80_FR_70415 80 FR 70196 - Mountain Valley Pipeline, LLC; Equitrans, LP; Notice of Applications

80 FR 70196 - Mountain Valley Pipeline, LLC; Equitrans, LP; Notice of Applications

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 80, Issue 219 (November 13, 2015)

Page Range70196-70198
FR Document2015-28771

Federal Register, Volume 80 Issue 219 (Friday, November 13, 2015)
[Federal Register Volume 80, Number 219 (Friday, November 13, 2015)]
[Notices]
[Pages 70196-70198]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2015-28771]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP16-10-000; Docket No. PF15-3-000; Docket No. CP16-13-000; 
Docket No. PF15-22-000]


Mountain Valley Pipeline, LLC; Equitrans, LP; Notice of 
Applications

    On October 23, 2015, Mountain Valley Pipeline, LLC (Mountain 
Valley), having its principal place of business at 625 Liberty Avenue, 
Suite 1700,

[[Page 70197]]

Pittsburgh, Pennsylvania 15222-3111, filed an application pursuant to 
section 7(c) of the Natural Gas Act (NGA) and the Federal Energy 
Regulatory Commission's (Commission) regulations seeking: (1) A 
certificate of public convenience and necessity authorizing Mountain 
Valley to construct, own, and operate the Mountain Valley Pipeline 
Project; (2) a blanket certificate of public convenience and necessity 
authorizing Mountain Valley to provide open-access interstate 
transportation services, with pre-granted abandonment approval; (3) a 
blanket certificate of public convenience and necessity under Part 157, 
Subpart F of the Commission's regulations for Mountain Valley to 
construct, operate, acquire, and abandon certain eligible facilities, 
and services related thereto; (4) approval for its proposed interim 
period rates and initial recourse rates for transportation service and 
for its pro forma tariff; and (5) such other authorizations or waivers 
as may be deemed necessary to allow for the construction to commence as 
proposed.
    On October 27, 2015, Equitrans, LP (Equitrans), having its 
principal place of business at 625 Liberty Avenue, Suite 1700, 
Pittsburgh, Pennsylvania 15222-3111, filed an application pursuant to 
sections 7(b) and 7(c) of the Natural Gas Act (NGA) and the Federal 
Energy Regulatory Commission's (Commission) regulations seeking a 
certificate of public convenience and necessity to construct, own, and 
operate the Equitrans Expansion Project. Equitrans also seeks authority 
to abandon an existing compressor station located in Greene County, 
Pennsylvania.
    The proposals of both applicants are more fully described in the 
applications, which are on file with the Commission and open to public 
inspection. The filings may also be viewed on the web at http://www.ferc.gov using the ``eLibrary'' link. Enter the docket number 
excluding the last three digits in the docket number field to access 
the document. For assistance, contact FERC at 
[email protected] or call toll-free, (866) 208-3676 or TTY, 
(202) 502-8659.
    Any questions regarding the Mountain Valley or Equitrans 
applications should be directed to Matthew Eggerding, Counsel, 625 
Liberty Avenue, Suite 1700, Pittsburgh, PA 15222, or call (412) 553-
5786, or fax (412) 553-7781, or by email [email protected].
    Mountain Valley requests authorization to construct facilities that 
will allow it to provide up to 2.0 million dekatherms per day of firm 
transportation service. Specifically, Mountain Valley proposes to 
construct and operate: (1) Approximately 301 miles of 42-inch diameter 
pipeline in West Virginia and Virginia; (2) three new compressor 
stations providing approximately 171,600 nominal horsepower (hp) of 
compression; and (3) other minor facilities.
    Equitrans requests authorization to construct, own, and operate: 
(1) Approximately 7.87 miles of pipeline in Allegheny, Washington, and 
Greene Counties, Pennsylvania and Wetzel County, West Virginia; (2) a 
new 31,300 nominal hp compressor station (Redhook Compressor Station) 
in Greene County, Pennsylvania; (3) a new interconnect in Wetzel 
County, West Virginia with Mountain Valley's planned pipeline system 
(Webster Interconnect); and (4) ancillary facilities. Equitrans also 
seeks authority to abandon an existing 4,800 hp compressor station in 
Greene County, Pennsylvania (Pratt Compressor Station) following the 
construction of the new Redhook Compressor Station.
    On October 31, 2014, Commission staff granted Mountain Valley's 
request to use the pre-filing process and assigned Docket No. PF15-3-
000 to staff activities involving the Projects. Now, as of the filing 
