81_FR_26304 81 FR 26220 - Eastern Shore Natural Gas Company; Notice of Availability of the Environmental Assessment for the Proposed White Oak Mainline Expansion Project and System Reliability Project

81 FR 26220 - Eastern Shore Natural Gas Company; Notice of Availability of the Environmental Assessment for the Proposed White Oak Mainline Expansion Project and System Reliability Project

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 81, Issue 84 (May 2, 2016)

Page Range26220-26221
FR Document2016-10097

Federal Register, Volume 81 Issue 84 (Monday, May 2, 2016)
[Federal Register Volume 81, Number 84 (Monday, May 2, 2016)]
[Notices]
[Pages 26220-26221]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2016-10097]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket Nos. CP15-18-000; CP15-18-001; CP15-498-000]


Eastern Shore Natural Gas Company; Notice of Availability of the 
Environmental Assessment for the Proposed White Oak Mainline Expansion 
Project and System Reliability Project

    The staff of the Federal Energy Regulatory Commission (FERC or 
Commission) has prepared an environmental assessment (EA) for the White 
Oak Mainline Expansion (White Oak) Project and System Reliability 
Project, proposed by Eastern Shore Natural Gas Company (Eastern Shore) 
in the above-referenced docket. Eastern Shore requests authorization to 
construct, install, own, operate, and maintain certain facilities 
located in Chester County, Pennsylvania and New Castle, Kent, and 
Sussex, Counties, Delaware.
    The EA assesses the potential environmental effects of the 
construction and operation of the White Oak and System Reliability 
Projects in accordance with the requirements of the National 
Environmental Policy Act (NEPA). The FERC staff concludes that approval 
of the proposed projects, with appropriate mitigating measures, would 
not constitute a major federal action significantly affecting the 
quality of the human environment.
    Specifically, the proposed White Oak Project includes the following 
facilities:
     3.3 miles of 16-inch-diameter looping pipeline (the 
Daleville Loop) in Chester County, Pennsylvania;
     2.1 miles of 16-inch-diameter looping pipeline 
(Kemblesville Loop) in Chester County, Pennsylvania; and
     3,550 horsepower of additional compression at Eastern 
Shore's existing Delaware City Compressor Station in New Castle County, 
Delaware.
    Specifically, the proposed System Reliability Project includes the 
following facilities:
     2.5 miles of 16-inch-diameter looping pipeline (Porter 
Road Loop) in New Castle County, Delaware;
     7.6 miles of 16-inch-diameter looping pipeline (Dover 
Loop) in Kent County, Delaware;
     installation of associated underground and aboveground 
facilities (two mainline valves, a meter and regulator station); and
     an additional 1,775 horsepower of compression at Eastern 
Shore's existing Bridgeville Compressor Station in Sussex County, 
Delaware.
    The FERC staff mailed copies of the EA to federal, state, and local 
government representatives and agencies; elected officials; 
environmental and public interest groups; Native American tribes; 
potentially affected landowners and other interested individuals and 
groups; newspapers and libraries in each project area; and parties to 
this proceeding.
    In addition, the EA is available for public viewing on the FERC's 
Web site (www.ferc.gov) using the eLibrary link. A limited number of 
copies of the EA are available for distribution and public inspection 
at: Federal Energy Regulatory Commission, Public Reference Room, 888 
First Street NE., Room 2A, Washington, DC 20426, (202) 502-8371.
    Any person wishing to comment on the EA may do so. Your comments 
should focus on the potential environmental effects, reasonable 
alternatives, and measures to avoid or lessen environmental impacts. 
The more specific your comments, the more useful they will be. To 
ensure that the Commission has the opportunity to consider your 
comments prior to making its decision on these projects, it is 
important that we receive your comments in Washington, DC on or before 
May 25, 2016.
    For your convenience, there are three methods you can use to file 
your comments with the Commission. In all instances, please reference 
the project docket number (CP15-18-001 or CP15-498-000 [as applicable]) 
with your submission. The Commission encourages electronic filing of 
comments and has expert staff available to assist you at (202) 502-8258 
or [email protected].
    (1) You can file your comments electronically using the eComment 
feature on the Commission's Web site (www.ferc.gov) under the link to 
Documents and Filings. This is an easy method for submitting brief, 
text-only comments on a project;
    (2) You can also file your comments electronically using the 
eFiling feature on the Commission's Web site (www.ferc.gov) under the 
link to Documents and Filings. With eFiling, you can provide comments 
in a variety of formats by attaching them as a file with your 
submission. New eFiling users must first create an account by clicking 
on ``eRegister.'' You must select the type of filing you are making. If 
you are filing a comment on a particular project, please select 
``Comment on a Filing''; or
    (3) You can file a paper copy of your comments by mailing them to 
the following address: Kimberly D. Bose, Secretary, Federal Energy 
Regulatory Commission, 888 First Street NE., Room 1A, Washington, DC 
20426.
    Any person seeking to become a party to the proceeding must file a 
motion to intervene pursuant to Rule 214 of the Commission's Rules of 
Practice and Procedures (18 CFR 385.214).\1\ Only intervenors have the 
right to seek rehearing of the Commission's decision. The Commission 
grants affected landowners and others with environmental concerns 
intervenor status upon showing good cause by stating that they have a 
clear and direct interest in this proceeding which no other party can 
adequately represent.

