80_FR_69097 80 FR 68882 - North Anna Power Station, Units 1 and 2, Virginia Electric and Power Company

80 FR 68882 - North Anna Power Station, Units 1 and 2, Virginia Electric and Power Company

NUCLEAR REGULATORY COMMISSION

Federal Register Volume 80, Issue 215 (November 6, 2015)

Page Range68882-68884
FR Document2015-28361

The U.S. Nuclear Regulatory Commission (NRC) is giving notice that the Director of the Office of Nuclear Reactor Regulation has issued a revised final Director's Decision (DD) with regard to a petition dated October 20, 2011, filed by Paul Gunter et al., herein referred to as ``the petitioners.''

Federal Register, Volume 80 Issue 215 (Friday, November 6, 2015)
[Federal Register Volume 80, Number 215 (Friday, November 6, 2015)]
[Notices]
[Pages 68882-68884]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2015-28361]


-----------------------------------------------------------------------

NUCLEAR REGULATORY COMMISSION

[Docket Nos. 50-338 and 50-339; NRC-2012-0258; License Nos.: NPF-4 and 
NPF-7]


North Anna Power Station, Units 1 and 2, Virginia Electric and 
Power Company

AGENCY: Nuclear Regulatory Commission.

ACTION: Revised director's decision under 10 CFR 2.206; issuance.

-----------------------------------------------------------------------

SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) is giving notice 
that the Director of the Office of Nuclear Reactor Regulation has 
issued a revised final Director's Decision (DD) with regard to a 
petition dated October 20, 2011, filed by Paul Gunter et al., herein 
referred to as ``the petitioners.''

DATES: November 6, 2015.

ADDRESSES: Please refer to Docket ID NRC-2012-0258 when contacting the 
NRC about the availability of information regarding this document. You 
may obtain publicly-available information related to this document 
using any of the following methods:
     Federal Rulemaking Web site: Go to http://www.regulations.gov and search for Docket ID NRC-2012-0258. Address 
questions about NRC dockets to Carol

[[Page 68883]]

Gallagher; telephone: 301-415-3463; email: [email protected]. For 
technical questions, contact the individual listed in the FOR FURTHER 
INFORMATION CONTACT section of this document.
     NRC's Agencywide Documents Access and Management System 
(ADAMS): You may obtain publicly-available documents online in the 
ADAMS Public Documents collection at http://www.nrc.gov/reading-rm/adams.html. To begin the search, select ``ADAMS Public Documents'' and 
then select ``Begin Web-based ADAMS Search.'' For problems with ADAMS, 
please contact the NRC's Public Document Room (PDR) reference staff at 
1-800-397-4209, 301-415-4737, or by email to [email protected]. The 
ADAMS accession number for each document referenced (if it available in 
ADAMS) is provided the first time that a document is referenced.
     NRC's PDR: You may examine and purchase copies of public 
documents at the NRC's PDR, Room O1-F21, One White Flint North, 11555 
Rockville Pike, Rockville, Maryland 20852.

FOR FURTHER INFORMATION CONTACT: V. Sreenivas, Office of Nuclear 
Reactor Regulation, U.S. Nuclear Regulatory Commission, Washington, DC 
20555-0001; telephone: 301-415-2597; email: [email protected].