of this application on October 23, 2015, the NEPA Pre-Filing Process 
for this project has ended. From this time forward, this proceeding 
will be conducted in Docket No. CP16-10-000 as noted in the caption of 
this Notice. Additionally, Equitrans, LP (Equitrans) filed a related 
application under CP16-13-000. On April 9, 2015, Commission staff 
granted Equitrans request to use the pre-filing process and assigned 
Docket No. PF15-22-000 to staff activities involving the Projects. Now, 
as of the filing of Equitrans' application on October 27, 2015, the 
NEPA Pre-Filing Process for this project has ended. From this time 
forward, Equitrans' proceeding will be conducted in Docket No. CP16-13-
000.
    Pursuant to section 157.9 of the Commission's rules, 18 CFR 157.9, 
within 90 days of this Notice the Commission staff will either: 
Complete its environmental assessment (EA) and place it into the 
Commission's public record (eLibrary) for this proceeding; or issue a 
Notice of Schedule for Environmental Review. If a Notice of Schedule 
for Environmental Review is issued, it will indicate, among other 
milestones, the anticipated date for the Commission staff's issuance of 
the final environmental impact statement (FEIS) or EA for this 
proposal. The filing of the EA in the Commission's public record for 
this proceeding or the issuance of a Notice of Schedule for 
Environmental Review will serve to notify federal and state agencies of 
the timing for the completion of all necessary reviews, and the 
subsequent need to complete all federal authorizations within 90 days 
of the date of issuance of the Commission staff's FEIS or EA.
    There are two ways to become involved in the Commission's review of 
this project. First, any person wishing to obtain legal status by 
becoming a party to the proceedings for this project should, on or 
before the comment date stated below file with the Federal Energy 
Regulatory Commission, 888 First Street NE., Washington, DC 20426, a 
motion to intervene in accordance with the requirements of the 
Commission's Rules of Practice and Procedure (18 CFR 385.214 or 
385.211) and the Regulations under the NGA (18 CFR 157.10). A person 
obtaining party status will be placed on the service list maintained by 
the Secretary of the Commission and will receive copies of all 
documents filed by the applicant and by all other parties. A party must 
submit 7 copies of filings made in the proceeding with the Commission 
and must mail a copy to the applicant and to every other party. Only 
parties to the proceeding can ask for court review of Commission orders 
in the proceeding.
    However, a person does not have to intervene in order to have 
comments considered. The second way to participate is by filing with 
the Secretary of the Commission, as soon as possible, an original and 
two copies of comments in support of or in opposition to this project. 
The Commission will consider these comments in determining the 
appropriate action to be taken, but the filing of a comment alone will 
not serve to make the filer a party to the proceeding. The Commission's 
rules require that persons filing comments in opposition to the project 
provide copies of their protests only to the party or parties directly 
involved in the protest.
    Persons who wish to comment only on the environmental review of 
this project should submit an original and two copies of their comments 
to the Secretary of the Commission. Environmental commentors will be 
placed on the Commission's environmental mailing list, will receive 
copies of the environmental documents, and will be notified of meetings 
associated with the Commission's environmental review process. 
Environmental commentors will not be required to serve copies of filed 
documents on all other parties. However, the non-party commentors will 
not receive copies of all documents filed by other parties or issued by 
the

[[Page 70198]]

Commission (except for the mailing of environmental documents issued by 
the Commission) and will not have the right to seek court review of the 
Commission's final order.
    The Commission strongly encourages electronic filings of comments, 
protests and interventions in lieu of paper using the ``eFiling'' link 
at http://www.ferc.gov. Persons unable to file electronically should 
submit an original and 5 copies of the protest or intervention to the 
Federal Energy regulatory Commission, 888 First Street NE., Washington, 
DC 20426.
    Comment Date: 5:00 p.m. Eastern Time on November 26, 2015.

