The U.S. Nuclear Regulatory Commission (NRC) is issuing a final revision to Section 5.4.2.1, ``Steam Generator Materials and Design,'' of NUREG-0800, ``Standard Review Plan [SRP] for the Review of Safety Analysis Reports for Nuclear Power Plants: LWR [Light Water Reactor] Edition.'' Revision 4 to Section 5.4.2.1 of the SRP reflects current NRC review methods and practices based on lessons learned from NRC reviews of design certification and combined license applications completed since the last revision of this section.

Federal Register, Volume 81 Issue 149 (Wednesday, August 3, 2016)
[Federal Register Volume 81, Number 149 (Wednesday, August 3, 2016)]
[Notices]
[Pages 51217-51218]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2016-18390]


-----------------------------------------------------------------------

NUCLEAR REGULATORY COMMISSION

[NRC-2016-0045]


Steam Generator Materials and Design

AGENCY: Nuclear Regulatory Commission.

ACTION: Standard review plan--final section revision; issuance.

-----------------------------------------------------------------------

SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) is issuing a 
final revision to Section 5.4.2.1, ``Steam Generator Materials and 
Design,'' of NUREG-0800, ``Standard Review Plan [SRP] for the Review of 
Safety Analysis Reports for Nuclear Power Plants: LWR [Light Water 
Reactor] Edition.'' Revision 4 to Section 5.4.2.1 of the SRP reflects 
current NRC review methods and practices based on lessons learned from 
NRC reviews of design certification and combined license applications 
completed since the last revision of this section.

DATES: The effective date of Revision 4 to Section 5.4.2.1 of the SRP 
is September 2, 2016.

ADDRESSES: Please refer to Docket ID NRC-2016-0045 when contacting the 
NRC about the availability of information regarding this document. You 
may obtain publicly-available information related to this document 
using any of the following methods:
     Federal Rulemaking Web site: Go to http://www.regulations.gov and search for Docket ID NRC-2016-0045. Address 
questions about NRC dockets to Carol Gallagher; telephone: 301-415-
3463; email: [email protected]. For technical questions, contact 
the individuals listed in the FOR FURTHER INFORMATION CONTACT section 
of this document.
     NRC's Agencywide Documents Access and Management System 
(ADAMS): You may obtain publicly-available documents online in the 
ADAMS Public Documents collection at http://www.nrc.gov/reading-rm/adams.html. To begin the search, select ``ADAMS Public Documents'' and 
then select ``Begin Web-based ADAMS Search.'' For problems with ADAMS, 
please contact the NRC's Public Document Room (PDR) reference staff at 
1-800-397-4209, 301-415-4737, or by email to [email protected]. A 
mark-up showing the Revision 4 changes made to SRP Section 5.4.2.1, and 
the final revision of SRP Section 5.4.2.1, Revision 4, are available in 
ADAMS under Accession Nos. ML16147A298 and ML16147A289.
     NRC's PDR: You may examine and purchase copies of public 
documents at the NRC's PDR, Room O1-F21, One White Flint North, 11555 
Rockville Pike, Rockville, Maryland 20852.
     The NUREG-0800 is available on the NRC's public Web site 
at http://www.nrc.gov/reading-rm/doc-collections/nuregs/staff/sr0800/.

FOR FURTHER INFORMATION CONTACT: Carolyn Lauron, telephone: 301-415-
2736, email: [email protected]; or Mark Notich, telephone: 301-
415.3053, email: [email protected]. Both are staff of the Office of 
New Reactors, U.S. Nuclear Regulatory Commission, Washington, DC 20555-
0001.

SUPPLEMENTARY INFORMATION: 

I. Background

    On April 22, 2016 (81 FR 23762), the NRC published for public 
comment the proposed revisions to SRP Section 5.4.2.1. The NRC received 
no comments on the proposed revisions. Therefore, the NRC is issuing 
Revision 4 to Section 5.4.2.1 of the SRP in final form for use. There 
have been minor editorial changes to this section since its issuance in 
proposed form for public comment. Details of the specific changes are 
included at the end of the revised section, under the subsection 
titled, ``Description of Changes.''
    Revision 4 to Section 5.4.2.1 of the SRP reflects current NRC 
review methods and practices based on lessons learned from NRC reviews 
of design certification and combined license applications completed 
since the last revision of this section.

