81_FR_7740 81 FR 7710 - Approval of Regional Haze BART Alternative Measure: Washington

81 FR 7710 - Approval of Regional Haze BART Alternative Measure: Washington

ENVIRONMENTAL PROTECTION AGENCY

Federal Register Volume 81, Issue 30 (February 16, 2016)

Page Range7710-7712
FR Document2016-02953

The Environmental Protection Agency (EPA) is taking final action to approve the Best Available Retrofit Technology (BART) alternative measure for the BP Cherry Point Refinery located near Ferndale, Washington. The BART alternative measure increases the oxides of nitrogen (NO<INF>X</INF>) emission limit from the R-1 HC Reactor Heater (R-1 Heater), a BART-eligible source currently subject to BART emission limits on NO<INF>X</INF>. To offset the increase in NO<INF>X</INF> emissions from this emission unit, the NO<INF>X</INF> emission limits on the 1st Stage Hydrocracker Fractionator Reboiler (R- 1 Reboiler), also a BART-eligible source subject to BART emission limits on NO<INF>X</INF>, will be reduced. The net effect of these changes is a decrease of 10.4 tons per year (tpy) of allowable NO<INF>X</INF> emissions from sources subject to BART at the BP Cherry Point Refinery.

Federal Register, Volume 81 Issue 30 (Tuesday, February 16, 2016)
[Federal Register Volume 81, Number 30 (Tuesday, February 16, 2016)]
[Rules and Regulations]
[Pages 7710-7712]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2016-02953]


-----------------------------------------------------------------------

ENVIRONMENTAL PROTECTION AGENCY

40 CFR Part 52

[EPA-R10-OAR-2015-0398; FRL-9942-15-Region 10]


Approval of Regional Haze BART Alternative Measure: Washington

AGENCY: Environmental Protection Agency (EPA).

ACTION: Final rule.

-----------------------------------------------------------------------

SUMMARY: The Environmental Protection Agency (EPA) is taking final 
action to approve the Best Available Retrofit Technology (BART) 
alternative measure for the BP Cherry Point Refinery located near 
Ferndale, Washington. The BART alternative measure increases the oxides 
of nitrogen (NOX) emission limit from the R-1 HC Reactor 
Heater (R-1 Heater), a BART-eligible source currently subject to BART 
emission limits on NOX. To offset the increase in 
NOX emissions from this emission unit, the NOX 
emission limits on the 1st Stage Hydrocracker Fractionator Reboiler (R-
1 Reboiler), also a BART-eligible source subject to BART emission 
limits on NOX, will be reduced. The net effect of these 
changes is a decrease of 10.4 tons per year (tpy) of allowable 
NOX emissions from sources subject to BART at the BP Cherry 
Point Refinery.

DATES: This final rule is effective March 17, 2016.

ADDRESSES: The EPA has established a docket for this action under 
Docket ID No. EPA-EPA-R10-OAR-2015-0398. All documents in the docket 
are listed on the http://www.regulations.gov Web site. Although listed 
in the index, some information may not be publicly available, i.e., 
Confidential Business Information or other information the disclosure 
of which is restricted by statute. Certain other material, such as 
copyrighted material, is not placed on the Internet and is publicly 
available only in hard copy form. Publicly available docket materials 
are available at http://www.regulations.gov or at EPA Region 10, Office 
of Air, Waste and Toxics, 1200 Sixth Avenue, Seattle, Washington 98101. 
The EPA requests that you contact the person listed in the FOR FURTHER 
INFORMATION CONTACT section to schedule your inspection. The Regional 
Office's official hours of business are Monday through Friday, 8:30 to 
4:30, excluding Federal holidays.

FOR FURTHER INFORMATION CONTACT: For information please contact John 
Chi at (206) 553-1185, or [email protected].

SUPPLEMENTARY INFORMATION:

Table of Contents

I. Background Information
II. Final Action
III. Incorporation by Reference
IV. Statutory and Executive Orders Review

I. Background Information

    On May 14, 2015, Washington submitted the BART alternative measure 
and the EPA proposed to approve it on November 16, 2015 (80 FR 70718). 
An explanation of the CAA requirements, a detailed analysis of the 
submittal, and the EPA's reasons for approval were provided in the 
notice of proposed rulemaking, and will not be restated here. The 
public comment period for this proposed rule ended on December 16, 
2015. The EPA received one comment in support of this action and no 
adverse comments.