    Dated: November 5, 2015.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2015-28771 Filed 11-12-15; 8:45 am]
BILLING CODE 6717-01-P



                                                  70196                       Federal Register / Vol. 80, No. 219 / Friday, November 13, 2015 / Notices

                                                  DEPARTMENT OF ENERGY                                    project will be approximately $449.8                  possible, an original and two copies of
                                                                                                          million.                                              comments in support of or in opposition
                                                  Federal Energy Regulatory                                  On February 20, 2015 the Commission                to this project. The Commission will
                                                  Commission                                              staff granted Columbia’s request to                   consider these comments in
                                                                                                          utilize the Pre-Filing Process and                    determining the appropriate action to be
                                                  [Docket Nos. Algonquin Gas Transmission,                assigned Docket No. PF15–12–000 to                    taken, but the filing of a comment alone
                                                  LLC CP16–9–000 Maritimes & Northeast                    staff activities involved in the Project.             will not serve to make the filer a party
                                                  Pipeline, L.L.C. PF15–12–000]                           Now, as of the filing of the October 22,              to the proceeding. The Commission’s
                                                                                                          2015 application, the Pre-Filing Process              rules require that persons filing
                                                  Notice of Application                                   for this project has ended. From this                 comments in opposition to the project
                                                     Take notice that on October 22, 2015,                time forward, this proceeding will be                 provide copies of their protests only to
                                                  Algonquin Gas Transmission, LLC                         conducted in Docket No. CP16–9–000,                   the party or parties directly involved in
                                                  (Algonquin) and Maritimes & Northeast                   as noted in the caption of this Notice.               the protest.
                                                                                                             Pursuant to section 157.9 of the                      Persons who wish to comment only
                                                  Pipeline, L.L.C. (Maritimes) (together,
                                                                                                          Commission’s rules (18 CFR 157.9),                    on the environmental review of this
                                                  the Applicants), 5400 Westheimer
                                                                                                          within 90 days of this Notice, the                    project should submit an original and
                                                  Court, Houston, Texas 77056–5310,
                                                                                                          Commission staff will either: complete                two copies of their comments to the
                                                  jointly filed in the above referenced
                                                                                                          its environmental assessment (EA) and                 Secretary of the Commission.
                                                  docket an application pursuant to
                                                                                                          place it into the Commission’s public                 Environmental commentors will be
                                                  section 7(c) of the Natural Gas Act
                                                                                                          record (eLibrary) for this proceeding; or             placed on the Commission’s
                                                  (NGA), and Part 157 of the
                                                                                                          issue a Notice of Schedule for                        environmental mailing list, will receive
                                                  Commission’s regulations requesting                     Environmental Review. If a Notice of                  copies of the environmental documents,
                                                  authorization to construct and operate                  Schedule for Environmental Review is                  and will be notified of meetings
                                                  the Atlantic Bridge Project, all as more                issued, it will indicate, among other                 associated with the Commission’s
                                                  fully set forth in the application which                milestones, the anticipated date for the              environmental review process.
                                                  is on file with the Commission and open                 Commission staff’s issuance of the final              Environmental commentors will not be
                                                  to public inspection. The filing is                     environmental impact statement (FEIS)                 required to serve copies of filed
                                                  available for review at the Commission                  or EA for this proposal. The filing of the            documents on all other parties.
                                                  in the Public Reference Room or may be                  EA in the Commission’s public record                  However, the non-party commentors
                                                  viewed on the Commission’s Web site                     for this proceeding or the issuance of a              will not receive copies of all documents
                                                  web at http://www.ferc.gov using the                    Notice of Schedule for Environmental                  filed by other parties or issued by the
                                                  ‘‘eLibrary’’ link. Enter the docket                     Review will serve to notify federal and               Commission (except for the mailing of
                                                  number excluding the last three digits in               state agencies of the timing for the                  environmental documents issued by the
                                                  the docket number field to access the                   completion of all necessary reviews, and              Commission) and will not have the right
                                                  document. For assistance, contact FERC                  the subsequent need to complete all                   to seek court review of the
                                                  at FERCOnlineSupport@ferc.gov or call                   federal authorizations within 90 days of              Commission’s final order.
                                                  toll-free, (866) 208–3676 or TYY, (202)                 the date of issuance of the Commission                   The Commission strongly encourages
                                                  502–8659.                                               staff’s FEIS or EA.                                   electronic filings of comments, protests
                                                     Any questions concerning this                           There are two ways to become                       and interventions in lieu of paper using
                                                  application may be directed to Berk                     involved in the Commission’s review of                the ‘‘eFiling’’ link at http://
                                                  Donaldson, General Manager, Rates and                   this project. First, any person wishing to            www.ferc.gov. Persons unable to file
                                                  Certificates, Algonquin Gas                             obtain legal status by becoming a party               electronically should submit an original
                                                  Transmission, LLC and Maritimes &                       to the proceedings for this project                   and 7 copies of the protest or
                                                  Northeast Pipeline, L.L.C., P.O. Box                    should, on or before the comment date                 intervention to the Federal Energy
                                                  1642, Houston, Texas 77251–1642 at                      stated below file with the Federal                    regulatory Commission, 888 First Street
                                                  (713) 627–4488.                                         Energy Regulatory Commission, 888                     NE., Washington, DC 20426.
                                                     Specifically the applicants propose to:              First Street NE., Washington, DC 20426,                  Comment Date: November 27, 2015.
                                                  (i) Construct 6.3 miles pipeline facilities             a motion to intervene in accordance
                                                                                                                                                                  Dated: November 5, 2015.
                                                  and related facilities in New York and                  with the requirements of the
                                                  Connecticut; (ii) modify three existing                                                                       Nathaniel J. Davis, Sr.,
                                                                                                          Commission’s Rules of Practice and
                                                  compressor stations in Connecticut                      Procedure (18 CFR 385.214 or 385.211)                 Deputy Secretary.
                                                  resulting in the addition of 18,800                     and the Regulations under the NGA (18                 [FR Doc. 2015–28770 Filed 11–12–15; 8:45 am]
                                                  horsepower (hp) of compression; (iii)                   CFR 157.10). A person obtaining party                 BILLING CODE 6717–01–P
                                                  construct and operate a new compressor                  status will be placed on the service list
                                                  station in Massachusetts resulting in the               maintained by the Secretary of the
                                                  addition of 7,700 hp of compression;                    Commission and will receive copies of                 DEPARTMENT OF ENERGY
                                                  (iv) modify six existing metering, and                  all documents filed by the applicant and              Federal Energy Regulatory
                                                  regulator stations (M&R) and construct a                by all other parties. A party must submit             Commission
                                                  new M&R Station; and (v) to abandon                     seven copies of filings made in the
                                                  certain existing facilities. The Atlantic               proceeding with the Commission and                    [Docket No. CP16–10–000; Docket No.
                                                  Bridge Project will allow both                          must mail a copy to the applicant and                 PF15–3–000; Docket No. CP16–13–000;
                                                  Algonquin and Maritimes to provide                                                                            Docket No. PF15–22–000]
jstallworth on DSK7TPTVN1PROD with NOTICES




