81_FR_3417 81 FR 3404 - Columbia Gas Transmission, LLC; Notice of Application

81 FR 3404 - Columbia Gas Transmission, LLC; Notice of Application

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 81, Issue 13 (January 21, 2016)

Page Range3404-3405
FR Document2016-01116

Federal Register, Volume 81 Issue 13 (Thursday, January 21, 2016)
[Federal Register Volume 81, Number 13 (Thursday, January 21, 2016)]
[Notices]
[Pages 3404-3405]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2016-01116]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP16-38-000; PF15-21-000]


Columbia Gas Transmission, LLC; Notice of Application

    Take notice that on December 30, 2015, Columbia Gas Transmission, 
LLC (Columbia), 5151 San Felipe, Suite 2500, Houston, TX 77056, filed 
an application pursuant to section 7(c) of the Natural Gas Act (NGA) 
and Part 157 of the Commission's Regulations requesting authority to 
construct and operate its WB Xpress Project which would include: (i) 
The construction of approximately 29.2 miles of various diameter 
pipeline, (ii) modifications to seven existing compressor stations, 
(iii) construction of two new compressor stations, and (iv) uprating 
the maximum allowable operating pressure (MAOP) on various segments of 
Columbia's existing Line WB and Line VB natural gas transmission 
systems. The WB Xpress Project facilities are designed to expand the 
capacity of Columbia's existing system to transport up to approximately 
1.3 million dekatherms per day (MMDth/d) of natural gas. Facilities to 
be constructed or uprated are located in Clay, Kanawha, Grant, Upshur, 
Randolph, Pendleton, Braxton, and Hardy Counties, West Virginia and in 
Clark, Fauquier, Fairfax, Loudoun, Shenandoah, and Warren Counties, 
Virginia. The cost to construct the project facilities is approximately 
780 million dollars.
    The filing may be viewed on the web at http://www.ferc.gov using 
the ``eLibrary'' link. Enter the docket number excluding the last three 
digits in the docket number field to access the document. For 
assistance, contact FERC at [email protected] or call toll-
free, (886) 208-3676 or TYY, (202) 502-8659.
    Any questions concerning this application should be directed to 
Michael D. Walker, Manager, FERC Certificates, Columbia Gas 
Transmission, LLC, P.O. Box 1273 Charleston, West Virginia 25325, 
phone: (304) 357-2443, Fax: (304) 357-2770, or email [email protected] 
or Brittany Carns, Community Relations & Stakeholder Outreach Manager 
at the

[[Page 3405]]

