80_FR_66204 80 FR 65996 - Northern Natural Gas Company; Notice of Intent to Prepare an Environmental Assessment for the Proposed Gaines County Crossover Compressor Station and Request for Comments on Environmental Issues

80 FR 65996 - Northern Natural Gas Company; Notice of Intent to Prepare an Environmental Assessment for the Proposed Gaines County Crossover Compressor Station and Request for Comments on Environmental Issues

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 80, Issue 208 (October 28, 2015)

Page Range65996-65997
FR Document2015-27398

Federal Register, Volume 80 Issue 208 (Wednesday, October 28, 2015)
[Federal Register Volume 80, Number 208 (Wednesday, October 28, 2015)]
[Notices]
[Pages 65996-65997]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2015-27398]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP15-552-000]


Northern Natural Gas Company; Notice of Intent to Prepare an 
Environmental Assessment for the Proposed Gaines County Crossover 
Compressor Station and Request for Comments on Environmental Issues

    The staff of the Federal Energy Regulatory Commission (FERC or 
Commission) will prepare an environmental assessment (EA) that will 
discuss the environmental impacts of the Gaines County Crossover 
Compressor Station (Project) involving construction and operation of 
facilities by Northern Natural Gas Company (Northern) in Gaines County, 
Texas. The Commission will use this EA in its decision-making process 
to determine whether the Project is in the public convenience and 
necessity.
    This notice announces the opening of the scoping process the 
Commission will use to gather input from the public and interested 
agencies on the Project. You can make a difference by providing us with 
your specific comments or concerns about the Project. Your comments 
should focus on the potential environmental effects, reasonable 
alternatives, and measures to avoid or lessen environmental impacts. 
Your input will help the Commission staff determine what issues they 
need to evaluate in the EA. To ensure that your comments are timely and 
properly recorded, please send your comments so that the Commission 
receives them in Washington, DC on or before November 23, 2015.
    If you sent comments on this Project to the Commission before the 
opening of this docket on September 9, 2015, you will need to file 
those comments in Docket No. CP15-552-000 to ensure they are considered 
as part of this proceeding.
    This notice is being sent to the Commission's current environmental 
mailing list for this Project. State and local government 
representatives should notify their constituents of this proposed 
Project and encourage them to comment on their areas of concern.
    If you are a landowner receiving this notice, a Northern 
representative may contact you about the acquisition of an easement to 
construct, operate, and maintain the proposed facilities. The company 
would seek to negotiate a mutually acceptable agreement. However, if 
the Commission approves the Project, that approval conveys with it the 
right of eminent domain. Therefore, if easement negotiations fail to 
produce an agreement, the pipeline company could initiate condemnation 
proceedings where compensation would be determined in accordance with 
state law.
    Northern has provided landowners with a fact sheet prepared by the 
FERC entitled ``An Interstate Natural Gas Facility On My Land? What Do 
I Need To Know?'' This fact sheet addresses a number of typically asked 
questions, including the use of eminent domain and how to participate 
in the Commission's proceedings. It is also available for viewing on 
the FERC Web site (www.ferc.gov/resources/guides/gas/gas.pdf).

Public Participation

    For your convenience, there are three methods you can use to submit 
your comments to the Commission. The Commission encourages electronic 
filing of comments and has expert staff available to assist you at 
(202) 502-8258 or [email protected]. Please carefully follow these 
instructions so that your comments are properly recorded.
    (1) You can file your comments electronically using the eComment 
feature on the Commission's Web site (www.ferc.gov) under the link to 
Documents and Filings. This is an easy method for submitting brief, 
text-only comments on a project;
    (2) You can file your comments electronically by using the eFiling 
feature on the Commission's Web site (www.ferc.gov) under the link to 
Documents and Filings. With eFiling, you can provide comments in a 
variety of formats by attaching them as a file with your submission. 
New eFiling users must first create an account by clicking on 
``eRegister.'' If you are filing a comment on a particular project, 
please select ``Comment on a Filing'' as the filing type; or
    (3) You can file a paper copy of your comments by mailing them to 
the following address. Be sure to reference the Project docket number 
(CP15-552-000) with your submission:
Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 
First Street NE., Room 1A, Washington, DC 20426.

