81_FR_28977 81 FR 28887 - Notice of Lodging of Proposed First Amended Consent Decree Under the Clean Water Act

81 FR 28887 - Notice of Lodging of Proposed First Amended Consent Decree Under the Clean Water Act

DEPARTMENT OF JUSTICE

Federal Register Volume 81, Issue 90 (May 10, 2016)

Page Range28887-28887
FR Document2016-10954

Federal Register, Volume 81 Issue 90 (Tuesday, May 10, 2016)
[Federal Register Volume 81, Number 90 (Tuesday, May 10, 2016)]
[Notices]
[Page 28887]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2016-10954]


=======================================================================
-----------------------------------------------------------------------

DEPARTMENT OF JUSTICE


Notice of Lodging of Proposed First Amended Consent Decree Under 
the Clean Water Act

    On May 2, 2016, the Department of Justice lodged a proposed First 
Amended Consent Decree with the United States District Court for the 
Northern District of Ohio in the lawsuit entitled United States v. City 
of Akron, Ohio, et al., Civil Action No. 09-cv-00272.
    In this action the United States, and the State of Ohio in a cross-
claim, sought civil penalties and injunctive relief for violations of 
the Clean Water Act, 33 U.S.C. 1251 et seq., in connection with the 
City of Akron's (``Akron's'' or ``City's'') operation of its municipal 
wastewater treatment facility and sewer system. Under the Consent 
Decree, which was approved by the Court in January 2014, Akron was 
required to develop and implement a comprehensive plan to address 
overflows from its combined sewer system and bypasses around secondary 
treatment at the wastewater treatment facility. That plan, known as the 
``Long Term Control Plan Update'' (``LTCP Update''), which was approved 
by the United States in November 2011 and the State of Ohio in April 
2012, sets forth specific projects that the City is required to 
implement, and identifies dates for completion of these projects.
    The proposed amendment modifies two provisions of the 2014 Consent 
Decree to take into account new engineering solutions. Both of the 
affected projects are included in the approved LTCP Update. The first 
modification requires that the City expand secondary treatment at its 
wastewater treatment plant sooner than is required under the current 
agreement: Under the amended Decree, the City will achieve 220 million 
gallons/day of secondary treatment capacity by 2019 instead of 2021. In 
exchange, the City may delay by approximately two years the 
installation of a biologically enhanced high rate treatment 
(``BioActiflo'') unit at the treatment plant. The City has committed 
to, and the United States previously approved (under the terms of the 
Consent Decree itself), an increase in the size of secondary treatment 
capacity, and an equivalent reduction in the size of the BioActiflo 
unit.
    The second modification eliminates the requirement for the City to 
construct a mile-and-a-half-long sewer line parallel to an existing 
interceptor that connects the combined sewer system to the wastewater 
treatment plant. In place of the parallel sewer, the amendment requires 
the City to construct a steel reinforced concrete cap along all but a 
fraction of the existing interceptor sewer line. The cap will be in 
place by November 2017, the same Achievement of Full Operation date as 
for the original project.
    The publication of this notice opens a period for public comment on 
the First Amended Consent Decree. Comments should be addressed to the 
Assistant Attorney General, Environment and Natural Resources Division, 
and should refer to United States v. City of Akron, Ohio, et al., D.J. 
Ref. No. 90-5-1-1-3144/2. All comments must be submitted no later than 
thirty (30) days after the publication date of this notice. Comments 
may be submitted either by email or by mail:

------------------------------------------------------------------------
         To submit comments:                     Send them to:
------------------------------------------------------------------------
By email............................  [email protected].
By mail.............................  Assistant Attorney General, U.S.
                                       DOJ--ENRD, P.O. Box 7611,
                                       Washington, DC 20044-7611.
------------------------------------------------------------------------

    During the public comment period, the First Amendment to the 
Consent Decree may be examined and downloaded at this Justice 
Department Web site: https://www.justice.gov/enrd/consent-decrees. We 
will provide a paper copy of the proposed amendment to the Consent 
Decree upon written request and payment of reproduction costs. Please 
mail your request and payment to: Consent Decree Library, U.S. DOJ--
ENRD, P.O. Box 7611, Washington, DC 20044-7611.
    Please enclose a check or money order for $7.25 (25 cents per page 
reproduction cost) payable to the United States Treasury.