II. Final Action

    The EPA is approving the BART alternative measure for the BP Cherry 
Point Refinery located near Ferndale, Washington by incorporating by 
reference the conditions of Revision 2 identified below. The EPA is 
removing the BP Cherry Point Refinery, BART Compliance Order No. 7836 
currently in the Federally approved SIP at 40 CFR 52.2470(d) and 
replacing it with provisions of the BP Cherry Point Refinery, BART 
Compliance Order No. 7836 Revision 2. The EPA is also approving new 
Condition 9 of the BART Compliance Order 7836 Revision 2 relating to 
decommissioned units. The conditions of the BP BART Compliance Order 
Revision 2 that are proposed for incorporation by reference are:
    Condition 1: 1.1, 1.1.1, 1.2, 1.2.1, 1.2.2;
    Condition 2: 2.1, 2.1.1, 2.1.2, 2.1.3, 2.1.4, 2.1.5, 2.2, 2.2.1, 
2.2.2, 2.3, 2.3.1, 2.3.2, 2.4, 2.4.1, 2.4.2, 2.4.2.1, 2.5, 2.5.1, 
2.5.1.1, 2.5.1.2, 2.5.2, 2.5.3, 2.5.4, 2.6, 2.6.1, 2.6.2, 2.6.3, 2.7, 
2.7.1, 2.7.2, 2.7.3, 2.7.4, 2.8, 2.8.1, 2.8.2,2.8.3, 2.8.4, 2.8.5, 
2.8.6;
    Condition 3, 3.1, 3.1.1, 3.1.2, 3.2, 3.2.1, 3.2.2, 3.2.3, 3.2.4;
    Condition 4, 4.1, 4.1.1, 4.1.1.1, 4.1.1.2, 4.1.1.3, 4.1.1.4;
    Condition 5, 5.1, 5.2;
    Condition 6, 6.1, 6.2, 6.3;
    Condition 7; and
    Condition 9.

III. Incorporation by Reference

    In accordance with requirements of 1 CFR 51.5, the EPA is revising 
our

[[Page 7711]]

incorporation by reference located in 40 CFR 52.2470(d)--``EPA-Approved 
State Source-Specific Requirements'' to reflect the approval of the 
BART alternative measure for the BP Cherry Point Refinery and the 
provision relating to decommissioned units. Due to the fact that the 
conditions in the original BART Order were renumbered in Revision 1, 
which was not submitted as a SIP revision, the EPA is removing the 
original IBR entry for ``BP Cherry Point Refinery'' in its entirety and 
incorporating in its place the specified conditions of Revision 2 
included in the docket for this action. The end result is that all of 
the conditions in the Original BART order remain in the SIP (but with 
different numbers) except as discussed in the notice of the proposed 
rulemaking with respect to the BART alternative measure and the 
addition of Condition 9. The EPA has made, and will continue to make, 
these documents generally available electronically through 
www.regulations.gov and/or in hard copy at the appropriate EPA office 
(see the ADDRESSES section of this preamble for more information).

IV. Statutory and Executive Orders Review

    Under the CAA, the Administrator is required to approve a SIP 
submission that complies with the provisions of the CAA and applicable 
Federal regulations. 42 U.S.C. 7410(k); 40 CFR 52.02(a). Thus, in 
reviewing SIP submissions, the EPA's role is to approve state choices, 
provided that they meet the criteria of the CAA. Accordingly, this 
action merely approves state law as meeting Federal requirements and 
does not impose additional requirements beyond those imposed by state 
law. For that reason, this action:

     Is not a ``significant regulatory action'' subject to 
review by the Office of Management and Budget under Executive Orders 
12866 (58 FR 51735, October 4, 1993) and 13563 (76 FR 3821, January 
21, 2011);
     does not impose an information collection burden under 
the provisions of the Paperwork Reduction Act (44 U.S.C. 3501 et 
seq.);
     is certified as not having a significant economic 
impact on a substantial number of small entities under the 
Regulatory Flexibility Act (5 U.S.C. 601 et seq.);
     does not contain any unfunded mandate or significantly 
or uniquely affect small governments, as described in the Unfunded 
Mandates Reform Act of 1995 (Public Law 104-4);
     does not have Federalism implications as specified in 
Executive Order 13132 (64 FR 43255, August 10, 1999);
     is not an economically significant regulatory action 
based on health or safety risks subject to Executive Order 13045 (62 
FR 19885, April 23, 1997);
     is not a significant regulatory action subject to 
Executive Order 13211 (66 FR 28355, May 22, 2001);
     is not subject to requirements of Section 12(d) of the 
National Technology Transfer and Advancement Act of 1995 (15 U.S.C. 
272 note) because this action does not involve technical standards; 
and
     does not provide the EPA with the discretionary 
authority to address, as appropriate, disproportionate human health 
or environmental effects, using practicable and legally permissible 
methods, under Executive Order 12898 (59 FR 7629, February 16, 
1994).

