81_FR_51346 81 FR 51197 - Elephant Butte Irrigation District; Notice of Preliminary Determination of a Qualifying Conduit Hydropower Facility and Soliciting Comments and Motions To Intervene

81 FR 51197 - Elephant Butte Irrigation District; Notice of Preliminary Determination of a Qualifying Conduit Hydropower Facility and Soliciting Comments and Motions To Intervene

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 81, Issue 149 (August 3, 2016)

Page Range51197-51198
FR Document2016-18358

Federal Register, Volume 81 Issue 149 (Wednesday, August 3, 2016)
[Federal Register Volume 81, Number 149 (Wednesday, August 3, 2016)]
[Notices]
[Pages 51197-51198]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2016-18358]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CD16-17-000]


Elephant Butte Irrigation District; Notice of Preliminary 
Determination of a Qualifying Conduit Hydropower Facility and 
Soliciting Comments and Motions To Intervene

    On July 26, 2016, Elephant Butte Irrigation District filed a notice 
of intent to construct a qualifying conduit hydropower facility, 
pursuant to section 30 of the Federal Power Act (FPA), as amended by 
section 4 of the Hydropower Regulatory Efficiency Act of 2013 (HREA). 
The proposed Drop 8 Facility would have an installed capacity of 40 
kilowatts (kW), and would be located at the existing Drop 8 check 
structure of Elephant Butte Irrigation District's Westside Irrigation 
Canal. The project would be located near La Mesa in Do[ntilde]a Ana 
County, New Mexico.
    Applicant Contact: Gary L. Esslinger, Treasurer/Manager, Elephant 
Butte Irrigation District, 530 S. Melendres, Las Cruces, NM 88005, 
Phone No. (575) 526-6671.
    FERC Contact: Christopher Chaney, Phone No. (202) 502-6778, email: 
[email protected].
    Qualifying Conduit Hydropower Facility Description: The proposed 
project would consist of: (1) A drywell, approximately 23 feet by 13 
feet, within the canal's right bank; (2) two new turbine/generating 
units with a total installed capacity of 40 kW; (3) two 24-inch-
diameter, 9-foot-long intake pipes; (4) one 48-inch-diameter, 120-foot-
long raceway returning water to the Westside Irrigation Canal; and (5) 
appurtenant facilities. The proposed project would have an estimated 
annual generating capacity of 230 megawatt-hours.
    A qualifying conduit hydropower facility is one that is determined 
or deemed to meet all of the criteria shown in the table below.

                          Table 1--Criteria for Qualifying Conduit Hydropower Facility
----------------------------------------------------------------------------------------------------------------
              Statutory Provision                                 Description                    Satisfies (Y/N)
----------------------------------------------------------------------------------------------------------------
FPA 30(a)(3)(A), as amended by HREA...........  The conduit the facility uses is a tunnel,                    Y
                                                 canal, pipeline, aqueduct, flume, ditch, or
                                                 similar manmade water conveyance that is
                                                 operated for the distribution of water for
                                                 agricultural, municipal, or industrial
                                                 consumption and not primarily for the
                                                 generation of electricity.
FPA 30(a)(3)(C)(i), as amended by HREA........  The facility is constructed, operated, or                     Y
                                                 maintained for the generation of electric
                                                 power and uses for such generation only the
                                                 hydroelectric potential of a non-federally
                                                 owned conduit.
FPA 30(a)(3)(C)(ii), as amended by HREA.......  The facility has an installed capacity that                   Y
                                                 does not exceed 5 megawatts.
FPA 30(a)(3)(C)(iii), as amended by HREA......  On or before August 9, 2013, the facility is                  Y
                                                 not licensed, or exempted from the licensing
                                                 requirements of Part I of the FPA.
----------------------------------------------------------------------------------------------------------------


[[Page 51198]]

