81_FR_12793 81 FR 12746 - Final Environmental Impact Statement for the Proposed Aiya Solar Project, Clark County, Nevada

81 FR 12746 - Final Environmental Impact Statement for the Proposed Aiya Solar Project, Clark County, Nevada

DEPARTMENT OF THE INTERIOR
Bureau of Indian Affairs

Federal Register Volume 81, Issue 47 (March 10, 2016)

Page Range12746-12746
FR Document2016-05458

In accordance with the National Environmental Policy Act (NEPA), the Bureau of Indian Affairs (BIA), as the lead Federal agency, with the Bureau of Land Management (BLM), Environmental Protection Agency (EPA), U.S. Fish and Wildlife Service (USFWS), and the Moapa Band of Paiute Indians (Tribe) as Cooperating Agencies, has prepared a final environmental impact statement (FEIS) for the proposed Aiya Solar Project on the Moapa River Indian Reservation in Clark County, Nevada. This notice announces that the FEIS is now available for public review.

Federal Register, Volume 81 Issue 47 (Thursday, March 10, 2016)
[Federal Register Volume 81, Number 47 (Thursday, March 10, 2016)]
[Notices]
[Page 12746]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2016-05458]



[[Page 12746]]

-----------------------------------------------------------------------

DEPARTMENT OF THE INTERIOR

Bureau of Indian Affairs

[167A2100DD/AAKC001030/AOA501010.999900]


Final Environmental Impact Statement for the Proposed Aiya Solar 
Project, Clark County, Nevada

AGENCY: Bureau of Indian Affairs, Interior.

ACTION: Notice of availability.

-----------------------------------------------------------------------

SUMMARY: In accordance with the National Environmental Policy Act 
(NEPA), the Bureau of Indian Affairs (BIA), as the lead Federal agency, 
with the Bureau of Land Management (BLM), Environmental Protection 
Agency (EPA), U.S. Fish and Wildlife Service (USFWS), and the Moapa 
Band of Paiute Indians (Tribe) as Cooperating Agencies, has prepared a 
final environmental impact statement (FEIS) for the proposed Aiya Solar 
Project on the Moapa River Indian Reservation in Clark County, Nevada. 
This notice announces that the FEIS is now available for public review.

DATES: The Record of Decision on the proposed action will be issued no 
sooner than 30 days after EPA publishes a Notice of Availability in the 
Federal Register.

ADDRESSES: You may request a compact disk copy of the FEIS by providing 
your name and address in writing or by voicemail to Mr. Chip Lewis, 
Acting Regional Environmental Protection Officer, BIA Western Regional 
Office, Branch of Environmental Quality Services, 2600 North Central 
Avenue, 4th Floor Mail Room, Phoenix, Arizona 85004-3008; fax (602) 
379-3833; email: [email protected]. The FEIS will be available for 
review at: BIA Western Regional Office, 2600 North Central Avenue, 12th 
Floor, Suite 210, Phoenix, Arizona; BIA Southern Paiute Agency, 180 
North 200 East, Suite 111, St. George, Utah; and the BLM Southern 
Nevada District Office, 4701 N. Torrey Pines Drive, Las Vegas, Nevada. 
The FEIS is also available on line at: www.AiyaSolarProjectEIS.com. 
Individual paper copies of the FEIS will be provided only upon request.

FOR FURTHER INFORMATION CONTACT: Mr. Chip Lewis, BIA Western Regional 
Office, Branch of Environmental Quality Services, 2600 North Central 
Avenue, Phoenix, Arizona 85004-3008, telephone (602) 379-6782; or Mr. 
Garry Cantley at (602) 379-6750.