Summary of the Proposed Project

    Northern proposes to construct and operate a new compressor station 
in Gaines County, Texas. The Project would include two new natural gas-
fired turbine compressor units rated at approximately 18,089 horsepower 
(HP) and would deliver about 210 million standard cubic feet of natural 
gas per day to supply natural gas for electrical power plants.
    If approved as proposed, the Project would include installation of 
two units: (1) Solar Taurus 70-10802S with approximately 11,152 HP; and 
(2) Solar Taurus 60-7302S with approximately 6,937 HP. The suction side 
of the compressor station would be connected to the existing 30-inch-
diameter Spraberry to Plains pipeline. The station would discharge to 
the existing 30-inch-diameter Kermit to Beaver pipeline. The proposed 
Project would also include the installation of two compressor 
buildings, a control building, an auxiliary building, a septic system 
and associated above-grade and below-grade piping, and valves and 
instrumentation.
    The general location of the proposed Project facilities is shown in 
appendix 1.\1\
---------------------------------------------------------------------------

    \1\ The appendices referenced in this notice will not appear in 
the Federal Register. Copies of appendices were sent to all those 
receiving this notice in the mail and are available at www.ferc.gov 
using the link called ``eLibrary'' or from the Commission's Public 
Reference Room, 888 First Street NE., Washington, DC 20426, or call 
(202) 502-8371. For instructions on connecting to eLibrary, refer to 
the last page of this notice.
---------------------------------------------------------------------------

Land Requirements for Construction

    Construction of the proposed Project facilities and temporary 
workspace would disturb approximately 27.8 acres of land. The total 
acreage maintained for permanent operation of the compressor station 
would be approximately 20 acres of land. Northern would acquire an 
approximately 20-acre site for the new compressor station and access 
road. The predominant land use that would be impacted by the proposed 
Project is agricultural and fallow cropland.

The EA Process

    The National Environmental Policy Act (NEPA) requires the 
Commission to take into account the environmental impacts that could 
result from an action whenever it considers the issuance of a 
Certificate of Public Convenience and

[[Page 65997]]

Necessity. NEPA also requires us \2\ to discover and address concerns 
the public may have about proposals. This process is referred to as 
``scoping.'' The main goal of the scoping process is to focus the 
analysis in the EA on the important environmental issues. By this 
notice, the Commission requests public comments on the scope of the 
issues to address in the EA. We will consider all filed comments during 
the preparation of the EA.
---------------------------------------------------------------------------

    \2\ ``We,'' ``us,'' and ``our'' refer to the environmental staff 
of the Commission's Office of Energy Projects.
---------------------------------------------------------------------------

    In the EA we will discuss impacts that could occur as a result of 
the construction and operation of the proposed Project under these 
general headings:
     geology and soils;
     land use;
     water resources, fisheries, and wetlands;
     cultural resources;
     vegetation and wildlife;
     air quality and noise;
     endangered and threatened species;
     public safety; and
     cumulative impacts
    We will also evaluate reasonable alternatives to the proposed 
Project or portions of the Project, and make recommendations on how to 
lessen or avoid impacts on the various resource areas.
    The EA will present our independent analysis of the issues. The EA 
will be available in the public record through eLibrary. Depending on 
the comments received during the scoping process, we may also publish 
and distribute the EA to the public for an allotted comment period. We 
will consider all comments on the EA before making our recommendations 
to the Commission. To ensure we have the opportunity to consider and 
address your comments, please carefully follow the instructions in the 
Public Participation section, beginning on page 2.
    With this notice, we are asking agencies with jurisdiction by law 
and/or special expertise with respect to the environmental issues of 
this Project to formally cooperate with us in the preparation of the 
EA.\3\ Agencies that would like to request cooperating agency status 
should follow the instructions for filing comments provided under the 
Public Participation section of this notice.
---------------------------------------------------------------------------