II. Backfitting and Finality Provisions

    Issuance of this revised SRP section does not constitute 
backfitting as defined in Sec.  50.109 of title 10 of the Code of 
Federal Regulations (10 CFR), ``Backfitting,'' (the Backfit Rule) or

[[Page 51218]]

otherwise be inconsistent with the issue finality provisions in 10 CFR 
part 52. The NRC's position is based upon the following considerations:
    1. The SRP positions do not constitute backfitting, inasmuch as the 
SRP is internal guidance directed at the NRC staff with respect to 
their regulatory responsibilities.
    The SRP provides guidance to the NRC staff on how to review an 
application for the NRC's regulatory approval in the form of licensing. 
Changes in internal NRC staff guidance are not matters for which either 
nuclear power plant applicants or licensees are protected under either 
the Backfit Rule or the issue finality provisions of 10 CFR part 52.
    2. The NRC staff has no intention to impose the SRP positions on 
current licensees and regulatory approvals either now or in the future.
    The NRC staff does not intend to impose or apply the positions 
described in the SRP to existing (already issued) licenses and 
regulatory approvals. Therefore, the issuance of a final SRP--even if 
considered guidance that is within the purview of the issue finality 
provisions in 10 CFR part 52--need not be evaluated as if it were a 
backfit or as being inconsistent with issue finality provisions. If, in 
the future, the NRC staff seeks to impose a position in the SRP on 
holders of already issued licenses in a manner which does not provide 
issue finality as described in the applicable issue finality provision, 
then the NRC staff must make the showing as set forth in the Backfit 
Rule or address the criteria for avoiding issue finality as described 
in the applicable issue finality provision.
    3. Backfitting and issue finality do not--with limited exceptions 
not applicable here--protect current or future applicants.
    Applicants and potential applicants are not, with certain 
exceptions, protected by either the Backfit Rule or any issue finality 
provisions under 10 CFR part 52. This is because neither the Backfit 
Rule nor the issue finality provisions under 10 CFR part 52--with 
certain exclusions discussed in the next paragraph--were intended to 
apply to every NRC action which substantially changes the expectations 
of current and future applicants.
    The exceptions to the general principle are applicable whenever an 
applicant references a 10 CFR part 52 license (e.g., an early site 
permit) and/or NRC regulatory approval (e.g., a design certification 
rule) with specified issue finality provisions. The NRC staff does not, 
at this time, intend to impose the positions represented in the SRP in 
a manner that is inconsistent with any issue finality provisions. If, 
in the future, the NRC staff seeks to impose a position in the SRP in a 
manner which does not provide issue finality as described in the 
applicable issue finality provision, then the NRC staff must address 
the criteria for avoiding issue finality as described in the applicable 
issue finality provision.

III. Congressional Review Act

    This SRP section revision is a rule as defined in the Congressional 
Review Act (5 U.S.C. 801-808). However, the Office of Management and 
Budget has not found it to be a major rule as defined in the 
Congressional Review Act.

    Dated at Rockville, Maryland, this 29th day of July 2016.

    For the Nuclear Regulatory Commission.
Joseph Colaccino,
Chief, New Reactor Rulemaking and Guidance Branch, Division of 
Engineering, Infrastructure, and Advanced Reactors, Office of New 
Reactors.
[FR Doc. 2016-18390 Filed 8-2-16; 8:45 am]
 BILLING CODE 7590-01-P



                                                                               Federal Register / Vol. 81, No. 149 / Wednesday, August 3, 2016 / Notices                                            51217