same address or via phone: (304) 359-2771 or email: 
[email protected].
    On April 16, 2015 the Commission granted Columbia's request to 
utilize the Pre-Filing Process and assigned Docket No. PF15-21-000 to 
staff activities involved in the WB Xpress Project. Now, as of the 
filing of the December 30 application, the Pre-Filing Process for this 
Project has ended. From this time forward, this proceeding will be 
conducted in Docket No. CP16-38-000 as noted in the caption of this 
Notice.
    Pursuant to section 157.9 of the Commission's rules, 18 CFR 157.9, 
within 90 days of this Notice the Commission staff will either: 
Complete its environmental assessment (EA) and place it into the 
Commission's public record (eLibrary) for this proceeding, or issue a 
Notice of Schedule for Environmental Review. If a Notice of Schedule 
for Environmental Review is issued, it will indicate, among other 
milestones, the anticipated date for the Commission staff's issuance of 
the final environmental impact statement (FEIS) or EA for this 
proposal. The filing of the EA in the Commission's public record for 
this proceeding or the issuance of a Notice of Schedule will serve to 
notify federal and state agencies of the timing for the completion of 
all necessary reviews, and the subsequent need to complete all federal 
authorizations within 90 days of the date of issuance of the Commission 
staff's FEIS or EA.
    There are two ways to become involved in the Commission's review of 
this project. First, any person wishing to obtain legal status by 
becoming a party to the proceedings for this project should, on or 
before the comment date stated below, file with the Federal Energy 
Regulatory Commission, 888 First Street NE., Washington, DC 20426, a 
motion to intervene in accordance with the requirements of the 
Commission's Rules of Practice and Procedure (18 CFR 385.214 or 
385.211) and the Regulations under the NGA (18 CFR 157.10). A person 
obtaining party status will be placed on the service list maintained by 
the Secretary of the Commission and will receive copies of all 
documents filed by the applicant and by all other parties. A party must 
submit 5 copies of filings made with the Commission and must mail a 
copy to the applicant and to every other party in the proceeding. Only 
parties to the proceeding can ask for court review of Commission orders 
in the proceeding.
    However, a person does not have to intervene in order to have 
comments considered. The second way to participate is by filing with 
the Secretary of the Commission, as soon as possible, an original and 
two copies of comments in support of or in opposition to this project. 
The Commission will consider these comments in determining the 
appropriate action to be taken, but the filing of a comment alone will 
not serve to make the filer a party to the proceeding. The Commission's 
rules require that persons filing comments in opposition to the project 
provide copies of their protests only to the party or parties directly 
involved in the protest.
    Persons who wish to comment only on the environmental review of 
this project should submit an original and two copies of their comments 
to the Secretary of the Commission. Environmental commenters will be 
placed on the Commission's environmental mailing list, will receive 
copies of the environmental documents, and will be notified of meetings 
associated with the Commission's environmental review process. 
Environmental commenters will not be required to serve copies of filed 
documents on all other parties. However, the non-party commenters will 
not receive copies of all documents filed by other parties or issued by 
the Commission (except for the mailing of environmental documents 
issued by the Commission) and will not have the right to seek court 
review of the Commission's final order.
    The Commission strongly encourages electronic filings of comments, 
protests and interventions in lieu of paper using the ``eFiling'' link 
at http://www.ferc.gov. Persons unable to file electronically should 
submit an original and 7 copies of the protest or intervention to the 
Federal Energy regulatory Commission, 888 First Street NE., Washington, 
DC 20426.
    Comment Date: 5:00 p.m. Eastern time on February 4, 2016.

    Dated: January 14, 2016.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2016-01116 Filed 1-20-16; 8:45 am]
 BILLING CODE 6717-01-P