    Preliminary Determination: The proposed addition of the 
hydroelectric project along the existing irrigation canal will not 
alter its primary purpose. Therefore, based upon the above criteria, 
Commission staff preliminarily determines that the proposal satisfies 
the requirements for a qualifying conduit hydropower facility, which is 
not required to be licensed or exempted from licensing.
    Comments and Motions to Intervene: Deadline for filing comments 
contesting whether the facility meets the qualifying criteria is 45 
days from the issuance date of this notice.
    Deadline for filing motions to intervene is 30 days from the 
issuance date of this notice.
    Anyone may submit comments or a motion to intervene in accordance 
with the requirements of Rules of Practice and Procedure, 18 CFR 
385.210 and 385.214. Any motions to intervene must be received on or 
before the specified deadline date for the particular proceeding.
    Filing and Service of Responsive Documents: All filings must (1) 
bear in all capital letters the ``COMMENTS CONTESTING QUALIFICATION FOR 
A CONDUIT HYDROPOWER FACILITY'' or ``MOTION TO INTERVENE,'' as 
applicable; (2) state in the heading the name of the applicant and the 
project number of the application to which the filing responds; (3) 
state the name, address, and telephone number of the person filing; and 
(4) otherwise comply with the requirements of sections 385.2001 through 
385.2005 of the Commission's regulations.\1\ All comments contesting 
Commission staff's preliminary determination that the facility meets 
the qualifying criteria must set forth their evidentiary basis.
---------------------------------------------------------------------------

    \1\ 18 CFR 385.2001-2005 (2015).
---------------------------------------------------------------------------

    The Commission strongly encourages electronic filing. Please file 
motions to intervene and comments using the Commission's eFiling system 
at http://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit 
brief comments up to 6,000 characters, without prior registration, 
using the eComment system at http://www.ferc.gov/docs-filing/ecomment.asp. You must include your name and contact information at the 
end of your comments. For assistance, please contact FERC Online 
Support at [email protected], (866) 208-3676 (toll free), or 
(202) 502-8659 (TTY). In lieu of electronic filing, please send a paper 
copy to: Secretary, Federal Energy Regulatory Commission, 888 First 
Street NE., Washington, DC 20426. A copy of all other filings in 
reference to this application must be accompanied by proof of service 
on all persons listed in the service list prepared by the Commission in 
this proceeding, in accordance with 18 CFR 4.34(b) and 385.2010.
    Locations of Notice of Intent: Copies of the notice of intent can 
be obtained directly from the applicant or such copies can be viewed 
and reproduced at the Commission in its Public Reference Room, Room 2A, 
888 First Street NE., Washington, DC 20426. The filing may also be 
viewed on the web at http://www.ferc.gov/docs-filing/elibrary.asp using 
the ``eLibrary'' link. Enter the docket number (i.e., CD16-17) in the 
docket number field to access the document. For assistance, call toll-
free 1-866-208-3676 or email [email protected]. For TTY, call 
(202) 502-8659.

    Dated: July 28, 2016.
Kimberly D. Bose,
Secretary.
[FR Doc. 2016-18358 Filed 8-2-16; 8:45 am]
BILLING CODE 6717-01-P



                                                                                Federal Register / Vol. 81, No. 149 / Wednesday, August 3, 2016 / Notices                                                   51197

