The U.S. Nuclear Regulatory Commission (NRC) is granting the Talen Energy request to withdraw its application for a combined license (COL) for the Bell Bend Nuclear Power Plant (BBNPP). This new reactor would be identified as the BBNPP located adjacent to the existing Susquehanna Steam Electric Station in Luzerne County, Pennsylvania.

Federal Register, Volume 81 Issue 189 (Thursday, September 29, 2016)
[Federal Register Volume 81, Number 189 (Thursday, September 29, 2016)]
[Notices]
[Page 67014]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2016-23556]


=======================================================================
-----------------------------------------------------------------------

NUCLEAR REGULATORY COMMISSION

[Docket No. 52-039; NRC-2008-0603]


Talen Energy Combined License Application for Bell Bend Nuclear 
Power Plant

AGENCY: Nuclear Regulatory Commission.

ACTION: Application for combined license; withdrawal.

-----------------------------------------------------------------------

SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) is granting the 
Talen Energy request to withdraw its application for a combined license 
(COL) for the Bell Bend Nuclear Power Plant (BBNPP). This new reactor 
would be identified as the BBNPP located adjacent to the existing 
Susquehanna Steam Electric Station in Luzerne County, Pennsylvania.

DATES: The effective date of the withdrawal is September 22, 2016.

ADDRESSES: Please refer to Docket ID NRC-2008-0603 when contacting the 
NRC about the availability of information regarding this document. You 
may obtain publicly-available information related to this document 
using any of the following methods:
     Federal Rulemaking Web site: Go to http://www.regulations.gov and search for Docket ID NRC-2008-0603. Address 
questions about NRC dockets to Carol Gallagher; telephone: 301-415-
3463; email: [email protected]. For technical questions, contact 
the individual listed in the FOR FURTHER INFORMATION CONTACT section of 
this document.
     NRC's Agencywide Documents Access and Management System 
(ADAMS): You may obtain publicly available documents online in the 
ADAMS Public Documents collection at http://www.nrc.gov/reading-rm/adams.html. To begin the search, select ``ADAMS Public Documents,'' and 
then select ``Begin Web-based ADAMS Search.'' For problems with ADAMS, 
please contact the NRC's Public Document Room (PDR) reference staff at 
1-800-397-4209, 301-415-4737, or by email to [email protected]. The 
ADAMS accession number for each document referenced (if that document 
is available in ADAMS) is provided the first time that a document is 
referenced.
     NRC's PDR: You may examine and purchase copies of public 
documents at the NRC's PDR, Room O1-F21, One White Flint North, 11555 
Rockville Pike, Rockville, Maryland 20852.

FOR FURTHER INFORMATION CONTACT: Tomeka Terry, Office of New Reactors, 
U.S. Nuclear Regulatory Commission, Washington DC 20555-0001; 
telephone: 301-415-1488, email: [email protected].

SUPPLEMENTARY INFORMATION: By letter dated October 10, 2008 (ADAMS 
Accession No. ML082880580), as supplemented by letters, dated November 
18, 2008 and November 24, 2008 (ADAMS Accession Nos. ML083250485 and 
ML083330405) and December 1, 2008 and December 8, 2008 (ADAMS Accession 
No. ML083400289 and ML083510577), Talen Energy (formerly PPL Bell Bend, 
LLC), submitted an application to the NRC for a COL for a single unit 
of the U.S. Evolutionary Power Reactor in accordance with the 
requirements contained in part 52 of title 10 of the Code of Federal 
Regulations (10 CFR), ``Licenses, Certifications, and Approvals for 
Nuclear Power Plants.'' This new reactor was identified as BBNPP 
located adjacent to the existing Susquehanna Steam Electric Station in 
Luzerne County, Pennsylvania.
    A notice acknowledging receipt and availability of the Talen 
Energy's COL application was published in the Federal Register on 
November 13, 2008 (73 FR 67214). Subsequently, a notice announcing the 
acceptance for docketing of the BBNPP COL application in accordance 
with 10 CFR part 2, ``Agency Rules of Practice and Procedure,'' and 10 
CFR part 52 was published in the Federal Register on December 29, 2008 
(73 FR 79519). The docket number established for this application was 
52-039.
    By letter dated January 9, 2014 (ADAMS Accession No. ML14030A074), 
Talen Energy requested that the NRC suspend the safety review portion 
of the COL application until further notice, and continue to focus its 
support on the necessary work leading to the issuance of the final 
environmental impact statement (FEIS). The NRC staff issued the FEIS, 
NUREG-2179, ``Environmental Impact Statement for a Combined License 
(COL) for Bell Bend Nuclear Power Plant, Final Report,'' on April 21, 
2016 (ADAMS Accession No. ML16075A311). The NRC granted the requested 
suspension by letter dated August 12, 2014 (ADAMS Accession No. 
ML14210A588).
    By its recent letter dated August 30, 2016 (ADAMS Accession No. 
ML16252A202), Talen Energy requested withdrawal of its BBNPP COL 
application, including the Safeguards/Security part of the application. 
Pursuant to the requirements in 10 CFR part 2, the Commission has 
granted Talen Energy its request to withdraw the BBNPP COL application.