    The SIP is not approved to apply on any Indian reservation land in 
Washington except as specifically noted below and is also not approved 
to apply in any other area where the EPA or an Indian tribe has 
demonstrated that a tribe has jurisdiction. In those areas of Indian 
country, the rule does not have tribal implications as specified by 
Executive Order 13175 (65 FR 67249, November 9, 2000).
    The Congressional Review Act, 5 U.S.C. 801 et seq., as added by the 
Small Business Regulatory Enforcement Fairness Act of 1996, generally 
provides that before a rule may take effect, the agency promulgating 
the rule must submit a rule report, which includes a copy of the rule, 
to each House of the Congress and to the Comptroller General of the 
United States. The EPA will submit a report containing this action and 
other required information to the U.S. Senate, the U.S. House of 
Representatives, and the Comptroller General of the United States prior 
to publication of the rule in the Federal Register. A major rule cannot 
take effect until 60 days after it is published in the Federal 
Register. This action is not a ``major rule'' as defined by 5 U.S.C. 
804(2).
    Under section 307(b)(1) of the CAA, petitions for judicial review 
of this action must be filed in the United States Court of Appeals for 
the appropriate circuit by April 18, 2016. Filing a petition for 
reconsideration by the Administrator of this final rule does not affect 
the finality of this action for the purposes of judicial review nor 
does it extend the time within which a petition for judicial review may 
be filed, and shall not postpone the effectiveness of such rule or 
action. This action may not be challenged later in proceedings to 
enforce its requirements. See section 307(b)(2).

List of Subjects in 40 CFR Part 52

    Environmental protection, Air pollution control, Incorporation by 
reference, Nitrogen dioxide, Ozone, Particulate matter, Reporting and 
recordkeeping requirements, Sulfur oxides, Volatile organic compounds.

    Dated: January 27, 2016.
Dennis J. McLerran,
Regional Administrator, Region 10.
    For the reasons set forth in the preamble, 40 CFR part 52 is 
amended as follows:

PART 52--APPROVAL AND PROMULGATION OF IMPLEMENTATION PLANS

0
1. The authority citation for part 52 continues to read as follows:

    Authority: 42 U.S.C. 7401 et seq.

Subpart WW--Washington

0
2. In Sec.  52.2470:
0
a. In paragraph (d), the table is amended by revising the entry for 
``BP Cherry Point Refinery.''
0
b. In paragraph (e), table 2 is amended by adding an entry entitled 
``Regional Haze State Implementation Plan--BP Cherry Point Refinery 
BART Revision'' to the end of the table.
    The revisions read as follows:


Sec.  52.2470  Identification of plan.

* * * * *
    (d) * * *

[[Page 7712]]



                          EPA-Approved State of Washington Source-Specific Requirements
----------------------------------------------------------------------------------------------------------------
                                    Order/Permit          State
         Name of source                number        effective date   EPA approval date        Explanation
----------------------------------------------------------------------------------------------------------------
 
                                                  * * * * * * *
BP Cherry Point Refinery.......  Administrative             5/13/15  2/16/16 [Insert     The following
                                  Order No. 7836,                     Federal Register    conditions: 1.1,
                                  Revision 2.                         citation].          1.1.1, 1.2, 1.2.1,
                                                                                          1.2.2, 2.1, 2.1.1,
                                                                                          2.1.2, 2.1.3, 2.1.4,
                                                                                          2.1.5, 2.2, 2.2.1,
                                                                                          2.2.2, 2.3, 2.3.1,
                                                                                          2.3.2, 2.4, 2.4.1,
                                                                                          2.4.2, 2.4.2.1, 2.5,
                                                                                          2.5.1, 2.5.1.1,
                                                                                          2.5.1.2, 2.5.2, 2.5.3,
                                                                                          2.5.4, 2.6, 2.6.1,
                                                                                          2.6.2, 2.6.3, 2.7,
                                                                                          2.7.1, 2.7.2, 2.7.3,
                                                                                          2.7.4, 2.8, 2.8.1,
                                                                                          2.8.2,2.8.3, 2.8.4,
                                                                                          2.8.5, 2.8.6, 3, 3.1,
                                                                                          3.1.1, 3.1.2, 3.2,
                                                                                          3.2.1, 3.2.2, 3.2.3,
                                                                                          3.2.4, 4, 4.1, 4.1.1,
                                                                                          4.1.1.1, 4.1.1.2,
                                                                                          4.1.1.3, 4.1.1.4, 5,
                                                                                          5.1, 5.2, 6, 6.1, 6.2,
                                                                                          6.3, 7, 9
 