                                                       Comments and Motions to Intervene:                    208–3676 (toll free), or (202) 502–8659                to construct a qualifying conduit
                                                    The deadline for filing comments                         (TTY). In lieu of electronic filing, please            hydropower facility, pursuant to section
                                                    contesting whether the facility meets the                send a paper copy to: Secretary, Federal               30 of the Federal Power Act (FPA), as
                                                    qualifying criteria is 45 days from the                  Energy Regulatory Commission, 888                      amended by section 4 of the
                                                    issuance date of this notice.                            First Street NE., Washington, DC 20426.                Hydropower Regulatory Efficiency Act
                                                       The deadline for filing motions to                    A copy of all other filings in reference               of 2013 (HREA). The proposed Drop 8
                                                    intervene is 30 days from the issuance                   to this application must be accompanied                Facility would have an installed
                                                    date of this notice.                                     by proof of service on all persons listed              capacity of 40 kilowatts (kW), and
                                                       Anyone may submit comments or a                       in the service list prepared by the
                                                    motion to intervene in accordance with                                                                          would be located at the existing Drop 8
                                                                                                             Commission in this proceeding, in
                                                    the requirements of Rules of Practice                                                                           check structure of Elephant Butte
                                                                                                             accordance with 18 CFR 4.34(b) and
                                                    and Procedure, 18 CFR 385.210 and                                                                               Irrigation District’s Westside Irrigation
                                                                                                             385.2010.
                                                    385.214. Any motions to intervene must                     Locations of Notice of Intent: Copies                Canal. The project would be located
                                                    be received on or before the specified                   of the notice of intent can be obtained                near La Mesa in Doña Ana County, New
                                                    deadline date for the particular                         directly from the applicant or such                    Mexico.
                                                    proceeding.                                              copies can be viewed and reproduced at                    Applicant Contact: Gary L. Esslinger,
                                                       Filing and Service of Responsive                      the Commission in its Public Reference                 Treasurer/Manager, Elephant Butte
                                                    Documents: All filings must (1) bear in                  Room, Room 2A, 888 First Street NE.,                   Irrigation District, 530 S. Melendres, Las
                                                    all capital letters the ‘‘COMMENTS                       Washington, DC 20426. The filing may                   Cruces, NM 88005, Phone No. (575)
                                                    CONTESTING QUALIFICATION FOR A                           also be viewed on the web at http://                   526–6671.
                                                    CONDUIT HYDROPOWER FACILITY’’                            www.ferc.gov/docs-filing/elibrary.asp
                                                    or ‘‘MOTION TO INTERVENE,’’ as                           using the ‘‘eLibrary’’ link. Enter the                    FERC Contact: Christopher Chaney,
                                                    applicable; (2) state in the heading the                 docket number (e.g., CD16–16–000) in                   Phone No. (202) 502–6778, email:
                                                    name of the applicant and the project                    the docket number field to access the                  Christopher.Chaney@ferc.gov.
                                                    number of the application to which the                   document. For assistance, call toll-free                  Qualifying Conduit Hydropower
                                                    filing responds; (3) state the name,                     1–866–208–3676 or email                                Facility Description: The proposed
                                                    address, and telephone number of the                     FERCOnlineSupport@ferc.gov. For TTY,                   project would consist of: (1) A drywell,
                                                    person filing; and (4) otherwise comply                  call (202) 502–8659.                                   approximately 23 feet by 13 feet, within
                                                    with the requirements of sections                          Dated: July 28, 2016.                                the canal’s right bank; (2) two new
                                                    385.2001 through 385.2005 of the                         Kimberly D. Bose,                                      turbine/generating units with a total
                                                    Commission’s regulations.1 All                           Secretary.                                             installed capacity of 40 kW; (3) two 24-
                                                    comments contesting Commission staff’s                                                                          inch-diameter, 9-foot-long intake pipes;
                                                                                                             [FR Doc. 2016–18361 Filed 8–2–16; 8:45 am]
                                                    preliminary determination that the                                                                              (4) one 48-inch-diameter, 120-foot-long
                                                                                                             BILLING CODE 6717–01–P
                                                    facility meets the qualifying criteria                                                                          raceway returning water to the Westside
                                                    must set forth their evidentiary basis.                                                                         Irrigation Canal; and (5) appurtenant
                                                       The Commission strongly encourages
                                                                                                             DEPARTMENT OF ENERGY                                   facilities. The proposed project would
                                                    electronic filing. Please file motions to
                                                    intervene and comments using the                                                                                have an estimated annual generating
                                                                                                             Federal Energy Regulatory                              capacity of 230 megawatt-hours.
                                                    Commission’s eFiling system at http://                   Commission
                                                    www.ferc.gov/docs-filing/efiling.asp.                                                                              A qualifying conduit hydropower
                                                    Commenters can submit brief comments                     [Docket No. CD16–17–000]                               facility is one that is determined or
                                                    up to 6,000 characters, without prior                                                                           deemed to meet all of the criteria shown
                                                                                                             Elephant Butte Irrigation District;
                                                    registration, using the eComment system                                                                         in the table below.
                                                                                                             Notice of Preliminary Determination of
                                                    at http://www.ferc.gov/docs-filing/
                                                                                                             a Qualifying Conduit Hydropower
                                                    ecomment.asp. You must include your
                                                                                                             Facility and Soliciting Comments and
                                                    name and contact information at the end
                                                                                                             Motions To Intervene
                                                    of your comments. For assistance,
                                                    please contact FERC Online Support at                       On July 26, 2016, Elephant Butte
                                                    FERCOnlineSupport@ferc.gov, (866)                        Irrigation District filed a notice of intent

