power Marketing Administrations are found at title 18, part 
300, subpart L of the Code of Federal Regulations (18 CFR part 300). 
The Acting Administrator will review and consider oral and written 
comments and the information gathered in the course of the proceeding 
when submitting the finalized Sam Rayburn Dam Power Repayment Studies 
and Rate Schedule Proposal in support of the proposed rate to the 
Deputy Secretary of Energy for confirmation and approval on an interim 
basis, and subsequently to the Federal Energy Regulatory Commission for 
confirmation and approval on a final basis.
    Once submitted for final confirmation and approval, the Commission 
will allow the public an opportunity to provide written comments on the 
proposed rate increase before making a final decision.

    Dated: September 30, 2015.
Scott Carpenter,
Acting Administrator.
[FR Doc. 2015-25765 Filed 10-8-15; 8:45 am]
BILLING CODE 6450-01-P



                                              61206                          Federal Register / Vol. 80, No. 196 / Friday, October 9, 2015 / Notices

                                              requirement ($50,670 or 4.3 percent).                   hours. Copies of the transcript and all               which is supported by power repayment
                                              Southwestern will continue to perform                   documents introduced may also be                      studies, to recover the required
                                              its Power Repayment Studies annually,                   obtained, for a fee, from the transcribing            revenues. The Revised 2015 Power
                                              and if the 2016 results should indicate                 service. A copy of all written comments               Repayment Study indicates that the
                                              the need for additional revenues,                       or an electronic copy in MS Word on                   proposed Rate Schedule would increase
                                              another rate filing will be conducted                   the proposed Robert D. Willis Rate                    annual revenues approximately 7.9
                                              and updated revenue requirements                        Schedule is due on or before November                 percent from $4,230,120 to $4,563,792
                                              implemented for fiscal year 2017 and                    9, 2015. Comments should be submitted                 effective January 1, 2016 through
                                              thereafter.                                             to the Senior Vice President and Chief                September 30, 2019.
                                                 Procedures for public participation in               Operating Officer, Southwestern, (see                 DATES: The consultation and comment
                                              power and transmission rate                             FOR FURTHER INFORMATION CONTACT).                     period will end on November 9, 2015.
                                              adjustments of the Power Marketing                         Procedures for the confirmation and                If requested, a combined Public
                                              Administrations are found at title 10,                  approval of rates for the Federal Power               Information and Comment Forum
                                              part 903, subpart A of the Code of                      Marketing Administrations are found at                (Forum) will be held in Tulsa,
                                              Federal Regulations (10 CFR part 903).                  title 18, part 300, subpart L of the Code             Oklahoma at 9:00 a.m. on October 22,
                                              Southwestern’s customers and other                      of Federal Regulations (18 CFR part                   2015. Persons desiring the Forum to be
                                              interested parties may request copies of                300). The Acting Administrator will                   held must send a written request for
                                              the 2015 Robert D. Willis Power                         review and consider oral and written                  such Forum to the Senior Vice
                                              Repayment Studies and the proposed                      comments and the information gathered                 President, Chief Operating Officer (see
                                              Rate Schedule. Submit requests to the                   in the course of the proceeding when                  FOR FURTHER INFORMATION CONTACT) by
                                              Director, Division of Resources and                     submitting the finalized Robert D. Willis             October 16, 2015. If no request is
                                              Rates, Office of Corporate Operations,                  Power Repayment Studies and Rate                      received, the Forum will not be held.
                                              Southwestern Power Administration,                      Schedule Proposal in support of the
                                              One West Third, Tulsa, OK 74103, (918)                                                                        ADDRESSES: If requested, the Forum will
                                                                                                      proposed rate to the Deputy Secretary of
                                              595–6684 or via email to swparates@                     Energy for confirmation and approval                  be held in Southwestern’s offices, Room
                                              swpa.gov.                                               on an interim basis, and subsequently to              1460, Williams Center Tower I, One
                                                 If requested a Public Information and                the Federal Energy Regulatory                         West Third Street, Tulsa, Oklahoma
                                              Comment Forum (Forum) will be held                      Commission for confirmation and                       74103.
                                              on October 28, 2015, to explain to                      approval on a final basis. Once                       FOR FURTHER INFORMATION CONTACT:
                                              customers and interested parties the                    submitted for final confirmation and                  Marshall Boyken, Senior Vice President,
                                              proposed Rate Schedule and supporting                   approval, the Commission will allow                   Chief Operating Officer, Office of
                                              2015 Power Repayment Studies, and to                    the public an opportunity to provide                  Corporate Operations, Southwestern
                                              allow for comment. A chairman, who                      written comments on the proposed rate                 Power Administration, U.S. Department
                                              will be responsible for orderly                         increase before making a final decision.              of Energy, One West Third Street, Tulsa,
                                              procedure, will conduct the Forum if                                                                          Oklahoma 74103, (918) 595–6646,
                                              requested. Questions concerning the                       Dated: September 30, 2015.
                                                                                                      Scott Carpenter,                                      marshall.boyken@swpa.gov.
                                              rates, studies, and information
                                              presented at the Forum will be                          Acting Administrator.                                 SUPPLEMENTARY INFORMATION: Originally
                                              answered, to the extent possible, at the                [FR Doc. 2015–25644 Filed 10–8–15; 8:45 am]           established by Secretarial Order No.
                                              Forum. Questions not answered at the                    BILLING CODE 6450–01–P
                                                                                                                                                            1865 dated August 31, 1943,
                                              Forum will be answered in writing.                                                                            Southwestern is an agency within the
                                              Questions involving voluminous data                                                                           U.S. Department of Energy created by
                                              contained in Southwestern’s records                     DEPARTMENT OF ENERGY                                  the Department of Energy Organization
                                              may best be answered by consultation                                                                          Act, Public Law 95–91, dated August 4,
                                              and review of pertinent records at                      Southwestern Power Administration                     1977.
                                              Southwestern’s offices.                                                                                          Southwestern markets power from 24
                                                 Persons requesting that a Forum be                   Sam Rayburn Dam Power Rate                            multi-purpose reservoir projects with
                                              held should indicate in writing to the                  AGENCY: Southwestern Power                            hydroelectric power facilities
                                              Senior Vice President and Chief                         Administration, DOE.                                  constructed and operated by the U.S.
                                              Operating Officer (see FOR FURTHER                      ACTION: Notice of public review and                   Army Corps of Engineers (Corps). These
                                              INFORMATION CONTACT) by letter, email,                  comment.                                              projects are located in the states of
                                              or facsimile transmission (918–595–                                                                           Arkansas, Missouri, Oklahoma, and
                                              6646) by October 16, 2015, their request                SUMMARY:   The Acting Administrator,                  Texas. Southwestern’s marketing area
                                              for such a Forum. If no request is                      Southwestern Power Administration                     includes these states plus Kansas and
                                              received, no such Forum will be held.                   (Southwestern), has prepared Current                  Louisiana. The costs associated with the
                                              Persons interested in speaking at the                   and Revised 2015 Power Repayment                      hydropower facilities of 22 of the 24
                                              Forum, if held, should submit a request                 Studies for the Sam Rayburn Dam                       projects are repaid via revenues
                                              to the Senior Vice President and Chief                  project which show the need for an                    received under the Integrated System
                                              Operating Officer, Southwestern, at least               increase in annual revenues to meet cost              rates, as are the costs associated with
                                              seven (7) calendar days prior to the                    recovery criteria. Such increased                     Southwestern’s transmission facilities
                                              Forum so that a list of forum                           revenues are needed primarily to cover                that consist of 1,380 miles of high-
                                              participants can be developed. The                      the costs associated with increased                   voltage transmission lines, 25
tkelley on DSK3SPTVN1PROD with NOTICES