SUPPLEMENTARY INFORMATION: Notice is hereby given that the Director of 
the Office of Nuclear Reactor Regulation, has issued a revision to a 
Director's Decision (DD) dated August 21, 2015 (ADAMS Accession No. 
15175A465), with regard to a petition dated October 20, 2011 (ADAMS 
Accession No. ML11293A116), filed by the petitioners. The petition was 
supplemented on November 2, 2011 (ADAMS Accession No. ML11308A027) and 
December 15, 2011 (ADAMS Accession No. ML12060A197). The petition 
concerns the operation of the North Anna Power Station, Units 1 and 2 
(North Anna 1 and 2), by the Virginia Electric and Power Company (VEPCO 
or the licensee). The petition requested that the NRC suspend the 
operating licenses for North Anna 1 and 2, until the completion of a 
set of activities described in the petition. The petitioner also 
requested that a public meeting be held to discuss this matter in the 
Washington, DC area.
    As the basis for the October 20, 2011, request, the petitioner 
raised several concerns, of which 12 were accepted for review by the 
NRC staff by letter dated March 16, 2012 (ADAMS Accession No. 
ML12060A090). These are summarized as follows:
    (1) Prior to the approval of restart for North Anna 1 and 2, after 
the earthquake of August 23, 2011, VEPCO should be required to obtain a 
license amendment from the NRC that reanalyzes and reevaluates the 
plant's design basis for earthquakes and for associated necessary 
retrofits.
    (2) Prior to the approval of restart for North Anna 1 and 2, after 
the earthquake of August 23, 2011, the licensee should be required to 
ensure that North Anna 1 and 2, are subjected to thorough inspections 
of the same level and rigor.
    (3) The licensee should be required to reanalyze and reevaluate the 
North Anna Independent Spent Fuel Storage Installation (lSFSI) due to 
damage caused by the earthquake of August 23, 2011, and ensure that no 
threat is posed to public health and safety by its operation.
    (4) The licensee should ensure the reliability and accuracy of the 
seismic instrumentation at North Anna 1 and 2.
    (5) The NRC staff made hasty decisions about the restart of North 
Anna 1 and 2, and gave priority to economic considerations. The long-
term action plan was not even complete before the NRC staff gave 
authorization to restart.
    (6) Regulatory commitments are an inadequate regulatory tool for 
ensuring that the critical long-term tasks identified in the NRC 
staff's confirmatory action letter dated November 11, 2011, are 
completed.
    (7) The licensee needs to address the possibility of both boildown 
and rapid draindown events at the North Anna 1 and 2, spent fuel pool 
(SFP).
    (8) The long-term storage of spent fuel in the SFP at North Anna 1 
and 2, and at the North Anna ISFSI poses challenges to the public 
health and safety.
    (9) ``Hardened on-site storage'' strategies for spent fuel should 
be used at North Anna 1 and 2.
    (10) Concerns exist about the response of North Anna 1 and 2, to a 
prolonged station blackout.
    (11) The current emergency evacuation plans for North Anna 1 and 2, 
need to be revised to reflect the possible need to evacuate a larger 
area than that identified in the current emergency planning zone.
    (12) Concerns exist about damage to the structural integrity of the 
spent fuel pool structure at North Anna 1 and 2, as represented on 
pages 41 and 42 of the NRC staff's technical evaluation for the restart 
of North Anna 1 and 2, dated November 11, 2011.
    On December 12, 2012 and February 2, 2012, the petitioners and the 
licensee met with the NRC staff's petition review board (meeting 
transcripts under ADAMS Accession Nos. ML12033A025 and ML12047A240), 
regarding the petition. These meetings gave the petitioner and the 
licensee an opportunity to provide additional information and to 
clarify issues raised in the petition.
    The NRC staff issued a partial DD on October 19, 2012 (ADAMS 
Accession No. ML12262A156). Twelve of the concerns were accepted for 
review by the NRC staff. As detailed in the partial DD, eight of these 
concerns were closed. The remaining four concerns accepted for review 
were identified as those that may take longer than the target timeframe 
for reaching a decision on a petition based on the fact they were 
undergoing NRC review as part of the agency's response to the Fukushima 
event in Japan.
    Regarding the four remaining concerns, the NRC staff sent a copy of 
the proposed DD to the Petitioners and to the licensee for comment on 
April 17, 2015 (ADAMS Accession Nos. ML14311A616 and ML15061A133, 
respectively). The Petitioners provided comments in a response dated 
May 18, 2015 (ADAMS Accession No. ML15138A277) and the licensee 
provided comments in a response dated May 20, 2015 (ADAMS Accession No. 
ML15147A517). The comments and the NRC staff's response to them are 
included with this director's decision.
    On August 21, 2015, the NRC issued a director's decision (ADAMS 
Accession No. ML15175A465). Subsequently, the NRC identified portions 
of the director's decision on the long-term storage of spent fuel in 
the SFP and ISFSI that required clarification. Accordingly, the 
decision's response to Concern 8 is revised to clarify the NRC's 
resolution of the concern.
    The Director of the Office of Nuclear Reactor Regulation has 
determined that the request to suspend the operating licenses for North 
Anna 1 and 2, until the completion of a set of activities described in 
the petition, be partially granted and partially denied. The reasons 
for this decision are explained in the revised director's decision DD-
15-09 pursuant to section 2.206 of title 10 of the Code of Federal 
Regulations (10 CFR) of the Commission's regulations.
    The NRC will file a copy of the revised director's decision with 
the Secretary of the Commission for the Commission's review in 
accordance with 10 CFR 2.206. As provided for by this regulation, the 
director's decision will constitute the final action of the Commission 
25 days after the date of the

[[Page 68884]]

decision, unless the Commission, on its own motion, institutes a review 
of the director's decision in that time.