    \3\ The Council on Environmental Quality regulations addressing 
cooperating agency responsibilities are at Title 40, Code of Federal 
Regulations, Part 1501.6.
---------------------------------------------------------------------------

Consultations Under Section 106 of the National Historic Preservation 
Act

    In accordance with the Advisory Council on Historic Preservation's 
implementing regulations for section 106 of the National Historic 
Preservation Act, we are using this notice to initiate consultation 
with the applicable State Historic Preservation Office (SHPO), and to 
solicit their views and those of other government agencies, interested 
Indian tribes, and the public on the Project's potential effects on 
historic properties.\4\ We will define the Project-specific Area of 
Potential Effects (APE) in consultation with the SHPO as the Project 
develops. On natural gas facility projects, the APE at a minimum 
encompasses all areas subject to ground disturbance (examples include 
construction right-of-way, contractor/pipe storage yards, compressor 
stations, and access roads). Our EA for this Project will document our 
findings on the impacts on historic properties and summarize the status 
of consultations under section 106.
---------------------------------------------------------------------------

    \4\ The Advisory Council on Historic Preservation's regulations 
are at Title 36, Code of Federal Regulations, Part 800. Those 
regulations define historic properties as any prehistoric or 
historic district, site, building, structure, or object included in 
or eligible for inclusion in the National Register of Historic 
Places.
---------------------------------------------------------------------------

Environmental Mailing List

    The environmental mailing list includes: Federal, state, and local 
government representatives and agencies; elected officials; 
environmental and public interest groups; Native American Tribes; other 
interested parties; and local libraries and newspapers. This list also 
includes all affected landowners (as defined in the Commission's 
regulations) who are potential right-of-way grantors, whose property 
may be used temporarily for Project purposes, or who own homes within 
certain distances of aboveground facilities, and anyone who submits 
comments on the Project. We will update the environmental mailing list 
as the analysis proceeds to ensure that we send the information related 
to this environmental review to all individuals, organizations, and 
government entities interested in and/or potentially affected by the 
proposed Project.
    If we publish and distribute the EA, copies will be sent to the 
environmental mailing list for public review and comment. If you would 
prefer to receive a paper copy of the document instead of the CD 
version or would like to remove your name from the mailing list, please 
return the attached Information Request (Appendix 2).

Becoming an Intervenor

    In addition to involvement in the EA scoping process, you may want 
to become an ``intervenor'' which is an official party to the 
Commission's proceeding. Intervenors play a more formal role in the 
process and are able to file briefs, appear at hearings, and be heard 
by the courts if they choose to appeal the Commission's final ruling. 
An intervenor formally participates in the proceeding by filing a 
request to intervene. Instructions for becoming an intervenor are in 
the ``Document-less Intervention Guide'' under the ``e-filing'' link on 
the Commission's Web site. Motions to intervene are more fully 
described at http://www.ferc.gov/resources/guides/how-to/intervene.asp.

Additional Information

    Additional information about the Project is available from the 
Commission's Office of External Affairs, at (866) 208-FERC, or on the 
FERC Web site at www.ferc.gov using the ``eLibrary'' link. Click on the 
eLibrary link, click on ``General Search'' and enter the docket number, 
excluding the last three digits in the Docket Number field (i.e., CP15-
552). Be sure you have selected an appropriate date range. For 
assistance, please contact FERC Online Support at 
[email protected] or toll free at (866) 208-3676, or for TTY, 
contact (202) 502-8659. The eLibrary link also provides access to the 
texts of formal documents issued by the Commission, such as orders, 
notices, and rulemakings.
    In addition, the Commission offers a free service called 
eSubscription which allows you to keep track of all formal issuances 
and submittals in specific dockets. This can reduce the amount of time 
you spend researching proceedings by automatically providing you with 
notification of these filings, document summaries, and direct links to 
the documents. Go to www.ferc.gov/docs-filing/esubscription.asp.
    Finally, public meetings or site visits will be posted on the 
Commission's calendar located at www.ferc.gov/EventCalendar/EventsList.aspx along with other related information.

