We are superseding Airworthiness Directive (AD) 2009-15-17 for certain Airbus Model A330-200 and -300 series airplanes; and Model A340-200 and -300 series airplanes. AD 2009-15-17 required an inspection for damage to the protective treatments or any corrosion of all main landing gear (MLG) bogie beams, and application of protective treatments if no damage or corrosion was found. If any damage or corrosion was found, corrective action followed by the application of protective treatments was required. This new AD continues to require inspections for damage to the protective treatments or any corrosion of all MLG bogie beams, application of protective treatments, and corrective action if necessary. This new AD also requires modification of the MLG bogie beams, which terminates the repetitive inspections for any modified bogie beam. This new AD allows optional methods of compliance for certain actions, and adds Airbus Model A330-200 Freighter series airplanes to the applicability. This new AD revises the compliance times and adds a one-time inspection for airplanes that were inspected too early. This AD was prompted by reports of thin paint coats and paint degradation on enhanced main landing gear (MLG) bogie beams, as well as reports that some airplanes have been inspected too early and not re-inspected as needed. We are issuing this AD to detect and correct damage or corrosion of the MLG bogie beams, which could cause a runway excursion event, bogie beam detachment from the airplane, or MLG collapse, and could result in damage to the airplane and injury to the occupants.

Federal Register, Volume 81 Issue 188 (Wednesday, September 28, 2016)
[Federal Register Volume 81, Number 188 (Wednesday, September 28, 2016)]
[Rules and Regulations]
[Pages 66518-66523]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2016-21150]


-----------------------------------------------------------------------

DEPARTMENT OF TRANSPORTATION

Federal Aviation Administration

14 CFR Part 39

[Docket No. FAA-2013-0828; Directorate Identifier 2012-NM-036-AD; 
Amendment 39-18637; AD 2016-18-07]
RIN 2120-AA64


Airworthiness Directives; Airbus Airplanes

AGENCY: Federal Aviation Administration (FAA), Department of 
Transportation (DOT).

ACTION: Final rule.

-----------------------------------------------------------------------

SUMMARY: We are superseding Airworthiness Directive (AD) 2009-15-17 for 
certain Airbus Model A330-200 and -300 series airplanes; and Model 
A340-200 and -300 series airplanes. AD 2009-15-17 required an 
inspection for damage to the protective treatments or any corrosion of 
all main landing gear (MLG) bogie beams, and application of protective 
treatments if no damage or corrosion was found. If any damage or 
corrosion was found, corrective action followed by the application of 
protective treatments was required. This new AD continues to require 
inspections for damage to the protective treatments or any corrosion of 
all MLG bogie beams, application of protective treatments, and 
corrective action if necessary. This new AD also requires modification 
of the MLG bogie beams, which terminates the repetitive inspections for 
any modified bogie beam. This new AD allows optional methods of 
compliance for certain actions, and adds Airbus Model A330-200 
Freighter series airplanes to the applicability. This new AD revises 
the compliance times and adds a one-time inspection for airplanes that 
were inspected too early. This AD was prompted by reports of thin paint 
coats and paint degradation on enhanced main landing gear (MLG) bogie 
beams, as well as reports that some airplanes have been inspected too 
early and not re-inspected as needed. We are issuing this AD to detect 
and correct damage or corrosion of the MLG bogie beams, which could 
cause a runway excursion event, bogie beam detachment from the 
airplane, or MLG collapse, and could result in damage to the airplane 
and injury to the occupants.

DATES: This AD is effective November 2, 2016.
    The Director of the Federal Register approved the incorporation by 
reference of certain publications listed in this AD as of November 2, 
2016.
    The Director of the Federal Register approved the incorporation by 
reference of certain other publications listed in this AD as of 
September 2, 2009 (74 FR 37523, July 29, 2009).

ADDRESSES: For Airbus service information identified in this final 
rule, contact Airbus SAS, Airworthiness Office--EAL, 1 Rond Point 
Maurice Bellonte, 31707 Blagnac Cedex, France; telephone: +33 5 61 93 
36 96; fax: +33 5 61 93 45 80; email: [email protected]; Internet: http://www.airbus.com. For Messier-Dowty 
service information identified in this final rule, contact Messier-
Dowty: Messier Services Americas, Customer Support Center, 45360 Severn 
Way, Sterling, VA 20166-8910; telephone: 703-450-8233; fax: 703-404-
1621; Internet: https://techpubs.services/messier-dowty.com. You may 
view this referenced service information at the FAA, Transport Airplane 
Directorate, 1601 Lind Avenue SW., Renton, WA. For information on the 
availability of this material at the FAA, call 425-227-1221. It is also 
available on the Internet at http://www.regulations.gov by searching 
for and locating Docket No. FAA-2013-0828.

Examining the AD Docket

    You may examine the AD docket on the Internet at http://www.regulations.gov by searching for and locating Docket No. FAA-2013-
0828; or in person at the Docket Management Facility between 9 a.m. and 
5 p.m., Monday through Friday, except Federal holidays. The AD docket 
contains this AD, the regulatory evaluation, any comments received, and 
other information. The address for the Docket Office (telephone: 800-
647-

[[Page 66519]]

5527) is Docket Management Facility, U.S. Department of Transportation, 
Docket Operations, M-30, West Building Ground Floor, Room W12-140, 1200 
New Jersey Avenue SE., Washington, DC 20590.

FOR FURTHER INFORMATION CONTACT: Vladimir Ulyanov, Aerospace Engineer, 
International Branch, ANM-116, Transport Airplane Directorate, FAA, 
1601 Lind Avenue SW., Renton, WA 98057-3356; telephone: 425-227-1138; 
fax: 425-227-1149.

SUPPLEMENTARY INFORMATION: 

Discussion

    We issued a second supplemental notice of proposed rulemaking 
(SNPRM) to amend 14 CFR part 39 to supersede AD 2009-15-17, Amendment 
39-15980 (74 FR 37523, July 29, 2009) (``AD 2009-15-17''). AD 2009-15-
17 applied to certain Airbus Model A330-200 and -300 series airplanes, 
and Model A340-200 and -300 series airplanes. The second SNPRM 
published in the Federal Register on February 5, 2016 (81 FR 6185) 
(``the second SNPRM''). We preceded the second SNPRM with the first 
SNPRM, which was published in the Federal Register on March 5, 2014 (79 
FR 12414) (``the first SNPRM''). We preceded the first SNPRM with a 
notice of proposed rulemaking (NPRM) that published in the Federal 
Register on September 25, 2013 (78 FR 58978) (``the NPRM''). The NPRM 
was prompted by reports of thin paint coats and paint degradation on 
enhanced MLG bogie beams. The NPRM proposed to continue to require 
inspections for damage to the protective treatments or any corrosion of 
all MLG bogie beams, application of protective treatments, and 
corrective action if necessary. The NPRM also proposed to require 
modification of the MLG bogie beams, which would terminate the 
repetitive inspections for any modified bogie beam. In addition, the 
NPRM proposed to allow optional methods of compliance for certain 
actions, and to add Airbus Model A330-200 Freighter series airplanes to 
the applicability. The first SNPRM proposed to revise the compliance 
times and add a one-time inspection for airplanes that were inspected 
too early. The second SNPRM proposed to clarify the required actions 
and the specific configurations to which the actions must be applied. 
We are issuing this AD to detect and correct damage or corrosion of the 
MLG bogie beams, which could cause a runway excursion event, bogie beam 
detachment from the airplane, or MLG collapse, and could result in 
damage to the airplane and injury to the occupants.
    The European Aviation Safety Agency (EASA), which is the Technical 
Agent for the Member States of the European Union, has issued EASA AD 
2013-0267R1, dated March 4, 2014; corrected May 8, 2014 (referred to 
after this as the Mandatory Continuing Airworthiness Information, or 
``the MCAI''), to correct an unsafe condition for certain Airbus Model 
A330-200 Freighter, -200, and -300 series airplanes; and Model A340-200 
and -300 series airplanes. The MCAI states:

    The operator of an A330 aeroplane (which has a common bogie beam 
with the A340) reported a fracture of the Right Hand (RH) main 
landing gear (MLG) bogie beam, which occurred while turning during 
low speed taxi maneuvers. The bogie fractured aft of the pivot point 
and remained attached to the sliding tube by the brake torque 
reaction rods. After this RH bogie failure, the aeroplane continued 
for approximately 40 meters on the forks of the sliding member 
before coming to rest on the taxiway.
    The investigations revealed that this event was due to corrosion 
pitting occurring on the bore of the bogie beam.
    This condition, if not detected and corrected, could lead to a 
runway excursion event or to detachment of the bogie from the 
aeroplane, or to MLG collapse, possibly resulting in damage to the 
aeroplane and injury to the occupants.
    To enable early detection and repair of corrosion of the 
internal surfaces, EASA issued EASA AD 2007-0314 to require a one-
time inspection of all MLG bogie beams, except Enhanced MLG bogie 
beams, and the reporting of the results to Airbus. EASA AD 2007-0314 
was revised and later superseded by EASA AD 2008-0093, reducing the 
inspection threshold period.
    The results of subsequent investigations showed thin paint coats 
and paint degradation, confirmed as well on Enhanced MLG bogie 
beams. To address this additional concern, EASA issued AD 2011-0141 
[which was not mandated by the FAA], retaining the requirements of 
EASA AD 2008-0093, which was superseded, to require a one-time 
visual inspection of all MLG bogie beams, including a visual 
examination of the internal diameter for corrosion or damage to 
protective treatments of the bogie beam and measurement of the paint 
thickness on the internal bore, accomplishment of the applicable 
corrective actions and a modification of the MLG bogie beam to 
improve the coat paint application method, and application of 
corrosion protection.
    Prompted by in-service requests, EASA issued EASA AD 2012-0015 
retaining the requirements of EASA AD 2011-0141, which was 
superseded, and introducing repetitive inspections of the MLG bogie 
beams, which allows extension of the compliance time for the MLG 
bogie beam modification from 15 years to 21 years. Modification of a 
MLG bogie beam constitutes terminating action for the repetitive 
inspections for that MLG bogie beam.
    Reports on inspection results provided to Airbus show that some 
aeroplanes were initially inspected too early (before 4 years and 6 
months since aeroplane first flight with bogie beam installed/
installed after overhaul) and have not been re-inspected as 
required.
    For the reasons described above, this [EASA] AD retains the 
requirements of EASA AD 2012-0015, which is superseded, and 
redefines the inspection periodicity. This [EASA] AD also introduces 
a specific one-time inspection for aeroplanes that have been 
inspected too early.
    Prompted by operator comments, this [EASA] AD is revised to 
clarify the required actions and the specific configurations to 
which the actions must be applied. Appendix 1 of this [EASA] AD has 
been amended accordingly.
    This [EASA] AD is republished to editorially correct paragraph 
(4).

    You may examine the MCAI in the AD docket on the Internet at http://www.regulations.gov by searching for and locating Docket No. FAA-2013-
0828.

Comments

    We gave the public the opportunity to participate in developing 
this AD. The following presents the comment received on the second 
SNPRM and the FAA's response.

Request To Revise the Applicability of the Second SNPRM

    American Airlines (AAL) requested that we revise the applicability 
of the proposed AD (in the second SNPRM) to exclude airplanes with MLG 
bogie beams that have had Airbus modification 58896 embodied in-
service, as specified in Airbus Service Bulletin A330-32-3237. AAL 
pointed out that paragraph (c) of the proposed AD (in the second SNPRM) 
does not reflect MLG bogie beams that were modified in-service.
    We disagree with the request to revise the applicability of the 
proposed AD (in the second SNPRM). Paragraph (k) of this AD 
specifically requires inspection, repair, modification, and re-
identification of the MLG bogie beams. However, paragraph (f) of this 
AD states that actions already done need not be repeated. If an 
operator has already accomplished the actions required by paragraph (k) 
of this AD before the effective date of this AD, then the modified 
airplane is already in compliance with the corresponding requirements 
of this AD. We have not made any changes to this AD in this regard.

Additional Changes Made in This AD

    We have revised paragraph (m)(1) of this AD to remove reference to 
paragraph (g) of this AD; the reporting requirement specified in 
paragraph (m)(1) of this AD is required only for the

[[Page 66520]]

inspection required by paragraph (k) of this AD.
    We have also revised paragraph (m)(2) of this AD to reference the 
correct service information for reporting inspection findings for the 
inspection required by paragraph (h) of this AD.