                                                    3404                          Federal Register / Vol. 81, No. 13 / Thursday, January 21, 2016 / Notices

                                                    environmental issues of this project to                   interested in and/or potentially affected               Dated: January 14, 2016.
                                                    formally cooperate with us in the                         by the proposed project.                              Nathaniel J. Davis, Sr.,
                                                    preparation of the EA.3 Agencies that                        Copies of the EA will be sent to the               Deputy Secretary.
                                                    would like to request cooperating                         environmental mailing list for public                 [FR Doc. 2016–01115 Filed 1–20–16; 8:45 am]
                                                    agency status should follow the                           review and comment. If you would                      BILLING CODE 6717–01–P
                                                    instructions for filing comments                          prefer to receive a paper copy of the
                                                    provided under the Public Participation                   document instead of the CD version or
                                                    section of this notice.                                   would like to remove your name from                   DEPARTMENT OF ENERGY
                                                    Consultations Under Section 106 of the                    the mailing list, please return the
                                                                                                              attached Information Request (appendix                Federal Energy Regulatory
                                                    National Historic Preservation Act
                                                                                                              2).                                                   Commission
                                                      In accordance with the Advisory
                                                    Council on Historic Preservation’s                        Becoming an Intervenor                                [Docket No. CP16–38–000; PF15–21–000]
                                                    implementing regulations for section                         In addition to involvement in the EA
                                                    106 of the National Historic                                                                                    Columbia Gas Transmission, LLC;
                                                                                                              scoping process, you may want to
                                                    Preservation Act, we are using this                                                                             Notice of Application
                                                                                                              become an ‘‘intervenor’’ which is an
                                                    notice to initiate consultation with the                  official party to the Commission’s                       Take notice that on December 30,
                                                    applicable State Historic Preservation                    proceeding. Intervenors play a more
                                                    Office (SHPO), and to solicit their views                                                                       2015, Columbia Gas Transmission, LLC
                                                                                                              formal role in the process and are able               (Columbia), 5151 San Felipe, Suite
                                                    and those of other government agencies,                   to file briefs, appear at hearings, and be
                                                    interested Indian tribes, and the public                                                                        2500, Houston, TX 77056, filed an
                                                                                                              heard by the courts if they choose to                 application pursuant to section 7(c) of
                                                    on the project’s potential effects on                     appeal the Commission’s final ruling.
                                                    historic properties.4 We will define the                                                                        the Natural Gas Act (NGA) and Part 157
                                                                                                              An intervenor formally participates in                of the Commission’s Regulations
                                                    project-specific Area of Potential Effects
                                                                                                              the proceeding by filing a request to                 requesting authority to construct and
                                                    (APE) in consultation with the SHPO as
                                                                                                              intervene. Instructions for becoming an               operate its WB Xpress Project which
                                                    the project develops. On natural gas
                                                                                                              intervenor are in the ‘‘Document-less                 would include: (i) The construction of
                                                    facility projects, the APE at a minimum
                                                                                                              Intervention Guide’’ under the ‘‘e-filing’’           approximately 29.2 miles of various
                                                    encompasses all areas subject to ground
                                                                                                              link on the Commission’s Web site.                    diameter pipeline, (ii) modifications to
                                                    disturbance (examples include
                                                                                                              Motions to intervene are more fully                   seven existing compressor stations, (iii)
                                                    construction right-of-way, contractor/
                                                                                                              described at http://www.ferc.gov/                     construction of two new compressor
                                                    pipe storage yards, compressor stations,
                                                                                                              resources/guides/how-to/intervene.asp.                stations, and (iv) uprating the maximum
                                                    and access roads). Our EA for this
                                                    project will document our findings on                     Additional Information                                allowable operating pressure (MAOP)
                                                    the impacts on historic properties and                                                                          on various segments of Columbia’s
                                                                                                                 Additional information about the                   existing Line WB and Line VB natural
                                                    summarize the status of consultations
                                                    under section 106.                                        project is available from the                         gas transmission systems. The WB
                                                                                                              Commission’s Office of External Affairs,              Xpress Project facilities are designed to
                                                    Environmental Mailing List                                at (866) 208–FERC, or on the FERC Web                 expand the capacity of Columbia’s
                                                       The environmental mailing list                         site at www.ferc.gov using the                        existing system to transport up to
                                                    includes: Federal, state, and local                       ‘‘eLibrary’’ link. Click on the eLibrary              approximately 1.3 million dekatherms
                                                    government representatives and                            link, click on ‘‘General Search’’ and                 per day (MMDth/d) of natural gas.
                                                    agencies; elected officials;                              enter the docket number, excluding the                Facilities to be constructed or uprated
                                                    environmental and public interest                         last three digits in the Docket Number                are located in Clay, Kanawha, Grant,
                                                    groups; Native American Tribes; other                     field (i.e., CP16–18). Be sure you have               Upshur, Randolph, Pendleton, Braxton,
                                                    interested parties; and local libraries                   selected an appropriate date range. For               and Hardy Counties, West Virginia and
                                                    and newspapers. This list also includes                   assistance, please contact FERC Online                in Clark, Fauquier, Fairfax, Loudoun,
                                                    all affected landowners (as defined in                    Support at FercOnlineSupport@ferc.gov                 Shenandoah, and Warren Counties,
                                                    the Commission’s regulations) who are                     or toll free at (866) 208–3676, or for                Virginia. The cost to construct the
                                                    potential right-of-way grantors, whose                    TTY, contact (202) 502–8659. The                      project facilities is approximately 780
                                                    property may be used temporarily for                      eLibrary link also provides access to the             million dollars.
                                                    project purposes, or who own homes                        texts of formal documents issued by the                  The filing may be viewed on the web
                                                    within certain distances of aboveground                   Commission, such as orders, notices,                  at http://www.ferc.gov using the
                                                    facilities, and anyone who submits                        and rulemakings.                                      ‘‘eLibrary’’ link. Enter the docket
                                                    comments on the project. We will                             In addition, the Commission offers a               number excluding the last three digits in
                                                    update the environmental mailing list as                  free service called eSubscription which               the docket number field to access the
                                                    the analysis proceeds to ensure that we                   allows you to keep track of all formal                document. For assistance, contact FERC
                                                    send the information related to this                      issuances and submittals in specific                  at FERCOnlineSupport@ferc.gov or call
                                                    environmental review to all individuals,                  dockets. This can reduce the amount of                toll-free, (886) 208–3676 or TYY, (202)
                                                    organizations, and government entities                    time you spend researching proceedings                502–8659.
                                                                                                              by automatically providing you with                      Any questions concerning this
                                                      3 The Council on Environmental Quality                  notification of these filings, document               application should be directed to
asabaliauskas on DSK9F6TC42PROD with NOTICES