    Dated at Rockville, Maryland, this 30th day of October, 2015.

    For the Nuclear Regulatory Commission.
William M. Dean,
Director, Office of Nuclear Reactor Regulation.
[FR Doc. 2015-28361 Filed 11-5-15; 8:45 am]
 BILLING CODE 7590-01-P



                                                  68882                        Federal Register / Vol. 80, No. 215 / Friday, November 6, 2015 / Notices

                                                    • Mail Comments to: Cindy Bladey,                     comments submissions to remove                        email at Elaine.Keegan@nrc.gov no later
                                                  Office of Administration, Mail Stop:                    identifying or contact information.                   than Tuesday, November 24, 2015.
                                                  OWFN–12–H08, U.S. Nuclear                                 If you are requesting or aggregating                Members of the public may also register
                                                  Regulatory Commission, Washington,                      comments from other persons for                       to provide oral comments during the
                                                  DC 20555–0001.                                          submission to the NRC, then you should                registration period prior to the meeting.
                                                    For additional direction on obtaining                 inform those persons not to include                   Individual oral comments may be
                                                  information and submitting comments,                    identifying or contact information that               limited by the time available, depending
                                                  see ‘‘Obtaining Information and                         they do not want to be publicly                       on the number of persons who register.
                                                  Submitting Comments’’ in the                            disclosed in their comment submission.                If special equipment or accommodations
                                                  SUPPLEMENTARY INFORMATION section of                    Your request should state that the NRC                are needed to attend or present
                                                  this document.                                          does not routinely edit comment                       information at the public meeting, the
                                                  FOR FURTHER INFORMATION CONTACT:                        submissions to remove such information                need should be brought to Ms. Keegan’s
                                                  Elaine Keegan, Office of Nuclear Reactor                before making the comment                             attention no later than Tuesday,
                                                  Regulation, U.S. Nuclear Regulatory                     submissions available to the public or                November 24, 2015, in order to provide
                                                  Commission, Washington, DC 20555–                       entering the comment submissions into                 the NRC staff with adequate notice to
                                                  0001; telephone: 1–800–368–5642,                        ADAMS.                                                determine whether the request can be
                                                  extension 8517; email: Elaine.Keegan@                   II. Discussion                                        accommodated. Additional details
                                                  nrc.gov.                                                                                                      regarding the meeting will be posted at
                                                                                                             The NRC is issuing for public                      least 10 days prior to the public meeting
                                                  SUPPLEMENTARY INFORMATION:                              comment the draft plant-specific                      on the NRC’s Public Meeting Schedule
                                                  I. Obtaining Information and                            Supplement 56 to the GEIS for license                 Web site at http://www.nrc.gov/public-
                                                  Submitting Comments                                     renewal of nuclear plants, NUREG–
                                                                                                                                                                involve/public-meetings/index.cfm.
                                                                                                          1437, regarding the renewal of operating
                                                  A. Obtaining Information                                license, NPF–43 for an additional 20                    Dated at Rockville, Maryland, this 29 day
                                                                                                          years of operation for Fermi 2.                       of October 2015.
                                                     Please refer to Docket ID NRC–2014–
                                                  0109 when contacting the NRC about                      Supplement 56 to the GEIS includes the                  For the Nuclear Regulatory Commission.
                                                  the availablitiy of information for this                preliminary analysis that evaluates the               James G. Danna,
                                                  action. You may obtain publicly-                        environmental impacts of the proposed                 Chief, Projects Branch 2, Division of License
                                                  available information related to this                   action and alternatives to the proposed               Renewal, Office of Nuclear Reactor
                                                  action by any of the following methods:                 action. The NRC’s preliminary                         Regulation.
                                                     • Federal Rulemaking Web site: Go to                 recommendation is that the adverse                    [FR Doc. 2015–28265 Filed 11–5–15; 8:45 am]
                                                  http://www.regulations.gov and search                   environmental impacts of license                      BILLING CODE 7590–01–P
                                                  for Docket ID NRC–2014–0109.                            renewal for Fermi 2 are not great enough
                                                     • NRC's Agencywide Documents                         to deny the option of license renewal for
                                                  Access and Management System                            energy-planning decisionmakers.                       NUCLEAR REGULATORY
                                                  (ADAMS): You may obtain publicly-                                                                             COMMISSION
                                                                                                          III. Public Meetings
                                                  available documents online in the                                                                             [Docket Nos. 50–338 and 50–339; NRC–
                                                  ADAMS Public Documents collection at                       The NRC staff will hold a public
                                                                                                                                                                2012–0258; License Nos.: NPF–4 and NPF–
                                                  http://www.nrc.gov/reading-rm/                          meeting prior to the close of the public              7]
                                                  adams.html. To begin the search, select                 comment period to present an overview
                                                  ‘‘ADAMS Public Documents’’ and then                     of the draft plant-specific supplement to             North Anna Power Station, Units 1 and
                                                  select ‘‘Begin Web-based ADAMS                          the GEIS and to accept public comment                 2, Virginia Electric and Power
                                                  Search.’’ For problems with ADAMS,                      on the document. The meeting will be                  Company
                                                  please contact the NRC’s Public                         held at the Monroe County Community
                                                                                                          College, La-Z-Boy-Center 1555 S.                      AGENCY:  Nuclear Regulatory
                                                  Document Room (PDR) reference staff at                                                                        Commission.
                                                  1–800–397–4209, 301–415–4737, or by                     Raisinville Road, Monroe, Michigan on
                                                                                                          Wednesday, December 2, 2015. There                    ACTION: Revised director’s decision
                                                  email to pdr.resource@nrc.gov. The draft
                                                  plant-specific supplement GEIS is                       will be a registration period from 6:30               under 10 CFR 2.206; issuance.
                                                  available in ADAMS under Accession                      p.m. until 7:00 p.m. The meeting will
                                                                                                          start at 7:00 p.m. and continue until                 SUMMARY:   The U.S. Nuclear Regulatory
                                                  No. ML15300A064 for Volume 1 and                                                                              Commission (NRC) is giving notice that
                                                  ML15300A073 for Volume 2.                               9:00 p.m., as necessary. The meeting
                                                                                                          will be transcribed and will include: (1)             the Director of the Office of Nuclear
                                                     • NRC's PDR: You may examine and                                                                           Reactor Regulation has issued a revised
                                                  purchase copies of public documents at                  A presentation of the contents of the
                                                                                                          draft plant-specific supplement to the                final Director’s Decision (DD) with
                                                  the NRC’s PDR, Room O1–F21, One                                                                               regard to a petition dated October 20,
                                                  White Flint North, 11555 Rockville                      GEIS; and (2) the opportunity for
                                                                                                          interested government agencies,                       2011, filed by Paul Gunter et al., herein
                                                  Pike, Rockville, Maryland 20852.                                                                              referred to as ‘‘the petitioners.’’
                                                                                                          organizations, and individuals to
                                                  B. Submitting Comments                                  provide comments on the draft report.                 DATES: November 6, 2015.
                                                    Please include Docket ID NRC–2014–                    To be considered in the final                         ADDRESSES: Please refer to Docket ID
                                                  0109 in your comment submission.                        supplement to the GEIS, comments                      NRC–2012–0258 when contacting the
                                                    The NRC cautions you not to include                   must be provided either at the                        NRC about the availability of
mstockstill on DSK4VPTVN1PROD with NOTICES