                                                    modalities; a discussion on the licensing               2016.html on or about November 22,                       • NRC’s Agencywide Documents
                                                    guidance for yttrium-90 microsphere                     2016.                                                 Access and Management System
                                                    brachytherapy; a discussion on the                        4. Persons who require special                      (ADAMS): You may obtain publicly-
                                                    training and experience requirements                    services, such as those for the hearing               available documents online in the
                                                    for authorized individuals for various                  impaired, should notify Ms. Smethers of               ADAMS Public Documents collection at
                                                    modalities; a presentation from                         their planned attendance.                             http://www.nrc.gov/reading-rm/
                                                    Spectrum Pharmaceuticals, Inc. on the                     This meeting will be held in                        adams.html. To begin the search, select
                                                    training and experience requirements                    accordance with the Atomic Energy Act                 ‘‘ADAMS Public Documents’’ and then
                                                    for alpha and beta emitters; an update                  of 1954, as amended (primarily Section                select ‘‘Begin Web-based ADAMS
                                                    on the worldwide supply of                              161a); the Federal Advisory Committee                 Search.’’ For problems with ADAMS,
                                                    molybdenum-99; and a discussion on                      Act (5 U.S.C. App); and the                           please contact the NRC’s Public
                                                    the licensing guidance for the                          Commission’s regulations in Title 10 of               Document Room (PDR) reference staff at
                                                    NorthStar® Generator. The agenda is                     the Code of Federal Regulations, part 7.              1–800–397–4209, 301–415–4737, or by
                                                    subject to change. The current agenda                     Dated at Rockville, Maryland, this 28th day         email to pdr.resource@nrc.gov. A mark-
                                                    and any updates will be available at                    of July, 2016.                                        up showing the Revision 4 changes
                                                    http://www.nrc.gov/reading-rm/doc-                      Andrew L. Bates,                                      made to SRP Section 5.4.2.1, and the
                                                    collections/acmui/meetings/2016.html                    Advisory Committee Management Officer.
                                                                                                                                                                  final revision of SRP Section 5.4.2.1,
                                                    or by emailing Ms. Michelle Smethers at                                                                       Revision 4, are available in ADAMS
                                                                                                            [FR Doc. 2016–18372 Filed 8–2–16; 8:45 am]
                                                    the contact information below.                                                                                under Accession Nos. ML16147A298
                                                                                                            BILLING CODE 7590–01–P
                                                       Purpose: Discuss issues related to 10                                                                      and ML16147A289.
                                                    CFR part 35 Medical Use of Byproduct                                                                             • NRC’s PDR: You may examine and
                                                    Material.                                               NUCLEAR REGULATORY                                    purchase copies of public documents at
                                                       Date and Time for Open Sessions:                     COMMISSION                                            the NRC’s PDR, Room O1–F21, One
                                                    October 06, 2016, from 8:00 a.m. to 3:00                                                                      White Flint North, 11555 Rockville
                                                    p.m. and October 07, 2016, from 8:00                                                                          Pike, Rockville, Maryland 20852.
                                                                                                            [NRC–2016–0045]
                                                    a.m. to 4:00 p.m.                                                                                                • The NUREG–0800 is available on
                                                       Data and Time for Closed Sessions:                   Steam Generator Materials and Design                  the NRC’s public Web site at http://
                                                    October 06, 2016, from 7:00 a.m. to 8:00                                                                      www.nrc.gov/reading-rm/doc-
                                                    a.m. and from 3:00 p.m. to 5:00 p.m.                    AGENCY:  Nuclear Regulatory                           collections/nuregs/staff/sr0800/.
                                                       Address for Public Meeting: U.S.                     Commission.                                           FOR FURTHER INFORMATION CONTACT:
                                                    Nuclear Regulatory Commission, Two                      ACTION: Standard review plan—final                    Carolyn Lauron, telephone: 301–415–
                                                    White Flint North Building, Room T2–                    section revision; issuance.                           2736, email: Carolyn.Lauron@nrc.gov; or
                                                    B3, 11545 Rockville Pike, Rockville,                                                                          Mark Notich, telephone: 301–415.3053,
                                                    Maryland 20852.                                         SUMMARY:   The U.S. Nuclear Regulatory                email: Mark.Notich@nrc.gov. Both are
                                                       Public Participation: Any member of                  Commission (NRC) is issuing a final                   staff of the Office of New Reactors, U.S.
                                                    the public who wishes to participate in                 revision to Section 5.4.2.1, ‘‘Steam                  Nuclear Regulatory Commission,
                                                    the meeting in person or via phone                      Generator Materials and Design,’’ of                  Washington, DC 20555–0001.
                                                    should contact Ms. Smethers using the                   NUREG–0800, ‘‘Standard Review Plan
                                                                                                                                                                  SUPPLEMENTARY INFORMATION:
                                                    information below. The meeting will                     [SRP] for the Review of Safety Analysis
                                                    also be webcast live: video.nrc.gov.                    Reports for Nuclear Power Plants: LWR                 I. Background
                                                                                                            [Light Water Reactor] Edition.’’ Revision
                                                    FOR FURTHER INFORMATION CONTACT:                                                                                 On April 22, 2016 (81 FR 23762), the
                                                                                                            4 to Section 5.4.2.1 of the SRP reflects
                                                    Michelle Smethers, email:                                                                                     NRC published for public comment the
                                                                                                            current NRC review methods and
                                                    michelle.smethers@nrc.gov, telephone:                                                                         proposed revisions to SRP Section
                                                                                                            practices based on lessons learned from
                                                    (301) 415–6711.                                                                                               5.4.2.1. The NRC received no comments
                                                                                                            NRC reviews of design certification and
                                                                                                                                                                  on the proposed revisions. Therefore,
                                                    Conduct of the Meeting                                  combined license applications
                                                                                                                                                                  the NRC is issuing Revision 4 to Section
                                                       Philip O. Alderson, M.D., will chair                 completed since the last revision of this
                                                                                                                                                                  5.4.2.1 of the SRP in final form for use.
                                                    the meeting. Dr. Alderson will conduct                  section.
                                                                                                                                                                  There have been minor editorial
                                                    the meeting in a manner that will                       DATES: The effective date of Revision 4               changes to this section since its issuance
                                                    facilitate the orderly conduct of                       to Section 5.4.2.1 of the SRP is                      in proposed form for public comment.
                                                    business. The following procedures                      September 2, 2016.                                    Details of the specific changes are
                                                    apply to public participation in the                    ADDRESSES: Please refer to Docket ID                  included at the end of the revised
                                                    meeting:                                                NRC–2016–0045 when contacting the                     section, under the subsection titled,
                                                       1. Persons who wish to provide a                     NRC about the availability of                         ‘‘Description of Changes.’’
                                                    written statement should submit an                      information regarding this document.                     Revision 4 to Section 5.4.2.1 of the
                                                    electronic copy to Ms. Smethers using                   You may obtain publicly-available                     SRP reflects current NRC review
                                                    the contact information listed above. All               information related to this document                  methods and practices based on lessons
                                                    submittals must be received by October                  using any of the following methods:                   learned from NRC reviews of design
                                                    3, 2016, and must pertain to the topic                     • Federal Rulemaking Web site: Go to               certification and combined license
                                                    on the agenda for the meeting.                          http://www.regulations.gov and search
asabaliauskas on DSK3SPTVN1PROD with NOTICES