                                                  * * * * * * *
----------------------------------------------------------------------------------------------------------------

    (e) * * *

                                Table 2--Attainment, Maintenance, and Other Plans
----------------------------------------------------------------------------------------------------------------
                                  Applicable geographic        State
     Name of SIP provision        or nonattainment area   submittal date  EPA approval date        Comments
----------------------------------------------------------------------------------------------------------------
 
                                                  * * * * * * *
Regional Haze State              Statewide..............         5/14/15  2/16/16 [Insert    ...................
 Implementation Plan--BP Cherry                                            Federal Register
 Point Refinery BART Revision.                                             citation].
----------------------------------------------------------------------------------------------------------------

[FR Doc. 2016-02953 Filed 2-12-16; 8:45 am]
 BILLING CODE 6560-50-P



                                                7710                 Federal Register / Vol. 81, No. 30 / Tuesday, February 16, 2016 / Rules and Regulations

                                                PART 52—APPROVAL AND                                                 Authority: 42 U.S.C. 7401 et seq.                        § 52.820   Identification of plan.
                                                PROMULGATION OF                                                                                                               *       *    *       *    *
                                                IMPLEMENTATION PLANS                                             Subpart Q—Iowa
                                                                                                                                                                                  (c) * * *
                                                ■ 1. The authority citation for part 52                          ■ 2. Amend § 52.820(c) by revising entry
                                                continues to read as follows:                                    567–21.1 to read as follows:

                                                                                                                     EPA-APPROVED IOWA REGULATIONS
                                                                                                                                                                State effective
                                                         Iowa citation                                                   Title                                                        EPA Approval date            Explanation
                                                                                                                                                                     date

                                                                                       Iowa Department of Natural Resources Environmental Protection Commission [567]


                                                            *                            *                           *                         *                        *                      *                     *

                                                                                                                                 Chapter 21—Compliance

                                                567–21.1 ...........................    Compliance Schedule .................................................         10/15/08    02/16/16 and [Insert Fed-
                                                                                                                                                                                    eral Register citation].

                                                            *                            *                           *                         *                        *                      *                     *