                                                                                                          to every other party. Only parties to the
                                                  additional firm transportation. The                     proceeding can ask for court review of                Mountain Valley Pipeline, LLC;
                                                  applicants request authorization to                     Commission orders in the proceeding.                  Equitrans, LP; Notice of Applications
                                                  charge an initial incremental Atlantic                     However, a person does not have to
                                                  Bridge Project recourse rate and related                intervene in order to have comments                     On October 23, 2015, Mountain
                                                  incremental fuel, and also requested a                  considered. The second way to                         Valley Pipeline, LLC (Mountain Valley),
                                                  pre-determination of rolled-in rates                    participate is by filing with the                     having its principal place of business at
                                                  treatment for the Project. The cost of the              Secretary of the Commission, as soon as               625 Liberty Avenue, Suite 1700,


                                             VerDate Sep<11>2014   15:03 Nov 12, 2015   Jkt 238001   PO 00000   Frm 00013   Fmt 4703   Sfmt 4703   E:\FR\FM\13NON1.SGM   13NON1


                                                                              Federal Register / Vol. 80, No. 219 / Friday, November 13, 2015 / Notices                                           70197

                                                  Pittsburgh, Pennsylvania 15222–3111,                    Mountain Valley proposes to construct                 Review will serve to notify federal and
                                                  filed an application pursuant to section                and operate: (1) Approximately 301                    state agencies of the timing for the
                                                  7(c) of the Natural Gas Act (NGA) and                   miles of 42-inch diameter pipeline in                 completion of all necessary reviews, and
                                                  the Federal Energy Regulatory                           West Virginia and Virginia; (2) three                 the subsequent need to complete all
                                                  Commission’s (Commission) regulations                   new compressor stations providing                     federal authorizations within 90 days of
                                                  seeking: (1) A certificate of public                    approximately 171,600 nominal                         the date of issuance of the Commission
                                                  convenience and necessity authorizing                   horsepower (hp) of compression; and (3)               staff’s FEIS or EA.
                                                  Mountain Valley to construct, own, and                  other minor facilities.                                  There are two ways to become
                                                  operate the Mountain Valley Pipeline                       Equitrans requests authorization to                involved in the Commission’s review of
                                                  Project; (2) a blanket certificate of public            construct, own, and operate: (1)                      this project. First, any person wishing to
                                                  convenience and necessity authorizing                   Approximately 7.87 miles of pipeline in               obtain legal status by becoming a party
                                                  Mountain Valley to provide open-access                  Allegheny, Washington, and Greene                     to the proceedings for this project
                                                  interstate transportation services, with                Counties, Pennsylvania and Wetzel                     should, on or before the comment date
                                                  pre-granted abandonment approval; (3)                   County, West Virginia; (2) a new 31,300               stated below file with the Federal
                                                  a blanket certificate of public                         nominal hp compressor station                         Energy Regulatory Commission, 888
                                                  convenience and necessity under Part                    (Redhook Compressor Station) in                       First Street NE., Washington, DC 20426,
                                                  157, Subpart F of the Commission’s                      Greene County, Pennsylvania; (3) a new                a motion to intervene in accordance
                                                  regulations for Mountain Valley to                      interconnect in Wetzel County, West                   with the requirements of the
                                                  construct, operate, acquire, and abandon                Virginia with Mountain Valley’s                       Commission’s Rules of Practice and
                                                  certain eligible facilities, and services               planned pipeline system (Webster                      Procedure (18 CFR 385.214 or 385.211)
                                                  related thereto; (4) approval for its                   Interconnect); and (4) ancillary                      and the Regulations under the NGA (18
                                                  proposed interim period rates and                       facilities. Equitrans also seeks authority            CFR 157.10). A person obtaining party
                                                  initial recourse rates for transportation               to abandon an existing 4,800 hp                       status will be placed on the service list
                                                  service and for its pro forma tariff; and               compressor station in Greene County,                  maintained by the Secretary of the
                                                  (5) such other authorizations or waivers                Pennsylvania (Pratt Compressor Station)               Commission and will receive copies of
                                                  as may be deemed necessary to allow for                 following the construction of the new                 all documents filed by the applicant and
