81_FR_1419 81 FR 1412 - Mill and Main Hydroelectric Project; Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications

81 FR 1412 - Mill and Main Hydroelectric Project; Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 81, Issue 7 (January 12, 2016)

Page Range1412-1412
FR Document2016-00401

Federal Register, Volume 81 Issue 7 (Tuesday, January 12, 2016)
[Federal Register Volume 81, Number 7 (Tuesday, January 12, 2016)]
[Notices]
[Page 1412]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2016-00401]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 14722-000]


Mill and Main Hydroelectric Project; Notice of Preliminary Permit 
Application Accepted for Filing and Soliciting Comments, Motions To 
Intervene, and Competing Applications

    On October 16, 2015, AS Clock Tower Owner, LLC, filed an 
application for a preliminary permit, pursuant to section 4(f) of the 
Federal Power Act (FPA), proposing to study the feasibility of the Mill 
and Main Hydroelectric Project (Mill and Main Project) to be located on 
the Assabet River, near Maynard, Middlesex County, Massachusetts. The 
sole purpose of a preliminary permit, if issued, is to grant the permit 
holder priority to file a license application during the permit term. A 
preliminary permit does not authorize the permit holder to perform any 
land-disturbing activities or otherwise enter upon lands or waters 
owned by others without the owners' express permission.
    The proposed project would consist of: (1) The existing 9.5-foot-
high, 170-foot-long granite block Ben Smith dam; (2) the existing 
18.75-acre Ben Smith dam impoundment with a storage capacity of 475 
acre-feet and a normal water surface elevation of 177 feet above mean 
sea level (msl); (3) an existing 1,600-foot-long power canal leading to 
an existing gatehouse at the upstream end of the existing 18.3-acre 
Mill Pond impoundment with a storage capacity of 130 acre-feet and a 
normal water surface elevation of 176 feet msl; (4) the existing 
masonry Mill Pond dam; (5) an existing 7-foot-diameter, 49-foot-long 
penstock; (6) an existing masonry powerhouse containing one turbine-
generator unit with an installed capacity of 290-kilowatts; (7) two 
300-foot-long masonry tailraces; (8) an existing 480-volt transmission 
line and a 13.8 kV step-up transformer to interconnect the project with 
the Clock Tower Place; and (9) appurtenant facilities. The estimated 
annual generation of the Mill and Main Project would be about 1,241 
megawatt-hours. The existing Ben Smith and Mill dams and appurtenant 
works are owned by AS Clock Tower Owner, LLC.
    Applicant Contact: Mr. Kurt W. Saraceno, AS Clock Tower Owner, LLC, 
c/o Saracen Properties. 41 Seyon Street, Suite 200, Waltham, MA 02453; 
phone: (781) 250-8000 x2710.
    FERC Contact: Patrick Crile; phone: (202) 502-8042 or email: 
[email protected].
    Deadline for filing comments, motions to intervene, competing 
applications (without notices of intent), or notices of intent to file 
competing applications: 60 days from the issuance of this notice. 
Competing applications and notices of intent must meet the requirements 
of 18 CFR 4.36.
    The Commission strongly encourages electronic filing. Please file 
comments, motions to intervene, notices of intent, and competing 
applications using the Commission's eFiling system at http://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief 
comments up to 6,000 characters, without prior registration, using the 
eComment system at http://www.ferc.gov/docs-filing/ecomment.asp. You 
must include your name and contact information at the end of your 
comments. For assistance, please contact FERC Online Support at 
[email protected], (866) 208-3676 (toll free), or (202) 502-
8659 (TTY). In lieu of electronic filing, please send a paper copy to: 
Secretary, Federal Energy Regulatory Commission, 888 First Street NE., 
Washington, DC 20426. The first page of any filing should include 
docket number P-14722-000.
    More information about this project, including a copy of the 
application, can be viewed or printed on the ``eLibrary'' link of 
Commission's Web site at http://www.ferc.gov/docs-filing/elibrary.asp. 
Enter the docket number (P-14722) in the docket number field to access 
the document. For assistance, contact FERC Online Support.