Conclusion

    We reviewed the available data, including the comment received, and 
determined that air safety and the public interest require adopting 
this AD with the changes described previously and minor editorial 
changes. We have determined that these minor changes:
     Are consistent with the intent that was proposed in the 
second SNPRM for correcting the unsafe condition; and
     Do not add any additional burden upon the public than was 
already proposed in the second SNPRM.

Related Service Information Under 1 CFR Part 51

    Airbus has issued the following service information.
     Airbus Service Bulletin A330-32-3225, Revision 02, 
including Appendix 1, dated October 26, 2012. This service information 
describes procedures for cleaning the internal bore and accomplishing a 
detailed inspection of internal surfaces of the left-hand (LH) and 
right-hand (RH) MLG bogie beams to detect any damage to the protective 
treatments and any corrosion, and measuring the paint thickness on the 
internal bore.
     Airbus Service Bulletin A330-32-3237, Revision 01, 
including Reporting Sheet, dated October 14, 2011. This service 
information describes procedures for a detailed inspection for damage 
and corrosion of the internal bores of the LH and RH MLG bogie beam and 
repair, as well as modification and re-identification.
     Airbus Service Bulletin A340-32-4268, Revision 03, 
including Appendix 1, dated January 14, 2013. This service information 
describes procedures for cleaning the internal bore and accomplishing a 
detailed inspection of internal surfaces of the LH and RH MLG bogie 
beams to detect any damage to the protective treatments and any 
corrosion, and measuring the paint thickness on the internal bore.
     Airbus Service Bulletin A340-32-4279, Revision 01, 
including Reporting Sheet, dated October 14, 2011. This service 
information describes procedures for a detailed inspection for damage 
and corrosion of the internal bores of the LH and RH MLG bogie beam, 
repair, modification, and reidentification.
    Messier-Bugatti-Dowty has issued the following service information.
     Messier-Dowty Service Bulletin A33/34-32-278, Revision 1, 
including Appendixes A and B, dated August 24, 2011. This service 
information describes procedures for inspections for damage and 
corrosion to the protective treatment of the internal bores of the LH 
and RH MLG bogie beam, and repairs.
     Messier-Dowty Service Bulletin A33/34-32-283, Revision 1, 
including Appendix A, dated July 10, 2012. This service information 
describes procedures for modification of the LH and RH MLG bogie beams.
     Messier-Dowty Service Bulletin A33/34-32-284, Revision 1, 
including Appendix A, dated July 10, 2012. This service information 
describes procedures for modification of the LH and RH MLG bogie beams.
    This service information is reasonably available because the 
interested parties have access to it through their normal course of 
business or by the means identified in the ADDRESSES section.

Costs of Compliance

    We estimate that this AD affects 51 airplanes of U.S. registry.
    We also estimate that it takes about 34 work-hours per product to 
comply with this AD, and 1 work-hour per product for reporting. The 
average labor rate is $85 per work-hour. Based on these figures, we 
estimate the cost of this AD on U.S. operators to be $151,725, or 
$2,975 per product.
    In addition, we estimate that any necessary follow-on actions would 
take about 10 work-hours at a labor rate of $85 per work-hour, for a 
cost of $850 per product. We have no way of determining the number of 
aircraft that might need these actions.

Paperwork Reduction Act

    A federal agency may not conduct or sponsor, and a person is not 
required to respond to, nor shall a person be subject to penalty for 
failure to comply with a collection of information subject to the 
requirements of the Paperwork Reduction Act unless that collection of 
information displays a current valid OMB control number. The control 
number for the collection of information required by this AD is 2120-
0056. The paperwork cost associated with this AD has been detailed in 
the Costs of Compliance section of this document and includes time for 
reviewing instructions, as well as completing and reviewing the 
collection of information. Therefore, all reporting associated with 
this AD is mandatory. Comments concerning the accuracy of this burden 
and suggestions for reducing the burden should be directed to the FAA 
at 800 Independence Ave. SW., Washington, DC 20591, ATTN: Information 
Collection Clearance Officer, AES-200.

Authority for This Rulemaking

    Title 49 of the United States Code specifies the FAA's authority to 
issue rules on aviation safety. Subtitle I, section 106, describes the 
authority of the FAA Administrator. ``Subtitle VII: Aviation 
Programs,'' describes in more detail the scope of the Agency's 
authority.
    We are issuing this rulemaking under the authority described in 
``Subtitle VII, Part A, Subpart III, Section 44701: General 
requirements.'' Under that section, Congress charges the FAA with 
promoting safe flight of civil aircraft in air commerce by prescribing 
regulations for practices, methods, and procedures the Administrator 
finds necessary for safety in air commerce. This regulation is within 
the scope of that authority because it addresses an unsafe condition 
that is likely to exist or develop on products identified in this 
rulemaking action.

Regulatory Findings

    We determined that this AD will not have federalism implications 
under Executive Order 13132. This AD will not have a substantial direct 
effect on the States, on the relationship between the national 
government and the States, or on the distribution of power and 
responsibilities among the various levels of government.
    For the reasons discussed above, I certify that this AD:
    1. Is not a ``significant regulatory action'' under Executive Order 
12866;
    2. Is not a ``significant rule'' under the DOT Regulatory Policies 
and Procedures (44 FR 11034, February 26, 1979);
    3. Will not affect intrastate aviation in Alaska; and
    4. Will not have a significant economic impact, positive or 
negative, on a substantial number of small entities under the criteria 
of the Regulatory Flexibility Act.

List of Subjects in 14 CFR Part 39

    Air transportation, Aircraft, Aviation safety, Incorporation by 
reference, Safety.

Adoption of the Amendment

    Accordingly, under the authority delegated to me by the 
Administrator, the FAA amends 14 CFR part 39 as follows:

[[Page 66521]]

PART 39--AIRWORTHINESS DIRECTIVES

0
1. The authority citation for part 39 continues to read as follows:

    Authority:  49 U.S.C. 106(g), 40113, 44701.


Sec.  39.13  [Amended]

0
2. The FAA amends Sec.  39.13 by removing Airworthiness Directive (AD) 
2009-15-17, Amendment 39-15980 (74 FR 37523, July 29, 2009), and adding 
the following new AD:

2016-18-07 Airbus: Amendment 39-18637; Docket No. FAA-2013-0828; 
Directorate Identifier 2012-NM-036-AD.

(a) Effective Date

    This AD is effective November 2, 2016.

(b) Affected ADs

    This AD replaces AD 2009-15-17, Amendment 39-15980 (74 FR 37523, 
July 29, 2009) (``AD 2009-15-17'').

(c) Applicability

    This AD applies to the airplanes identified in paragraphs (c)(1) 
and (c)(2) of this AD, certificated in any category, all 
manufacturer serial numbers (MSN), except those on which Airbus 
modification 58896 has been embodied in production.
    (1) Airbus Model A330-223F, -243F, -201, -202, -203, -223, -243, 
-301, -302, -303, -321, -322, -323, -341, -342, and -343 airplanes.
    (2) Airbus Model A340-211, -212, -213, -311, -312, and -313 
airplanes.

(d) Subject

    Air Transport Association (ATA) of America Code 32, Landing 
gear.

(e) Reason

    This AD was prompted by reports of thin paint coats and paint 
degradation on enhanced main landing gear (MLG) bogie beams, as well 
as reports that some airplanes have been inspected too early and not 
re-inspected as needed. We are issuing this AD to detect and correct 
damage or corrosion of the MLG bogie beams, which could cause a 
runway excursion event, bogie beam detachment from the airplane, or 
MLG collapse, and could result in damage to the airplane and injury 
to the occupants.

(f) Compliance

    Comply with this AD within the compliance times specified, 
unless already done.

(g) Repetitive Inspections for Certain Airplane Configurations

    For airplanes equipped with basic MLG (201252 series), or growth 
MLG (201490 series): After 54 months at the earliest, but no later 
than 72 months since the left-hand (LH) or right-hand (RH) MLG bogie 
beam's first flight on an airplane, or since its first flight on an 
airplane after overhaul, as applicable, clean the internal bore and 
accomplish a detailed inspection of internal surfaces of the LH and 
RH MLG bogie beams to detect any damage to the protective treatments 
and any corrosion, and measure the paint thickness on the internal 
bore, in accordance with the Accomplishment Instructions of Airbus 
Service Bulletin A330-32-3225, Revision 02, including Appendix 1, 
dated October 26, 2012; or Airbus Service Bulletin A340-32-4268, 
Revision 03, including Appendix 1, dated January 14, 2013; as 
applicable. Repeat the inspections thereafter at intervals not less 
than 54 months, but not exceeding 72 months, after the most recent 
inspection. During overhaul of a MLG bogie beam, any corrosion will 
be removed, which means that the first inspection after overhaul of 
that MLG bogie beam, as required by this paragraph, is between 54 
months and 72 months since its first flight on an airplane after 
overhaul.

(h) One-Time Detailed Inspection for Certain Airplane Configurations

    For airplanes equipped with basic MLG (201252 series), or growth 
MLG (201490 series) having a LH or RH MLG bogie beam that has 
already exceeded 72 months since its first flight on an airplane, or 
since its first flight on an airplane after overhaul, as applicable, 
as of the effective date of this AD; and that has been inspected as 
specified in Airbus Service Bulletin A330-32-3225 or Airbus Service 
Bulletin A340-32-4268, as applicable, earlier than 54 months since 
first flight of the affected MLG bogie beam on an airplane, or since 
its first flight on an airplane after its most recent overhaul, as 
applicable: Within the applicable compliance time indicated in 
paragraphs (h)(1) through (h)(4) of this AD, clean the internal bore 
and accomplish a detailed inspection of the internal surfaces of the 
LH and RH MLG bogie beams to detect any damage to the protective 
treatments and any corrosion, and measure the paint thickness on the 
internal bore, in accordance with the Accomplishment Instructions of 
Airbus Service Bulletin A330-32-3225, Revision 02, including 
Appendix 1, dated October 26, 2012; or Airbus Service Bulletin A340-
32-4268, Revision 03, including Appendix 1, dated January 14, 2013; 
as applicable.
    (1) For MLG bogie beams having the configurations specified in 
both paragraphs (h)(1)(i) and (h)(1)(ii) of this AD: Do the detailed 
inspection specified in the introductory text of paragraph (h) of 
this AD within 9 months after the effective date of this AD.
    (i) MLG bogie beams having between 72 and 120 months since first 
flight on an airplane, or since the MLG bogie beam's first flight on 
an airplane after the MLG bogie beam's most recent overhaul, as 
applicable.
    (ii) MLG bogie beams on which the first inspection was done 
after 51 months and before 54 months since first flight of the MLG 
bogie beam on an airplane, or since the MLG bogie beam's first 
flight on an airplane after the MLG bogie beam's most recent 
overhaul, as applicable.
    (2) For MLG bogie beams having the configurations specified in 
both paragraphs (h)(2)(i) and (h)(2)(ii) of this AD: Do the detailed 
inspection specified in the introductory text of paragraph (h) of 
this AD within 3 months after the effective date of this AD.
    (i) MLG bogie beams having between 72 and 120 months since first 
flight on an airplane, or since the MLG bogie beam's first flight on 
an airplane after the MLG bogie beam's most recent overhaul, as 
applicable.
    (ii) MLG bogie beams on which the first inspection was done 
after 45 months and before 51 months since first flight of the MLG 
bogie beam on an airplane, or since the MLG bogie beam's first 
flight on an airplane after the MLG bogie beam's most recent 
overhaul, as applicable.
    (3) For MLG bogie beams having the configurations specified in 
both paragraphs (h)(3)(i) and (h)(3)(ii) of this AD: Do the detailed 
inspection specified in the introductory text of paragraph (h) of 
this AD within 3 months after the effective date of this AD.
    (i) MLG bogie beams having between 72 and 96 months since first 
flight on an airplane, or since the MLG bogie beam's first flight on 
an airplane after the MLG bogie beam's most recent overhaul, as 
applicable.
    (ii) MLG bogie beams which have accumulated, at the effective 
date of this AD, less than 96 months and on which the first 
inspection was done before 51 months since first flight of the MLG 
bogie beam on an airplane, or since the MLG bogie beam's first 
flight on an airplane after the after the MLG bogie beam's most 
recent overhaul, as applicable.
    (4) For MLG bogie beams having the configurations specified in 
both paragraphs (h)(4)(i) and (h)(4)(ii) of this AD: Do the detailed 
inspection specified in the introductory text of paragraph (h) of 
this AD within 1 month after the effective date of this AD.
    (i) MLG bogie beams having between 96 and 120 months since first 
flight on an airplane, or since the MLG bogie beam's first flight on 
an airplane after the MLG bogie beam's most recent overhaul, as 
applicable.
    (ii) MLG bogie beams which has accumulated, at the effective 
date of this AD, 96 months or more and on which the first inspection 
was done before 45 months since first flight of the MLG bogie beam 
on an airplane, or since the MLG bogie beam's first flight on an 
airplane after the MLG bogie beam's most recent overhaul, as 
applicable.