                                                  identifying or contact information that                 transcribed public meeting or submitted               information regarding this document.
                                                  you do not want to be publicly                          in writing by the comment deadline                    You may obtain publicly-available
                                                  disclosed in your comment submission.                   identified in the DATES section of this               information related to this document
                                                  The NRC posts all comment                               notice. Persons may pre-register to                   using any of the following methods:
                                                  submissions at http://                                  attend or present oral comments at the                   • Federal Rulemaking Web site: Go to
                                                  www.regulations.gov as well as entering                 meeting by contacting Ms. Elaine                      http://www.regulations.gov and search
                                                  the comment submissions into ADAMS.                     Keegan, the NRC project manager, at 1–                for Docket ID NRC–2012–0258. Address
                                                  The NRC does not routinely edit                         800–368–5642, extension 8517, or by                   questions about NRC dockets to Carol


                                             VerDate Sep<11>2014   17:21 Nov 05, 2015   Jkt 238001   PO 00000   Frm 00049   Fmt 4703   Sfmt 4703   E:\FR\FM\06NON1.SGM   06NON1


                                                                               Federal Register / Vol. 80, No. 215 / Friday, November 6, 2015 / Notices                                           68883

                                                  Gallagher; telephone: 301–415–3463;                        (1) Prior to the approval of restart for           met with the NRC staff’s petition review
                                                  email: Carol.Gallagher@nrc.gov. For                     North Anna 1 and 2, after the                         board (meeting transcripts under
                                                  technical questions, contact the                        earthquake of August 23, 2011, VEPCO                  ADAMS Accession Nos. ML12033A025
                                                  individual listed in the FOR FURTHER                    should be required to obtain a license                and ML12047A240), regarding the
                                                  INFORMATION CONTACT section of this                     amendment from the NRC that                           petition. These meetings gave the
                                                  document.                                               reanalyzes and reevaluates the plant’s                petitioner and the licensee an
                                                     • NRC's Agencywide Documents                         design basis for earthquakes and for                  opportunity to provide additional
                                                  Access and Management System                            associated necessary retrofits.                       information and to clarify issues raised
                                                  (ADAMS): You may obtain publicly-                          (2) Prior to the approval of restart for           in the petition.
                                                  available documents online in the                       North Anna 1 and 2, after the                            The NRC staff issued a partial DD on
                                                  ADAMS Public Documents collection at                    earthquake of August 23, 2011, the                    October 19, 2012 (ADAMS Accession
                                                  http://www.nrc.gov/reading-rm/                          licensee should be required to ensure                 No. ML12262A156). Twelve of the
                                                  adams.html. To begin the search, select                 that North Anna 1 and 2, are subjected                concerns were accepted for review by
                                                  ‘‘ADAMS Public Documents’’ and then                     to thorough inspections of the same                   the NRC staff. As detailed in the partial
                                                  select ‘‘Begin Web-based ADAMS                          level and rigor.                                      DD, eight of these concerns were closed.
                                                  Search.'' For problems with ADAMS,                         (3) The licensee should be required to             The remaining four concerns accepted
                                                  please contact the NRC’s Public                         reanalyze and reevaluate the North                    for review were identified as those that
                                                  Document Room (PDR) reference staff at                  Anna Independent Spent Fuel Storage                   may take longer than the target
                                                  1–800–397–4209, 301–415–4737, or by                     Installation (lSFSI) due to damage                    timeframe for reaching a decision on a
                                                  email to pdr.resource@nrc.gov. The                      caused by the earthquake of August 23,                petition based on the fact they were
                                                  ADAMS accession number for each                         2011, and ensure that no threat is posed              undergoing NRC review as part of the
                                                  document referenced (if it available in                 to public health and safety by its                    agency’s response to the Fukushima
                                                  ADAMS) is provided the first time that                  operation.                                            event in Japan.
                                                  a document is referenced.                                  (4) The licensee should ensure the                    Regarding the four remaining
                                                     • NRC's PDR: You may examine and                     reliability and accuracy of the seismic               concerns, the NRC staff sent a copy of
                                                  purchase copies of public documents at                  instrumentation at North Anna 1 and 2.                the proposed DD to the Petitioners and
                                                  the NRC’s PDR, Room O1–F21, One                            (5) The NRC staff made hasty                       to the licensee for comment on April 17,