                                                  the construction to commence as                         Redhook Compressor Station.                           by all other parties. A party must submit
                                                  proposed.                                                  On October 31, 2014, Commission                    7 copies of filings made in the
                                                     On October 27, 2015, Equitrans, LP                   staff granted Mountain Valley’s request               proceeding with the Commission and
                                                  (Equitrans), having its principal place of              to use the pre-filing process and                     must mail a copy to the applicant and
                                                  business at 625 Liberty Avenue, Suite                   assigned Docket No. PF15–3–000 to staff               to every other party. Only parties to the
                                                  1700, Pittsburgh, Pennsylvania 15222–                   activities involving the Projects. Now, as            proceeding can ask for court review of
                                                  3111, filed an application pursuant to                  of the filing of this application on                  Commission orders in the proceeding.
                                                  sections 7(b) and 7(c) of the Natural Gas               October 23, 2015, the NEPA Pre-Filing                    However, a person does not have to
                                                  Act (NGA) and the Federal Energy                        Process for this project has ended. From              intervene in order to have comments
                                                  Regulatory Commission’s (Commission)                    this time forward, this proceeding will               considered. The second way to
                                                  regulations seeking a certificate of                    be conducted in Docket No. CP16–10–                   participate is by filing with the
                                                  public convenience and necessity to                     000 as noted in the caption of this                   Secretary of the Commission, as soon as
                                                  construct, own, and operate the                         Notice. Additionally, Equitrans, LP                   possible, an original and two copies of
                                                  Equitrans Expansion Project. Equitrans                  (Equitrans) filed a related application               comments in support of or in opposition
                                                  also seeks authority to abandon an                      under CP16–13–000. On April 9, 2015,                  to this project. The Commission will
                                                  existing compressor station located in                  Commission staff granted Equitrans                    consider these comments in
                                                  Greene County, Pennsylvania.                            request to use the pre-filing process and             determining the appropriate action to be
                                                     The proposals of both applicants are                 assigned Docket No. PF15–22–000 to                    taken, but the filing of a comment alone
                                                  more fully described in the applications,               staff activities involving the Projects.              will not serve to make the filer a party
                                                  which are on file with the Commission                   Now, as of the filing of Equitrans’                   to the proceeding. The Commission’s
                                                  and open to public inspection. The                      application on October 27, 2015, the                  rules require that persons filing
                                                  filings may also be viewed on the web                   NEPA Pre-Filing Process for this project              comments in opposition to the project
                                                  at http://www.ferc.gov using the                        has ended. From this time forward,                    provide copies of their protests only to
                                                  ‘‘eLibrary’’ link. Enter the docket                     Equitrans’ proceeding will be conducted               the party or parties directly involved in
                                                  number excluding the last three digits in               in Docket No. CP16–13–000.                            the protest.
                                                  the docket number field to access the                      Pursuant to section 157.9 of the                      Persons who wish to comment only
                                                  document. For assistance, contact FERC                  Commission’s rules, 18 CFR 157.9,                     on the environmental review of this
                                                  at FERCOnlineSupport@ferc.gov or call                   within 90 days of this Notice the                     project should submit an original and
                                                  toll-free, (866) 208–3676 or TTY, (202)                 Commission staff will either: Complete                two copies of their comments to the
                                                  502–8659.                                               its environmental assessment (EA) and                 Secretary of the Commission.
                                                     Any questions regarding the                          place it into the Commission’s public                 Environmental commentors will be
                                                  Mountain Valley or Equitrans                            record (eLibrary) for this proceeding; or             placed on the Commission’s
                                                  applications should be directed to                      issue a Notice of Schedule for                        environmental mailing list, will receive
                                                  Matthew Eggerding, Counsel, 625                         Environmental Review. If a Notice of                  copies of the environmental documents,
                                                  Liberty Avenue, Suite 1700, Pittsburgh,                 Schedule for Environmental Review is                  and will be notified of meetings
                                                                                                          issued, it will indicate, among other                 associated with the Commission’s
jstallworth on DSK7TPTVN1PROD with NOTICES