    Dated at Rockville, Maryland, this 22nd day of September 2016.

    For the Nuclear Regulatory Commission.
Francis M. Akstulewicz,
Director, Division of New Reactor Licensing, Office of New Reactors.
[FR Doc. 2016-23556 Filed 9-28-16; 8:45 am]
 BILLING CODE 7590-01-P



                                                  67014                    Federal Register / Vol. 81, No. 189 / Thursday, September 29, 2016 / Notices

                                                     Schedule updates, including weather-                 Search.’’ For problems with ADAMS,                    Combined License (COL) for Bell Bend
                                                  related cancellations, are also available               please contact the NRC’s Public                       Nuclear Power Plant, Final Report,’’ on
                                                  at www.ntsb.gov.                                        Document Room (PDR) reference staff at                April 21, 2016 (ADAMS Accession No.
                                                  FOR MORE INFORMATION CONTACT: Candi                     1–800–397–4209, 301–415–4737, or by                   ML16075A311). The NRC granted the
                                                  Bing at (202) 314–6403 or by email at                   email to pdr.resource@nrc.gov. The                    requested suspension by letter dated
                                                  bingc@ntsb.gov.                                         ADAMS accession number for each                       August 12, 2014 (ADAMS Accession
                                                  FOR MEDIA INFORMATION CONTACT: Keith                    document referenced (if that document                 No. ML14210A588).
                                                  Holloway at (202) 314–6100 or by email                  is available in ADAMS) is provided the
                                                                                                          first time that a document is referenced.               By its recent letter dated August 30,
                                                  at Keith.Holloway@ntsb.gov.                                                                                   2016 (ADAMS Accession No.
                                                                                                             • NRC’s PDR: You may examine and
                                                    Dated: Thursday, August 25, 2016.                     purchase copies of public documents at                ML16252A202), Talen Energy requested
                                                  Candi R. Bing,                                          the NRC’s PDR, Room O1–F21, One                       withdrawal of its BBNPP COL
                                                  Federal Register Liaison Officer.                       White Flint North, 11555 Rockville                    application, including the Safeguards/
                                                  [FR Doc. 2016–23683 Filed 9–27–16; 4:15 pm]             Pike, Rockville, Maryland 20852.                      Security part of the application.
                                                  BILLING CODE 7533–01–P                                  FOR FURTHER INFORMATION CONTACT:                      Pursuant to the requirements in 10 CFR
                                                                                                          Tomeka Terry, Office of New Reactors,                 part 2, the Commission has granted
                                                                                                          U.S. Nuclear Regulatory Commission,                   Talen Energy its request to withdraw the
                                                  NUCLEAR REGULATORY                                      Washington DC 20555–0001; telephone:                  BBNPP COL application.
                                                  COMMISSION                                              301–415–1488, email: Tomeka.Terry@                      Dated at Rockville, Maryland, this 22nd
                                                                                                          nrc.gov.                                              day of September 2016.
                                                  [Docket No. 52–039; NRC–2008–0603]
                                                                                                          SUPPLEMENTARY INFORMATION: By letter                    For the Nuclear Regulatory Commission.
                                                  Talen Energy Combined License                           dated October 10, 2008 (ADAMS                         Francis M. Akstulewicz,
                                                  Application for Bell Bend Nuclear                       Accession No. ML082880580), as
                                                                                                                                                                Director, Division of New Reactor Licensing,
                                                  Power Plant                                             supplemented by letters, dated
                                                                                                                                                                Office of New Reactors.
                                                                                                          November 18, 2008 and November 24,
                                                  AGENCY:  Nuclear Regulatory                             2008 (ADAMS Accession Nos.                            [FR Doc. 2016–23556 Filed 9–28–16; 8:45 am]
                                                  Commission.                                             ML083250485 and ML083330405) and                      BILLING CODE 7590–01–P
                                                  ACTION: Application for combined                        December 1, 2008 and December 8, 2008
                                                  license; withdrawal.                                    (ADAMS Accession No. ML083400289
                                                                                                          and ML083510577), Talen Energy
                                                  SUMMARY:   The U.S. Nuclear Regulatory                                                                        POSTAL SERVICE
                                                                                                          (formerly PPL Bell Bend, LLC),
                                                  Commission (NRC) is granting the Talen
                                                                                                          submitted an application to the NRC for
                                                  Energy request to withdraw its                                                                                Product Change—Priority Mail
                                                                                                          a COL for a single unit of the U.S.
                                                  application for a combined license                                                                            Negotiated Service Agreement
                                                                                                          Evolutionary Power Reactor in
                                                  (COL) for the Bell Bend Nuclear Power
                                                                                                          accordance with the requirements
                                                  Plant (BBNPP). This new reactor would                                                                         AGENCY:    Postal ServiceTM.
                                                                                                          contained in part 52 of title 10 of the
                                                  be identified as the BBNPP located
                                                                                                          Code of Federal Regulations (10 CFR),                 ACTION:   Notice.
                                                  adjacent to the existing Susquehanna
                                                                                                          ‘‘Licenses, Certifications, and Approvals
                                                  Steam Electric Station in Luzerne
                                                                                                          for Nuclear Power Plants.’’ This new                  SUMMARY:    The Postal Service gives
                                                  County, Pennsylvania.
                                                                                                          reactor was identified as BBNPP located               notice of filing a request with the Postal
                                                  DATES: The effective date of the                        adjacent to the existing Susquehanna
                                                  withdrawal is September 22, 2016.                                                                             Regulatory Commission to add a
                                                                                                          Steam Electric Station in Luzerne                     domestic shipping services contract to
                                                  ADDRESSES: Please refer to Docket ID                    County, Pennsylvania.                                 the list of Negotiated Service
                                                  NRC–2008–0603 when contacting the                          A notice acknowledging receipt and
                                                  NRC about the availability of                                                                                 Agreements in the Mail Classification
                                                                                                          availability of the Talen Energy’s COL
                                                  information regarding this document.                    application was published in the                      Schedule’s Competitive Products List.
                                                  You may obtain publicly-available                       Federal Register on November 13, 2008                 DATES:   Effective date: September 29,
                                                  information related to this document                    (73 FR 67214). Subsequently, a notice                 2016.
                                                  using any of the following methods:                     announcing the acceptance for
                                                     • Federal Rulemaking Web site: Go to                 docketing of the BBNPP COL                            FOR FURTHER INFORMATION CONTACT:
                                                  http://www.regulations.gov and search                   application in accordance with 10 CFR                 Elizabeth A. Reed, 202–268–3179.
                                                  for Docket ID NRC–2008–0603. Address                    part 2, ‘‘Agency Rules of Practice and                SUPPLEMENTARY INFORMATION:      The
                                                  questions about NRC dockets to Carol                    Procedure,’’ and 10 CFR part 52 was                   United States Postal Service® hereby
                                                  Gallagher; telephone: 301–415–3463;                     published in the Federal Register on
                                                  email: Carol.Gallagher@nrc.gov. For                                                                           gives notice that, pursuant to 39 U.S.C.
                                                                                                          December 29, 2008 (73 FR 79519). The
                                                  technical questions, contact the                                                                              3642 and 3632(b)(3), on September 23,
                                                                                                          docket number established for this
                                                  individual listed in the FOR FURTHER                    application was 52–039.                               2016, it filed with the Postal Regulatory
                                                  INFORMATION CONTACT section of this                        By letter dated January 9, 2014                    Commission a Request of the United
                                                  document.                                               (ADAMS Accession No. ML14030A074),                    States Postal Service to Add Priority
                                                     • NRC’s Agencywide Documents                         Talen Energy requested that the NRC                   Mail Contract 240 to Competitive
                                                  Access and Management System                            suspend the safety review portion of the              Product List. Documents are available at
mstockstill on DSK3G9T082PROD with NOTICES