                                                    regulations addressing cooperating agency                 summaries, and direct links to the                    Michael D. Walker, Manager, FERC
                                                    responsibilities are at Title 40, Code of Federal
                                                    Regulations, Part 1501.6.
                                                                                                              documents. Go to www.ferc.gov/docs-                   Certificates, Columbia Gas
                                                      4 The Advisory Council on Historic Preservation’s       filing/esubscription.asp.                             Transmission, LLC, P.O. Box 1273
                                                    regulations are at Title 36, Code of Federal                 Finally, public meetings or site visits            Charleston, West Virginia 25325, phone:
                                                    Regulations, Part 800. Those regulations define           will be posted on the Commission’s                    (304) 357–2443, Fax: (304) 357–2770, or
                                                    historic properties as any prehistoric or historic
                                                    district, site, building, structure, or object included
                                                                                                              calendar located at www.ferc.gov/                     email mdwalker@cpg.com or Brittany
                                                    in or eligible for inclusion in the National Register     EventCalendar/EventsList.aspx along                   Carns, Community Relations &
                                                    of Historic Places.                                       with other related information.                       Stakeholder Outreach Manager at the


                                               VerDate Sep<11>2014    18:26 Jan 20, 2016   Jkt 238001   PO 00000   Frm 00028   Fmt 4703   Sfmt 4703   E:\FR\FM\21JAN1.SGM   21JAN1


                                                                                 Federal Register / Vol. 81, No. 13 / Thursday, January 21, 2016 / Notices                                            3405