[[Page 26221]]

Simply filing environmental comments will not give you intervenor 
status, but you do not need intervenor status to have your comments 
considered.
---------------------------------------------------------------------------

    \1\ See the previous discussion on the methods for filing 
comments.
---------------------------------------------------------------------------

    Additional information about the projects is available from the 
Commission's Office of External Affairs, at (866) 208-FERC, or on the 
FERC Web site (www.ferc.gov) using the eLibrary link. Click on the 
eLibrary link, click on ``General Search,'' and enter the docket number 
excluding the last three digits in the Docket Number field (i.e., CP15-
18 or CP15-498). Be sure you have selected an appropriate date range. 
For assistance, please contact FERC Online Support at 
[email protected] or toll free at (866) 208-3676, or for TTY, 
contact (202) 502-8659. The eLibrary link also provides access to the 
texts of formal documents issued by the Commission, such as orders, 
notices, and rulemakings.
    In addition, the Commission offers a free service called 
eSubscription which allows you to keep track of all formal issuances 
and submittals in specific dockets. This can reduce the amount of time 
you spend researching proceedings by automatically providing you with 
notification of these filings, document summaries, and direct links to 
the documents. Go to www.ferc.gov/docs-filing/esubscription.asp.

    Dated: April 25, 2016.
Kimberly D. Bose,
Secretary.
[FR Doc. 2016-10097 Filed 4-29-16; 8:45 am]
 BILLING CODE 6717-01-P