                                                                                         TABLE 1—CRITERIA FOR QUALIFYING CONDUIT HYDROPOWER FACILITY
                                                                                                                                                                                                         Satisfies
                                                             Statutory Provision                                                           Description                                                    (Y/N)

                                                    FPA 30(a)(3)(A), as amended             The conduit the facility uses is a tunnel, canal, pipeline, aqueduct, flume, ditch, or similar                  Y
                                                      by HREA.                                manmade water conveyance that is operated for the distribution of water for agricultural,
                                                                                              municipal, or industrial consumption and not primarily for the generation of electricity.
                                                    FPA 30(a)(3)(C)(i), as amended          The facility is constructed, operated, or maintained for the generation of electric power and                   Y
                                                      by HREA.                                uses for such generation only the hydroelectric potential of a non-federally owned conduit.
                                                    FPA 30(a)(3)(C)(ii), as amend-          The facility has an installed capacity that does not exceed 5 megawatts ..................................      Y
asabaliauskas on DSK3SPTVN1PROD with NOTICES




                                                      ed by HREA.
                                                    FPA 30(a)(3)(C)(iii), as amend-         On or before August 9, 2013, the facility is not licensed, or exempted from the licensing re-                   Y
                                                      ed by HREA.                            quirements of Part I of the FPA.




                                                      1 18   CFR 385.2001–2005 (2015).



                                               VerDate Sep<11>2014    18:21 Aug 02, 2016   Jkt 238001   PO 00000   Frm 00024   Fmt 4703   Sfmt 4703   E:\FR\FM\03AUN1.SGM    03AUN1