                                                  White Flint North, 11555 Rockville                      decisions about the restart of North                  2015 (ADAMS Accession Nos.
                                                  Pike, Rockville, Maryland 20852.                        Anna 1 and 2, and gave priority to                    ML14311A616 and ML15061A133,
                                                                                                          economic considerations. The long-term                respectively). The Petitioners provided
                                                  FOR FURTHER INFORMATION CONTACT: V.
                                                                                                          action plan was not even complete                     comments in a response dated May 18,
                                                  Sreenivas, Office of Nuclear Reactor
                                                                                                          before the NRC staff gave authorization               2015 (ADAMS Accession No.
                                                  Regulation, U.S. Nuclear Regulatory                                                                           ML15138A277) and the licensee
                                                  Commission, Washington, DC 20555–                       to restart.
                                                                                                             (6) Regulatory commitments are an                  provided comments in a response dated
                                                  0001; telephone: 301–415–2597; email:                                                                         May 20, 2015 (ADAMS Accession No.
                                                  V.Sreenivas@nrc.gov.                                    inadequate regulatory tool for ensuring
                                                                                                          that the critical long-term tasks                     ML15147A517). The comments and the
                                                  SUPPLEMENTARY INFORMATION: Notice is                                                                          NRC staff’s response to them are
                                                                                                          identified in the NRC staff’s
                                                  hereby given that the Director of the                   confirmatory action letter dated                      included with this director’s decision.
                                                  Office of Nuclear Reactor Regulation,                   November 11, 2011, are completed.                        On August 21, 2015, the NRC issued
                                                  has issued a revision to a Director’s                      (7) The licensee needs to address the              a director’s decision (ADAMS Accession
                                                  Decision (DD) dated August 21, 2015                     possibility of both boildown and rapid                No. ML15175A465). Subsequently, the
                                                  (ADAMS Accession No. 15175A465),                        draindown events at the North Anna 1                  NRC identified portions of the director’s
                                                  with regard to a petition dated October                 and 2, spent fuel pool (SFP).                         decision on the long-term storage of
                                                  20, 2011 (ADAMS Accession No.                              (8) The long-term storage of spent fuel            spent fuel in the SFP and ISFSI that
                                                  ML11293A116), filed by the petitioners.                 in the SFP at North Anna 1 and 2, and                 required clarification. Accordingly, the
                                                  The petition was supplemented on                        at the North Anna ISFSI poses                         decision’s response to Concern 8 is
                                                  November 2, 2011 (ADAMS Accession                       challenges to the public health and                   revised to clarify the NRC’s resolution of
                                                  No. ML11308A027) and December 15,                       safety.                                               the concern.
                                                  2011 (ADAMS Accession No.                                  (9) ‘‘Hardened on-site storage’’                      The Director of the Office of Nuclear
                                                  ML12060A197). The petition concerns                     strategies for spent fuel should be used              Reactor Regulation has determined that
                                                  the operation of the North Anna Power                   at North Anna 1 and 2.                                the request to suspend the operating
                                                  Station, Units 1 and 2 (North Anna 1                       (10) Concerns exist about the response             licenses for North Anna 1 and 2, until
                                                  and 2), by the Virginia Electric and                    of North Anna 1 and 2, to a prolonged                 the completion of a set of activities
                                                  Power Company (VEPCO or the                             station blackout.                                     described in the petition, be partially
                                                  licensee). The petition requested that                     (11) The current emergency                         granted and partially denied. The
                                                  the NRC suspend the operating licenses                  evacuation plans for North Anna 1 and                 reasons for this decision are explained
                                                  for North Anna 1 and 2, until the                       2, need to be revised to reflect the                  in the revised director’s decision DD–
                                                  completion of a set of activities                       possible need to evacuate a larger area               15–09 pursuant to section 2.206 of title
                                                  described in the petition. The petitioner               than that identified in the current                   10 of the Code of Federal Regulations
                                                  also requested that a public meeting be                 emergency planning zone.                              (10 CFR) of the Commission’s
                                                  held to discuss this matter in the                         (12) Concerns exist about damage to                regulations.
mstockstill on DSK4VPTVN1PROD with NOTICES