                                                26220                            Federal Register / Vol. 81, No. 84 / Monday, May 2, 2016 / Notices

                                                to the applicant’s request for blanket                  Natural Gas Company (Eastern Shore) in                   Any person wishing to comment on
                                                authorization, under 18 CFR part 34, of                 the above-referenced docket. Eastern                  the EA may do so. Your comments
                                                future issuances of securities and                      Shore requests authorization to                       should focus on the potential
                                                assumptions of liability, is May 11,                    construct, install, own, operate, and                 environmental effects, reasonable
                                                2016.                                                   maintain certain facilities located in                alternatives, and measures to avoid or
                                                   The Commission encourages                            Chester County, Pennsylvania and New                  lessen environmental impacts. The more
                                                electronic submission of protests and                   Castle, Kent, and Sussex, Counties,                   specific your comments, the more useful
                                                interventions in lieu of paper, using the               Delaware.                                             they will be. To ensure that the
                                                FERC Online links at http://                              The EA assesses the potential                       Commission has the opportunity to
                                                www.ferc.gov. To facilitate electronic                  environmental effects of the                          consider your comments prior to
                                                service, persons with Internet access                   construction and operation of the White               making its decision on these projects, it
                                                who will eFile a document and/or be                     Oak and System Reliability Projects in                is important that we receive your
                                                listed as a contact for an intervenor                   accordance with the requirements of the               comments in Washington, DC on or
                                                must create and validate an                             National Environmental Policy Act                     before May 25, 2016.
                                                eRegistration account using the                         (NEPA). The FERC staff concludes that                    For your convenience, there are three
                                                eRegistration link. Select the eFiling                  approval of the proposed projects, with               methods you can use to file your
                                                link to log on and submit the                           appropriate mitigating measures, would                comments with the Commission. In all
                                                intervention or protests.                               not constitute a major federal action                 instances, please reference the project
                                                   Persons unable to file electronically                significantly affecting the quality of the            docket number (CP15–18–001 or CP15–
                                                should submit an original and 5 copies                  human environment.                                    498–000 [as applicable]) with your
                                                of the intervention or protest to the                     Specifically, the proposed White Oak                submission. The Commission
                                                Federal Energy Regulatory Commission,                   Project includes the following facilities:            encourages electronic filing of
                                                888 First Street NE., Washington, DC                      • 3.3 miles of 16-inch-diameter                     comments and has expert staff available
                                                20426.                                                  looping pipeline (the Daleville Loop) in              to assist you at (202) 502–8258 or
                                                   The filings in the above-referenced                  Chester County, Pennsylvania;                         efiling@ferc.gov.
                                                proceeding are accessible in the                          • 2.1 miles of 16-inch-diameter                        (1) You can file your comments
                                                Commission’s eLibrary system by                         looping pipeline (Kemblesville Loop) in               electronically using the eComment
                                                clicking on the appropriate link in the                 Chester County, Pennsylvania; and                     feature on the Commission’s Web site
                                                above list. They are also available for                   • 3,550 horsepower of additional                    (www.ferc.gov) under the link to
                                                electronic review in the Commission’s                   compression at Eastern Shore’s existing               Documents and Filings. This is an easy
                                                Public Reference Room in Washington,                    Delaware City Compressor Station in                   method for submitting brief, text-only
                                                DC. There is an eSubscription link on                   New Castle County, Delaware.                          comments on a project;
                                                the Web site that enables subscribers to                                                                         (2) You can also file your comments
                                                                                                          Specifically, the proposed System
                                                receive email notification when a                                                                             electronically using the eFiling feature
                                                                                                        Reliability Project includes the
                                                document is added to a subscribed                                                                             on the Commission’s Web site
                                                                                                        following facilities:
                                                                                                                                                              (www.ferc.gov) under the link to
                                                docket(s). For assistance with any FERC                   • 2.5 miles of 16-inch-diameter
                                                Online service, please email                                                                                  Documents and Filings. With eFiling,
                                                                                                        looping pipeline (Porter Road Loop) in
                                                FERCOnlineSupport@ferc.gov. or call                                                                           you can provide comments in a variety
                                                                                                        New Castle County, Delaware;
                                                                                                                                                              of formats by attaching them as a file
                                                (866) 208–3676 (toll free). For TTY, call                 • 7.6 miles of 16-inch-diameter                     with your submission. New eFiling
                                                (202) 502–8659.                                         looping pipeline (Dover Loop) in Kent                 users must first create an account by
                                                  Dated: April 21, 2016.                                County, Delaware;                                     clicking on ‘‘eRegister.’’ You must select
                                                Kimberly D. Bose,                                         • installation of associated                        the type of filing you are making. If you
                                                Secretary.                                              underground and aboveground facilities                are filing a comment on a particular
                                                [FR Doc. 2016–10136 Filed 4–29–16; 8:45 am]
                                                                                                        (two mainline valves, a meter and                     project, please select ‘‘Comment on a
                                                                                                        regulator station); and                               Filing’’; or
                                                                                                          • an additional 1,775 horsepower of
                                                BILLING CODE 6717–01–P
                                                                                                                                                                 (3) You can file a paper copy of your
                                                                                                        compression at Eastern Shore’s existing               comments by mailing them to the
                                                DEPARTMENT OF ENERGY                                    Bridgeville Compressor Station in                     following address: Kimberly D. Bose,
                                                                                                        Sussex County, Delaware.                              Secretary, Federal Energy Regulatory
                                                Federal Energy Regulatory                                 The FERC staff mailed copies of the                 Commission, 888 First Street NE., Room
                                                Commission                                              EA to federal, state, and local                       1A, Washington, DC 20426.
                                                                                                        government representatives and                           Any person seeking to become a party
                                                [Docket Nos. CP15–18–000; CP15–18–001;                  agencies; elected officials;
                                                CP15–498–000]                                                                                                 to the proceeding must file a motion to
                                                                                                        environmental and public interest                     intervene pursuant to Rule 214 of the
                                                Eastern Shore Natural Gas Company;                      groups; Native American tribes;                       Commission’s Rules of Practice and
                                                Notice of Availability of the                           potentially affected landowners and                   Procedures (18 CFR 385.214).1 Only
                                                Environmental Assessment for the                        other interested individuals and groups;              intervenors have the right to seek
                                                Proposed White Oak Mainline                             newspapers and libraries in each project              rehearing of the Commission’s decision.
                                                Expansion Project and System                            area; and parties to this proceeding.                 The Commission grants affected
                                                Reliability Project                                       In addition, the EA is available for                landowners and others with
                                                                                                        public viewing on the FERC’s Web site
srobinson on DSK5SPTVN1PROD with NOTICES