SUPPLEMENTARY INFORMATION: The proposed Federal action, taken under 25 
U.S.C. 415, is BIA's approval of a solar energy ground lease and 
associated agreements entered into by the Tribe with Aiya Solar 
Project, LLC (Aiya Solar or Applicant), a wholly owned subsidiary of 
First Solar, Inc. (First Solar), to provide for construction and 
operation of an up-to 100 megawatt (MW) alternating current solar 
photovoltaic (PV) electricity generation facility located entirely on 
the Moapa River Indian Reservation and specifically on lands held in 
trust by the United States for the Tribe. The proposed 230 kilovolt 
(kV) generation-tie transmission line required for interconnection 
would be located on Tribal lands, private lands and Federal lands 
administered and managed by BLM. The Applicant has accordingly 
requested that the BIA and BLM additionally approve rights-of-way 
(ROWs) authorizing the construction and operation of the transmission 
line. Together, the proposed solar energy facility, transmission line, 
and other associated facilities make up the proposed Aiya Solar Project 
(Project).
    The Project would be located in Township 14 South, Range 66 East, 
Sections 29, 30, 31, and 32 Mount Diablo Meridian, Nevada. The 
generation facility would generate electricity using PV panels. Also 
included would be inverters, a collection system, an on-site substation 
to step-up the voltage to transmission level voltage at 230 kV, an 
operations and maintenance building, and other related facilities. An 
overhead 230 kV generation-tie transmission line, approximately 2.7 
miles long, would connect the solar project to NV Energy's Reid-Gardner 
230kV substation.
    Construction of the Project is expected to take approximately 12 to 
15 months. The Applicant is expected to operate the energy facility for 
30 years, with two options to renew the lease for an additional 10 
years, if mutually acceptable to the Tribe and Applicant. During 
construction, the PV panels will be placed on top of fixed-tilt and/or 
single-axis tracking mounting systems that are set on steel posts 
embedded in the ground. Other foundation design techniques may be used 
depending on the site topography and conditions. No water will be used 
to generate electricity during operations. Water will be needed during 
construction for dust control and a minimal amount will be needed 
during operations for landscape irrigation and administrative and 
sanitary water use on site. The water supply required for construction 
of the Project would be leased from the Moapa Band and would be 
provided via a new temporary intake installed in the Muddy River and a 
new temporary above-ground pipeline approximately two miles in length. 
Operational water would be provided through a tap into an existing 
water pipeline that crosses the solar site. Access to the Project will 
be provided via State Highway 168.
    The purposes of the Project are to: (1) Provide a long-term, 
diverse, and viable economic revenue base and job opportunities for the 
Tribe; (2) help Nevada and neighboring states to meet their state 
renewable energy needs; and (3) allow the Tribe, in partnership with 
the Applicant, to optimize the use of the lease site while maximizing 
the potential economic benefit to the Tribe.
    The BIA and BLM will use the EIS to make decisions on the land 
lease and ROW applications under their respective jurisdiction; EPA may 
use the document to make decisions under its authorities; the Tribe may 
use the EIS to make decisions under its Tribal Environmental Policy 
Ordinance; and the USFWS may use the EIS to support its decision under 
the Endangered Species Act.

    Authority:  This notice is published in accordance with section 
1503.1 of the Council on Environmental Quality regulations (40 CFR 
part 1500 et seq.) and the Department of the Interior Regulations 
(43 CFR part 46) implementing the procedural requirements of NEPA 
(42 U.S.C. 4321 et seq.), and in accordance with the exercise of 
authority delegated to the Assistant Secretary--Indian Affairs by 
part 209 of the Department Manual.

    Dated: March 1, 2016.
Lawrence S. Roberts,
Acting Assistant Secretary--Indian Affairs.
[FR Doc. 2016-05458 Filed 3-9-16; 8:45 am]
 BILLING CODE 4337-15-P