    Dated: October 22, 2015.
Kimberly D. Bose,
Secretary.
[FR Doc. 2015-27398 Filed 10-27-15; 8:45 am]
 BILLING CODE 6717-01-P



                                                  65996                     Federal Register / Vol. 80, No. 208 / Wednesday, October 28, 2015 / Notices

                                                  send a paper copy to: Secretary, Federal                local government representatives should               Kimberly D. Bose, Secretary, Federal
                                                  Energy Regulatory Commission, 888                       notify their constituents of this                       Energy Regulatory Commission, 888
                                                  First Street NE., Washington, DC 20426.                 proposed Project and encourage them to                  First Street NE., Room 1A,
                                                  The first page of any filing should                     comment on their areas of concern.                      Washington, DC 20426.
                                                  include docket number P–2790–064.                          If you are a landowner receiving this
                                                                                                          notice, a Northern representative may                 Summary of the Proposed Project
                                                    Dated: October 22, 2015.
                                                  Kimberly D. Bose,                                       contact you about the acquisition of an                  Northern proposes to construct and
                                                                                                          easement to construct, operate, and                   operate a new compressor station in
                                                  Secretary.
                                                                                                          maintain the proposed facilities. The                 Gaines County, Texas. The Project
                                                  [FR Doc. 2015–27404 Filed 10–27–15; 8:45 am]
                                                                                                          company would seek to negotiate a                     would include two new natural gas-
                                                  BILLING CODE 6717–01–P
                                                                                                          mutually acceptable agreement.                        fired turbine compressor units rated at
                                                                                                          However, if the Commission approves                   approximately 18,089 horsepower (HP)
                                                                                                          the Project, that approval conveys with               and would deliver about 210 million
                                                  DEPARTMENT OF ENERGY
                                                                                                          it the right of eminent domain.                       standard cubic feet of natural gas per
                                                  Federal Energy Regulatory                               Therefore, if easement negotiations fail              day to supply natural gas for electrical
                                                  Commission                                              to produce an agreement, the pipeline                 power plants.
                                                                                                          company could initiate condemnation
                                                  [Docket No. CP15–552–000]                               proceedings where compensation would                     If approved as proposed, the Project
                                                                                                          be determined in accordance with state                would include installation of two units:
                                                  Northern Natural Gas Company; Notice                    law.                                                  (1) Solar Taurus 70–10802S with
                                                  of Intent to Prepare an Environmental                                                                         approximately 11,152 HP; and (2) Solar
                                                                                                             Northern has provided landowners
                                                  Assessment for the Proposed Gaines                                                                            Taurus 60–7302S with approximately
                                                                                                          with a fact sheet prepared by the FERC
                                                  County Crossover Compressor Station                                                                           6,937 HP. The suction side of the
                                                                                                          entitled ‘‘An Interstate Natural Gas
                                                  and Request for Comments on                                                                                   compressor station would be connected
                                                                                                          Facility On My Land? What Do I Need
                                                  Environmental Issues                                                                                          to the existing 30-inch-diameter
                                                                                                          To Know?’’ This fact sheet addresses a
                                                     The staff of the Federal Energy                      number of typically asked questions,                  Spraberry to Plains pipeline. The station
                                                  Regulatory Commission (FERC or                          including the use of eminent domain                   would discharge to the existing 30-inch-
                                                  Commission) will prepare an                             and how to participate in the                         diameter Kermit to Beaver pipeline. The
                                                  environmental assessment (EA) that will                 Commission’s proceedings. It is also                  proposed Project would also include the
                                                  discuss the environmental impacts of                    available for viewing on the FERC Web                 installation of two compressor
                                                  the Gaines County Crossover                             site (www.ferc.gov/resources/guides/                  buildings, a control building, an
                                                  Compressor Station (Project) involving                  gas/gas.pdf).                                         auxiliary building, a septic system and
                                                  construction and operation of facilities                                                                      associated above-grade and below-grade
                                                                                                          Public Participation                                  piping, and valves and instrumentation.
                                                  by Northern Natural Gas Company
                                                  (Northern) in Gaines County, Texas. The                   For your convenience, there are three                  The general location of the proposed
                                                  Commission will use this EA in its                      methods you can use to submit your                    Project facilities is shown in appendix
                                                  decision-making process to determine                    comments to the Commission. The                       1.1
                                                  whether the Project is in the public                    Commission encourages electronic filing
                                                                                                          of comments and has expert staff                      Land Requirements for Construction
                                                  convenience and necessity.
                                                     This notice announces the opening of                 available to assist you at (202) 502–8258               Construction of the proposed Project
                                                  the scoping process the Commission                      or efiling@ferc.gov. Please carefully                 facilities and temporary workspace
                                                  will use to gather input from the public                follow these instructions so that your                would disturb approximately 27.8 acres
                                                  and interested agencies on the Project.                 comments are properly recorded.                       of land. The total acreage maintained for
                                                  You can make a difference by providing                     (1) You can file your comments                     permanent operation of the compressor
                                                  us with your specific comments or                       electronically using the eComment                     station would be approximately 20 acres
                                                  concerns about the Project. Your                        feature on the Commission’s Web site                  of land. Northern would acquire an
                                                  comments should focus on the potential                  (www.ferc.gov) under the link to                      approximately 20-acre site for the new
                                                  environmental effects, reasonable                       Documents and Filings. This is an easy                compressor station and access road. The
                                                  alternatives, and measures to avoid or                  method for submitting brief, text-only                predominant land use that would be
                                                  lessen environmental impacts. Your                      comments on a project;                                impacted by the proposed Project is
                                                  input will help the Commission staff                       (2) You can file your comments                     agricultural and fallow cropland.
                                                  determine what issues they need to                      electronically by using the eFiling
                                                  evaluate in the EA. To ensure that your                 feature on the Commission’s Web site                  The EA Process
                                                  comments are timely and properly                        (www.ferc.gov) under the link to
                                                                                                          Documents and Filings. With eFiling,                    The National Environmental Policy
                                                  recorded, please send your comments so
                                                                                                          you can provide comments in a variety                 Act (NEPA) requires the Commission to
                                                  that the Commission receives them in
                                                                                                          of formats by attaching them as a file                take into account the environmental
                                                  Washington, DC on or before November
                                                                                                          with your submission. New eFiling                     impacts that could result from an action
                                                  23, 2015.
                                                                                                          users must first create an account by                 whenever it considers the issuance of a
                                                     If you sent comments on this Project
                                                                                                          clicking on ‘‘eRegister.’’ If you are filing          Certificate of Public Convenience and
                                                  to the Commission before the opening of
                                                                                                          a comment on a particular project,
mstockstill on DSK4VPTVN1PROD with NOTICES