(i) Application of Protective Treatment

    If, during any inspection required by paragraph (g) or (h) of 
this AD, no damage or corrosion is found: Before further flight, 
apply the protective treatments to the MLG bogie beam, in accordance 
with the Accomplishment Instructions of Messier-Dowty Service 
Bulletin A33/34-32-272, Revision 1, including Appendixes A, B, C, 
and D, dated September 22, 2008.

(j) Repair and Application of Protective Treatment

    If, during any inspection required by paragraph (g) or (h) of 
this AD, any damage or corrosion is found: Before further flight, 
repair and apply the protective treatments to the MLG bogie beam, in 
accordance with the Accomplishment Instructions of Messier-Dowty 
Service Bulletin A33/34-32-272, Revision 1, including Appendixes A, 
B, C, and D, dated September 22, 2008.

[[Page 66522]]

(k) Inspection and Corrective Actions

    For airplanes equipped with basic MLG (201252 series), growth 
MLG (201490 series), or enhanced MLG (10-210 series): Before the 
accumulation of 252 total months on an MLG bogie beam, or within 90 
days after the effective date of this AD, whichever occurs later, do 
the actions specified in paragraphs (k)(1) and (k)(2) of this AD 
concurrently and in sequence.
    (1) Except as provided by paragraph (k)(3) of this AD: Do a 
detailed inspection for damage and corrosion of the internal bores 
of the LH and RH MLG bogie beam, in accordance with the 
Accomplishment Instructions of Airbus Service Bulletin A330-32-3237 
or A340-32-4279, both Revision 01, both including Reporting Sheet, 
both dated October 14, 2011, as applicable. If any damage or 
corrosion is found, before further flight, repair in accordance with 
the Accomplishment Instructions of Airbus Service Bulletin A330-32-
3237 or A340-32-4279, both Revision 01, both including Reporting 
Sheet, both dated October 14, 2011, as applicable.
    (2) Except as provided by paragraph (k)(3) of this AD: Modify 
and re-identify, as applicable, the LH and RH MLG bogie beams, in 
accordance with the Accomplishment Instructions of Airbus Service 
Bulletin A330-32-3237 or A340-32-4279, both Revision 01, both 
including Reporting Sheet, both dated October 14, 2011, as 
applicable.
    (3) The inspection requirements of paragraph (k)(1) of this AD, 
and the modification requirements only of paragraph (k)(2) of this 
AD, do not apply to any MLG bogie beam with a serial number listed 
in Appendix A of Messier-Dowty Service Bulletin A33/34-32-283 or 
A33/34-32-284, both Revision 1, both dated July 10, 2012, as 
applicable.

(l) Optional Methods of Compliance for Certain Airplane Configurations

    Inspections and corrective actions on both MLG bogie beams done 
in accordance with the instructions of Messier-Dowty Service 
Bulletin A33/34-32-271, Revision 1, including Appendixes A and B, 
dated November 16, 2007; or Messier-Dowty Service Bulletin A33/34-
32-272, Revision 1, including Appendixes A, B, C, and D, dated 
September 22, 2008; as applicable; are acceptable methods of 
compliance for the requirements of paragraph (g) of this AD, 
provided each inspection is accomplished between 54 months and 72 
months since the first flight of the affected MLG bogie beam on an 
airplane, or since the MLG bogie beam's first flight after the MLG 
bogie beam's most recent overhaul, as applicable.

(m) Reporting Requirement

    (1) Submit a report of the findings (both positive and negative) 
of each inspection required by paragraph (k) of this AD, as 
applicable, to Airbus, Customer Service Directorate, 1 Rond Point 
Maurice Bellonte, 31707 Blagnac Cedex, France, using the applicable 
Reporting Sheet in Airbus Service Bulletin A330-32-3237, Revision 
01, including Reporting Sheet, dated October 14, 2011; or Airbus 
Service Bulletin A340-32-4279, Revision 01, including Reporting 
Sheet, dated October 14, 2011; at the applicable time specified in 
paragraph (m)(1)(i) or (m)(1)(ii) of this AD.
    (i) If the inspection was done on or after the effective date of 
this AD: Submit the report within 90 days after the inspection.
    (ii) If the inspection was done before the effective date of 
this AD: Submit the report within 90 days after the effective date 
of this AD.
    (2) Submit a report of the findings (both positive and negative) 
of the inspection required by paragraph (h) of this AD to Airbus, 
Customer Service Directorate, 1 Rond Point Maurice Bellonte, 31707 
Blagnac Cedex, France, using the applicable Reporting Sheet in 
Airbus Service Bulletin A330-32-3225, Revision 02, including 
Appendix 1, dated October 26, 2012; or Airbus Service Bulletin A340-
32-4268, Revision 03, including Appendix 1, dated January 14, 2013; 
at the applicable time specified in paragraph (m)(2)(i) or 
(m)(2)(ii) of this AD.
    (i) If the inspection was done on or after the effective date of 
this AD: Submit the report within 30 days after the inspection.
    (ii) If the inspection was done before the effective date of 
this AD: Submit the report within 30 days after the effective date 
of this AD.

(n) Optional Method of Compliance for Certain Requirements

    (1) Inspections for damage and corrosion to the protective 
treatment of the internal bores of the LH and RH MLG bogie beam, and 
repairs, done in accordance with Messier-Dowty Service Bulletin A33/
34-32-278, Revision 1, including Appendixes A and B, dated August 
24, 2011, are acceptable methods of compliance with the 
corresponding requirements of paragraph (k)(1) of this AD.
    (2) Modification of the LH and RH MLG bogie beams, done in 
accordance with Messier-Dowty Service Bulletins A33/34-32-283 or 
A33/34-32-284, both Revision 1, both including Appendix A, both 
dated July 10, 2012, as applicable, is an acceptable method of 
compliance with the corresponding requirements of paragraph (k)(2) 
of this AD.

(o) Optional Terminating Action for Certain Requirements

    Modification of both LH and RH MLG bogie beams on an airplane, 
done in accordance with paragraph (k) of this AD, or as specified in 
paragraphs (n)(1) and (n)(2) of this AD, terminates the repetitive 
inspections required by paragraph (g) of this AD for this airplane.

(p) Credit for Previous Actions

    (1) This paragraph provides credit for the corresponding 
inspections and corrective actions done on an LH or RH MLG bogie 
beam required by paragraph (g) of this AD, if those actions were 
performed before the effective date of this AD using Airbus Service 
Bulletin A330-32-3225, dated November 21, 2007; or Revision 1, dated 
October 30, 2008; provided the inspections and corrective actions 
were accomplished between 54 months and 72 months since first flight 
of the affected MLG bogie beam on an airplane, or since its first 
flight after the MLG bogie beam's most recent overhaul, as 
applicable. Airbus Service Bulletin A330-32-3225, dated November 21, 
2007, is not incorporated by reference in this AD. Airbus Mandatory 
Service Bulletin A330-32-3225, Revision 01, including Appendix 1, 
dated October 30, 2008, was incorporated by reference in AD 2009-15-
07.
    (2) This paragraph provides credit for the corresponding 
inspections and corrective actions done on an LH or RH MLG bogie 
beam required by paragraph (g) of this AD, if those actions were 
performed before the effective date of this AD using Airbus 
Mandatory Service Bulletin A340-32-4268, dated November 21, 2007; 
Revision 01, including Appendix 1, dated October 30, 2008; or 
Revision 02, dated October 26, 2012; provided these inspections and 
corrective actions were accomplished between 54 months and 72 months 
since first flight of the affected MLG bogie beam on an airplane, or 
since its first flight after the MLG bogie beam's most recent 
overhaul, as applicable. Airbus Service Bulletin A340-32-4268, dated 
November 21, 2007; and Revision 02, dated October 26, 2012; are not 
incorporated by reference in this AD. Airbus Mandatory Service 
Bulletin A340-32-4268, Revision 01, including Appendix 1, dated 
October 30, 2008, was incorporated by reference in AD 2009-15-17.
    (3) This paragraph provides credit for the corresponding actions 
required by paragraph (n)(1) of this AD, if those actions were 
performed before the effective date of this AD using Messier-Dowty 
Service Bulletin A33/34-32-271, dated September 13, 2007, which is 
not incorporated by reference in this AD.
    (4) This paragraph provides credit for the corresponding actions 
required by paragraphs (j) and (n)(1) of this AD, if those actions 
were performed before the effective date of this AD using Messier-
Dowty Service Bulletin A33/34-32-272, including Appendixes A, B, C, 
and D, dated November 16, 2007, which is not incorporated by 
reference in this AD.
    (5) This paragraph provides credit for the corresponding actions 
required by paragraphs (k), (m), and (r)(1)(i) of this AD, if those 
actions were performed before the effective date of this AD using 
Airbus Service Bulletin A330-32-3237, including Reporting Sheet, 
dated January 18, 2011.
    (6) This paragraph provides credit for the corresponding actions 
required by paragraphs (k), (m), and (r)(1)(i) of this AD, if those 
actions were performed before the effective date of this AD using 
Airbus Service Bulletin A340-32-4279, including Reporting Sheet, 
dated January 18, 2011.
    (7) This paragraph provides credit for the corresponding actions 
required by paragraphs (k)(3), (n)(2), (r)(1)(ii), and (r)(1)(iii) 
of this AD, if those actions were performed before the effective 
date of this AD using Messier-Dowty Service Bulletin A33/34-32-283, 
including Appendix A, dated May 11, 2010, which is not incorporated 
by reference in this AD.
    (8) This paragraph provides credit for the corresponding actions 
required by paragraphs (k)(3), (n)(2), (r)(1)(ii), and (r)(1)(iii) 
of this AD, if those actions were performed before the effective 
date of this AD

[[Page 66523]]

using Messier-Dowty Service Bulletin A33/34-32-284, including 
Appendix A, dated May 11, 2010, which is not incorporated by 
reference in this AD.
    (9) This paragraph provides credit for the corresponding actions 
required by paragraphs (n)(1) and (r)(1)(ii) of this AD, if those 
actions were performed before the effective date of this AD using 
Messier-Dowty Service Bulletin A33/34-32-278, including Appendixes A 
and B, dated February 17, 2010, which is not incorporated by 
reference in this AD.

(q) Clarification of Inspection Compliance Times

    After accomplishment of the one-time detailed inspection 
required by paragraph (h) of this AD, the repetitive actions 
required by paragraph (g) of this AD remain applicable, and must be 
done within the compliance times specified in paragraph (g) of this 
AD.

(r) Parts Installation Limitations

    (1) After modification of an airplane, as required by paragraph 
(k) of this AD, or as specified in paragraphs (n)(1) and (n)(2) of 
this AD, do not install an MLG bogie beam on any airplane unless it 
is done in compliance with the requirements of paragraph (r)(1)(i), 
(r)(1)(ii), or (r)(1)(iii) of this AD.
    (i) The MLG bogie beam has been modified and re-identified in 
accordance with the Accomplishment Instructions of Airbus Service 
Bulletin A330-32-3237 or A340-32-4279, both Revision 01, both 
including Reporting Sheet, both dated October 14, 2011, as 
applicable.
    (ii) The MLG bogie beam has been inspected and all applicable 
corrective actions have been done in accordance with the 
Accomplishment Instructions of Messier-Dowty Service Bulletin A33/
34-32-278, Revision 1, dated August 24, 2011; and modified in 
accordance with the Accomplishment Instructions of Messier-Dowty 
Service Bulletin A33/34-32-283 or A33/34-32-284, both Revision 1, 
both including Appendix A, both dated July 10, 2012.
    (iii) The MLG bogie beam has a serial number listed in Appendix 
A of Messier-Dowty Service Bulletin A33/34-32-283 or A33/34-32-284, 
both Revision 1, both dated July 10, 2012, as applicable.
    (2) As of the effective date of this AD, except as specified in 
paragraph (r)(1) of this AD, installation of an MLG bogie beam on an 
airplane is allowed, provided that following the installation it is 
inspected and all applicable repairs and corrective actions have 
been done in accordance with the requirements of this AD.