                                                  (ADAMS): You may obtain publicly                        COL application until further notice,                 www.prc.gov, Docket Nos. MC2016–201,
                                                  available documents online in the                       and continue to focus its support on the              CP2016–290.
                                                  ADAMS Public Documents collection at                    necessary work leading to the issuance
                                                                                                                                                                Stanley F. Mires,
                                                  http://www.nrc.gov/reading-rm/                          of the final environmental impact
                                                  adams.html. To begin the search, select                 statement (FEIS). The NRC staff issued                Attorney, Federal Compliance.
                                                  ‘‘ADAMS Public Documents,’’ and then                    the FEIS, NUREG–2179,                                 [FR Doc. 2016–23513 Filed 9–28–16; 8:45 am]
                                                  select ‘‘Begin Web-based ADAMS                          ‘‘Environmental Impact Statement for a                BILLING CODE 7710–12–P




                                             VerDate Sep<11>2014   18:51 Sep 28, 2016   Jkt 238001   PO 00000   Frm 00096   Fmt 4703   Sfmt 9990   E:\FR\FM\29SEN1.SGM   29SEN1



Document Created: 2016-09-29 04:14:32
Document Modified: 2016-09-29 04:14:32
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
ActionApplication for combined license; withdrawal.
DatesThe effective date of the withdrawal is September 22, 2016.