                                                  Washington, DC area.                                    the structural integrity of the spent fuel               The NRC will file a copy of the
                                                     As the basis for the October 20, 2011,               pool structure at North Anna 1 and 2,                 revised director’s decision with the
                                                  request, the petitioner raised several                  as represented on pages 41 and 42 of the              Secretary of the Commission for the
                                                  concerns, of which 12 were accepted for                 NRC staff’s technical evaluation for the              Commission’s review in accordance
                                                  review by the NRC staff by letter dated                 restart of North Anna 1 and 2, dated                  with 10 CFR 2.206. As provided for by
                                                  March 16, 2012 (ADAMS Accession No.                     November 11, 2011.                                    this regulation, the director’s decision
                                                  ML12060A090). These are summarized                         On December 12, 2012 and February                  will constitute the final action of the
                                                  as follows:                                             2, 2012, the petitioners and the licensee             Commission 25 days after the date of the


                                             VerDate Sep<11>2014   17:21 Nov 05, 2015   Jkt 238001   PO 00000   Frm 00050   Fmt 4703   Sfmt 4703   E:\FR\FM\06NON1.SGM   06NON1


                                                  68884                        Federal Register / Vol. 80, No. 215 / Friday, November 6, 2015 / Notices

                                                  decision, unless the Commission, on its                   This meeting will be webcast live at                reasonable accommodation will be
                                                  own motion, institutes a review of the                  the Web address—http://www.nrc.gov/.                  made on a case-by-case basis.
                                                  director’s decision in that time.                                                                             *     *     *     *    *
                                                                                                          Week of November 23, 2015—Tentative
                                                    Dated at Rockville, Maryland, this 30th day                                                                    Members of the public may request to
                                                  of October, 2015.                                         There are no meetings scheduled for                 receive this information electronically.
                                                    For the Nuclear Regulatory Commission.                the week of November 23, 2015.                        If you would like to be added to the
                                                  William M. Dean,                                        Week of November 30, 2015—Tentative                   distribution, please contact the Nuclear
                                                  Director, Office of Nuclear Reactor                                                                           Regulatory Commission, Office of the
                                                  Regulation.                                             Thursday, December 3, 2015                            Secretary, Washington, DC 20555 (301–
                                                  [FR Doc. 2015–28361 Filed 11–5–15; 8:45 am]             9:30 a.m. Briefing on Equal                           415–1969), or email
                                                  BILLING CODE 7590–01–P                                      Employment Opportunity and Civil                  Brenda.Akstulewicz@nrc.gov or
                                                                                                              Rights Outreach (Public Meeting);                 Patricia.Jimenez@nrc.gov.
                                                                                                              (Contact: Larniece McKoy Moore:                     Dated: November 4, 2015.
                                                  NUCLEAR REGULATORY                                          301–415–1942).                                    Denise L. McGovern,
                                                  COMMISSION                                                                                                    Policy Coordinator, Office of the Secretary.
                                                                                                            This meeting will be webcast live at
                                                  [NRC–2015–0001]                                         the Web address—http://www.nrc.gov/.                  [FR Doc. 2015–28482 Filed 11–4–15; 4:15 pm]
                                                                                                                                                                BILLING CODE 7590–01–P
                                                                                                          Week of December 7, 2015—Tentative
                                                  Sunshine Act Meeting Notice
                                                                                                            There are no meetings scheduled for
                                                  DATES: November 9, 16, 23, 30,                          the week of December 7, 2015.                         SECURITIES AND EXCHANGE
                                                  December 7, 14, 2015.                                                                                         COMMISSION
                                                                                                          Week of December 14, 2015—Tentative
                                                  PLACE: Commissioners’ Conference
                                                  Room, 11555 Rockville Pike, Rockville,                  Tuesday, December 15, 2015                            [Release No. 34–76327; File No. SR–BATS–
                                                  Maryland.                                                                                                     2015–93
                                                                                                          9:00 a.m. Hearing on Construction