(s) Other FAA AD Provisions

    The following provisions also apply to this AD:
    (1) Alternative Methods of Compliance (AMOCs): The Manager, 
International Branch, ANM-116, Transport Airplane Directorate, FAA, 
has the authority to approve AMOCs for this AD, if requested using 
the procedures found in 14 CFR 39.19. In accordance with 14 CFR 
39.19, send your request to your principal inspector or local Flight 
Standards District Office, as appropriate. If sending information 
directly to the International Branch, send it to ATTN: Vladimir 
Ulyanov, Aerospace Engineer, International Branch, ANM-116, 
Transport Airplane Directorate, FAA, 1601 Lind Avenue SW., Renton, 
WA 98057-3356; telephone: 425-227-1138; fax: 425-227-1149. 
Information may be emailed to: [email protected]. 
Before using any approved AMOC, notify your appropriate principal 
inspector, or lacking a principal inspector, the manager of the 
local flight standards district office/certificate holding district 
office. The AMOC approval letter must specifically reference this 
AD.
    (2) Contacting the Manufacturer: As of the effective date of 
this AD, for any requirement in this AD to obtain corrective actions 
from a manufacturer, the action must be accomplished using a method 
approved by the Manager, International Branch, ANM-116, Transport 
Airplane Directorate, FAA; or the European Aviation Safety Agency 
(EASA); or Airbus's EASA Design Organization Approval (DOA). If 
approved by the DOA, the approval must include the DOA-authorized 
signature.
    (3) Reporting Requirements: A federal agency may not conduct or 
sponsor, and a person is not required to respond to, nor shall a 
person be subject to a penalty for failure to comply with a 
collection of information subject to the requirements of the 
Paperwork Reduction Act unless that collection of information 
displays a current valid OMB Control Number. The OMB Control Number 
for this information collection is 2120-0056. Public reporting for 
this collection of information is estimated to be approximately 5 
minutes per response, including the time for reviewing instructions, 
completing and reviewing the collection of information. All 
responses to this collection of information are mandatory. Comments 
concerning the accuracy of this burden and suggestions for reducing 
the burden should be directed to the FAA at: 800 Independence Ave. 
SW., Washington, DC 20591, Attn: Information Collection Clearance 
Officer, AES-200.

(t) Related Information

    (1) Refer to Mandatory Continuing Airworthiness Information 
(MCAI) AD 2013-0267R1, dated March 4, 2014; corrected March 8, 2014, 
for related information. This MCAI may be found in the AD docket on 
the Internet at http://www.regulations.gov by searching for and 
locating Docket No. FAA-2013-0828.
    (2) Service information identified in this AD that is not 
incorporated by reference is available at the addresses specified in 
paragraphs (u)(5), (u)(6), and (u)(7) of this AD.

(u) Material Incorporated by Reference

    (1) The Director of the Federal Register approved the 
incorporation by reference (IBR) of the service information listed 
in this paragraph under 5 U.S.C. 552(a) and 1 CFR part 51.
    (2) You must use this service information as applicable to do 
the actions required by this AD, unless this AD specifies otherwise.
    (3) The following service information was approved for IBR on 
November 2, 2016.
    (i) Airbus Service Bulletin A330-32-3225, Revision 02, including 
Appendix 1, dated October 26, 2012.
    (ii) Airbus Service Bulletin A330-32-3237, Revision 01, 
including Reporting Sheet, dated October 14, 2011.
    (iii) Airbus Service Bulletin A340-32-4268, Revision 03, 
including Appendix 1, dated January 14, 2013.
    (iv) Airbus Service Bulletin A340-32-4279, Revision 01, 
including Reporting Sheet, dated October 14, 2011.
    (v) Messier-Dowty Service Bulletin A33/34-32-278, Revision 1, 
including Appendixes A and B, dated August 24, 2011.
    (vi) Messier-Dowty Service Bulletin A33/34-32-283, Revision 1, 
including Appendix A, dated July 10, 2012.
    (vii) Messier-Dowty Service Bulletin A33/34-32-284, Revision 1, 
including Appendix A, dated July 10, 2012.
    (4) The following service information was approved for IBR on 
September 2, 2009 (74 FR 37523, July 29, 2009).
    (i) Messier-Dowty Service Bulletin A33/34-32-271, Revision 1, 
including Appendixes A and B, dated November 16, 2007.
    (ii) Messier-Dowty Service Bulletin A33/34-32-272, Revision 1, 
including Appendixes A, B, C, and D, dated September 22, 2008.
    (5) For Airbus service information identified in this AD, 
contact Airbus SAS, Airworthiness Office--EAL, 1 Rond Point Maurice 
Bellonte, 31707 Blagnac Cedex, France; telephone: +33 5 61 93 36 96; 
fax: +33 5 61 93 45 80; email: [email protected]; 
Internet: http://www.airbus.com.
    (6) For Messier-Dowty service information identified in this AD, 
contact Messier-Dowty: Messier Services Americas, Customer Support 
Center, 45360 Severn Way, Sterling, VA 20166-8910; telephone 703-
450-8233; fax 703-404-1621; Internet: https://techpubs.services/messier-dowty.com.
    (7) You may view this service information at the FAA, Transport 
Airplane Directorate, 1601 Lind Avenue SW., Renton, WA. For 
information on the availability of this material at the FAA, call 
425-227-1221.
    (8) You may view this service information that is incorporated 
by reference at the National Archives and Records Administration 
(NARA). For information on the availability of this material at 
NARA, call 202-741-6030, or go to: http://www.archives.gov/federal-register/cfr/ibr-locations.html.

    Issued in Renton, Washington, on August 24, 2016.
John P. Piccola, Jr.,
Acting Manager, Transport Airplane Directorate, Aircraft Certification 
Service.
[FR Doc. 2016-21150 Filed 9-27-16; 8:45 am]
 BILLING CODE 4910-13-P



                                              66518        Federal Register / Vol. 81, No. 188 / Wednesday, September 28, 2016 / Rules and Regulations

                                              Instructions of Bombardier Service Bulletin             aero.bombardier.com; Internet: http://                compliance times and adds a one-time
                                              84–30–10, Revision E, dated October 10,                 www.bombardier.com.                                   inspection for airplanes that were
                                              2014, within the compliance times specified                (4) You may view this service information          inspected too early. This AD was
                                              in paragraph (g) of this AD.                            at the FAA, Transport Airplane Directorate,
                                                (2) Bombardier Service Bulletin 84–30–10,             1601 Lind Avenue SW., Renton, WA. For
                                                                                                                                                            prompted by reports of thin paint coats
                                              Revision A, dated April 7, 2008.                        information on the availability of this               and paint degradation on enhanced
                                                (3) Bombardier Service Bulletin 84–30–10,             material at the FAA, call 425–227–1221.               main landing gear (MLG) bogie beams,
                                              Revision B, dated January 20, 2010.                        (5) You may view this service information          as well as reports that some airplanes
                                                (4) Bombardier Service Bulletin 84–30–10,             that is incorporated by reference at the              have been inspected too early and not
                                              Revision C, dated July 14, 2011.                        National Archives and Records                         re-inspected as needed. We are issuing
                                                (5) Bombardier Service Bulletin 84–30–10,             Administration (NARA). For information on             this AD to detect and correct damage or
                                              Revision D, dated December 20, 2011.                    the availability of this material at NARA, call       corrosion of the MLG bogie beams,
                                                                                                      202–741–6030, or go to: http://
                                              (j) Other FAA AD Provisions
                                                                                                      www.archives.gov/federal-register/cfr/ibr-
                                                                                                                                                            which could cause a runway excursion
                                                 The following provisions also apply to this          locations.html.                                       event, bogie beam detachment from the
                                              AD:                                                                                                           airplane, or MLG collapse, and could
                                                 (1) Alternative Methods of Compliance                  Issued in Renton, Washington, on                    result in damage to the airplane and
                                              (AMOCs): The Manager, New York ACO,                     September 12, 2016.
                                                                                                                                                            injury to the occupants.
                                              ANE–170, FAA, has the authority to approve              Michael Kaszycki,
                                                                                                                                                            DATES: This AD is effective November 2,
                                              AMOCs for this AD, if requested using the               Acting Manager, Transport Airplane
                                              procedures found in 14 CFR 39.19. In                    Directorate, Aircraft Certification Service.
                                                                                                                                                            2016.
                                              accordance with 14 CFR 39.19, send your                                                                          The Director of the Federal Register
                                                                                                      [FR Doc. 2016–22705 Filed 9–27–16; 8:45 am]
                                              request to your principal inspector or local                                                                  approved the incorporation by reference
                                                                                                      BILLING CODE 4910–13–P
                                              Flight Standards District Office, as                                                                          of certain publications listed in this AD
                                              appropriate. If sending information directly                                                                  as of November 2, 2016.
                                              to the ACO, send it to ATTN: Program                                                                             The Director of the Federal Register
                                              Manager, Continuing Operational Safety,                 DEPARTMENT OF TRANSPORTATION
                                                                                                                                                            approved the incorporation by reference
                                              FAA, New York ACO, 1600 Stewart Avenue,                                                                       of certain other publications listed in
                                              Suite 410, Westbury, NY 11590; telephone                Federal Aviation Administration
                                              516–228–7300; fax 516–794–5531. Before
                                                                                                                                                            this AD as of September 2, 2009 (74 FR
                                              using any approved AMOC, notify your                    14 CFR Part 39                                        37523, July 29, 2009).
                                              appropriate principal inspector, or lacking a                                                                 ADDRESSES: For Airbus service
                                              principal inspector, the manager of the local           [Docket No. FAA–2013–0828; Directorate
                                                                                                                                                            information identified in this final rule,
                                              flight standards district office/certificate            Identifier 2012–NM–036–AD; Amendment
                                                                                                      39–18637; AD 2016–18–07]                              contact Airbus SAS, Airworthiness
                                              holding district office.                                                                                      Office—EAL, 1 Rond Point Maurice
                                                 (2) Contacting the Manufacturer: For any             RIN 2120–AA64
                                              requirement in this AD to obtain corrective
                                                                                                                                                            Bellonte, 31707 Blagnac Cedex, France;
                                              actions from a manufacturer, the action must                                                                  telephone: +33 5 61 93 36 96; fax: +33
                                                                                                      Airworthiness Directives; Airbus                      5 61 93 45 80; email:
                                              be accomplished using a method approved                 Airplanes
                                              by the Manager, New York ACO, ANE–170,                                                                        airworthiness.A330–A340@airbus.com;
                                              Engine and Propeller Directorate, FAA; or               AGENCY:  Federal Aviation                             Internet: http://www.airbus.com. For
                                              TCCA; or Bombardier, Inc.’s TCCA DAO. If                Administration (FAA), Department of                   Messier-Dowty service information
                                              approved by the DAO, the approval must                  Transportation (DOT).                                 identified in this final rule, contact
                                              include the DAO-authorized signature.                                                                         Messier-Dowty: Messier Services
                                                                                                      ACTION: Final rule.
                                              (k) Related Information                                                                                       Americas, Customer Support Center,
                                                (1) Refer to Mandatory Continuing                     SUMMARY:   We are superseding                         45360 Severn Way, Sterling, VA 20166–
                                              Airworthiness Information (MCAI) Canadian               Airworthiness Directive (AD) 2009–15–                 8910; telephone: 703–450–8233; fax:
                                              Airworthiness Directive CF–2015–24, dated               17 for certain Airbus Model A330–200                  703–404–1621; Internet: https://
                                              August 24, 2015, for related information.               and –300 series airplanes; and Model                  techpubs.services/messier-dowty.com.
                                              This MCAI may be found in the AD docket                 A340–200 and –300 series airplanes. AD                You may view this referenced service
                                              on the Internet at http://www.regulations.gov           2009–15–17 required an inspection for                 information at the FAA, Transport
                                              by searching for and locating Docket No.                damage to the protective treatments or                Airplane Directorate, 1601 Lind Avenue
                                              FAA–2016–6148.                                          any corrosion of all main landing gear
                                                (2) Service information identified in this                                                                  SW., Renton, WA. For information on
                                              AD that is not incorporated by reference is             (MLG) bogie beams, and application of                 the availability of this material at the
                                              available at the addresses specified in                 protective treatments if no damage or                 FAA, call 425–227–1221. It is also
                                              paragraphs (l)(3) and (l)(4) of this AD.                corrosion was found. If any damage or                 available on the Internet at http://
                                                                                                      corrosion was found, corrective action                www.regulations.gov by searching for
                                              (l) Material Incorporated by Reference
                                                                                                      followed by the application of                        and locating Docket No. FAA–2013–
                                                 (1) The Director of the Federal Register             protective treatments was required. This              0828.
                                              approved the incorporation by reference                 new AD continues to require
                                              (IBR) of the service information listed in this                                                               Examining the AD Docket
                                              paragraph under 5 U.S.C. 552(a) and 1 CFR
                                                                                                      inspections for damage to the protective
                                              part 51.                                                treatments or any corrosion of all MLG                  You may examine the AD docket on
                                                 (2) You must use this service information            bogie beams, application of protective                the Internet at http://
                                              as applicable to do the actions required by             treatments, and corrective action if                  www.regulations.gov by searching for
                                              this AD, unless this AD specifies otherwise.            necessary. This new AD also requires                  and locating Docket No. FAA–2013–
                                                 (i) Bombardier Service Bulletin 84–30–10,            modification of the MLG bogie beams,                  0828; or in person at the Docket
sradovich on DSK3GMQ082PROD with RULES