                                                  this docket on September 9, 2015, you                                                                           1 The appendices referenced in this notice will
                                                  will need to file those comments in                     please select ‘‘Comment on a Filing’’ as              not appear in the Federal Register. Copies of
                                                  Docket No. CP15–552–000 to ensure                       the filing type; or                                   appendices were sent to all those receiving this
                                                  they are considered as part of this                        (3) You can file a paper copy of your              notice in the mail and are available at www.ferc.gov
                                                  proceeding.                                             comments by mailing them to the                       using the link called ‘‘eLibrary’’ or from the
                                                                                                                                                                Commission’s Public Reference Room, 888 First
                                                     This notice is being sent to the                     following address. Be sure to reference               Street NE., Washington, DC 20426, or call (202)
                                                  Commission’s current environmental                      the Project docket number (CP15–552–                  502–8371. For instructions on connecting to
                                                  mailing list for this Project. State and                000) with your submission:                            eLibrary, refer to the last page of this notice.



                                             VerDate Sep<11>2014   19:16 Oct 27, 2015   Jkt 238001   PO 00000   Frm 00014   Fmt 4703   Sfmt 4703   E:\FR\FM\28OCN1.SGM   28OCN1


                                                                            Federal Register / Vol. 80, No. 208 / Wednesday, October 28, 2015 / Notices                                                    65997

                                                  Necessity. NEPA also requires us 2 to                   Consultations Under Section 106 of the                    Becoming an Intervenor
                                                  discover and address concerns the                       National Historic Preservation Act
                                                  public may have about proposals. This                                                                                In addition to involvement in the EA
                                                                                                            In accordance with the Advisory                         scoping process, you may want to
                                                  process is referred to as ‘‘scoping.’’ The              Council on Historic Preservation’s
                                                  main goal of the scoping process is to                                                                            become an ‘‘intervenor’’ which is an
                                                                                                          implementing regulations for section                      official party to the Commission’s
                                                  focus the analysis in the EA on the                     106 of the National Historic
                                                  important environmental issues. By this                                                                           proceeding. Intervenors play a more
                                                                                                          Preservation Act, we are using this
                                                  notice, the Commission requests public                                                                            formal role in the process and are able
                                                                                                          notice to initiate consultation with the
                                                  comments on the scope of the issues to                  applicable State Historic Preservation                    to file briefs, appear at hearings, and be
                                                  address in the EA. We will consider all                 Office (SHPO), and to solicit their views                 heard by the courts if they choose to
                                                  filed comments during the preparation                   and those of other government agencies,                   appeal the Commission’s final ruling.
                                                  of the EA.                                              interested Indian tribes, and the public                  An intervenor formally participates in
                                                     In the EA we will discuss impacts that               on the Project’s potential effects on                     the proceeding by filing a request to
                                                  could occur as a result of the                          historic properties.4 We will define the                  intervene. Instructions for becoming an
                                                  construction and operation of the                       Project-specific Area of Potential Effects                intervenor are in the ‘‘Document-less
                                                  proposed Project under these general                    (APE) in consultation with the SHPO as                    Intervention Guide’’ under the ‘‘e-filing’’
                                                  headings:                                               the Project develops. On natural gas                      link on the Commission’s Web site.
                                                     • geology and soils;                                 facility projects, the APE at a minimum                   Motions to intervene are more fully
                                                     • land use;                                          encompasses all areas subject to ground                   described at http://www.ferc.gov/
                                                     • water resources, fisheries, and                    disturbance (examples include                             resources/guides/how-to/intervene.asp.
                                                  wetlands;                                               construction right-of-way, contractor/
                                                                                                          pipe storage yards, compressor stations,                  Additional Information
                                                     • cultural resources;
                                                                                                          and access roads). Our EA for this                           Additional information about the
                                                     • vegetation and wildlife;                           Project will document our findings on
                                                     • air quality and noise;                                                                                       Project is available from the