                                                                                                                                                              environmental concerns intervenor
                                                  The staff of the Federal Energy                       (www.ferc.gov) using the eLibrary link.               status upon showing good cause by
                                                Regulatory Commission (FERC or                          A limited number of copies of the EA                  stating that they have a clear and direct
                                                Commission) has prepared an                             are available for distribution and public             interest in this proceeding which no
                                                environmental assessment (EA) for the                   inspection at: Federal Energy Regulatory              other party can adequately represent.
                                                White Oak Mainline Expansion (White                     Commission, Public Reference Room,
                                                Oak) Project and System Reliability                     888 First Street NE., Room 2A,                           1 See the previous discussion on the methods for

                                                Project, proposed by Eastern Shore                      Washington, DC 20426, (202) 502–8371.                 filing comments.



                                           VerDate Sep<11>2014   20:30 Apr 29, 2016   Jkt 238001   PO 00000   Frm 00023   Fmt 4703   Sfmt 4703   E:\FR\FM\02MYN1.SGM   02MYN1


                                                                                 Federal Register / Vol. 81, No. 84 / Monday, May 2, 2016 / Notices                                              26221

                                                Simply filing environmental comments                    385.214). Anyone filing a motion to                      a. Type of Application: Major Original
                                                will not give you intervenor status, but                intervene or protest must serve a copy                License.
                                                you do not need intervenor status to                    of that document on the Applicant.                       b. Project No.: P–12496–002.
                                                have your comments considered.                             Notice is hereby given that the                       c. Date filed: April 21, 2014.
                                                   Additional information about the                     deadline for filing protests with regard                 d. Applicant: Rugraw, LLC.
                                                projects is available from the                          to the applicant’s request for blanket                   e. Name of Project: Lassen Lodge
                                                Commission’s Office of External Affairs,                authorization, under 18 CFR part 34, of               Hydroelectric Project.
                                                at (866) 208–FERC, or on the FERC Web                   future issuances of securities and                       f. Location: On the South Fork Battle
                                                site (www.ferc.gov) using the eLibrary                  assumptions of liability, is May 11,                  Creek near the Town of Mineral in
                                                link. Click on the eLibrary link, click on              2016.                                                 Tehama County, California. The project
                                                ‘‘General Search,’’ and enter the docket                   The Commission encourages                          would be located on private lands. No
                                                number excluding the last three digits in               electronic submission of protests and                 federal lands or Indian reservations are
                                                the Docket Number field (i.e., CP15–18                  interventions in lieu of paper, using the             located within the proposed project
                                                or CP15–498). Be sure you have selected                 FERC Online links at http://                          boundary.
                                                an appropriate date range. For                          www.ferc.gov. To facilitate electronic                   g. Filed Pursuant to: Federal Power
                                                assistance, please contact FERC Online                  service, persons with Internet access                 Act 16 U.S.C. 791(a)–825(r).
                                                Support at FercOnlineSupport@ferc.gov                   who will eFile a document and/or be                      h. Applicant Contact: Charlie Kuffner,
                                                or toll free at (866) 208–3676, or for                  listed as a contact for an intervenor                 70 Paseo Mirasol, Tiburon, CA 94920;
                                                TTY, contact (202) 502–8659. The                        must create and validate an                           (415) 652–8553
                                                                                                                                                                 i. FERC Contact: Kenneth Hogan at
                                                eLibrary link also provides access to the               eRegistration account using the
                                                                                                                                                              (202) 502–8434; or via email at
                                                texts of formal documents issued by the                 eRegistration link. Select the eFiling
                                                                                                                                                              kenneth.hogan@ferc.gov.
                                                Commission, such as orders, notices,                    link to log on and submit the                            j. Deadline for filing comments,
                                                and rulemakings.                                        intervention or protests.                             recommendations, terms and
                                                   In addition, the Commission offers a                    Persons unable to file electronically              conditions, and prescriptions: 60 days
                                                free service called eSubscription which                 should submit an original and 5 copies                from the issuance date of this notice;
                                                allows you to keep track of all formal                  of the intervention or protest to the                 reply comments are due 105 days from
                                                issuances and submittals in specific                    Federal Energy Regulatory Commission,                 the issuance date of this notice.
                                                dockets. This can reduce the amount of                  888 First Street NE., Washington, DC                     The Commission strongly encourages
                                                time you spend researching proceedings                  20426.                                                electronic filing. Please file comments,
                                                by automatically providing you with                        The filings in the above-referenced                recommendations, terms and
                                                notification of these filings, document                 proceeding are accessible in the                      conditions, and prescriptions using the