                                              Revision E, dated October 10, 2014.                     which terminates the repetitive                       Management Facility between 9 a.m.
                                                 (ii) Reserved.                                       inspections for any modified bogie                    and 5 p.m., Monday through Friday,
                                                 (3) For service information identified in
                                              this AD, contact Bombardier, Inc., Q-Series
                                                                                                      beam. This new AD allows optional                     except Federal holidays. The AD docket
                                              Technical Help Desk, 123 Garratt Boulevard,             methods of compliance for certain                     contains this AD, the regulatory
                                              Toronto, Ontario M3K 1Y5, Canada;                       actions, and adds Airbus Model A330–                  evaluation, any comments received, and
                                              telephone: 416–375–4000; fax: 416–375–                  200 Freighter series airplanes to the                 other information. The address for the
                                              4539; email: thd.qseries@                               applicability. This new AD revises the                Docket Office (telephone: 800–647–


                                         VerDate Sep<11>2014   17:53 Sep 27, 2016   Jkt 238001   PO 00000   Frm 00032   Fmt 4700   Sfmt 4700   E:\FR\FM\28SER1.SGM   28SER1


                                                           Federal Register / Vol. 81, No. 188 / Wednesday, September 28, 2016 / Rules and Regulations                                           66519

                                              5527) is Docket Management Facility,                      The European Aviation Safety Agency                 initially inspected too early (before 4 years
                                              U.S. Department of Transportation,                      (EASA), which is the Technical Agent                  and 6 months since aeroplane first flight with
                                              Docket Operations, M–30, West                           for the Member States of the European                 bogie beam installed/installed after overhaul)
                                                                                                      Union, has issued EASA AD 2013–                       and have not been re-inspected as required.
                                              Building Ground Floor, Room W12–140,
                                                                                                                                                              For the reasons described above, this
                                              1200 New Jersey Avenue SE.,                             0267R1, dated March 4, 2014; corrected                [EASA] AD retains the requirements of EASA
                                              Washington, DC 20590.                                   May 8, 2014 (referred to after this as the            AD 2012–0015, which is superseded, and
                                              FOR FURTHER INFORMATION CONTACT:                        Mandatory Continuing Airworthiness                    redefines the inspection periodicity. This
                                              Vladimir Ulyanov, Aerospace Engineer,                   Information, or ‘‘the MCAI’’), to correct             [EASA] AD also introduces a specific one-
                                              International Branch, ANM–116,                          an unsafe condition for certain Airbus                time inspection for aeroplanes that have been
                                              Transport Airplane Directorate, FAA,                    Model A330–200 Freighter, –200, and                   inspected too early.
                                              1601 Lind Avenue SW., Renton, WA                        –300 series airplanes; and Model A340–                  Prompted by operator comments, this
                                                                                                      200 and –300 series airplanes. The                    [EASA] AD is revised to clarify the required
                                              98057–3356; telephone: 425–227–1138;                                                                          actions and the specific configurations to
                                              fax: 425–227–1149.                                      MCAI states:
                                                                                                                                                            which the actions must be applied. Appendix
                                              SUPPLEMENTARY INFORMATION:                                 The operator of an A330 aeroplane (which           1 of this [EASA] AD has been amended
                                                                                                      has a common bogie beam with the A340)                accordingly.
                                              Discussion                                              reported a fracture of the Right Hand (RH)              This [EASA] AD is republished to
                                                 We issued a second supplemental                      main landing gear (MLG) bogie beam, which             editorially correct paragraph (4).
                                              notice of proposed rulemaking (SNPRM)                   occurred while turning during low speed taxi
                                                                                                      maneuvers. The bogie fractured aft of the               You may examine the MCAI in the
                                              to amend 14 CFR part 39 to supersede                    pivot point and remained attached to the              AD docket on the Internet at http://
                                              AD 2009–15–17, Amendment 39–15980                       sliding tube by the brake torque reaction             www.regulations.gov by searching for
                                              (74 FR 37523, July 29, 2009) (‘‘AD 2009–                rods. After this RH bogie failure, the                and locating Docket No. FAA–2013–
                                              15–17’’). AD 2009–15–17 applied to                      aeroplane continued for approximately 40              0828.
                                              certain Airbus Model A330–200 and                       meters on the forks of the sliding member
                                              –300 series airplanes, and Model A340–                  before coming to rest on the taxiway.                 Comments
                                              200 and –300 series airplanes. The                         The investigations revealed that this event
                                                                                                                                                              We gave the public the opportunity to
                                              second SNPRM published in the                           was due to corrosion pitting occurring on the
                                                                                                      bore of the bogie beam.                               participate in developing this AD. The
                                              Federal Register on February 5, 2016                                                                          following presents the comment
                                                                                                         This condition, if not detected and
                                              (81 FR 6185) (‘‘the second SNPRM’’).                    corrected, could lead to a runway excursion           received on the second SNPRM and the
                                              We preceded the second SNPRM with                       event or to detachment of the bogie from the          FAA’s response.
                                              the first SNPRM, which was published                    aeroplane, or to MLG collapse, possibly
                                              in the Federal Register on March 5,                     resulting in damage to the aeroplane and              Request To Revise the Applicability of
                                              2014 (79 FR 12414) (‘‘the first SNPRM’’).               injury to the occupants.                              the Second SNPRM
                                              We preceded the first SNPRM with a                         To enable early detection and repair of               American Airlines (AAL) requested
                                              notice of proposed rulemaking (NPRM)                    corrosion of the internal surfaces, EASA              that we revise the applicability of the
                                              that published in the Federal Register                  issued EASA AD 2007–0314 to require a one-
                                                                                                                                                            proposed AD (in the second SNPRM) to
                                                                                                      time inspection of all MLG bogie beams,
                                              on September 25, 2013 (78 FR 58978)                                                                           exclude airplanes with MLG bogie
                                                                                                      except Enhanced MLG bogie beams, and the
                                              (‘‘the NPRM’’). The NPRM was                            reporting of the results to Airbus. EASA AD           beams that have had Airbus
                                              prompted by reports of thin paint coats                 2007–0314 was revised and later superseded            modification 58896 embodied in-
                                              and paint degradation on enhanced                       by EASA AD 2008–0093, reducing the                    service, as specified in Airbus Service
                                              MLG bogie beams. The NPRM proposed                      inspection threshold period.                          Bulletin A330–32–3237. AAL pointed
                                              to continue to require inspections for                     The results of subsequent investigations           out that paragraph (c) of the proposed
                                              damage to the protective treatments or                  showed thin paint coats and paint                     AD (in the second SNPRM) does not
                                              any corrosion of all MLG bogie beams,                   degradation, confirmed as well on Enhanced            reflect MLG bogie beams that were
                                              application of protective treatments, and               MLG bogie beams. To address this additional
                                                                                                                                                            modified in-service.
                                                                                                      concern, EASA issued AD 2011–0141 [which
                                              corrective action if necessary. The                                                                              We disagree with the request to revise
                                                                                                      was not mandated by the FAA], retaining the
                                              NPRM also proposed to require                           requirements of EASA AD 2008–0093, which              the applicability of the proposed AD (in
                                              modification of the MLG bogie beams,                    was superseded, to require a one-time visual          the second SNPRM). Paragraph (k) of
                                              which would terminate the repetitive                    inspection of all MLG bogie beams, including          this AD specifically requires inspection,
                                              inspections for any modified bogie                      a visual examination of the internal diameter         repair, modification, and re-
                                              beam. In addition, the NPRM proposed                    for corrosion or damage to protective                 identification of the MLG bogie beams.
                                              to allow optional methods of                            treatments of the bogie beam and                      However, paragraph (f) of this AD states
                                              compliance for certain actions, and to                  measurement of the paint thickness on the             that actions already done need not be
                                              add Airbus Model A330–200 Freighter                     internal bore, accomplishment of the
                                                                                                                                                            repeated. If an operator has already
                                              series airplanes to the applicability. The              applicable corrective actions and a
                                                                                                      modification of the MLG bogie beam to                 accomplished the actions required by
                                              first SNPRM proposed to revise the                      improve the coat paint application method,            paragraph (k) of this AD before the
                                              compliance times and add a one-time                     and application of corrosion protection.              effective date of this AD, then the
                                              inspection for airplanes that were                         Prompted by in-service requests, EASA              modified airplane is already in
                                              inspected too early. The second SNPRM                   issued EASA AD 2012–0015 retaining the                compliance with the corresponding
                                              proposed to clarify the required actions                requirements of EASA AD 2011–0141, which              requirements of this AD. We have not
                                              and the specific configurations to which                was superseded, and introducing repetitive            made any changes to this AD in this
                                              the actions must be applied. We are                     inspections of the MLG bogie beams, which             regard.
sradovich on DSK3GMQ082PROD with RULES




                                              issuing this AD to detect and correct                   allows extension of the compliance time for
                                              damage or corrosion of the MLG bogie                    the MLG bogie beam modification from 15               Additional Changes Made in This AD
                                                                                                      years to 21 years. Modification of a MLG
                                              beams, which could cause a runway                       bogie beam constitutes terminating action for           We have revised paragraph (m)(1) of
                                              excursion event, bogie beam detachment                  the repetitive inspections for that MLG bogie         this AD to remove reference to
                                              from the airplane, or MLG collapse, and                 beam.                                                 paragraph (g) of this AD; the reporting
                                              could result in damage to the airplane                     Reports on inspection results provided to          requirement specified in paragraph
                                              and injury to the occupants.                            Airbus show that some aeroplanes were                 (m)(1) of this AD is required only for the


                                         VerDate Sep<11>2014   17:53 Sep 27, 2016   Jkt 238001   PO 00000   Frm 00033   Fmt 4700   Sfmt 4700   E:\FR\FM\28SER1.SGM   28SER1