                                                  12746                        Federal Register / Vol. 81, No. 47 / Thursday, March 10, 2016 / Notices

                                                  DEPARTMENT OF THE INTERIOR                              energy ground lease and associated                    ground pipeline approximately two
                                                                                                          agreements entered into by the Tribe                  miles in length. Operational water
                                                  Bureau of Indian Affairs                                with Aiya Solar Project, LLC (Aiya Solar              would be provided through a tap into an
                                                  [167A2100DD/AAKC001030/AOA501010.                       or Applicant), a wholly owned                         existing water pipeline that crosses the
                                                  999900]                                                 subsidiary of First Solar, Inc. (First                solar site. Access to the Project will be
                                                                                                          Solar), to provide for construction and               provided via State Highway 168.
                                                  Final Environmental Impact Statement                    operation of an up-to 100 megawatt                       The purposes of the Project are to: (1)
                                                  for the Proposed Aiya Solar Project,                    (MW) alternating current solar                        Provide a long-term, diverse, and viable
                                                  Clark County, Nevada                                    photovoltaic (PV) electricity generation              economic revenue base and job
                                                                                                          facility located entirely on the Moapa                opportunities for the Tribe; (2) help
                                                  AGENCY:   Bureau of Indian Affairs,                     River Indian Reservation and                          Nevada and neighboring states to meet
                                                  Interior.                                               specifically on lands held in trust by the            their state renewable energy needs; and
                                                  ACTION: Notice of availability.                         United States for the Tribe. The                      (3) allow the Tribe, in partnership with
                                                                                                          proposed 230 kilovolt (kV) generation-                the Applicant, to optimize the use of the
                                                  SUMMARY:   In accordance with the                       tie transmission line required for                    lease site while maximizing the
                                                  National Environmental Policy Act                       interconnection would be located on                   potential economic benefit to the Tribe.
                                                  (NEPA), the Bureau of Indian Affairs                    Tribal lands, private lands and Federal                  The BIA and BLM will use the EIS to
                                                  (BIA), as the lead Federal agency, with                 lands administered and managed by                     make decisions on the land lease and
                                                  the Bureau of Land Management (BLM),                    BLM. The Applicant has accordingly                    ROW applications under their
                                                  Environmental Protection Agency                         requested that the BIA and BLM                        respective jurisdiction; EPA may use the
                                                  (EPA), U.S. Fish and Wildlife Service                   additionally approve rights-of-way                    document to make decisions under its
                                                  (USFWS), and the Moapa Band of Paiute                   (ROWs) authorizing the construction                   authorities; the Tribe may use the EIS to
                                                  Indians (Tribe) as Cooperating Agencies,                and operation of the transmission line.               make decisions under its Tribal
                                                  has prepared a final environmental                      Together, the proposed solar energy                   Environmental Policy Ordinance; and
                                                  impact statement (FEIS) for the                         facility, transmission line, and other                the USFWS may use the EIS to support
                                                  proposed Aiya Solar Project on the                      associated facilities make up the                     its decision under the Endangered
                                                  Moapa River Indian Reservation in                       proposed Aiya Solar Project (Project).                Species Act.
                                                  Clark County, Nevada. This notice                          The Project would be located in
                                                  announces that the FEIS is now                          Township 14 South, Range 66 East,                       Authority: This notice is published in
                                                  available for public review.                                                                                  accordance with section 1503.1 of the
                                                                                                          Sections 29, 30, 31, and 32 Mount
                                                                                                                                                                Council on Environmental Quality
                                                  DATES: The Record of Decision on the                    Diablo Meridian, Nevada. The                          regulations (40 CFR part 1500 et seq.) and the
                                                  proposed action will be issued no                       generation facility would generate                    Department of the Interior Regulations (43
                                                  sooner than 30 days after EPA publishes                 electricity using PV panels. Also                     CFR part 46) implementing the procedural
                                                  a Notice of Availability in the Federal                 included would be inverters, a                        requirements of NEPA (42 U.S.C. 4321 et
                                                  Register.                                               collection system, an on-site substation              seq.), and in accordance with the exercise of
                                                  ADDRESSES: You may request a compact                    to step-up the voltage to transmission                authority delegated to the Assistant
                                                                                                          level voltage at 230 kV, an operations                Secretary—Indian Affairs by part 209 of the
                                                  disk copy of the FEIS by providing your
                                                                                                          and maintenance building, and other                   Department Manual.
                                                  name and address in writing or by
                                                  voicemail to Mr. Chip Lewis, Acting                     related facilities. An overhead 230 kV                  Dated: March 1, 2016.
                                                  Regional Environmental Protection                       generation-tie transmission line,                     Lawrence S. Roberts,
                                                  Officer, BIA Western Regional Office,                   approximately 2.7 miles long, would                   Acting Assistant Secretary—Indian Affairs.
                                                  Branch of Environmental Quality                         connect the solar project to NV Energy’s              [FR Doc. 2016–05458 Filed 3–9–16; 8:45 am]
                                                  Services, 2600 North Central Avenue,                    Reid-Gardner 230kV substation.
                                                                                                                                                                BILLING CODE 4337–15–P
                                                  4th Floor Mail Room, Phoenix, Arizona                      Construction of the Project is
                                                  85004–3008; fax (602) 379–3833; email:                  expected to take approximately 12 to 15
                                                  chip.lewis@bia.gov. The FEIS will be                    months. The Applicant is expected to                  DEPARTMENT OF THE INTERIOR
                                                  available for review at: BIA Western                    operate the energy facility for 30 years,
                                                  Regional Office, 2600 North Central                     with two options to renew the lease for               Bureau of Indian Affairs
                                                                                                          an additional 10 years, if mutually
                                                  Avenue, 12th Floor, Suite 210, Phoenix,
                                                                                                          acceptable to the Tribe and Applicant.                [167 A2100DD/AAKC001030/
                                                  Arizona; BIA Southern Paiute Agency,
                                                                                                          During construction, the PV panels will               A0A501010.999900]
                                                  180 North 200 East, Suite 111, St.
                                                                                                          be placed on top of fixed-tilt and/or
                                                  George, Utah; and the BLM Southern                                                                            Indian Gaming; Extension of Tribal-
                                                                                                          single-axis tracking mounting systems
                                                  Nevada District Office, 4701 N. Torrey                                                                        State Class III Gaming Compact
                                                                                                          that are set on steel posts embedded in
                                                  Pines Drive, Las Vegas, Nevada. The                                                                           (Rosebud Sioux Tribe and the State of
                                                                                                          the ground. Other foundation design
                                                  FEIS is also available on line at:                                                                            South Dakota)
                                                                                                          techniques may be used depending on
                                                  www.AiyaSolarProjectEIS.com.
                                                                                                          the site topography and conditions. No
                                                  Individual paper copies of the FEIS will                                                                      AGENCY:   Bureau of Indian Affairs,
                                                                                                          water will be used to generate electricity
                                                  be provided only upon request.                          during operations. Water will be needed               Interior.
                                                  FOR FURTHER INFORMATION CONTACT: Mr.                    during construction for dust control and              ACTION: Notice.
                                                  Chip Lewis, BIA Western Regional                        a minimal amount will be needed
                                                  Office, Branch of Environmental Quality                                                                       SUMMARY:  This notice announces the
mstockstill on DSK4VPTVN1PROD with NOTICES