Randall M. Stone,
Acting Assistant Section Chief, Environmental Enforcement Section, 
Environment and Natural Resources Division.
[FR Doc. 2016-10954 Filed 5-9-16; 8:45 am]
BILLING CODE 4410-15-P



                                                                                   Federal Register / Vol. 81, No. 90 / Tuesday, May 10, 2016 / Notices                                                     28887

                                                    110–246, which amended the Act; (2)                     approved LTCP Update. The first                         U.S. DOJ—ENRD, P.O. Box 7611,
                                                    responses to the Advisory Council                       modification requires that the City                     Washington, DC 20044–7611.
                                                    Report; and (3) other items within the                  expand secondary treatment at its                         Please enclose a check or money order
                                                    jurisdiction of the Council.                            wastewater treatment plant sooner than                  for $7.25 (25 cents per page
                                                                                                            is required under the current agreement:                reproduction cost) payable to the United
                                                    Public Disclosure
                                                                                                            Under the amended Decree, the City                      States Treasury.
                                                      Before including your address, phone                  will achieve 220 million gallons/day of
                                                    number, email address, or other                                                                                 Randall M. Stone,
                                                                                                            secondary treatment capacity by 2019
                                                    personal identifying information in your                instead of 2021. In exchange, the City                  Acting Assistant Section Chief,
                                                    comment, please be advised that your                                                                            Environmental Enforcement Section,
                                                                                                            may delay by approximately two years                    Environment and Natural Resources Division.
                                                    entire comment—including your                           the installation of a biologically
                                                    personal identifying information—may                                                                            [FR Doc. 2016–10954 Filed 5–9–16; 8:45 am]
                                                                                                            enhanced high rate treatment
                                                    be made publicly available at any time.                 (‘‘BioActiflo’’) unit at the treatment                  BILLING CODE 4410–15–P
                                                    While you can ask us in your comment                    plant. The City has committed to, and
                                                    to withhold your personal identifying                   the United States previously approved
                                                    information from public review, we                                                                              DEPARTMENT OF JUSTICE
                                                                                                            (under the terms of the Consent Decree
                                                    cannot guarantee that we will be able to                itself), an increase in the size of                     [OMB Number 1105–0099]
                                                    do so.                                                  secondary treatment capacity, and an
                                                      Dated: April 4, 2016.                                 equivalent reduction in the size of the                 United States Marshals Service;
                                                    Shelly Wiser,                                           BioActiflo unit.                                        Agency Information Collection
                                                    Acting Regional Director, Upper Colorado                   The second modification eliminates                   Activities; Proposed Collection
                                                    Region.                                                 the requirement for the City to construct               Comments Requested; Extension With
                                                    [FR Doc. 2016–10202 Filed 5–9–16; 8:45 am]              a mile-and-a-half-long sewer line                       Change, of a Previously Approved
                                                    BILLING CODE 4332–90–P                                  parallel to an existing interceptor that                Collection USMS Medical Forms
                                                                                                            connects the combined sewer system to                   AGENCY:  U.S. Marshals Service,
                                                                                                            the wastewater treatment plant. In place                Department of Justice.
                                                    DEPARTMENT OF JUSTICE                                   of the parallel sewer, the amendment
                                                                                                                                                                    ACTION: 60-day notice.
                                                                                                            requires the City to construct a steel
                                                    Notice of Lodging of Proposed First                     reinforced concrete cap along all but a                 SUMMARY:   The Department of Justice
                                                    Amended Consent Decree Under the                        fraction of the existing interceptor sewer              (DOJ), U.S. Marshals Service, will be
                                                    Clean Water Act                                         line. The cap will be in place by                       submitting the following information
                                                       On May 2, 2016, the Department of                    November 2017, the same Achievement                     collection request to the Office of
                                                    Justice lodged a proposed First                         of Full Operation date as for the original              Management and Budget (OMB) for
                                                    Amended Consent Decree with the                         project.                                                review and approval in accordance with
                                                    United States District Court for the                       The publication of this notice opens                 the Paperwork Reduction Act of 1995.
                                                    Northern District of Ohio in the lawsuit                a period for public comment on the First                DATES: Comments are encouraged and