                                                *       *       *        *       *                               All documents in the docket are listed                       this proposed rule ended on December
                                                [FR Doc. 2016–02957 Filed 2–12–16; 8:45 am]                      on the http://www.regulations.gov Web                        16, 2015. The EPA received one
                                                BILLING CODE 6560–50–P                                           site. Although listed in the index, some                     comment in support of this action and
                                                                                                                 information may not be publicly                              no adverse comments.
                                                                                                                 available, i.e., Confidential Business                       II. Final Action
                                                ENVIRONMENTAL PROTECTION                                         Information or other information the
                                                AGENCY                                                           disclosure of which is restricted by                            The EPA is approving the BART
                                                                                                                 statute. Certain other material, such as                     alternative measure for the BP Cherry
                                                40 CFR Part 52                                                   copyrighted material, is not placed on                       Point Refinery located near Ferndale,
                                                [EPA–R10–OAR–2015–0398; FRL–9942–15–                             the Internet and is publicly available                       Washington by incorporating by
                                                Region 10]                                                       only in hard copy form. Publicly                             reference the conditions of Revision 2
                                                                                                                 available docket materials are available                     identified below. The EPA is removing
                                                Approval of Regional Haze BART                                   at http://www.regulations.gov or at EPA                      the BP Cherry Point Refinery, BART
                                                Alternative Measure: Washington                                  Region 10, Office of Air, Waste and                          Compliance Order No. 7836 currently in
                                                AGENCY:  Environmental Protection                                Toxics, 1200 Sixth Avenue, Seattle,                          the Federally approved SIP at 40 CFR
                                                Agency (EPA).                                                    Washington 98101. The EPA requests                           52.2470(d) and replacing it with
                                                                                                                 that you contact the person listed in the                    provisions of the BP Cherry Point
                                                ACTION: Final rule.
                                                                                                                 FOR FURTHER INFORMATION CONTACT                              Refinery, BART Compliance Order No.
                                                SUMMARY:    The Environmental Protection                         section to schedule your inspection. The                     7836 Revision 2. The EPA is also
                                                Agency (EPA) is taking final action to                           Regional Office’s official hours of                          approving new Condition 9 of the BART
                                                approve the Best Available Retrofit                              business are Monday through Friday,                          Compliance Order 7836 Revision 2
                                                Technology (BART) alternative measure                            8:30 to 4:30, excluding Federal holidays.                    relating to decommissioned units. The
                                                for the BP Cherry Point Refinery located                                                                                      conditions of the BP BART Compliance
                                                                                                                 FOR FURTHER INFORMATION CONTACT: For
                                                near Ferndale, Washington. The BART                                                                                           Order Revision 2 that are proposed for
                                                                                                                 information please contact John Chi at
                                                alternative measure increases the oxides                                                                                      incorporation by reference are:
                                                                                                                 (206) 553–1185, or chi.john@epa.gov.                            Condition 1: 1.1, 1.1.1, 1.2, 1.2.1,
                                                of nitrogen (NOX) emission limit from
                                                the R–1 HC Reactor Heater (R–1 Heater),                          SUPPLEMENTARY INFORMATION:                                   1.2.2;
                                                a BART-eligible source currently subject                                                                                         Condition 2: 2.1, 2.1.1, 2.1.2, 2.1.3,
                                                                                                                 Table of Contents
                                                to BART emission limits on NOX. To                                                                                            2.1.4, 2.1.5, 2.2, 2.2.1, 2.2.2, 2.3, 2.3.1,
                                                offset the increase in NOX emissions                             I. Background Information                                    2.3.2, 2.4, 2.4.1, 2.4.2, 2.4.2.1, 2.5, 2.5.1,
                                                from this emission unit, the NOX                                 II. Final Action                                             2.5.1.1, 2.5.1.2, 2.5.2, 2.5.3, 2.5.4, 2.6,
                                                emission limits on the 1st Stage                                 III. Incorporation by Reference                              2.6.1, 2.6.2, 2.6.3, 2.7, 2.7.1, 2.7.2, 2.7.3,
                                                Hydrocracker Fractionator Reboiler (R–                           IV. Statutory and Executive Orders Review                    2.7.4, 2.8, 2.8.1, 2.8.2,2.8.3, 2.8.4, 2.8.5,
                                                1 Reboiler), also a BART-eligible source                                                                                      2.8.6;
                                                subject to BART emission limits on                               I. Background Information                                       Condition 3, 3.1, 3.1.1, 3.1.2, 3.2,
                                                NOX, will be reduced. The net effect of                            On May 14, 2015, Washington                                3.2.1, 3.2.2, 3.2.3, 3.2.4;
                                                these changes is a decrease of 10.4 tons                                                                                         Condition 4, 4.1, 4.1.1, 4.1.1.1, 4.1.1.2,
                                                                                                                 submitted the BART alternative measure
                                                per year (tpy) of allowable NOX                                                                                               4.1.1.3, 4.1.1.4;
                                                                                                                 and the EPA proposed to approve it on                           Condition 5, 5.1, 5.2;
mstockstill on DSK4VPTVN1PROD with RULES




                                                emissions from sources subject to BART                           November 16, 2015 (80 FR 70718). An
                                                at the BP Cherry Point Refinery.                                                                                                 Condition 6, 6.1, 6.2, 6.3;
                                                                                                                 explanation of the CAA requirements, a                          Condition 7; and
                                                DATES: This final rule is effective March                        detailed analysis of the submittal, and                         Condition 9.
                                                17, 2016.                                                        the EPA’s reasons for approval were
                                                ADDRESSES: The EPA has established a                             provided in the notice of proposed                           III. Incorporation by Reference
                                                docket for this action under Docket ID                           rulemaking, and will not be restated                            In accordance with requirements of 1
                                                No. EPA–EPA–R10–OAR–2015–0398.                                   here. The public comment period for                          CFR 51.5, the EPA is revising our


                                           VerDate Sep<11>2014      17:32 Feb 12, 2016       Jkt 238001   PO 00000       Frm 00016   Fmt 4700      Sfmt 4700    E:\FR\FM\16FER1.SGM   16FER1


                                                                 Federal Register / Vol. 81, No. 30 / Tuesday, February 16, 2016 / Rules and Regulations                                              7711