                                                                                                          during operations for landscape
                                                  Services, 2600 North Central Avenue,                    irrigation and administrative and                     extension of the Class III gaming
                                                  Phoenix, Arizona 85004–3008,                            sanitary water use on site. The water                 compact between the Rosebud Sioux
                                                  telephone (602) 379–6782; or Mr. Garry                  supply required for construction of the               Tribe and the State of South Dakota.
                                                  Cantley at (602) 379–6750.                              Project would be leased from the Moapa                DATES: Effective March 10, 2016.
                                                  SUPPLEMENTARY INFORMATION: The                          Band and would be provided via a new                  FOR FURTHER INFORMATION CONTACT: Ms.
                                                  proposed Federal action, taken under 25                 temporary intake installed in the Muddy               Paula L. Hart, Director, Office of Indian
                                                  U.S.C. 415, is BIA’s approval of a solar                River and a new temporary above-                      Gaming, Office of the Assistant


                                             VerDate Sep<11>2014   17:55 Mar 09, 2016   Jkt 238001   PO 00000   Frm 00067   Fmt 4703   Sfmt 4703   E:\FR\FM\10MRN1.SGM   10MRN1



Document Created: 2018-02-02 15:11:59
Document Modified: 2018-02-02 15:11:59
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
ActionNotice of availability.
DatesThe Record of Decision on the proposed action will be issued no sooner than 30 days after EPA publishes a Notice of Availability in the Federal Register.
ContactMr. Chip Lewis, BIA Western Regional Office, Branch of Environmental Quality Services, 2600 North Central Avenue, Phoenix, Arizona 85004-3008, telephone (602) 379-6782; or Mr. Garry Cantley at (602) 379-6750.
FR Citation81 FR 12746 