                                                    entitled United States v. City of Akron,                Amended Consent Decree. Comments                        will be accepted for 60 days until July
                                                    Ohio, et al., Civil Action No. 09–cv–                   should be addressed to the Assistant                    11, 2016.
                                                    00272.                                                  Attorney General, Environment and
                                                                                                                                                                    FOR FURTHER INFORMATION CONTACT: If
                                                       In this action the United States, and                Natural Resources Division, and should
                                                                                                            refer to United States v. City of Akron,                you have additional comments
                                                    the State of Ohio in a cross-claim,                                                                             especially on the estimated public
                                                    sought civil penalties and injunctive                   Ohio, et al., D.J. Ref. No. 90–5–1–1–
                                                                                                            3144/2. All comments must be                            burden or associated response time,
                                                    relief for violations of the Clean Water
                                                                                                            submitted no later than thirty (30) days                suggestions, or need a copy of the
                                                    Act, 33 U.S.C. 1251 et seq., in
                                                                                                            after the publication date of this notice.              proposed information collection
                                                    connection with the City of Akron’s
                                                                                                            Comments may be submitted either by                     instrument with instructions or
                                                    (‘‘Akron’s’’ or ‘‘City’s’’) operation of its
                                                                                                            email or by mail:                                       additional information, please contact
                                                    municipal wastewater treatment facility
                                                                                                                                                                    Nicole Timmons, U.S. Marshals Service,
                                                    and sewer system. Under the Consent
                                                                                                            To submit                                               Washington, DC 20530–0001 (phone:
                                                    Decree, which was approved by the                                           Send them to:
                                                                                                            comments:                                               202–307–5168).
                                                    Court in January 2014, Akron was
                                                    required to develop and implement a                                                                             SUPPLEMENTARY INFORMATION: Written
                                                                                                            By email .......    pubcomment-ees.enrd@                comments and suggestions from the
                                                    comprehensive plan to address                                                 usdoj.gov.
                                                    overflows from its combined sewer                       By mail .........   Assistant Attorney General,
                                                                                                                                                                    public and affected agencies concerning
                                                    system and bypasses around secondary                                          U.S. DOJ—ENRD, P.O.               the proposed collection of information
                                                    treatment at the wastewater treatment                                         Box 7611, Washington, DC          are encouraged. Your comments should
                                                    facility. That plan, known as the ‘‘Long                                      20044–7611.                       address one or more of the following
                                                    Term Control Plan Update’’ (‘‘LTCP                                                                              four points:
                                                    Update’’), which was approved by the                      During the public comment period,                     —Evaluate whether the proposed
                                                    United States in November 2011 and the                  the First Amendment to the Consent                           collection of information is
                                                    State of Ohio in April 2012, sets forth                 Decree may be examined and                                   necessary for the proper
asabaliauskas on DSK3SPTVN1PROD with NOTICES




                                                    specific projects that the City is required             downloaded at this Justice Department                        performance of the functions of the
                                                    to implement, and identifies dates for                  Web site: https://www.justice.gov/enrd/                      U.S. Marshals Service, including
                                                    completion of these projects.                           consent-decrees. We will provide a                           whether the information will have
                                                       The proposed amendment modifies                      paper copy of the proposed amendment                         practical utility;
                                                    two provisions of the 2014 Consent                      to the Consent Decree upon written                      —Evaluate the accuracy of the agency’s
                                                    Decree to take into account new                         request and payment of reproduction                          estimate of the burden of the
                                                    engineering solutions. Both of the                      costs. Please mail your request and                          proposed collection of information,
                                                    affected projects are included in the                   payment to: Consent Decree Library,                          including the validity of the


                                               VerDate Sep<11>2014   17:33 May 09, 2016   Jkt 238001   PO 00000   Frm 00070     Fmt 4703   Sfmt 4703   E:\FR\FM\10MYN1.SGM   10MYN1



Document Created: 2016-05-10 05:19:31
Document Modified: 2016-05-10 05:19:31
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation81 FR 28887 

2025 Federal Register | Disclaimer | Privacy Policy
USC | CFR | eCFR