                                                                                                                                                                  applications completed since the last
                                                       2. Questions and comments from                       for Docket ID NRC–2016–0045. Address                  revision of this section.
                                                    members of the public will be permitted                 questions about NRC dockets to Carol
                                                    during the meeting, at the discretion of                Gallagher; telephone: 301–415–3463;                   II. Backfitting and Finality Provisions
                                                    the Chairman.                                           email: Carol.Gallagher@nrc.gov. For                      Issuance of this revised SRP section
                                                       3. The draft transcript and meeting                  technical questions, contact the                      does not constitute backfitting as
                                                    summary will be available on ACMUI’s                    individuals listed in the FOR FURTHER                 defined in § 50.109 of title 10 of the
                                                    Web site http://www.nrc.gov/reading-                    INFORMATION CONTACT section of this                   Code of Federal Regulations (10 CFR),
                                                    rm/doc-collections/acmui/meetings/                      document.                                             ‘‘Backfitting,’’ (the Backfit Rule) or


                                               VerDate Sep<11>2014   18:21 Aug 02, 2016   Jkt 238001   PO 00000   Frm 00044   Fmt 4703   Sfmt 4703   E:\FR\FM\03AUN1.SGM   03AUN1


                                                    51218                      Federal Register / Vol. 81, No. 149 / Wednesday, August 3, 2016 / Notices

                                                    otherwise be inconsistent with the issue                a manner that is inconsistent with any                technical questions, contact the
                                                    finality provisions in 10 CFR part 52.                  issue finality provisions. If, in the                 individual listed in the FOR FURTHER
                                                    The NRC’s position is based upon the                    future, the NRC staff seeks to impose a               INFORMATION CONTACT section of this
                                                    following considerations:                               position in the SRP in a manner which                 document.
                                                       1. The SRP positions do not constitute               does not provide issue finality as                       • NRC’s Agencywide Documents
                                                    backfitting, inasmuch as the SRP is                     described in the applicable issue finality            Access and Management System
                                                    internal guidance directed at the NRC                   provision, then the NRC staff must                    (ADAMS): You may obtain publicly-
                                                    staff with respect to their regulatory                  address the criteria for avoiding issue               available documents online in the
                                                    responsibilities.                                       finality as described in the applicable               ADAMS Public Documents collection at
                                                       The SRP provides guidance to the                     issue finality provision.                             http://www.nrc.gov/reading-rm/
                                                    NRC staff on how to review an                                                                                 adams.html. To begin the search, select
                                                    application for the NRC’s regulatory                    III. Congressional Review Act
                                                                                                                                                                  ‘‘ADAMS Public Documents’’ and then
                                                    approval in the form of licensing.                        This SRP section revision is a rule as              select ‘‘Begin Web-based ADAMS
                                                    Changes in internal NRC staff guidance                  defined in the Congressional Review                   Search.’’ For problems with ADAMS,
                                                    are not matters for which either nuclear                Act (5 U.S.C. 801–808). However, the                  please contact the NRC’s Public
                                                    power plant applicants or licensees are                 Office of Management and Budget has                   Document Room (PDR) reference staff at
                                                    protected under either the Backfit Rule                 not found it to be a major rule as                    1–800–397–4209, 301–415–4737, or by
                                                    or the issue finality provisions of 10                  defined in the Congressional Review                   email to pdr.resource@nrc.gov. The
                                                    CFR part 52.                                            Act.                                                  ADAMS accession number for each
                                                       2. The NRC staff has no intention to                                                                       document referenced in this document
                                                    impose the SRP positions on current                        Dated at Rockville, Maryland, this 29th day
                                                                                                            of July 2016.                                         (if that document is available in
                                                    licensees and regulatory approvals                                                                            ADAMS) is provided the first time that
                                                    either now or in the future.                               For the Nuclear Regulatory Commission.
                                                                                                            Joseph Colaccino,                                     a document is referenced.
                                                       The NRC staff does not intend to
                                                                                                            Chief, New Reactor Rulemaking and
                                                                                                                                                                     • NRC’s PDR: You may examine and
                                                    impose or apply the positions described
                                                                                                            Guidance Branch, Division of Engineering,             purchase copies of public documents at
                                                    in the SRP to existing (already issued)