                                              chairman may allow others to speak if                   operations and maintenance costs and                  substations, and 46 microwave and VHF
                                              time permits.                                           increased interest expense associated                 radio sites. Costs associated with the
                                                 A transcript of the Forum, if held, will             with investments and replacements in                  Sam Rayburn and Robert D. Willis
                                              be made. Copies of the transcript and all               the hydroelectric generating facilities.              Dams, two Corps projects that are
                                              documents introduced will be available                  The Acting Administrator of                           isolated hydraulically, electrically, and
                                              for review at Southwestern’s offices (see               Southwestern has developed a proposed                 financially from the Integrated System,
                                              ADDRESSES) during normal business                       Sam Rayburn Dam Rate Schedule,                        are repaid by separate rate schedules.


                                         VerDate Sep<11>2014   17:44 Oct 08, 2015   Jkt 238001   PO 00000   Frm 00052   Fmt 4703   Sfmt 4703   E:\FR\FM\09OCN1.SGM   09OCN1


                                                                             Federal Register / Vol. 80, No. 196 / Friday, October 9, 2015 / Notices                                                61207

                                                 Guidelines for preparation of power                  Forum will be answered in writing.                      Dated: September 30, 2015.
                                              repayment studies are included in DOE                   Questions involving voluminous data                   Scott Carpenter,
                                              Order No. RA 6120.2 entitled Power                      contained in Southwestern’s records                   Acting Administrator.
                                              Marketing Administration Financial                      may best be answered by consultation                  [FR Doc. 2015–25765 Filed 10–8–15; 8:45 am]
                                              Reporting. Following DOE guidelines,                    and review of pertinent records at                    BILLING CODE 6450–01–P
                                              Southwestern prepared a 2015 Current                    Southwestern’s offices.
                                              Power Repayment Study using the
                                              existing Sam Rayburn Dam Rate                              Persons requesting that a Forum be
                                                                                                      held should indicate in writing to the                ENVIRONMENTAL PROTECTION
                                              Schedule.1 This study indicates that                                                                          AGENCY
                                              Southwestern’s legal requirement to                     Senior Vice President and Chief
                                              repay the investment in the power                       Operating Officer (see FOR FURTHER                    [ER–FRL–9023–4]
                                              generating facility for power and energy                INFORMATION CONTACT) by letter, email,
                                              marketed by Southwestern will not be                    or facsimile transmission (918–595–                   Environmental Impact Statements;
                                              met without an increase in revenues.                    6646) by October 16, 2015, their request              Notice of Availability
                                              The need for increased revenues is                      for such a Forum. If no request is                      Responsible Agency: Office of Federal,
                                              primarily due to increased operations                   received, no such Forum will be held.                 Activities, General Information (202)
                                              and maintenance costs and increased                     Persons interested in speaking at the                 564–7146 or http://www2.epa.gov/nepa.
                                              interest expense associated with                        Forum, if held, should submit a request               Weekly receipt of Environmental Impact
                                              investments and replacements in the                     to the Senior Vice President and Chief                  Statements (EISs)
                                              Corps hydroelectric generating facilities.              Operating Officer, Southwestern, at least             Filed 09/28/2015 Through 10/02/2015
                                              The 2015 Revised Power Repayment                        seven (7) calendar days prior to the                  Pursuant to 40 CFR 1506.9.
                                              Study shows that additional annual                      Forum so that a list of forum
                                              revenues of $333,672 (a 7.9 percent                                                                           Notice
                                                                                                      participants can be developed. The
                                              increase), beginning January 1, 2016, are               chairman may allow others to speak if                   Section 309(a) of the Clean Air Act
                                              needed to satisfy repayment criteria.                   time permits.                                         requires that EPA make public its
                                                 Southwestern will continue to                                                                              comments on EISs issued by other
                                              perform its Power Repayment Studies                        A transcript of the Forum, if held, will           Federal agencies. EPA’s comment letters
                                              annually, and if the 2016 results should                be made. Copies of the transcript and all             on EISs are available at: https://