                                              66520        Federal Register / Vol. 81, No. 188 / Wednesday, September 28, 2016 / Rules and Regulations

                                              inspection required by paragraph (k) of                    Messier-Bugatti-Dowty has issued the               should be directed to the FAA at 800
                                              this AD.                                                following service information.                        Independence Ave. SW., Washington,
                                                We have also revised paragraph (m)(2)                    • Messier-Dowty Service Bulletin                   DC 20591, ATTN: Information
                                              of this AD to reference the correct                     A33/34–32–278, Revision 1, including                  Collection Clearance Officer, AES–200.
                                              service information for reporting                       Appendixes A and B, dated August 24,
                                              inspection findings for the inspection                  2011. This service information describes              Authority for This Rulemaking
                                              required by paragraph (h) of this AD.                   procedures for inspections for damage                    Title 49 of the United States Code
                                                                                                      and corrosion to the protective                       specifies the FAA’s authority to issue
                                              Conclusion                                              treatment of the internal bores of the LH             rules on aviation safety. Subtitle I,
                                                We reviewed the available data,                       and RH MLG bogie beam, and repairs.                   section 106, describes the authority of
                                              including the comment received, and                        • Messier-Dowty Service Bulletin
                                                                                                                                                            the FAA Administrator. ‘‘Subtitle VII:
                                              determined that air safety and the                      A33/34–32–283, Revision 1, including
                                                                                                                                                            Aviation Programs,’’ describes in more
                                              public interest require adopting this AD                Appendix A, dated July 10, 2012. This
                                                                                                                                                            detail the scope of the Agency’s
                                              with the changes described previously                   service information describes
                                                                                                                                                            authority.
                                              and minor editorial changes. We have                    procedures for modification of the LH
                                              determined that these minor changes:                    and RH MLG bogie beams.                                  We are issuing this rulemaking under
                                                • Are consistent with the intent that                    • Messier-Dowty Service Bulletin                   the authority described in ‘‘Subtitle VII,
                                              was proposed in the second SNPRM for                    A33/34–32–284, Revision 1, including                  Part A, Subpart III, Section 44701:
                                              correcting the unsafe condition; and                    Appendix A, dated July 10, 2012. This                 General requirements.’’ Under that
                                                • Do not add any additional burden                    service information describes                         section, Congress charges the FAA with
                                              upon the public than was already                        procedures for modification of the LH                 promoting safe flight of civil aircraft in
                                              proposed in the second SNPRM.                           and RH MLG bogie beams.                               air commerce by prescribing regulations
                                                                                                         This service information is reasonably             for practices, methods, and procedures
                                              Related Service Information Under 1                     available because the interested parties              the Administrator finds necessary for
                                              CFR Part 51                                             have access to it through their normal                safety in air commerce. This regulation
                                                 Airbus has issued the following                      course of business or by the means                    is within the scope of that authority
                                              service information.                                    identified in the ADDRESSES section.                  because it addresses an unsafe condition
                                                 • Airbus Service Bulletin A330–32–                                                                         that is likely to exist or develop on
                                                                                                      Costs of Compliance
                                              3225, Revision 02, including Appendix                                                                         products identified in this rulemaking
                                                                                                         We estimate that this AD affects 51                action.
                                              1, dated October 26, 2012. This service                 airplanes of U.S. registry.
                                              information describes procedures for                       We also estimate that it takes about 34            Regulatory Findings
                                              cleaning the internal bore and                          work-hours per product to comply with
                                              accomplishing a detailed inspection of                  this AD, and 1 work-hour per product                    We determined that this AD will not
                                              internal surfaces of the left-hand (LH)                 for reporting. The average labor rate is              have federalism implications under
                                              and right-hand (RH) MLG bogie beams                     $85 per work-hour. Based on these                     Executive Order 13132. This AD will
                                              to detect any damage to the protective                  figures, we estimate the cost of this AD              not have a substantial direct effect on
                                              treatments and any corrosion, and                       on U.S. operators to be $151,725, or                  the States, on the relationship between
                                              measuring the paint thickness on the                    $2,975 per product.                                   the national government and the States,
                                              internal bore.                                             In addition, we estimate that any                  or on the distribution of power and
                                                 • Airbus Service Bulletin A330–32–                   necessary follow-on actions would take                responsibilities among the various
                                              3237, Revision 01, including Reporting                  about 10 work-hours at a labor rate of                levels of government.
                                              Sheet, dated October 14, 2011. This                     $85 per work-hour, for a cost of $850                   For the reasons discussed above, I
                                              service information describes                           per product. We have no way of                        certify that this AD:
                                              procedures for a detailed inspection for                determining the number of aircraft that                 1. Is not a ‘‘significant regulatory
                                              damage and corrosion of the internal                    might need these actions.                             action’’ under Executive Order 12866;
                                              bores of the LH and RH MLG bogie
                                              beam and repair, as well as modification                Paperwork Reduction Act                                 2. Is not a ‘‘significant rule’’ under the
                                              and re-identification.                                    A federal agency may not conduct or                 DOT Regulatory Policies and Procedures
                                                 • Airbus Service Bulletin A340–32–                   sponsor, and a person is not required to              (44 FR 11034, February 26, 1979);
                                              4268, Revision 03, including Appendix                   respond to, nor shall a person be subject               3. Will not affect intrastate aviation in
                                              1, dated January 14, 2013. This service                 to penalty for failure to comply with a               Alaska; and
                                              information describes procedures for                    collection of information subject to the                4. Will not have a significant
                                              cleaning the internal bore and                          requirements of the Paperwork                         economic impact, positive or negative,
                                              accomplishing a detailed inspection of                  Reduction Act unless that collection of               on a substantial number of small entities
                                              internal surfaces of the LH and RH MLG                  information displays a current valid                  under the criteria of the Regulatory
                                              bogie beams to detect any damage to the                 OMB control number. The control                       Flexibility Act.
                                              protective treatments and any corrosion,                number for the collection of information
                                              and measuring the paint thickness on                    required by this AD is 2120–0056. The                 List of Subjects in 14 CFR Part 39
                                              the internal bore.                                      paperwork cost associated with this AD
                                                 • Airbus Service Bulletin A340–32–                   has been detailed in the Costs of                       Air transportation, Aircraft, Aviation
                                              4279, Revision 01, including Reporting                  Compliance section of this document                   safety, Incorporation by reference,
sradovich on DSK3GMQ082PROD with RULES




                                              Sheet, dated October 14, 2011. This                     and includes time for reviewing                       Safety.
                                              service information describes                           instructions, as well as completing and               Adoption of the Amendment
                                              procedures for a detailed inspection for                reviewing the collection of information.
                                              damage and corrosion of the internal                    Therefore, all reporting associated with                Accordingly, under the authority
                                              bores of the LH and RH MLG bogie                        this AD is mandatory. Comments                        delegated to me by the Administrator,
                                              beam, repair, modification, and                         concerning the accuracy of this burden                the FAA amends 14 CFR part 39 as
                                              reidentification.                                       and suggestions for reducing the burden               follows:


                                         VerDate Sep<11>2014   17:53 Sep 27, 2016   Jkt 238001   PO 00000   Frm 00034   Fmt 4700   Sfmt 4700   E:\FR\FM\28SER1.SGM   28SER1


                                                           Federal Register / Vol. 81, No. 188 / Wednesday, September 28, 2016 / Rules and Regulations                                             66521

                                              PART 39—AIRWORTHINESS                                   corrosion, and measure the paint thickness               (i) MLG bogie beams having between 72
                                              DIRECTIVES                                              on the internal bore, in accordance with the          and 120 months since first flight on an
                                                                                                      Accomplishment Instructions of Airbus                 airplane, or since the MLG bogie beam’s first
                                              ■ 1. The authority citation for part 39                 Service Bulletin A330–32–3225, Revision 02,           flight on an airplane after the MLG bogie
                                              continues to read as follows:                           including Appendix 1, dated October 26,               beam’s most recent overhaul, as applicable.
                                                                                                      2012; or Airbus Service Bulletin A340–32–                (ii) MLG bogie beams on which the first
                                                  Authority: 49 U.S.C. 106(g), 40113, 44701.          4268, Revision 03, including Appendix 1,              inspection was done after 45 months and
                                                                                                      dated January 14, 2013; as applicable. Repeat         before 51 months since first flight of the MLG
                                              § 39.13   [Amended]                                     the inspections thereafter at intervals not less      bogie beam on an airplane, or since the MLG
                                              ■ 2. The FAA amends § 39.13 by                          than 54 months, but not exceeding 72                  bogie beam’s first flight on an airplane after
                                              removing Airworthiness Directive (AD)                   months, after the most recent inspection.             the MLG bogie beam’s most recent overhaul,
                                              2009–15–17, Amendment 39–15980 (74                      During overhaul of a MLG bogie beam, any              as applicable.
                                                                                                      corrosion will be removed, which means that              (3) For MLG bogie beams having the
                                              FR 37523, July 29, 2009), and adding the
                                                                                                      the first inspection after overhaul of that           configurations specified in both paragraphs
                                              following new AD:                                       MLG bogie beam, as required by this                   (h)(3)(i) and (h)(3)(ii) of this AD: Do the
                                              2016–18–07 Airbus: Amendment 39–18637;                  paragraph, is between 54 months and 72                detailed inspection specified in the
                                                  Docket No. FAA–2013–0828; Directorate               months since its first flight on an airplane          introductory text of paragraph (h) of this AD
                                                  Identifier 2012–NM–036–AD.                          after overhaul.                                       within 3 months after the effective date of
                                              (a) Effective Date                                      (h) One-Time Detailed Inspection for Certain          this AD.
                                                                                                      Airplane Configurations                                  (i) MLG bogie beams having between 72
                                                This AD is effective November 2, 2016.                                                                      and 96 months since first flight on an
                                                                                                         For airplanes equipped with basic MLG              airplane, or since the MLG bogie beam’s first
                                              (b) Affected ADs
                                                                                                      (201252 series), or growth MLG (201490                flight on an airplane after the MLG bogie
                                                This AD replaces AD 2009–15–17,                       series) having a LH or RH MLG bogie beam              beam’s most recent overhaul, as applicable.
                                              Amendment 39–15980 (74 FR 37523, July 29,               that has already exceeded 72 months since its            (ii) MLG bogie beams which have
                                              2009) (‘‘AD 2009–15–17’’).                              first flight on an airplane, or since its first       accumulated, at the effective date of this AD,
                                              (c) Applicability                                       flight on an airplane after overhaul, as              less than 96 months and on which the first
                                                                                                      applicable, as of the effective date of this AD;      inspection was done before 51 months since
                                                 This AD applies to the airplanes identified          and that has been inspected as specified in           first flight of the MLG bogie beam on an
                                              in paragraphs (c)(1) and (c)(2) of this AD,             Airbus Service Bulletin A330–32–3225 or               airplane, or since the MLG bogie beam’s first
                                              certificated in any category, all manufacturer          Airbus Service Bulletin A340–32–4268, as
                                              serial numbers (MSN), except those on which                                                                   flight on an airplane after the after the MLG
                                                                                                      applicable, earlier than 54 months since first        bogie beam’s most recent overhaul, as
                                              Airbus modification 58896 has been                      flight of the affected MLG bogie beam on an
                                              embodied in production.                                                                                       applicable.
                                                                                                      airplane, or since its first flight on an                (4) For MLG bogie beams having the
                                                 (1) Airbus Model A330–223F, –243F, –201,             airplane after its most recent overhaul, as
                                              –202, –203, –223, –243, –301, –302, –303,                                                                     configurations specified in both paragraphs
                                                                                                      applicable: Within the applicable compliance          (h)(4)(i) and (h)(4)(ii) of this AD: Do the
                                              –321, –322, –323, –341, –342, and –343                  time indicated in paragraphs (h)(1) through
                                              airplanes.                                                                                                    detailed inspection specified in the
                                                                                                      (h)(4) of this AD, clean the internal bore and        introductory text of paragraph (h) of this AD
                                                 (2) Airbus Model A340–211, –212, –213,               accomplish a detailed inspection of the
                                              –311, –312, and –313 airplanes.                                                                               within 1 month after the effective date of this
                                                                                                      internal surfaces of the LH and RH MLG                AD.
                                              (d) Subject                                             bogie beams to detect any damage to the                  (i) MLG bogie beams having between 96
                                                Air Transport Association (ATA) of                    protective treatments and any corrosion, and          and 120 months since first flight on an
                                              America Code 32, Landing gear.                          measure the paint thickness on the internal           airplane, or since the MLG bogie beam’s first
                                                                                                      bore, in accordance with the                          flight on an airplane after the MLG bogie
                                              (e) Reason                                              Accomplishment Instructions of Airbus                 beam’s most recent overhaul, as applicable.
                                                 This AD was prompted by reports of thin              Service Bulletin A330–32–3225, Revision 02,              (ii) MLG bogie beams which has
                                              paint coats and paint degradation on                    including Appendix 1, dated October 26,               accumulated, at the effective date of this AD,
                                              enhanced main landing gear (MLG) bogie                  2012; or Airbus Service Bulletin A340–32–             96 months or more and on which the first
                                              beams, as well as reports that some airplanes           4268, Revision 03, including Appendix 1,              inspection was done before 45 months since
                                              have been inspected too early and not re-               dated January 14, 2013; as applicable.                first flight of the MLG bogie beam on an
                                              inspected as needed. We are issuing this AD                (1) For MLG bogie beams having the                 airplane, or since the MLG bogie beam’s first
                                              to detect and correct damage or corrosion of            configurations specified in both paragraphs           flight on an airplane after the MLG bogie
                                              the MLG bogie beams, which could cause a                (h)(1)(i) and (h)(1)(ii) of this AD: Do the           beam’s most recent overhaul, as applicable.
                                              runway excursion event, bogie beam                      detailed inspection specified in the
                                                                                                      introductory text of paragraph (h) of this AD         (i) Application of Protective Treatment
                                              detachment from the airplane, or MLG
                                              collapse, and could result in damage to the             within 9 months after the effective date of              If, during any inspection required by
                                              airplane and injury to the occupants.                   this AD.                                              paragraph (g) or (h) of this AD, no damage
                                                                                                         (i) MLG bogie beams having between 72              or corrosion is found: Before further flight,
                                              (f) Compliance                                          and 120 months since first flight on an               apply the protective treatments to the MLG
                                                 Comply with this AD within the                       airplane, or since the MLG bogie beam’s first         bogie beam, in accordance with the
                                              compliance times specified, unless already              flight on an airplane after the MLG bogie             Accomplishment Instructions of Messier-
                                              done.                                                   beam’s most recent overhaul, as applicable.           Dowty Service Bulletin A33/34–32–272,
                                                                                                         (ii) MLG bogie beams on which the first            Revision 1, including Appendixes A, B, C,
                                              (g) Repetitive Inspections for Certain                  inspection was done after 51 months and               and D, dated September 22, 2008.
                                              Airplane Configurations                                 before 54 months since first flight of the MLG
                                                 For airplanes equipped with basic MLG                bogie beam on an airplane, or since the MLG           (j) Repair and Application of Protective
                                              (201252 series), or growth MLG (201490                  bogie beam’s first flight on an airplane after        Treatment
                                              series): After 54 months at the earliest, but no        the MLG bogie beam’s most recent overhaul,               If, during any inspection required by
sradovich on DSK3GMQ082PROD with RULES