                                                                                                          the impacts on historic properties and                    Commission’s Office of External Affairs,
                                                     • endangered and threatened species;                 summarize the status of consultations                     at (866) 208–FERC, or on the FERC Web
                                                     • public safety; and                                 under section 106.
                                                                                                                                                                    site at www.ferc.gov using the
                                                     • cumulative impacts                                 Environmental Mailing List                                ‘‘eLibrary’’ link. Click on the eLibrary
                                                     We will also evaluate reasonable                        The environmental mailing list                         link, click on ‘‘General Search’’ and
                                                  alternatives to the proposed Project or                 includes: Federal, state, and local                       enter the docket number, excluding the
                                                  portions of the Project, and make                       government representatives and                            last three digits in the Docket Number
                                                  recommendations on how to lessen or                     agencies; elected officials;                              field (i.e., CP15–552). Be sure you have
                                                  avoid impacts on the various resource                   environmental and public interest                         selected an appropriate date range. For
                                                  areas.                                                  groups; Native American Tribes; other                     assistance, please contact FERC Online
                                                     The EA will present our independent                  interested parties; and local libraries                   Support at FercOnlineSupport@ferc.gov
                                                  analysis of the issues. The EA will be                  and newspapers. This list also includes                   or toll free at (866) 208–3676, or for
                                                  available in the public record through                  all affected landowners (as defined in                    TTY, contact (202) 502–8659. The
                                                  eLibrary. Depending on the comments                     the Commission’s regulations) who are                     eLibrary link also provides access to the
                                                  received during the scoping process, we                 potential right-of-way grantors, whose                    texts of formal documents issued by the
                                                  may also publish and distribute the EA                  property may be used temporarily for                      Commission, such as orders, notices,
                                                  to the public for an allotted comment                   Project purposes, or who own homes                        and rulemakings.
                                                  period. We will consider all comments                   within certain distances of aboveground
                                                  on the EA before making our                                                                                          In addition, the Commission offers a
                                                                                                          facilities, and anyone who submits
                                                  recommendations to the Commission.                                                                                free service called eSubscription which
                                                                                                          comments on the Project. We will
                                                  To ensure we have the opportunity to                                                                              allows you to keep track of all formal
                                                                                                          update the environmental mailing list as
                                                  consider and address your comments,                     the analysis proceeds to ensure that we                   issuances and submittals in specific
                                                  please carefully follow the instructions                send the information related to this                      dockets. This can reduce the amount of
                                                  in the Public Participation section,                    environmental review to all individuals,                  time you spend researching proceedings
                                                  beginning on page 2.                                    organizations, and government entities                    by automatically providing you with
                                                     With this notice, we are asking                      interested in and/or potentially affected                 notification of these filings, document
                                                  agencies with jurisdiction by law and/                  by the proposed Project.                                  summaries, and direct links to the
                                                  or special expertise with respect to the                   If we publish and distribute the EA,                   documents. Go to www.ferc.gov/docs-
                                                  environmental issues of this Project to                 copies will be sent to the environmental                  filing/esubscription.asp.
                                                  formally cooperate with us in the                       mailing list for public review and                           Finally, public meetings or site visits
                                                  preparation of the EA.3 Agencies that                   comment. If you would prefer to receive                   will be posted on the Commission’s
                                                  would like to request cooperating                       a paper copy of the document instead of                   calendar located at www.ferc.gov/
                                                  agency status should follow the                         the CD version or would like to remove                    EventCalendar/EventsList.aspx along
                                                  instructions for filing comments                        your name from the mailing list, please                   with other related information.
                                                  provided under the Public Participation                 return the attached Information Request
                                                                                                                                                                      Dated: October 22, 2015.
mstockstill on DSK4VPTVN1PROD with NOTICES