                                              indicate the need for additional                        documents introduced will be available                cdxnodengn.epa.gov/cdx-enepa-public/
                                              revenues, another rate filing will be                   for review at Southwestern’s offices (see             action/eis/search.
                                              conducted and updated revenue                           ADDRESSES) during normal business                     EIS No. 20150284, Draft, NPS, CA,
                                              requirements implemented for fiscal                     hours. Copies of the transcript and all                 Scorpion Pier Replacement, Comment
                                              year 2017 and thereafter.                               documents introduced may also be                        Period Ends: 12/18/2015, Contact:
                                                 Procedures for public participation in               obtained, for a fee, from the transcribing              Karl Bachman 805–658–5700.
                                              power and transmission rate                             service. A copy of all written comments               EIS No. 20150285, Final, FERC, OR,
                                              adjustments of the Power Marketing                      or an electronic copy in MS Word on                     Jordan Cove Energy and Pacific
                                              Administrations are found at title 10,                  the proposed Sam Rayburn Dam Rate                       Connector Gas Pipeline Project,
                                              part 903, subpart A of the Code of                      Schedule is due on or before November                   Review Period Ends: 11/08/2015,
                                              Federal Regulations (10 CFR part 903).                  9, 2015. Comments should be submitted                   Contact: Paul Friedman 202–502–
                                              Southwestern’s customers and other                      to the Senior Vice President and Chief                  8059.
                                              interested parties may request copies of                Operating Officer, Southwestern, (see                 EIS No. 20150286, Draft, FERC, ID, Bear
                                              the 2015 Sam Rayburn Dam Power                          FOR FURTHER INFORMATION CONTACT).                       River Narrows Hydroelectric Project-
                                              Repayment Studies and the proposed                                                                              FERC Project 12486–008, Comment
                                              Rate Schedule. Submit requests to the                      Procedures for the confirmation and                  Period Ends: 11/30/2015, Contact:
                                              Director, Division of Resources and                     approval of rates for the Federal Power                 Shana Murray 202–502–8333.
                                              Rates, Office of Corporate Operations,                  Marketing Administrations are found at                EIS No. 20150287, Draft, NGA, MO,
                                              Southwestern Power Administration,                      title 18, part 300, subpart L of the Code               Next NGA West Campus in the
                                              One West Third, Tulsa, OK 74103, (918)                  of Federal Regulations (18 CFR part                     Greater St. Louis Metropolitan Area,
                                              595–6684 or via email to swparates@                     300). The Acting Administrator will                     Comment Period Ends: 11/23/2015,
                                              swpa.gov.                                               review and consider oral and written                    Contact: David Berczek (NGA) 314–
                                                 If requested a Public Information and                comments and the information gathered                   676–1123 and Amy Blair (COE) 816–
                                              Comment Forum (Forum) will be held                      in the course of the proceeding when                    389–3393.
                                              on October 22, 2015, to explain to                      submitting the finalized Sam Rayburn                  EIS No. 20150288, Draft, USACE, NE.,
                                              customers and interested parties the                    Dam Power Repayment Studies and                         Nebraska Highway 12 Niobrara East
                                              proposed Rate Schedule and supporting                   Rate Schedule Proposal in support of                    and West, Comment Period Ends: 11/
                                              2015 Power Repayment Studies, and to                    the proposed rate to the Deputy                         23/2015, Contact: Rebecca J. Latka
                                              allow for comment. A chairman, who                      Secretary of Energy for confirmation and                402–995–2681.
                                              will be responsible for orderly                         approval on an interim basis, and
                                              procedure, will conduct the Forum if                                                                          Amended Notices
                                                                                                      subsequently to the Federal Energy
                                              requested. Questions concerning the                                                                           EIS No. 20150207, Draft, DOE, NH,
                                                                                                      Regulatory Commission for
                                              rates, studies, and information                                                                                 Northern Pass Transmission Line
                                                                                                      confirmation and approval on a final
                                              presented at the Forum will be                                                                                  Project, Comment Period Ends: 12/31/
                                                                                                      basis.
tkelley on DSK3SPTVN1PROD with NOTICES