                                                incorporation by reference located in 40                small entities under the Regulatory                   ‘‘major rule’’ as defined by 5 U.S.C.
                                                CFR 52.2470(d)—‘‘EPA-Approved State                     Flexibility Act (5 U.S.C. 601 et seq.);               804(2).
                                                Source-Specific Requirements’’ to                          • does not contain any unfunded mandate               Under section 307(b)(1) of the CAA,
                                                reflect the approval of the BART                        or significantly or uniquely affect small             petitions for judicial review of this
                                                                                                        governments, as described in the Unfunded
                                                alternative measure for the BP Cherry                   Mandates Reform Act of 1995 (Public Law
                                                                                                                                                              action must be filed in the United States
                                                Point Refinery and the provision                        104–4);                                               Court of Appeals for the appropriate
                                                relating to decommissioned units. Due                      • does not have Federalism implications as         circuit by April 18, 2016. Filing a
                                                to the fact that the conditions in the                  specified in Executive Order 13132 (64 FR             petition for reconsideration by the
                                                original BART Order were renumbered                     43255, August 10, 1999);                              Administrator of this final rule does not
                                                in Revision 1, which was not submitted                     • is not an economically significant               affect the finality of this action for the
                                                as a SIP revision, the EPA is removing                  regulatory action based on health or safety           purposes of judicial review nor does it
                                                the original IBR entry for ‘‘BP Cherry                  risks subject to Executive Order 13045 (62 FR         extend the time within which a petition
                                                Point Refinery’’ in its entirety and                    19885, April 23, 1997);                               for judicial review may be filed, and
                                                                                                           • is not a significant regulatory action
                                                incorporating in its place the specified                subject to Executive Order 13211 (66 FR
                                                                                                                                                              shall not postpone the effectiveness of
                                                conditions of Revision 2 included in the                28355, May 22, 2001);                                 such rule or action. This action may not
                                                docket for this action. The end result is                  • is not subject to requirements of Section        be challenged later in proceedings to
                                                that all of the conditions in the Original              12(d) of the National Technology Transfer             enforce its requirements. See section
                                                BART order remain in the SIP (but with                  and Advancement Act of 1995 (15 U.S.C. 272            307(b)(2).
                                                different numbers) except as discussed                  note) because this action does not involve
                                                                                                        technical standards; and                              List of Subjects in 40 CFR Part 52
                                                in the notice of the proposed
                                                rulemaking with respect to the BART                        • does not provide the EPA with the                  Environmental protection, Air
                                                alternative measure and the addition of                 discretionary authority to address, as                pollution control, Incorporation by
                                                                                                        appropriate, disproportionate human health            reference, Nitrogen dioxide, Ozone,
                                                Condition 9. The EPA has made, and                      or environmental effects, using practicable
                                                will continue to make, these documents                  and legally permissible methods, under
                                                                                                                                                              Particulate matter, Reporting and
                                                generally available electronically                      Executive Order 12898 (59 FR 7629, February           recordkeeping requirements, Sulfur
                                                through www.regulations.gov and/or in                   16, 1994).                                            oxides, Volatile organic compounds.
                                                hard copy at the appropriate EPA office                                                                         Dated: January 27, 2016.
                                                (see the ADDRESSES section of this                         The SIP is not approved to apply on
                                                                                                        any Indian reservation land in                        Dennis J. McLerran,
                                                preamble for more information).                                                                               Regional Administrator, Region 10.
                                                                                                        Washington except as specifically noted
                                                IV. Statutory and Executive Orders                      below and is also not approved to apply                 For the reasons set forth in the
                                                Review                                                  in any other area where the EPA or an                 preamble, 40 CFR part 52 is amended as
                                                                                                        Indian tribe has demonstrated that a                  follows:
                                                  Under the CAA, the Administrator is                   tribe has jurisdiction. In those areas of
                                                required to approve a SIP submission                    Indian country, the rule does not have                PART 52—APPROVAL AND
                                                that complies with the provisions of the                tribal implications as specified by                   PROMULGATION OF
                                                CAA and applicable Federal regulations.                 Executive Order 13175 (65 FR 67249,                   IMPLEMENTATION PLANS
                                                42 U.S.C. 7410(k); 40 CFR 52.02(a).                     November 9, 2000).
                                                Thus, in reviewing SIP submissions, the                                                                       ■ 1. The authority citation for part 52
                                                EPA’s role is to approve state choices,                    The Congressional Review Act, 5                    continues to read as follows:
                                                provided that they meet the criteria of                 U.S.C. 801 et seq., as added by the Small
                                                                                                        Business Regulatory Enforcement                           Authority: 42 U.S.C. 7401 et seq.
                                                the CAA. Accordingly, this action
                                                merely approves state law as meeting                    Fairness Act of 1996, generally provides              Subpart WW—Washington
                                                Federal requirements and does not                       that before a rule may take effect, the
                                                impose additional requirements beyond                   agency promulgating the rule must                     ■ 2. In § 52.2470:
                                                those imposed by state law. For that                    submit a rule report, which includes a                ■ a. In paragraph (d), the table is
                                                reason, this action:                                    copy of the rule, to each House of the                amended by revising the entry for ‘‘BP
                                                                                                        Congress and to the Comptroller General               Cherry Point Refinery.’’
                                                  • Is not a ‘‘significant regulatory action’’          of the United States. The EPA will                    ■ b. In paragraph (e), table 2 is amended
                                                subject to review by the Office of                      submit a report containing this action
                                                Management and Budget under Executive
                                                                                                                                                              by adding an entry entitled ‘‘Regional
                                                                                                        and other required information to the                 Haze State Implementation Plan—BP
                                                Orders 12866 (58 FR 51735, October 4, 1993)
                                                                                                        U.S. Senate, the U.S. House of                        Cherry Point Refinery BART Revision’’
                                                and 13563 (76 FR 3821, January 21, 2011);
                                                  • does not impose an information
                                                                                                        Representatives, and the Comptroller                  to the end of the table.
                                                collection burden under the provisions of the           General of the United States prior to                   The revisions read as follows:
                                                Paperwork Reduction Act (44 U.S.C. 3501 et              publication of the rule in the Federal
                                                seq.);                                                  Register. A major rule cannot take effect             § 52.2470    Identification of plan.
                                                  • is certified as not having a significant            until 60 days after it is published in the            *       *    *      *     *
                                                economic impact on a substantial number of              Federal Register. This action is not a                    (d) * * *
mstockstill on DSK4VPTVN1PROD with RULES