    Dated: January 6, 2016.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2016-00401 Filed 1-11-16; 8:45 am]
BILLING CODE 6717-01-P



                                              1412                          Federal Register / Vol. 81, No. 7 / Tuesday, January 12, 2016 / Notices

                                              DEPARTMENT OF ENERGY                                    Protests may be considered, but                        tailraces; (8) an existing 480-volt
                                                                                                      intervention is necessary to become a                  transmission line and a 13.8 kV step-up
                                              Federal Energy Regulatory                               party to the proceeding.                               transformer to interconnect the project
                                              Commission                                                 eFiling is encouraged. More detailed                with the Clock Tower Place; and (9)
                                                                                                      information relating to filing                         appurtenant facilities. The estimated
                                              Combined Notice of Filings #1                           requirements, interventions, protests,                 annual generation of the Mill and Main
                                                 Take notice that the Commission                      service, and qualifying facilities filings             Project would be about 1,241 megawatt-
                                              received the following electric rate                    can be found at: http://www.ferc.gov/                  hours. The existing Ben Smith and Mill
                                              filings:                                                docs-filing/efiling/filing-req.pdf. For                dams and appurtenant works are owned
                                                 Docket Numbers: ER16–683–000.                        other information, call (866) 208–3676                 by AS Clock Tower Owner, LLC.
                                                 Applicants: Southern California                      (toll free). For TTY, call (202) 502–8659.
                                                                                                                                                                Applicant Contact: Mr. Kurt W.
                                              Edison Company.                                           Dated: January 6, 2016.
                                                                                                                                                             Saraceno, AS Clock Tower Owner, LLC,
                                                 Description: Section 205(d) Rate                     Nathaniel J. Davis, Sr.,                               c/o Saracen Properties. 41 Seyon Street,
                                              Filing: LGIA Sunray Energy, LLC SEGS                    Deputy Secretary.                                      Suite 200, Waltham, MA 02453; phone:
                                              II Project to be effective 1/1/2016.                    [FR Doc. 2016–00398 Filed 1–11–16; 8:45 am]
                                                 Filed Date: 1/6/16.                                                                                         (781) 250–8000 x2710.
                                                                                                      BILLING CODE 6717–01–P
                                                 Accession Number: 20160106–5000.                                                                               FERC Contact: Patrick Crile; phone:
                                                 Comments Due: 5 p.m. ET 1/27/16.                                                                            (202) 502–8042 or email: Patrick.Crile@
                                                 Docket Numbers: ER16–684–000.                        DEPARTMENT OF ENERGY                                   ferc.gov.
                                                 Applicants: AlphaGen Power LLC.                                                                                Deadline for filing comments, motions
                                                 Description: Section 205(d) Rate                     Federal Energy Regulatory                              to intervene, competing applications
                                              Filing: Cancellation of MBR tariff to be                Commission                                             (without notices of intent), or notices of
                                              effective 3/6/2016.                                     [Project No. 14722–000]                                intent to file competing applications: 60
                                                 Filed Date: 1/6/16.                                                                                         days from the issuance of this notice.
                                                 Accession Number: 20160106–5126.                     Mill and Main Hydroelectric Project;                   Competing applications and notices of
                                                 Comments Due: 5 p.m. ET 1/27/16.                     Notice of Preliminary Permit                           intent must meet the requirements of 18
                                                 Docket Numbers: ER16–685–000.                        Application Accepted for Filing and                    CFR 4.36.
                                                 Applicants: PJM Interconnection,                     Soliciting Comments, Motions To
                                              L.L.C.                                                  Intervene, and Competing Applications                     The Commission strongly encourages
                                                 Description: Section 205(d) Rate                                                                            electronic filing. Please file comments,
                                              Filing: Original Service Agreement No.                     On October 16, 2015, AS Clock Tower                 motions to intervene, notices of intent,
                                              4327; Queue No. AA1–057 to be                           Owner, LLC, filed an application for a                 and competing applications using the
                                              effective 12/9/2015.                                    preliminary permit, pursuant to section                Commission’s eFiling system at http://
                                                 Filed Date: 1/6/16.                                  4(f) of the Federal Power Act (FPA),                   www.ferc.gov/docs-filing/efiling.asp.
                                                 Accession Number: 20160106–5171.                     proposing to study the feasibility of the              Commenters can submit brief comments
                                                 Comments Due: 5 p.m. ET 1/27/16.                     Mill and Main Hydroelectric Project                    up to 6,000 characters, without prior
                                                                                                      (Mill and Main Project) to be located on               registration, using the eComment system
                                                 Docket Numbers: ER16–686–000.                        the Assabet River, near Maynard,
                                                 Applicants: Southern California                                                                             at http://www.ferc.gov/docs-filing/
                                                                                                      Middlesex County, Massachusetts. The                   ecomment.asp. You must include your
                                              Edison Company.                                         sole purpose of a preliminary permit, if
                                                 Description: Section 205(d) Rate                                                                            name and contact information at the end
                                                                                                      issued, is to grant the permit holder
                                              Filing: Revised Non-Trasmission                                                                                of your comments. For assistance,
                                                                                                      priority to file a license application
                                              Depreciation Rates in SCE’s Formula                                                                            please contact FERC Online Support at
                                                                                                      during the permit term. A preliminary
                                              Transmission Rate to be effective 1/1/                                                                         FERCOnlineSupport@ferc.gov, (866)
                                                                                                      permit does not authorize the permit
                                              2015.                                                   holder to perform any land-disturbing                  208–3676 (toll free), or (202) 502–8659
                                                 Filed Date: 1/6/16.                                  activities or otherwise enter upon lands               (TTY). In lieu of electronic filing, please
                                                 Accession Number: 20160106–5226.                     or waters owned by others without the                  send a paper copy to: Secretary, Federal
                                                 Comments Due: 5 p.m. ET 1/27/16.                     owners’ express permission.                            Energy Regulatory Commission, 888
                                                 Docket Numbers: ER16–687–000.                           The proposed project would consist                  First Street NE., Washington, DC 20426.
                                                 Applicants: PacifiCorp.                              of: (1) The existing 9.5-foot-high, 170-               The first page of any filing should
                                                 Description: Section 205(d) Rate                     foot-long granite block Ben Smith dam;                 include docket number P–14722–000.
                                              Filing: Noble Americas Energy                           (2) the existing 18.75-acre Ben Smith                     More information about this project,
                                              Solutions NITSA Rev 9 to be effective 1/                dam impoundment with a storage                         including a copy of the application, can
                                              1/2016.                                                 capacity of 475 acre-feet and a normal                 be viewed or printed on the ‘‘eLibrary’’
                                                 Filed Date: 1/6/16.                                  water surface elevation of 177 feet above              link of Commission’s Web site at http://
                                                 Accession Number: 20160106–5233.                     mean sea level (msl); (3) an existing                  www.ferc.gov/docs-filing/elibrary.asp.
                                                 Comments Due: 5 p.m. ET 1/27/16.                     1,600-foot-long power canal leading to                 Enter the docket number (P–14722) in
                                                 The filings are accessible in the                    an existing gatehouse at the upstream                  the docket number field to access the
                                              Commission’s eLibrary system by                         end of the existing 18.3-acre Mill Pond                document. For assistance, contact FERC
                                              clicking on the links or querying the                   impoundment with a storage capacity of
                                                                                                                                                             Online Support.
                                              docket number.                                          130 acre-feet and a normal water surface
tkelley on DSK3SPTVN1PROD with NOTICES