                                              answered, to the extent possible, at the                                                                        2015, Contact: Brian Mills 202–586–
                                              Forum. Questions not answered at the                       Once submitted for final confirmation                8267 Revision to FR Notice Published
                                                                                                      and approval, the Commission will                       07/24/2015; Extending Comment
                                                1 FERC, on February 6, 2014, confirmed and            allow the public an opportunity to                      Period from 10/29/2015 to 12/31/
                                              approved the existing Sam Rayburn Dam rate              provide written comments on the
                                              schedule for the period October 1 2013 through
                                                                                                                                                              20115.
                                              September 30, 2017. See 146 FERC ¶ 62,105 (FERC         proposed rate increase before making a                EIS No. 20150264, Final, FHWA, TN,
                                              Docket No. EF14–2–000).                                 final decision.                                         Pellissippi Parkway Extension (State


                                         VerDate Sep<11>2014   17:44 Oct 08, 2015   Jkt 238001   PO 00000   Frm 00053   Fmt 4703   Sfmt 4703   E:\FR\FM\09OCN1.SGM   09OCN1



Document Created: 2015-12-15 08:34:05
Document Modified: 2015-12-15 08:34:05
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
ActionNotice of public review and comment.
DatesThe consultation and comment period will end on November 9, 2015. If requested, a combined Public Information and Comment Forum (Forum) will be held in Tulsa, Oklahoma at 9:00 a.m. on October 22, 2015. Persons desiring the Forum to be held must send a written request for such Forum to the Senior Vice President, Chief Operating Officer (see FOR FURTHER INFORMATION CONTACT) by October 16, 2015. If no request is received, the Forum will not be held.
ContactMarshall Boyken, Senior Vice President, Chief Operating Officer, Office of Corporate Operations, Southwestern Power Administration, U.S. Department of Energy, One West Third Street, Tulsa, Oklahoma 74103, (918) 595-6646, [email protected]
FR Citation80 FR 61206 