                                              later than 72 months since the left-hand (LH)           as applicable.                                        paragraph (g) or (h) of this AD, any damage
                                              or right-hand (RH) MLG bogie beam’s first                  (2) For MLG bogie beams having the                 or corrosion is found: Before further flight,
                                              flight on an airplane, or since its first flight        configurations specified in both paragraphs           repair and apply the protective treatments to
                                              on an airplane after overhaul, as applicable,           (h)(2)(i) and (h)(2)(ii) of this AD: Do the           the MLG bogie beam, in accordance with the
                                              clean the internal bore and accomplish a                detailed inspection specified in the                  Accomplishment Instructions of Messier-
                                              detailed inspection of internal surfaces of the         introductory text of paragraph (h) of this AD         Dowty Service Bulletin A33/34–32–272,
                                              LH and RH MLG bogie beams to detect any                 within 3 months after the effective date of           Revision 1, including Appendixes A, B, C,
                                              damage to the protective treatments and any             this AD.                                              and D, dated September 22, 2008.



                                         VerDate Sep<11>2014   17:53 Sep 27, 2016   Jkt 238001   PO 00000   Frm 00035   Fmt 4700   Sfmt 4700   E:\FR\FM\28SER1.SGM   28SER1


                                              66522        Federal Register / Vol. 81, No. 188 / Wednesday, September 28, 2016 / Rules and Regulations

                                              (k) Inspection and Corrective Actions                   Sheet, dated October 14, 2011; at the                 beam’s most recent overhaul, as applicable.
                                                 For airplanes equipped with basic MLG                applicable time specified in paragraph                Airbus Service Bulletin A330–32–3225,
                                              (201252 series), growth MLG (201490 series),            (m)(1)(i) or (m)(1)(ii) of this AD.                   dated November 21, 2007, is not incorporated
                                              or enhanced MLG (10–210 series): Before the                (i) If the inspection was done on or after         by reference in this AD. Airbus Mandatory
                                              accumulation of 252 total months on an MLG              the effective date of this AD: Submit the             Service Bulletin A330–32–3225, Revision 01,
                                              bogie beam, or within 90 days after the                 report within 90 days after the inspection.           including Appendix 1, dated October 30,
                                              effective date of this AD, whichever occurs                (ii) If the inspection was done before the         2008, was incorporated by reference in AD
                                              later, do the actions specified in paragraphs           effective date of this AD: Submit the report          2009–15–07.
                                              (k)(1) and (k)(2) of this AD concurrently and           within 90 days after the effective date of this          (2) This paragraph provides credit for the
                                              in sequence.                                            AD.                                                   corresponding inspections and corrective
                                                 (1) Except as provided by paragraph (k)(3)              (2) Submit a report of the findings (both          actions done on an LH or RH MLG bogie
                                              of this AD: Do a detailed inspection for                positive and negative) of the inspection              beam required by paragraph (g) of this AD,
                                              damage and corrosion of the internal bores of           required by paragraph (h) of this AD to               if those actions were performed before the
                                              the LH and RH MLG bogie beam, in                        Airbus, Customer Service Directorate, 1 Rond          effective date of this AD using Airbus
                                              accordance with the Accomplishment                      Point Maurice Bellonte, 31707 Blagnac                 Mandatory Service Bulletin A340–32–4268,
                                              Instructions of Airbus Service Bulletin A330–           Cedex, France, using the applicable                   dated November 21, 2007; Revision 01,
                                              32–3237 or A340–32–4279, both Revision 01,              Reporting Sheet in Airbus Service Bulletin            including Appendix 1, dated October 30,
                                              both including Reporting Sheet, both dated              A330–32–3225, Revision 02, including                  2008; or Revision 02, dated October 26, 2012;
                                              October 14, 2011, as applicable. If any                 Appendix 1, dated October 26, 2012; or                provided these inspections and corrective
                                              damage or corrosion is found, before further            Airbus Service Bulletin A340–32–4268,                 actions were accomplished between 54
                                              flight, repair in accordance with the                   Revision 03, including Appendix 1, dated              months and 72 months since first flight of the
                                              Accomplishment Instructions of Airbus                   January 14, 2013; at the applicable time              affected MLG bogie beam on an airplane, or
                                              Service Bulletin A330–32–3237 or A340–32–               specified in paragraph (m)(2)(i) or (m)(2)(ii)        since its first flight after the MLG bogie
                                              4279, both Revision 01, both including                  of this AD.                                           beam’s most recent overhaul, as applicable.
                                              Reporting Sheet, both dated October 14,                    (i) If the inspection was done on or after         Airbus Service Bulletin A340–32–4268,
                                              2011, as applicable.                                    the effective date of this AD: Submit the             dated November 21, 2007; and Revision 02,
                                                 (2) Except as provided by paragraph (k)(3)           report within 30 days after the inspection.           dated October 26, 2012; are not incorporated
                                              of this AD: Modify and re-identify, as                     (ii) If the inspection was done before the         by reference in this AD. Airbus Mandatory
                                              applicable, the LH and RH MLG bogie beams,              effective date of this AD: Submit the report          Service Bulletin A340–32–4268, Revision 01,
                                              in accordance with the Accomplishment                   within 30 days after the effective date of this       including Appendix 1, dated October 30,
                                              Instructions of Airbus Service Bulletin A330–           AD.                                                   2008, was incorporated by reference in AD
                                              32–3237 or A340–32–4279, both Revision 01,              (n) Optional Method of Compliance for                 2009–15–17.
                                              both including Reporting Sheet, both dated              Certain Requirements                                     (3) This paragraph provides credit for the
                                              October 14, 2011, as applicable.                                                                              corresponding actions required by paragraph
                                                                                                        (1) Inspections for damage and corrosion to         (n)(1) of this AD, if those actions were
                                                 (3) The inspection requirements of                   the protective treatment of the internal bores
                                              paragraph (k)(1) of this AD, and the                                                                          performed before the effective date of this AD
                                                                                                      of the LH and RH MLG bogie beam, and                  using Messier-Dowty Service Bulletin A33/
                                              modification requirements only of paragraph             repairs, done in accordance with Messier-
                                              (k)(2) of this AD, do not apply to any MLG                                                                    34–32–271, dated September 13, 2007, which
                                                                                                      Dowty Service Bulletin A33/34–32–278,                 is not incorporated by reference in this AD.
                                              bogie beam with a serial number listed in               Revision 1, including Appendixes A and B,
                                              Appendix A of Messier-Dowty Service                                                                              (4) This paragraph provides credit for the
                                                                                                      dated August 24, 2011, are acceptable                 corresponding actions required by
                                              Bulletin A33/34–32–283 or A33/34–32–284,                methods of compliance with the
                                              both Revision 1, both dated July 10, 2012, as                                                                 paragraphs (j) and (n)(1) of this AD, if those
                                                                                                      corresponding requirements of paragraph               actions were performed before the effective
                                              applicable.                                             (k)(1) of this AD.                                    date of this AD using Messier-Dowty Service
                                              (l) Optional Methods of Compliance for                    (2) Modification of the LH and RH MLG               Bulletin A33/34–32–272, including
                                              Certain Airplane Configurations                         bogie beams, done in accordance with
                                                                                                                                                            Appendixes A, B, C, and D, dated November
                                                                                                      Messier-Dowty Service Bulletins A33/34–32–
                                                 Inspections and corrective actions on both                                                                 16, 2007, which is not incorporated by
                                                                                                      283 or A33/34–32–284, both Revision 1, both
                                              MLG bogie beams done in accordance with                                                                       reference in this AD.
                                                                                                      including Appendix A, both dated July 10,
                                              the instructions of Messier-Dowty Service                                                                        (5) This paragraph provides credit for the
                                                                                                      2012, as applicable, is an acceptable method
                                              Bulletin A33/34–32–271, Revision 1,                                                                           corresponding actions required by
                                                                                                      of compliance with the corresponding
                                              including Appendixes A and B, dated                                                                           paragraphs (k), (m), and (r)(1)(i) of this AD,
                                                                                                      requirements of paragraph (k)(2) of this AD.
                                              November 16, 2007; or Messier-Dowty                                                                           if those actions were performed before the
                                              Service Bulletin A33/34–32–272, Revision 1,             (o) Optional Terminating Action for Certain           effective date of this AD using Airbus Service
                                              including Appendixes A, B, C, and D, dated              Requirements                                          Bulletin A330–32–3237, including Reporting
                                              September 22, 2008; as applicable; are                    Modification of both LH and RH MLG                  Sheet, dated January 18, 2011.
                                              acceptable methods of compliance for the                bogie beams on an airplane, done in                      (6) This paragraph provides credit for the
                                              requirements of paragraph (g) of this AD,               accordance with paragraph (k) of this AD, or          corresponding actions required by
                                              provided each inspection is accomplished                as specified in paragraphs (n)(1) and (n)(2) of       paragraphs (k), (m), and (r)(1)(i) of this AD,
                                              between 54 months and 72 months since the               this AD, terminates the repetitive inspections        if those actions were performed before the
                                              first flight of the affected MLG bogie beam on          required by paragraph (g) of this AD for this         effective date of this AD using Airbus Service
                                              an airplane, or since the MLG bogie beam’s              airplane.                                             Bulletin A340–32–4279, including Reporting
                                              first flight after the MLG bogie beam’s most                                                                  Sheet, dated January 18, 2011.
                                              recent overhaul, as applicable.                         (p) Credit for Previous Actions                          (7) This paragraph provides credit for the
                                                                                                         (1) This paragraph provides credit for the         corresponding actions required by
                                              (m) Reporting Requirement                               corresponding inspections and corrective              paragraphs (k)(3), (n)(2), (r)(1)(ii), and
                                                (1) Submit a report of the findings (both             actions done on an LH or RH MLG bogie                 (r)(1)(iii) of this AD, if those actions were
                                              positive and negative) of each inspection               beam required by paragraph (g) of this AD,            performed before the effective date of this AD
                                              required by paragraph (k) of this AD, as                if those actions were performed before the            using Messier-Dowty Service Bulletin A33/
sradovich on DSK3GMQ082PROD with RULES