                                                  section of this notice.                                 (Appendix 2).
                                                                                                                                                                    Kimberly D. Bose,
                                                    2 ‘‘We,’’ ‘‘us,’’ and ‘‘our’’ refer to the              4 The Advisory Council on Historic Preservation’s       Secretary.
                                                  environmental staff of the Commission’s Office of       regulations are at Title 36, Code of Federal              [FR Doc. 2015–27398 Filed 10–27–15; 8:45 am]
                                                  Energy Projects.                                        Regulations, Part 800. Those regulations define
                                                    3 The Council on Environmental Quality                historic properties as any prehistoric or historic        BILLING CODE 6717–01–P
                                                  regulations addressing cooperating agency               district, site, building, structure, or object included
                                                  responsibilities are at Title 40, Code of Federal       in or eligible for inclusion in the National Register
                                                  Regulations, Part 1501.6.                               of Historic Places.



                                             VerDate Sep<11>2014   19:16 Oct 27, 2015   Jkt 238001   PO 00000   Frm 00015   Fmt 4703   Sfmt 9990   E:\FR\FM\28OCN1.SGM     28OCN1



Document Created: 2018-02-27 08:57:53
Document Modified: 2018-02-27 08:57:53
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation80 FR 65996 

2025 Federal Register | Disclaimer | Privacy Policy
USC | CFR | eCFR