                                                    same address or via phone: (304) 359–                   comments in support of or in opposition                   Description: Application of Aspirity
                                                    2771 or email: brittanycarns@cpg.com.                   to this project. The Commission will                   Energy Northeast, LLC, et al. for
                                                       On April 16, 2015 the Commission                     consider these comments in                             Authorization under Section 203 of the
                                                    granted Columbia’s request to utilize the               determining the appropriate action to be               FPA and Requests for Expedited
                                                    Pre-Filing Process and assigned Docket                  taken, but the filing of a comment alone               Consideration and Confidential
                                                    No. PF15–21–000 to staff activities                     will not serve to make the filer a party               Treatment.
                                                    involved in the WB Xpress Project.                      to the proceeding. The Commission’s                       Filed Date: 1/13/16.
                                                    Now, as of the filing of the December 30                rules require that persons filing                         Accession Number: 20160113–5289.
                                                    application, the Pre-Filing Process for                 comments in opposition to the project                     Comments Due: 5 p.m. ET 2/3/16.
                                                    this Project has ended. From this time                  provide copies of their protests only to                  Take notice that the Commission
                                                    forward, this proceeding will be                        the party or parties directly involved in              received the following exempt
                                                    conducted in Docket No. CP16–38–000                     the protest.                                           wholesale generator filings:
                                                    as noted in the caption of this Notice.                    Persons who wish to comment only
                                                       Pursuant to section 157.9 of the                                                                               Docket Numbers: EG16–38–000.
                                                                                                            on the environmental review of this                       Applicants: Innovative Solar 43, LLC.
                                                    Commission’s rules, 18 CFR 157.9,                       project should submit an original and
                                                    within 90 days of this Notice the                                                                                 Description: Notice of Self-
                                                                                                            two copies of their comments to the                    Certification of Exempt Wholesale
                                                    Commission staff will either: Complete                  Secretary of the Commission.
                                                    its environmental assessment (EA) and                                                                          Generator (EWG) of Innovative Solar 43,
                                                                                                            Environmental commenters will be                       LLC.
                                                    place it into the Commission’s public                   placed on the Commission’s
                                                    record (eLibrary) for this proceeding, or                                                                         Filed Date: 1/13/16.
                                                                                                            environmental mailing list, will receive                  Accession Number: 20160113–5225.
                                                    issue a Notice of Schedule for                          copies of the environmental documents,
                                                    Environmental Review. If a Notice of                                                                              Comments Due: 5 p.m. ET 2/3/16.
                                                                                                            and will be notified of meetings                          Take notice that the Commission
                                                    Schedule for Environmental Review is                    associated with the Commission’s
                                                    issued, it will indicate, among other                                                                          received the following electric rate
                                                                                                            environmental review process.                          filings:
                                                    milestones, the anticipated date for the                Environmental commenters will not be
                                                    Commission staff’s issuance of the final                required to serve copies of filed                         Docket Numbers: ER10–1818–012;
                                                    environmental impact statement (FEIS)                   documents on all other parties.                        ER10–1819–014; ER10–1820–017;
                                                    or EA for this proposal. The filing of the                                                                     ER10–1817–013.
                                                                                                            However, the non-party commenters
                                                    EA in the Commission’s public record                                                                              Applicants: Public Service Company
                                                                                                            will not receive copies of all documents
                                                    for this proceeding or the issuance of a                                                                       of Colorado, Northern States Power
                                                                                                            filed by other parties or issued by the
                                                    Notice of Schedule will serve to notify                                                                        Company, a Minnesota corporation,
                                                                                                            Commission (except for the mailing of
                                                    federal and state agencies of the timing                                                                       Northern States Power Company, a
                                                                                                            environmental documents issued by the
                                                    for the completion of all necessary                                                                            Wisconsin corporation, Southwestern
                                                                                                            Commission) and will not have the right
                                                    reviews, and the subsequent need to                                                                            Public Service Company.
                                                                                                            to seek court review of the
                                                    complete all federal authorizations                                                                               Description: Triennial Market Power
                                                                                                            Commission’s final order.
                                                    within 90 days of the date of issuance                                                                         Analysis and Notice of Change in Status
                                                    of the Commission staff’s FEIS or EA.                      The Commission strongly encourages
                                                                                                                                                                   of Public Service Company of Colorado,
                                                       There are two ways to become                         electronic filings of comments, protests
                                                                                                                                                                   et al.
                                                    involved in the Commission’s review of                  and interventions in lieu of paper using
                                                                                                                                                                      Filed Date: 1/14/16.
                                                    this project. First, any person wishing to              the ‘‘eFiling’’ link at http://
                                                                                                                                                                      Accession Number: 20160114–5292.
                                                    obtain legal status by becoming a party                 www.ferc.gov. Persons unable to file
                                                                                                                                                                      Comments Due: 5 p.m. ET 3/14/16.
                                                    to the proceedings for this project                     electronically should submit an original
                                                                                                            and 7 copies of the protest or                            Docket Numbers: ER14–1656–007.
                                                    should, on or before the comment date                                                                             Applicants: CSOLAR IV West, LLC.
                                                    stated below, file with the Federal                     intervention to the Federal Energy
                                                                                                            regulatory Commission, 888 First Street                   Description: Notification of Change in
                                                    Energy Regulatory Commission, 888                                                                              Status of CSOLAR IV West, LLC.
                                                    First Street NE., Washington, DC 20426,                 NE., Washington, DC 20426.
                                                                                                               Comment Date: 5:00 p.m. Eastern time                   Filed Date: 1/14/16.
                                                    a motion to intervene in accordance                                                                               Accession Number: 20160114–5268.
                                                    with the requirements of the                            on February 4, 2016.
                                                                                                                                                                      Comments Due: 5 p.m. ET 2/4/16.
                                                    Commission’s Rules of Practice and                        Dated: January 14, 2016.
                                                    Procedure (18 CFR 385.214 or 385.211)                                                                             Docket Numbers: ER15–2679–002.
                                                                                                            Nathaniel J. Davis, Sr.,                                  Applicants: Latigo Wind Park, LLC.
                                                    and the Regulations under the NGA (18                   Deputy Secretary.
                                                    CFR 157.10). A person obtaining party                                                                             Description: Compliance filing: Latigo
                                                                                                            [FR Doc. 2016–01116 Filed 1–20–16; 8:45 am]            Wind Park, LLC MBR Tariff to be
                                                    status will be placed on the service list
                                                    maintained by the Secretary of the                      BILLING CODE 6717–01–P                                 effective 11/15/2015.
                                                    Commission and will receive copies of                                                                             Filed Date: 1/14/16.
                                                    all documents filed by the applicant and                                                                          Accession Number: 20160114–5273.
                                                                                                            DEPARTMENT OF ENERGY                                      Comments Due: 5 p.m. ET 2/4/16.
                                                    by all other parties. A party must submit
                                                    5 copies of filings made with the                       Federal Energy Regulatory                                 Docket Numbers: ER15–2680–002.
                                                    Commission and must mail a copy to                      Commission                                                Applicants: Sandstone Solar LLC.
                                                    the applicant and to every other party in                                                                         Description: Compliance filing:
                                                    the proceeding. Only parties to the                     Combined Notice of Filings #1                          Sandstone Solar LLC MBR Tariff to be
asabaliauskas on DSK9F6TC42PROD with NOTICES