                                           VerDate Sep<11>2014   17:32 Feb 12, 2016   Jkt 238001   PO 00000   Frm 00017   Fmt 4700   Sfmt 4700   E:\FR\FM\16FER1.SGM   16FER1


                                                7712             Federal Register / Vol. 81, No. 30 / Tuesday, February 16, 2016 / Rules and Regulations

                                                                              EPA-APPROVED STATE OF WASHINGTON SOURCE-SPECIFIC REQUIREMENTS
                                                                                                                     State effective
                                                     Name of source             Order/Permit number                                                EPA approval date                                 Explanation
                                                                                                                          date


                                                        *                       *                    *                                         *                     *                          *                     *
                                                BP Cherry Point Refin-        Administrative Order                             5/13/15        2/16/16 [Insert Federal         The following conditions: 1.1, 1.1.1, 1.2, 1.2.1,
                                                 ery.                           No. 7836, Revision 2.                                            Register citation].            1.2.2, 2.1, 2.1.1, 2.1.2, 2.1.3, 2.1.4, 2.1.5,
                                                                                                                                                                                2.2, 2.2.1, 2.2.2, 2.3, 2.3.1, 2.3.2, 2.4, 2.4.1,
                                                                                                                                                                                2.4.2, 2.4.2.1, 2.5, 2.5.1, 2.5.1.1, 2.5.1.2,
                                                                                                                                                                                2.5.2, 2.5.3, 2.5.4, 2.6, 2.6.1, 2.6.2, 2.6.3,
                                                                                                                                                                                2.7, 2.7.1, 2.7.2, 2.7.3, 2.7.4, 2.8, 2.8.1,
                                                                                                                                                                                2.8.2,2.8.3, 2.8.4, 2.8.5, 2.8.6, 3, 3.1, 3.1.1,
                                                                                                                                                                                3.1.2, 3.2, 3.2.1, 3.2.2, 3.2.3, 3.2.4, 4, 4.1,
                                                                                                                                                                                4.1.1, 4.1.1.1, 4.1.1.2, 4.1.1.3, 4.1.1.4, 5, 5.1,
                                                                                                                                                                                5.2, 6, 6.1, 6.2, 6.3, 7, 9

                                                          *                       *                              *                             *                          *                      *                    *



                                                   (e) * * *
                                                                                             TABLE 2—ATTAINMENT, MAINTENANCE, AND OTHER PLANS
                                                                                                                                                                  State submittal
                                                   Name of SIP provision               Applicable geographic or nonattainment area                                                      EPA approval date           Comments
                                                                                                                                                                       date


                                                         *                        *                          *                                 *                          *                     *                     *
                                                Regional Haze State Im-          Statewide ....................................................................          5/14/15    2/16/16 [Insert Federal
                                                  plementation Plan—BP                                                                                                                Register citation].
                                                  Cherry Point Refinery
                                                  BART Revision.