                                                 Any person desiring to intervene or                  elevation of 176 feet msl; (4) the existing              Dated: January 6, 2016.
                                              protest in any of the above proceedings                 masonry Mill Pond dam; (5) an existing                 Nathaniel J. Davis, Sr.,
                                              must file in accordance with Rules 211                  7-foot-diameter, 49-foot-long penstock;                Deputy Secretary.
                                              and 214 of the Commission’s                             (6) an existing masonry powerhouse                     [FR Doc. 2016–00401 Filed 1–11–16; 8:45 am]
                                              Regulations (18 CFR 385.211 and                         containing one turbine-generator unit
                                                                                                                                                             BILLING CODE 6717–01–P
                                              385.214) on or before 5:00 p.m. Eastern                 with an installed capacity of 290-
                                              time on the specified comment date.                     kilowatts; (7) two 300-foot-long masonry


                                         VerDate Sep<11>2014   20:14 Jan 11, 2016   Jkt 238001   PO 00000   Frm 00027   Fmt 4703   Sfmt 9990   E:\FR\FM\12JAN1.SGM   12JAN1



Document Created: 2016-01-12 01:22:55
Document Modified: 2016-01-12 01:22:55
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation81 FR 1412 

2025 Federal Register | Disclaimer | Privacy Policy
USC | CFR | eCFR