                                                  PA 15222, or call (412) 553–5786, or fax
                                                  (412) 553–7781, or by email                             milestones, the anticipated date for the              environmental review process.
                                                  meggerding@eqt.com.                                     Commission staff’s issuance of the final              Environmental commentors will not be
                                                     Mountain Valley requests                             environmental impact statement (FEIS)                 required to serve copies of filed
                                                  authorization to construct facilities that              or EA for this proposal. The filing of the            documents on all other parties.
                                                  will allow it to provide up to 2.0 million              EA in the Commission’s public record                  However, the non-party commentors
                                                  dekatherms per day of firm                              for this proceeding or the issuance of a              will not receive copies of all documents
                                                  transportation service. Specifically,                   Notice of Schedule for Environmental                  filed by other parties or issued by the


                                             VerDate Sep<11>2014   15:03 Nov 12, 2015   Jkt 238001   PO 00000   Frm 00014   Fmt 4703   Sfmt 4703   E:\FR\FM\13NON1.SGM   13NON1


                                                  70198                       Federal Register / Vol. 80, No. 219 / Friday, November 13, 2015 / Notices

                                                  Commission (except for the mailing of                   www.ferc.gov/docs-filing/efiling.asp.                    m. Individuals desiring to be included
                                                  environmental documents issued by the                   Commenters can submit brief comments                  on the Commission’s mailing list should
                                                  Commission) and will not have the right                 up to 6,000 characters, without prior                 so indicate by writing to the Secretary
                                                  to seek court review of the                             registration, using the eComment system               of the Commission.
                                                  Commission’s final order.                               at http://www.ferc.gov/docs-filing/                      n. Comments, Protests, or Motions to
                                                    The Commission strongly encourages                    ecomment.asp. You must include your                   Intervene: Anyone may submit
                                                  electronic filings of comments, protests                name and contact information at the end               comments, a protest, or a motion to
                                                  and interventions in lieu of paper using                of your comments. For assistance,                     intervene in accordance with the
                                                  the ‘‘eFiling’’ link at http://                         please contact FERC Online Support at                 requirements of Rules of Practice and
                                                  www.ferc.gov. Persons unable to file                    FERCOnlineSupport@ferc.gov, (866)                     Procedure, 18 CFR 385.210, .211, .214.
                                                  electronically should submit an original                208–3676 (toll free), or (202) 502–8659               In determining the appropriate action to
                                                  and 5 copies of the protest or                          (TTY). In lieu of electronic filing, please           take, the Commission will consider all
                                                  intervention to the Federal Energy                      send a paper copy to: Secretary, Federal              protests or other comments filed, but
                                                  regulatory Commission, 888 First Street                 Energy Regulatory Commission, 888                     only those who file a motion to
                                                  NE., Washington, DC 20426.                              First Street NE., Washington, DC 20426.               intervene in accordance with the
                                                    Comment Date: 5:00 p.m. Eastern                       Please include the project number (P–                 Commission’s Rules may become a
                                                  Time on November 26, 2015.                              2246–074) on any comments, motions to                 party to the proceeding. Any comments,
                                                    Dated: November 5, 2015.                              intervene, protests, or recommendations               protests, or motions to intervene must
                                                  Nathaniel J. Davis, Sr.,
                                                                                                          filed.                                                be received on or before the specified
                                                  Deputy Secretary.
                                                                                                             k. Description of Request: The                     comment date for the particular
                                                                                                          licensee requests a temporary variance                application.
                                                  [FR Doc. 2015–28771 Filed 11–12–15; 8:45 am]
                                                                                                          of the minimum flow requirements in                      o. Filing and Service of Responsive
                                                  BILLING CODE 6717–01–P
                                                                                                          the lower Yuba River below Englebright                Documents: Any filing must (1) bear in
                                                                                                          Dam from December 1, 2015 through                     all capital letters the title
                                                  DEPARTMENT OF ENERGY                                    March 31, 2016, due to low reservoir                  ‘‘COMMENTS’’, ‘‘PROTEST’’, or
                                                                                                          storage and dry watershed conditions.                 ‘‘MOTION TO INTERVENE’’ as