                                                    51198                       Federal Register / Vol. 81, No. 149 / Wednesday, August 3, 2016 / Notices

                                                       Preliminary Determination: The                        by proof of service on all persons listed             address: https://www.epa.gov/sites/
                                                    proposed addition of the hydroelectric                   in the service list prepared by the                   production/files/2016-07/documents/
                                                    project along the existing irrigation                    Commission in this proceeding, in                     gasp_response2014.pdf.
                                                    canal will not alter its primary purpose.                accordance with 18 CFR 4.34(b) and
                                                    Therefore, based upon the above                          385.2010.                                             FOR FURTHER INFORMATION CONTACT:   Art
                                                    criteria, Commission staff preliminarily                   Locations of Notice of Intent: Copies               Hofmeister, Air Permits Section, EPA
                                                    determines that the proposal satisfies                   of the notice of intent can be obtained               Region 4, at (404) 562–9115 or
                                                    the requirements for a qualifying                        directly from the applicant or such                   hofmeister.art@epa.gov.
                                                    conduit hydropower facility, which is                    copies can be viewed and reproduced at                SUPPLEMENTARY INFORMATION:      The CAA
                                                    not required to be licensed or exempted                  the Commission in its Public Reference                affords EPA a 45-day period to review
                                                    from licensing.                                          Room, Room 2A, 888 First Street NE.,                  and, as appropriate, the authority to
                                                       Comments and Motions to Intervene:                    Washington, DC 20426. The filing may
                                                    Deadline for filing comments contesting                                                                        object to operating permits proposed by
                                                                                                             also be viewed on the web at http://
                                                    whether the facility meets the qualifying                                                                      state permitting authorities under title V
                                                                                                             www.ferc.gov/docs-filing/elibrary.asp
                                                    criteria is 45 days from the issuance                                                                          of the CAA, 42 U.S.C. 7661–7661f.
                                                                                                             using the ‘‘eLibrary’’ link. Enter the
                                                    date of this notice.                                     docket number (i.e., CD16–17) in the                  Section 505(b)(2) of the CAA and 40
                                                       Deadline for filing motions to                        docket number field to access the                     CFR 70.8(d) authorize any person to
                                                    intervene is 30 days from the issuance                   document. For assistance, call toll-free              petition the EPA Administrator to object
                                                    date of this notice.                                     1–866–208–3676 or email                               to a title V operating permit within 60
                                                       Anyone may submit comments or a                       FERCOnlineSupport@ferc.gov. For TTY,                  days after the expiration of EPA’s 45-
                                                    motion to intervene in accordance with                   call (202) 502–8659.                                  day review period if EPA has not
                                                    the requirements of Rules of Practice                                                                          objected on its own initiative. Petitions
                                                    and Procedure, 18 CFR 385.210 and                          Dated: July 28, 2016.
                                                                                                                                                                   must be based only on objections to the
                                                    385.214. Any motions to intervene must                   Kimberly D. Bose,
                                                                                                                                                                   permit that were raised with reasonable
                                                    be received on or before the specified                   Secretary.
                                                                                                                                                                   specificity during the public comment
                                                    deadline date for the particular                         [FR Doc. 2016–18358 Filed 8–2–16; 8:45 am]
                                                                                                                                                                   period provided by the state, unless the
                                                    proceeding.                                              BILLING CODE 6717–01–P
                                                                                                                                                                   petitioner demonstrates that it was
                                                       Filing and Service of Responsive
                                                                                                                                                                   impracticable to raise these issues
                                                    Documents: All filings must (1) bear in
                                                    all capital letters the ‘‘COMMENTS                                                                             during the comment period or the
                                                                                                             ENVIRONMENTAL PROTECTION                              grounds for the issues arose after this
                                                    CONTESTING QUALIFICATION FOR A                           AGENCY
                                                    CONDUIT HYDROPOWER FACILITY’’                                                                                  period. Pursuant to sections 307(b) and
                                                    or ‘‘MOTION TO INTERVENE,’’ as                           [Petitions IV–2014–5 and –6; FRL–9950–17–             505(b)(2) of the CAA, a petition for
                                                    applicable; (2) state in the heading the                 Region 4]                                             judicial review of those parts of the
                                                    name of the applicant and the project                                                                          Order that deny issues in the petition
                                                                                                             Clean Air Act Operating Permit
                                                    number of the application to which the                                                                         may be filed in the United States Court
                                                                                                             Program; Petitions for Objection to
                                                    filing responds; (3) state the name,                                                                           of Appeals for the appropriate circuit
                                                                                                             State Operating Permits for ABC Coke
                                                    address, and telephone number of the                                                                           within 60 days from the date this notice
                                                                                                             and Walter Coke (Jefferson County,
                                                    person filing; and (4) otherwise comply                                                                        is published in the Federal Register.
                                                                                                             Alabama)
                                                    with the requirements of sections                                                                                 Petitioners submitted petitions
                                                    385.2001 through 385.2005 of the                         AGENCY:  Environmental Protection                     regarding the aforementioned ABC Coke
                                                    Commission’s regulations.1 All                           Agency (EPA).
                                                                                                                                                                   and Walter Coke facilities, requesting
                                                    comments contesting Commission staff’s                   ACTION: Notice of final order on
                                                                                                                                                                   that EPA object to the CAA title V
                                                    preliminary determination that the                       petitions to object to state operating                operating permits (#4–07–0001–03 and
                                                    facility meets the qualifying criteria                   permits.
                                                    must set forth their evidentiary basis.                                                                        4–07–0355–03, respectively). Petitioner
                                                       The Commission strongly encourages                    SUMMARY:    The Environmental Protection              alleged that the permits were not
                                                    electronic filing. Please file motions to                Agency (EPA) Administrator signed an                  consistent with the CAA because: (1)
                                                    intervene and comments using the                         Order, dated July 15, 2016, denying                   They lack the conditions necessary to
                                                    Commission’s eFiling system at http://                   petitions to object to Clean Air Act                  assure compliance with the general
                                                    www.ferc.gov/docs-filing/efiling.asp.                    (CAA) title V operating permits issued                prohibition against ‘‘air pollution’’; (2)
                                                    Commenters can submit brief comments                     by the Jefferson County Department of                 they contain conditions governing
                                                    up to 6,000 characters, without prior                    Health (JCDH) to ABC Coke for its                     fugitive dust that are too vague or too
                                                    registration, using the eComment system                  facility located in Tarrant and Walter                restrictive; and (3) JCDH failed to
                                                    at http://www.ferc.gov/docs-filing/                      Coke for its facility located in North                provide Petitioner with sufficient
                                                    ecomment.asp. You must include your                      Birmingham, both in Jefferson County,                 emissions information to participate
                                                    name and contact information at the end                  Alabama. This Order constitutes a final               meaningfully in the permitting process
                                                    of your comments. For assistance,                        action on the petitions submitted by                  with respect to Walter Coke.
                                                    please contact FERC Online Support at                    Gasp (Petitioner) and received by EPA
                                                                                                             on October 3, 2014, and December 2,                      On July 15, 2016, the Administrator
                                                    FERCOnlineSupport@ferc.gov, (866)
                                                                                                             2014, respectively.                                   issued an Order denying the petitions.
                                                    208–3676 (toll free), or (202) 502–8659
asabaliauskas on DSK3SPTVN1PROD with NOTICES