                                                                                                            Infrastructure, and Advanced Reactors, Office         the NRC’s PDR, Room O1–F21, One
                                                    licenses and regulatory approvals.
                                                                                                            of New Reactors.                                      White Flint North, 11555 Rockville
                                                    Therefore, the issuance of a final SRP—
                                                    even if considered guidance that is                     [FR Doc. 2016–18390 Filed 8–2–16; 8:45 am]            Pike, Rockville, Maryland 20852.
                                                    within the purview of the issue finality                BILLING CODE 7590–01–P                                FOR FURTHER INFORMATION CONTACT:
                                                    provisions in 10 CFR part 52—need not                                                                         Karen R. Cotton, Office of Nuclear
                                                    be evaluated as if it were a backfit or as                                                                    Reactor Regulation, U.S. Nuclear
                                                    being inconsistent with issue finality                  NUCLEAR REGULATORY                                    Regulatory Commission, Washington,
                                                    provisions. If, in the future, the NRC                  COMMISSION                                            DC 20555–0001; telephone: 301–415–
                                                    staff seeks to impose a position in the                 [Docket Nos. 50–280 and 50–281 NRC–                   1438, email: Karen.Cotton@nrc.gov.
                                                    SRP on holders of already issued                        2016–0105]                                            SUPPLEMENTARY INFORMATION:
                                                    licenses in a manner which does not
                                                                                                            Virginia Electric Power Company;                      I. Background
                                                    provide issue finality as described in the
                                                    applicable issue finality provision, then               Surry Power Station, Unit Nos. 1 and                    Dominion is the holder of Facility
                                                    the NRC staff must make the showing as                  2; Use of AREVA’s M5® Alloy Fuel Rod                  Operating License Nos. DPR–32 and
                                                    set forth in the Backfit Rule or address                Cladding Material                                     DPR–37, which authorize operation of
                                                    the criteria for avoiding issue finality as                                                                   SPS. The licenses provide, among other
                                                                                                            AGENCY:  Nuclear Regulatory                           things, that the facility is subject to all
                                                    described in the applicable issue finality              Commission.
                                                    provision.                                                                                                    rules, regulations, and orders of the NRC
                                                       3. Backfitting and issue finality do                 ACTION: Exemption; issuance.                          now or hereafter in effect.
                                                    not—with limited exceptions not                                                                                 The facility consists of two
                                                                                                            SUMMARY:   The U.S. Nuclear Regulatory
                                                    applicable here—protect current or                                                                            pressurized-water reactors (PWR)
                                                                                                            Commission (NRC) is issuing an
                                                    future applicants.                                                                                            located in Surry County, Virginia.
                                                                                                            exemption in response to a September
                                                       Applicants and potential applicants
                                                                                                            30, 2016, request from Virginia Electric              II. Request/Action
                                                    are not, with certain exceptions,
                                                                                                            Power Company (Dominion or the                           Pursuant to § 50.12 of title 10 of the
                                                    protected by either the Backfit Rule or
                                                                                                            licensee) in order to use AREVA’s M5®                 Code of Federal Regulations (10 CFR),
                                                    any issue finality provisions under 10
                                                                                                            alloy fuel rod cladding material at Surry             ‘‘Specific exemptions,’’ the licensee has
                                                    CFR part 52. This is because neither the
                                                                                                            Power Station, Unit Nos. 1 and 2 (SPS).               requested, by letter dated September 30,
                                                    Backfit Rule nor the issue finality
                                                    provisions under 10 CFR part 52—with                    DATES: The exemption was issued on                    2015 (ADAMS Accession No.
                                                    certain exclusions discussed in the next                July 27, 2016.                                        ML15282A036), an exemption from 10
                                                    paragraph—were intended to apply to                     ADDRESSES: Please refer to Docket ID                  CFR 50.46, ‘‘Acceptance criteria for
                                                    every NRC action which substantially                    NRC–2016–0105 when contacting the                     emergency core cooling systems [ECCS]
                                                    changes the expectations of current and                 NRC about the availability of                         for light-water nuclear power reactors,’’
                                                    future applicants.                                      information regarding this document.                  and 10 CFR part 50, appendix K, ‘‘ECCS
                                                       The exceptions to the general                        You may obtain publicly-available                     Evaluation Models,’’ to allow the use of
asabaliauskas on DSK3SPTVN1PROD with NOTICES