                                                  Federal Energy Regulatory                               License Article 33 requires that the                  applicable; (2) set forth in the heading
                                                  Commission                                              licensee provide a minimum flow of:                   the name of the applicant and the
                                                                                                          600 cubic feet per second (cfs) from                  project number of the application to
                                                  [Project No. 2246–074]                                  October 16 through December 31; 1,000                 which the filing responds; (3) furnish
                                                                                                          cfs from January 1–15; and 600 cfs from               the name, address, and telephone
                                                  Yuba County Water Agency; Notice of
                                                                                                          January 16 through March 31. In order                 number of the person protesting or
                                                  Application Accepted for Filing,
                                                                                                          to conserve water resources during the                intervening; and (4) otherwise comply
                                                  Soliciting Comments, Motions To
                                                                                                          current drought, the licensee proposes                with the requirements of 18 CFR
                                                  Intervene, and Protests
                                                                                                          to instead, release 550 cfs from                      385.2001 through 385.2005. All
                                                    Take notice that the following                        December 1, 2015 through March 31,                    comments, motions to intervene, or
                                                  hydroelectric application has been filed                2016. In addition, the licensee requests              protests must set forth their evidentiary
                                                  with the Commission and is available                    that the minimum flow compliance                      basis and otherwise comply with the
                                                  for public inspection:                                  criteria during this period be based on               requirements of 18 CFR 4.34(b). All
                                                    a. Type of Application: Application                   a 5-day running average of average daily              comments, motions to intervene, or
                                                  for Temporary Variance of Minimum                       streamflows, with instantaneous flows                 protests should relate to project works
                                                  Flow Requirement.                                       never less than 90 percent of the                     which are the subject of the license
                                                    b. Project No.: 2246–074.                             specified 550 cfs minimum flow and                    surrender. Agencies may obtain copies
                                                    c. Date Filed: October 30, 2015.                      never less than 550 cfs for more than 48              of the application directly from the
                                                    d. Applicant: Yuba County Water                       hours.                                                applicant. A copy of any protest or
                                                  Agency (licensee).                                         l. Locations of the Application: A                 motion to intervene must be served
                                                    e. Name of Project: Yuba River                        copy of the application is available for              upon each representative of the
                                                  Project.                                                inspection and reproduction at the                    applicant specified in the particular
                                                    f. Location: North Yuba River, Middle                 Commission’s Public Reference Room,                   application. If an intervener files
                                                  Yuba River, and Oregon Creek in Yuba,                   located at 888 First Street NE., Room                 comments or documents with the
                                                  Nevada, and Sierra counties, CA.                        2A, Washington, DC 20426, or by calling               Commission relating to the merits of an
                                                    g. Filed Pursuant to: Federal Power                   (202) 502–8371. This filing may also be               issue that may affect the responsibilities
                                                  Act, 16 U.S.C. 791(a)–825(r).                           viewed on the Commission’s Web site at                of a particular resource agency, they
                                                    h. Applicant Contact: Mr. Curt                        http://www.ferc.gov/docs-filing/                      must also serve a copy of the document
                                                  Aikens, General Manager, Yuba County                    elibrary.asp. Enter the docket number                 on that resource agency. A copy of all
                                                  Water Agency, 1200 F Street,                            excluding the last three digits in the                other filings in reference to this
                                                  Marysville, CA 95901–4740, (530) 741–                   docket number field to access the                     application must be accompanied by
                                                  5015.                                                   document. You may also register online                proof of service on all persons listed in
                                                    i. FERC Contact: Mr. John Aedo, (415)                 at http://www.ferc.gov/docs-filing/                   the service list prepared by the
                                                  369–3335, or john.aedo@ferc.gov.                        esubscription.asp to be notified via                  Commission in this proceeding, in
                                                    j. Deadline for filing comments,                      email of new filings and issuances
jstallworth on DSK7TPTVN1PROD with NOTICES