                                                [FR Doc. 2016–02953 Filed 2–12–16; 8:45 am]                   rule, the suspension will not occur and                          insurance unless an appropriate public
                                                BILLING CODE 6560–50–P                                        a notice of this will be provided by                             body adopts adequate floodplain
                                                                                                              publication in the Federal Register on a                         management measures with effective
                                                                                                              subsequent date. Also, information                               enforcement measures. The
                                                DEPARTMENT OF HOMELAND                                        identifying the current participation                            communities listed in this document no
                                                SECURITY                                                      status of a community can be obtained                            longer meet that statutory requirement
                                                                                                              from FEMA’s Community Status Book                                for compliance with program
                                                Federal Emergency Management                                  (CSB). The CSB is available at http://                           regulations, 44 CFR part 59.
                                                Agency                                                        www.fema.gov/fema/csb.shtm.                                      Accordingly, the communities will be
                                                                                                              DATES: The effective date of each                                suspended on the effective date in the
                                                44 CFR Part 64                                                community’s scheduled suspension is                              third column. As of that date, flood
                                                                                                              the third date (‘‘Susp.’’) listed in the                         insurance will no longer be available in
                                                [Docket ID FEMA–2015–0001; Internal
                                                                                                              third column of the following tables.                            the community. We recognize that some
                                                Agency Docket No. FEMA–8419]
                                                                                                                                                                               of these communities may adopt and
                                                                                                              FOR FURTHER INFORMATION CONTACT: If
                                                Suspension of Community Eligibility                                                                                            submit the required documentation of
                                                                                                              you want to determine whether a                                  legally enforceable floodplain
                                                AGENCY:  Federal Emergency                                    particular community was suspended                               management measures after this rule is
                                                Management Agency, DHS.                                       on the suspension date or for further                            published but prior to the actual
                                                                                                              information, contact Patricia Suber,                             suspension date. These communities
                                                ACTION: Final rule.
                                                                                                              Federal Insurance and Mitigation                                 will not be suspended and will continue
                                                SUMMARY:   This rule identifies                               Administration, Federal Emergency                                to be eligible for the sale of NFIP flood
                                                communities where the sale of flood                           Management Agency, 500 C Street SW.,                             insurance. A notice withdrawing the
                                                insurance has been authorized under                           Washington, DC 20472, (202) 646–4149.                            suspension of such communities will be
                                                the National Flood Insurance Program                          SUPPLEMENTARY INFORMATION: The NFIP                              published in the Federal Register.
                                                (NFIP) that are scheduled for                                 enables property owners to purchase                                 In addition, FEMA publishes a Flood
                                                suspension on the effective dates listed                      Federal flood insurance that is not                              Insurance Rate Map (FIRM) that
                                                within this rule because of                                   otherwise generally available from                               identifies the Special Flood Hazard
                                                noncompliance with the floodplain                             private insurers. In return, communities                         Areas (SFHAs) in these communities.
mstockstill on DSK4VPTVN1PROD with RULES




                                                management requirements of the                                agree to adopt and administer local                              The date of the FIRM, if one has been
                                                program. If the Federal Emergency                             floodplain management measures aimed                             published, is indicated in the fourth
                                                Management Agency (FEMA) receives                             at protecting lives and new construction                         column of the table. No direct Federal
                                                documentation that the community has                          from future flooding. Section 1315 of                            financial assistance (except assistance
                                                adopted the required floodplain                               the National Flood Insurance Act of                              pursuant to the Robert T. Stafford
                                                management measures prior to the                              1968, as amended, 42 U.S.C. 4022,                                Disaster Relief and Emergency
                                                effective suspension date given in this                       prohibits the sale of NFIP flood                                 Assistance Act not in connection with a


                                           VerDate Sep<11>2014   17:32 Feb 12, 2016   Jkt 238001      PO 00000       Frm 00018      Fmt 4700       Sfmt 4700      E:\FR\FM\16FER1.SGM   16FER1



Document Created: 2016-02-13 03:13:32
Document Modified: 2016-02-13 03:13:32
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionRules and Regulations
ActionFinal rule.
DatesThis final rule is effective March 17, 2016.
ContactFor information please contact John Chi at (206) 553-1185, or [email protected]
FR Citation81 FR 7710 
CFR AssociatedEnvironmental Protection; Air Pollution Control; Incorporation by Reference; Nitrogen Dioxide; Ozone; Particulate Matter; Reporting and Recordkeeping Requirements; Sulfur Oxides and Volatile Organic Compounds

2025 Federal Register | Disclaimer | Privacy Policy
USC | CFR | eCFR