                                                    principle are applicable whenever an                    information related to this document                  fuel rods clad with AREVA’s M5® alloy.
                                                    applicant references a 10 CFR part 52                   using any of the following methods:                   The regulations in 10 CFR 50.46 require
                                                    license (e.g., an early site permit) and/                  • Federal Rulemaking Web site: Go to               that the calculated cooling performance
                                                    or NRC regulatory approval (e.g., a                     http://www.regulations.gov and search                 following postulated loss-of-coolant
                                                    design certification rule) with specified               for Docket ID: NRC–2016–0105. Address                 accidents (LOCAs) at reactors fueled
                                                    issue finality provisions. The NRC staff                questions about NRC dockets to Carol                  with zircaloy or ZIRLOTM cladding
                                                    does not, at this time, intend to impose                Gallagher; telephone: 301–415–3463;                   conforms to the criteria set forth in 10
                                                    the positions represented in the SRP in                 email: Carol.Gallagher@nrc.gov. For                   CFR 50.46(b). In addition, 10 CFR part


                                               VerDate Sep<11>2014   18:21 Aug 02, 2016   Jkt 238001   PO 00000   Frm 00045   Fmt 4703   Sfmt 4703   E:\FR\FM\03AUN1.SGM   03AUN1



Document Created: 2016-08-02 23:43:53
Document Modified: 2016-08-02 23:43:53
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
ActionStandard review plan--final section revision; issuance.
DatesThe effective date of Revision 4 to Section 5.4.2.1 of the SRP is September 2, 2016.
ContactCarolyn Lauron, telephone: 301-415- 2736, email: [email protected]; or Mark Notich, telephone: 301- 415.3053, email: [email protected] Both are staff of the Office of New Reactors, U.S. Nuclear Regulatory Commission, Washington, DC 20555- 0001.