                                                                                                                                                                accordance with 18 CFR 4.34(b) and
                                                  motions to intervene, protests, and                     related to this or other pending projects.            385.2010.
                                                  recommendations is December 7, 2015.                    For assistance, call 1–866–208- 3676 or
                                                  The Commission strongly encourages                      email FERCOnlineSupport@ferc.gov, for                   Dated: November 5, 2015.
                                                  electronic filing. Please file motions to               TTY, call (202) 502–8659. A copy is also              Nathaniel J. Davis, Sr.,
                                                  intervene, protests, comments, or                       available for inspection and                          Deputy Secretary.
                                                  recommendations using the                               reproduction at the address in item (h)               [FR Doc. 2015–28772 Filed 11–12–15; 8:45 am]
                                                  Commission’s eFiling system at http://                  above.                                                BILLING CODE 6717–01–P




                                             VerDate Sep<11>2014   15:03 Nov 12, 2015   Jkt 238001   PO 00000   Frm 00015   Fmt 4703   Sfmt 9990   E:\FR\FM\13NON1.SGM   13NON1



Document Created: 2018-03-01 11:23:19
Document Modified: 2018-03-01 11:23:19
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
Dates5:00 p.m. Eastern Time on November 26, 2015.
FR Citation80 FR 70196 

2025 Federal Register | Disclaimer | Privacy Policy