                                                  STATUS: Public and Closed.                                  Permit for SHINE Medical Isotope                  Self-Regulatory Organizations; BATS
                                                  Week of November 9, 2015                                    Production Facility: Section 189a of              Exchange, Inc.; Notice of Filing and
                                                                                                              the Atomic Energy Act Proceeding                  Immediate Effectiveness of a Proposed
                                                  Monday, November 9, 2015                                    (Public Meeting); (Contact: Steven                Rule Change To Delete Rule 22.10,
                                                  2:45 p.m. Affirmation Session (Public                       Lynch: 301–415–1524).                             Limitations on Dealings
                                                       Meeting) (Tentative).                                This meeting will be webcast live at
                                                    a. Pacific Gas and Electric Company                                                                         November 2, 2015.
                                                                                                          the Web address—http://www.nrc.gov/.
                                                       (Diablo Canyon Nuclear Power                                                                                Pursuant to Section 19(b)(1) of the
                                                       Plant), Friends of the Earth's                     Thursday, December 17, 2015                           Securities Exchange Act of 1934 (the
                                                       Appeal of LBP±15±6 (Tentative)                     9:30 a.m. Briefing on Project AIM 2020                ‘‘Act’’),1 and Rule 19b–4 thereunder,2
                                                    b. Entergy Nuclear Operations, Inc.                        (Public Meeting); (Contact: John                 notice is hereby given that on October
                                                       (Palisades Nuclear Plant)—Appeal                        Jolicoeur 301–415–1642).                         21, 2015, BATS Exchange, Inc. (the
                                                       of LBP–15–17 (Tentative)                                                                                 ‘‘Exchange’’ or ‘‘BATS’’) filed with the
                                                                                                             This meeting will be webcast live at               Securities and Exchange Commission
                                                    c. Entergy Nuclear Operations, Inc.
                                                                                                          the Web address—http://www.nrc.gov/.                  (‘‘Commission’’) the proposed rule
                                                       (Palisades Nuclear Plant)—Appeal
                                                       of LBP–15–20 (Tentative)                           *     *      *    *      *                            change as described in Items I, II and III
                                                    d. Entergy Nuclear Operations, Inc.                      The schedule for Commission                        below, which Items have been prepared
                                                       (Indian Point Nuclear Generating                   meetings is subject to change on short                by the Exchange. The Exchange has
                                                       Units 2 and 3)—Petition for                        notice. For more information or to verify             designated this proposal as a ‘‘non-
                                                       Interlocutory Review of Atomic                     the status of meetings, contact Denise                controversial’’ proposed rule change
                                                       Safety and Licensing Board’s July                  McGovern at 301–415–0681 or via email                 pursuant to Section 19(b)(3)(A) of the
                                                       20, 2015 Order (Denying New York                   at Denise.McGovern@nrc.gov.                           Act 3 and Rule 19b–4(f)(6)(iii)
                                                       Motion to Withdraw Proprietary                     *     *      *    *      *                            thereunder,4 which renders it effective
                                                       Designation) (Tentative).                             The NRC Commission Meeting                         upon filing with the Commission. The
                                                                                                          Schedule can be found on the Internet                 Commission is publishing this notice to
                                                  Week of November 16, 2015—Tentative                                                                           solicit comments on the proposed rule
                                                                                                          at:http://www.nrc.gov/public-involve/
                                                  Tuesday, November 17, 2015                              public-meetings/schedule.html.                        change from interested persons.
                                                  9:00 a.m. Briefing on the Status of                     *     *      *    *      *                            I. Self-Regulatory Organization’s
                                                      Lessons Learned from the                               The NRC provides reasonable                        Statement of the Terms of Substance of
                                                      Fukushima Dai-Ichi Accident                         accommodation to individuals with                     the Proposed Rule Change
                                                      (Public Meeting); (Contact: Gregory                 disabilities where appropriate. If you                  The Exchange filed a proposal for the
                                                      Bowman: 301–415–2939).                              need a reasonable accommodation to                    BATS Options Market (‘‘BATS
                                                    This meeting will be webcast live at                  participate in these public meetings, or              Options’’) to adopt a principles-based
                                                  the Web address—http://www.nrc.gov/.                    need this meeting notice or the                       approach to prohibit the misuse of
mstockstill on DSK4VPTVN1PROD with NOTICES