                                                                                                             ADDRESSES: Copies of the Order, the
                                                                                                                                                                   The Order explains EPA’s rationale for
                                                    (TTY). In lieu of electronic filing, please
                                                    send a paper copy to: Secretary, Federal                 petitions, and all pertinent information              denying the petitions.
                                                    Energy Regulatory Commission, 888                        relating thereto are on file at the                     Dated: July 26, 2016.
                                                    First Street NE., Washington, DC 20426.                  following location: EPA Region 4; Air,                Heather McTeer Toney,
                                                    A copy of all other filings in reference                 Pesticides and Toxics Management                      Regional Administrator, Region 4.
                                                    to this application must be accompanied                  Division; 61 Forsyth Street SW., Atlanta,             [FR Doc. 2016–18394 Filed 8–2–16; 8:45 am]
                                                                                                             Georgia 30303–8960. The Order is also
                                                                                                                                                                   BILLING CODE 6560–50–P
                                                      1 18   CFR 385.2001–2005 (2015).                       available electronically at the following


                                               VerDate Sep<11>2014    18:21 Aug 02, 2016   Jkt 238001   PO 00000   Frm 00025   Fmt 4703   Sfmt 4703   E:\FR\FM\03AUN1.SGM   03AUN1



Document Created: 2016-08-02 23:44:04
Document Modified: 2016-08-02 23:44:04
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation81 FR 51197 

2025 Federal Register | Disclaimer | Privacy Policy