                                                summaries, and direct links to the                      Commission’s eLibrary system by                       Commission’s eFiling system at http://
                                                documents. Go to www.ferc.gov/docs-                     clicking on the appropriate link in the               www.ferc.gov/docs-filing/efiling.asp.
                                                filing/esubscription.asp.                               above list. They are also available for               Commenters can submit brief comments
                                                  Dated: April 25, 2016.                                electronic review in the Commission’s                 up to 6,000 characters, without prior
                                                Kimberly D. Bose,
                                                                                                        Public Reference Room in Washington,                  registration, using the eComment system
                                                                                                        DC. There is an eSubscription link on                 at http://www.ferc.gov/docs-filing/
                                                Secretary.
                                                                                                        the Web site that enables subscribers to              ecomment.asp. You must include your
                                                [FR Doc. 2016–10097 Filed 4–29–16; 8:45 am]
                                                                                                        receive email notification when a                     name and contact information at the end
                                                BILLING CODE 6717–01–P                                  document is added to a subscribed                     of your comments. For assistance,
                                                                                                        docket(s). For assistance with any FERC               please contact FERC Online Support at
                                                                                                        Online service, please email                          FERCOnlineSupport@ferc.gov, (866)
                                                DEPARTMENT OF ENERGY
                                                                                                        FERCOnlineSupport@ferc.gov. or call                   208–3676 (toll free), or (202) 502–8659
                                                Federal Energy Regulatory                               (866) 208–3676 (toll free). For TTY, call             (TTY). In lieu of electronic filing, please
                                                Commission                                              (202) 502–8659.                                       send a paper copy to: Secretary, Federal
                                                [Docket No. ER16–1440–000]
                                                                                                          Dated: April 21, 2016.                              Energy Regulatory Commission, 888
                                                                                                        Kimberly D. Bose,                                     First Street NE., Washington, DC 20426.
                                                Roswell Solar, LLC; Supplemental                        Secretary.                                            The first page of any filing should
                                                Notice That Initial Market-Based Rate                   [FR Doc. 2016–10135 Filed 4–29–16; 8:45 am]           include docket number P–12496–002.
                                                Filing Includes Request for Blanket                     BILLING CODE 6717–01–P
                                                                                                                                                                 The Commission’s Rules of Practice
                                                Section 204 Authorization                                                                                     require all intervenors filing documents
                                                                                                                                                              with the Commission to serve a copy of
                                                  This is a supplemental notice in the                  DEPARTMENT OF ENERGY                                  that document on each person on the
                                                above-referenced proceeding of Roswell                                                                        official service list for the project.
                                                Solar, LLC’s application for market-                    Federal Energy Regulatory                             Further, if an intervenor files comments
                                                based rate authority, with an                           Commission                                            or documents with the Commission
                                                accompanying rate tariff, noting that                                                                         relating to the merits of an issue that
                                                such application includes a request for                 [Project No. 12496–002]
                                                                                                                                                              may affect the responsibilities of a
                                                blanket authorization, under 18 CFR                     Rugraw, LLC; Notice of Application                    particular resource agency, they must
                                                part 34, of future issuances of securities              Ready for Environmental Analysis and                  also serve a copy of the document on
                                                and assumptions of liability.
srobinson on DSK5SPTVN1PROD with NOTICES




                                                                                                        Soliciting Comments,                                  that resource agency.
                                                  Any person desiring to intervene or to                Recommendations, Terms and                               k. This application has been accepted
                                                protest should file with the Federal                    Conditions, and Prescriptions                         and is now ready for environmental
                                                Energy Regulatory Commission, 888                                                                             analysis.
                                                First Street NE., Washington, DC 20426,                   Take notice that the following                         l. The proposed Lassen Lodge Project
                                                in accordance with Rules 211 and 214                    hydroelectric application has been filed              would consist of: (1) A 6-foot-high and
                                                of the Commission’s Rules of Practice                   with the Commission and is available                  94-foot-long diversion dam; (2) an
                                                and Procedure (18 CFR 385.211 and                       for public inspection.                                impoundment of approximately 0.5


                                           VerDate Sep<11>2014   20:30 Apr 29, 2016   Jkt 238001   PO 00000   Frm 00024   Fmt 4703   Sfmt 4703   E:\FR\FM\02MYN1.SGM   02MYN1



Document Created: 2016-04-30 13:35:35
Document Modified: 2016-04-30 13:35:35
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation81 FR 26220 

2025 Federal Register | Disclaimer | Privacy Policy
USC | CFR | eCFR