                                                                                                          transcript or other information from the              material nonpublic information by
                                                  Thursday, November 19, 2015                             public meetings in another format (e.g.               Market Makers by deleting Rule 22.10
                                                  9:00 a.m. Hearing on Combined                           braille, large print), please notify                  (Limitations on Dealings).
                                                      Licenses for South Texas Project,                   Kimberly Meyer, NRC Disability
                                                      Units 3 and 4: Section 189a of the                  Program Manager, at 301–287–0739, by                    1 15 U.S.C. 78s(b)(1).
                                                      Atomic Energy Act Proceeding                        videophone at 240–428–3217, or by                       2 17 CFR 240.19b–4.
                                                      (Public Meeting); (Contact: Tom                     email at Kimberly.Meyer-Chambers@                       3 15 U.S.C. 78s(b)(3)(A).

                                                      Tai: 301–415–8484).                                 nrc.gov. Determinations on requests for                 4 17 CFR 240.19b–4(f)(6)(iii).




                                             VerDate Sep<11>2014   17:21 Nov 05, 2015   Jkt 238001   PO 00000   Frm 00051   Fmt 4703   Sfmt 4703   E:\FR\FM\06NON1.SGM   06NON1



Document Created: 2015-12-14 15:09:00
Document Modified: 2015-12-14 15:09:00
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
ActionRevised director's decision under 10 CFR 2.206; issuance.
DatesNovember 6, 2015.
ContactV. Sreenivas, Office of Nuclear Reactor Regulation, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001; telephone: 301-415-2597; email: [email protected]