                                              applicable, to Airbus, Customer Service                 effective date of this AD using Airbus Service        34–32–283, including Appendix A, dated
                                              Directorate, 1 Rond Point Maurice Bellonte,             Bulletin A330–32–3225, dated November 21,             May 11, 2010, which is not incorporated by
                                              31707 Blagnac Cedex, France, using the                  2007; or Revision 1, dated October 30, 2008;          reference in this AD.
                                              applicable Reporting Sheet in Airbus Service            provided the inspections and corrective                  (8) This paragraph provides credit for the
                                              Bulletin A330–32–3237, Revision 01,                     actions were accomplished between 54                  corresponding actions required by
                                              including Reporting Sheet, dated October 14,            months and 72 months since first flight of the        paragraphs (k)(3), (n)(2), (r)(1)(ii), and
                                              2011; or Airbus Service Bulletin A340–32–               affected MLG bogie beam on an airplane, or            (r)(1)(iii) of this AD, if those actions were
                                              4279, Revision 01, including Reporting                  since its first flight after the MLG bogie            performed before the effective date of this AD



                                         VerDate Sep<11>2014   17:53 Sep 27, 2016   Jkt 238001   PO 00000   Frm 00036   Fmt 4700   Sfmt 4700   E:\FR\FM\28SER1.SGM   28SER1


                                                           Federal Register / Vol. 81, No. 188 / Wednesday, September 28, 2016 / Rules and Regulations                                              66523

                                              using Messier-Dowty Service Bulletin A33/               appropriate. If sending information directly             (3) The following service information was
                                              34–32–284, including Appendix A, dated                  to the International Branch, send it to ATTN:         approved for IBR on November 2, 2016.
                                              May 11, 2010, which is not incorporated by              Vladimir Ulyanov, Aerospace Engineer,                    (i) Airbus Service Bulletin A330–32–3225,
                                              reference in this AD.                                   International Branch, ANM–116, Transport              Revision 02, including Appendix 1, dated
                                                 (9) This paragraph provides credit for the           Airplane Directorate, FAA, 1601 Lind                  October 26, 2012.
                                              corresponding actions required by                       Avenue SW., Renton, WA 98057–3356;
                                                                                                                                                               (ii) Airbus Service Bulletin A330–32–3237,
                                              paragraphs (n)(1) and (r)(1)(ii) of this AD, if         telephone: 425–227–1138; fax: 425–227–
                                              those actions were performed before the                                                                       Revision 01, including Reporting Sheet,
                                                                                                      1149. Information may be emailed to: 9-
                                              effective date of this AD using Messier-Dowty           ANM-116-AMOC-REQUESTS@faa.gov.                        dated October 14, 2011.
                                              Service Bulletin A33/34–32–278, including               Before using any approved AMOC, notify                   (iii) Airbus Service Bulletin A340–32–
                                              Appendixes A and B, dated February 17,                  your appropriate principal inspector, or              4268, Revision 03, including Appendix 1,
                                              2010, which is not incorporated by reference            lacking a principal inspector, the manager of         dated January 14, 2013.
                                              in this AD.                                             the local flight standards district office/              (iv) Airbus Service Bulletin A340–32–
                                              (q) Clarification of Inspection Compliance              certificate holding district office. The AMOC         4279, Revision 01, including Reporting
                                              Times                                                   approval letter must specifically reference           Sheet, dated October 14, 2011.
                                                                                                      this AD.                                                 (v) Messier-Dowty Service Bulletin A33/
                                                After accomplishment of the one-time                     (2) Contacting the Manufacturer: As of the
                                              detailed inspection required by paragraph (h)                                                                 34–32–278, Revision 1, including
                                                                                                      effective date of this AD, for any requirement        Appendixes A and B, dated August 24, 2011.
                                              of this AD, the repetitive actions required by          in this AD to obtain corrective actions from
                                              paragraph (g) of this AD remain applicable,                                                                      (vi) Messier-Dowty Service Bulletin A33/
                                                                                                      a manufacturer, the action must be
                                              and must be done within the compliance                  accomplished using a method approved by               34–32–283, Revision 1, including Appendix
                                              times specified in paragraph (g) of this AD.            the Manager, International Branch, ANM–               A, dated July 10, 2012.
                                              (r) Parts Installation Limitations                      116, Transport Airplane Directorate, FAA; or             (vii) Messier-Dowty Service Bulletin A33/
                                                                                                      the European Aviation Safety Agency                   34–32–284, Revision 1, including Appendix
                                                 (1) After modification of an airplane, as
                                                                                                      (EASA); or Airbus’s EASA Design                       A, dated July 10, 2012.
                                              required by paragraph (k) of this AD, or as
                                                                                                      Organization Approval (DOA). If approved by              (4) The following service information was
                                              specified in paragraphs (n)(1) and (n)(2) of
                                              this AD, do not install an MLG bogie beam               the DOA, the approval must include the                approved for IBR on September 2, 2009 (74
                                              on any airplane unless it is done in                    DOA-authorized signature.                             FR 37523, July 29, 2009).
                                              compliance with the requirements of                        (3) Reporting Requirements: A federal                 (i) Messier-Dowty Service Bulletin A33/
                                              paragraph (r)(1)(i), (r)(1)(ii), or (r)(1)(iii) of      agency may not conduct or sponsor, and a              34–32–271, Revision 1, including
                                              this AD.                                                person is not required to respond to, nor
                                                                                                                                                            Appendixes A and B, dated November 16,
                                                 (i) The MLG bogie beam has been modified             shall a person be subject to a penalty for
                                                                                                      failure to comply with a collection of                2007.
                                              and re-identified in accordance with the                                                                         (ii) Messier-Dowty Service Bulletin A33/
                                              Accomplishment Instructions of Airbus                   information subject to the requirements of
                                                                                                      the Paperwork Reduction Act unless that               34–32–272, Revision 1, including
                                              Service Bulletin A330–32–3237 or A340–32–
                                                                                                      collection of information displays a current          Appendixes A, B, C, and D, dated September
                                              4279, both Revision 01, both including
                                                                                                      valid OMB Control Number. The OMB                     22, 2008.
                                              Reporting Sheet, both dated October 14,
                                              2011, as applicable.                                    Control Number for this information                      (5) For Airbus service information
                                                 (ii) The MLG bogie beam has been                     collection is 2120–0056. Public reporting for         identified in this AD, contact Airbus SAS,
                                              inspected and all applicable corrective                 this collection of information is estimated to        Airworthiness Office—EAL, 1 Rond Point
                                              actions have been done in accordance with               be approximately 5 minutes per response,              Maurice Bellonte, 31707 Blagnac Cedex,
                                              the Accomplishment Instructions of Messier-             including the time for reviewing instructions,        France; telephone: +33 5 61 93 36 96; fax:
                                              Dowty Service Bulletin A33/34–32–278,                   completing and reviewing the collection of            +33 5 61 93 45 80; email:
                                              Revision 1, dated August 24, 2011; and                  information. All responses to this collection         airworthiness.A330-A340@airbus.com;
                                              modified in accordance with the                         of information are mandatory. Comments
                                                                                                                                                            Internet: http://www.airbus.com.
                                              Accomplishment Instructions of Messier-                 concerning the accuracy of this burden and
                                                                                                      suggestions for reducing the burden should               (6) For Messier-Dowty service information
                                              Dowty Service Bulletin A33/34–32–283 or                                                                       identified in this AD, contact Messier-Dowty:
                                              A33/34–32–284, both Revision 1, both                    be directed to the FAA at: 800 Independence
                                                                                                      Ave. SW., Washington, DC 20591, Attn:                 Messier Services Americas, Customer
                                              including Appendix A, both dated July 10,
                                              2012.                                                   Information Collection Clearance Officer,             Support Center, 45360 Severn Way, Sterling,
                                                 (iii) The MLG bogie beam has a serial                AES–200.                                              VA 20166–8910; telephone 703–450–8233;
                                              number listed in Appendix A of Messier-                                                                       fax 703–404–1621; Internet: https://
                                                                                                      (t) Related Information
                                              Dowty Service Bulletin A33/34–32–283 or                                                                       techpubs.services/messier-dowty.com.
                                              A33/34–32–284, both Revision 1, both dated                 (1) Refer to Mandatory Continuing                     (7) You may view this service information
                                              July 10, 2012, as applicable.                           Airworthiness Information (MCAI) AD 2013–             at the FAA, Transport Airplane Directorate,
                                                 (2) As of the effective date of this AD,             0267R1, dated March 4, 2014; corrected                1601 Lind Avenue SW., Renton, WA. For
                                              except as specified in paragraph (r)(1) of this         March 8, 2014, for related information. This
                                                                                                                                                            information on the availability of this
                                              AD, installation of an MLG bogie beam on an             MCAI may be found in the AD docket on the
                                                                                                                                                            material at the FAA, call 425–227–1221.
                                              airplane is allowed, provided that following            Internet at http://www.regulations.gov by
                                                                                                      searching for and locating Docket No. FAA–               (8) You may view this service information
                                              the installation it is inspected and all
                                                                                                      2013–0828.                                            that is incorporated by reference at the
                                              applicable repairs and corrective actions
                                              have been done in accordance with the                      (2) Service information identified in this         National Archives and Records
                                              requirements of this AD.                                AD that is not incorporated by reference is           Administration (NARA). For information on
                                                                                                      available at the addresses specified in               the availability of this material at NARA, call
                                              (s) Other FAA AD Provisions                             paragraphs (u)(5), (u)(6), and (u)(7) of this         202–741–6030, or go to: http://
                                                 The following provisions also apply to this          AD.                                                   www.archives.gov/federal-register/cfr/ibr-
                                              AD:                                                                                                           locations.html.
                                                 (1) Alternative Methods of Compliance                (u) Material Incorporated by Reference
                                                                                                                                                              Issued in Renton, Washington, on August
sradovich on DSK3GMQ082PROD with RULES




                                              (AMOCs): The Manager, International                        (1) The Director of the Federal Register
                                              Branch, ANM–116, Transport Airplane                     approved the incorporation by reference               24, 2016.
                                              Directorate, FAA, has the authority to                  (IBR) of the service information listed in this       John P. Piccola, Jr.,
                                              approve AMOCs for this AD, if requested                 paragraph under 5 U.S.C. 552(a) and 1 CFR
                                                                                                                                                            Acting Manager, Transport Airplane
                                              using the procedures found in 14 CFR 39.19.             part 51.
                                                                                                                                                            Directorate, Aircraft Certification Service.
                                              In accordance with 14 CFR 39.19, send your                 (2) You must use this service information
                                              request to your principal inspector or local            as applicable to do the actions required by           [FR Doc. 2016–21150 Filed 9–27–16; 8:45 am]
                                              Flight Standards District Office, as                    this AD, unless this AD specifies otherwise.          BILLING CODE 4910–13–P




                                         VerDate Sep<11>2014   17:53 Sep 27, 2016   Jkt 238001   PO 00000   Frm 00037   Fmt 4700   Sfmt 4700   E:\FR\FM\28SER1.SGM   28SER1



Document Created: 2016-09-28 01:08:08
Document Modified: 2016-09-28 01:08:08
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionRules and Regulations
ActionFinal rule.
DatesThis AD is effective November 2, 2016.
ContactVladimir Ulyanov, Aerospace Engineer, International Branch, ANM-116, Transport Airplane Directorate, FAA, 1601 Lind Avenue SW., Renton, WA 98057-3356; telephone: 425-227-1138; fax: 425-227-1149.
FR Citation81 FR 66518 
RIN Number2120-AA64
CFR AssociatedAir Transportation; Aircraft; Aviation Safety; Incorporation by Reference and Safety

2025 Federal Register | Disclaimer | Privacy Policy
USC | CFR | eCFR