                                                    proceeding can ask for court review of                                                                         effective 11/1/2015.
                                                    Commission orders in the proceeding.                       Take notice that the Commission                        Filed Date: 1/14/16.
                                                       However, a person does not have to                   received the following electric corporate                 Accession Number: 20160114–5272.
                                                    intervene in order to have comments                     filings:                                                  Comments Due: 5 p.m. ET 2/4/16.
                                                    considered. The second way to                              Docket Numbers: EC16–60–000.                           Docket Numbers: ER16–452–003.
                                                    participate is by filing with the                          Applicants: Aspirity Energy Mid-                       Applicants: RE Tranquillity LLC.
                                                    Secretary of the Commission, as soon as                 States, LLC, Aspirity Energy Northeast,                   Description: Tariff Amendment:
                                                    possible, an original and two copies of                 LLC.                                                   Additional Amendment to Application


                                               VerDate Sep<11>2014   18:26 Jan 20, 2016   Jkt 238001   PO 00000   Frm 00029   Fmt 4703   Sfmt 4703   E:\FR\FM\21JAN1.SGM   21JAN1



Document Created: 2018-02-02 12:33:51
Document Modified: 2018-02-02 12:33:51
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
Dates5:00 p.m. Eastern time on February 4, 2016.
FR Citation81 FR 3404 

2025 Federal Register | Disclaimer | Privacy Policy