81_FR_7865 81 FR 7835 - Atomic Safety And Licensing Board; Before Administrative Judges: Paul S. Ryerson, Chairman, Dr. Gary S. Arnold, Dr. Craig M. White; In the Matter of PSEG Power, LLC and PSEG Nuclear, LLC (Early Site Permit Application); Notice of Hearing

81 FR 7835 - Atomic Safety And Licensing Board; Before Administrative Judges: Paul S. Ryerson, Chairman, Dr. Gary S. Arnold, Dr. Craig M. White; In the Matter of PSEG Power, LLC and PSEG Nuclear, LLC (Early Site Permit Application); Notice of Hearing

NUCLEAR REGULATORY COMMISSION

Federal Register Volume 81, Issue 30 (February 16, 2016)

Page Range7835-7835
FR Document2016-03054

Federal Register, Volume 81 Issue 30 (Tuesday, February 16, 2016)
[Federal Register Volume 81, Number 30 (Tuesday, February 16, 2016)]
[Notices]
[Page 7835]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2016-03054]


-----------------------------------------------------------------------

NUCLEAR REGULATORY COMMISSION

[Docket No. 52-043-ESP; ASLBP No. 15-943-01-ESP-BD01]


Atomic Safety And Licensing Board; Before Administrative Judges: 
Paul S. Ryerson, Chairman, Dr. Gary S. Arnold, Dr. Craig M. White; In 
the Matter of PSEG Power, LLC and PSEG Nuclear, LLC (Early Site Permit 
Application); Notice of Hearing

February 8, 2016.
    The Atomic Safety and Licensing Board gives notice that, pursuant 
to section 189a(1)(A) of the Atomic Energy Act, 42 U.S.C. 
2239(a)(1)(A), and 10 CFR 52.21, it will convene an uncontested 
mandatory hearing on March 24, 2016 to receive testimony and exhibits 
regarding an application from PSEG Power, LLC and PSEG Nuclear, LLC 
(collectively PSEG) for a 10 CFR part 52, subpart A Early Site Permit 
(ESP).\1\ In its ESP application, PSEG proposes a site for a potential 
nuclear power facility adjacent to two existing facilities in Salem 
County, New Jersey (the PSEG Site).\2\ This mandatory hearing will 
concern safety and environmental matters relating to the proposed 
issuance of the requested ESP.\3\
---------------------------------------------------------------------------

    \1\ See 75 FR 68,624, 68,624 (Nov. 8, 2010).
    \2\ The existing nuclear power facilities are Salem Generating 
Station Units 1 and 2 and Hope Creek Generating Station Unit 1. 
Safety Evaluation of the Early Site Permit Application in the Matter 
of PSEG Power, LLC and PSEG Nuclear, LLC for the PSEG Early Site 
Permit Site (Sept. 29, 2015) at 1-1 (ADAMS Accession No. 
ML14302A447).
    \3\ See Licensing Board Order (Initial Scheduling Order) (Nov. 
16, 2015) at Attach. A (unpublished).
---------------------------------------------------------------------------

I. Hearing Date, Time, and Location

    The evidentiary hearing will commence on Thursday, March 24, 2016 
at 9:00 a.m. EDT, and, if necessary, will continue day-to-day 
thereafter until concluded. The evidentiary hearing will take place in 
the Atomic Safety and Licensing Board Panel's hearing room, located 
within the Nuclear Regulatory Commission's headquarters at 11555 
Rockville Pike, Rockville, Maryland 20852. Members of the public who 
wish to observe the mandatory hearing are advised to arrive early. 
Security measures will include searches of handcarried items such as 
briefcases or backpacks.

II. Limited Appearance Statements

    No petition was received in response to the NRC's notice in the 
Federal Register of an opportunity to seek to intervene.\4\ 
Participation in the evidentiary hearing will be limited to the 
designated witnesses and counsel for the parties.
---------------------------------------------------------------------------

    \4\ See 75 FR 68,625.
---------------------------------------------------------------------------

    Prior to the evidentiary hearing, any person (other than a party or 
the representative of a party to this proceeding) may nonetheless 
submit a written limited appearance statement pursuant to 10 CFR 
2.315(a) that sets forth a position on matters related to this 
proceeding. Limited appearance statements should be emailed to 
[email protected]. As provided by NRC regulations, however, no 
limited appearance statement shall be considered as evidence.\5\
---------------------------------------------------------------------------

    \5\ 10 CFR 2.315(a).
---------------------------------------------------------------------------

III. Document Availability

    Documents relating to this proceeding (including any updated or 
revised scheduling information regarding the evidentiary hearing) are 
available for public inspection electronically on the NRC's Electronic 
Hearing Docket (EHD). EHD is accessible from the NRC Web site at 
https://adams.nrc.gov/ehd. For additional information regarding the EHD 
please see http://www.nrc.gov/about-nrc/regulatory/adjudicatory.html#ehd. Persons who do not have access to the internet 
or who encounter problems in accessing the documents located on the 
NRC's Web site may contact the NRC Public Document Room reference staff 
by email to [email protected] or by telephone at (800) 397-4209 or (301) 415-
4737. Reference staff are available Monday through Friday between 8:00 
a.m. and 4:00 p.m. ET, except federal holidays. For additional 
information regarding the NRC Public Document Room please see http://www.nrc.gov/reading-rm/pdr.html.
    It is so ordered.

    For The Atomic Safety and Licensing Board. Rockville, Maryland.

    Dated: February 8, 2016.
Paul S. Ryerson,
Chairman, Administrative Judge.
[FR Doc. 2016-03054 Filed 2-12-16; 8:45 am]
 BILLING CODE 7590-01-P



                                                                                 Federal Register / Vol. 81, No. 30 / Tuesday, February 16, 2016 / Notices                                                 7835

                                                  Lodge Project, which includes a mine                      to two existing facilities in Salem                   adjudicatory.html#ehd. Persons who do
                                                  for the purpose of extracting rare earth                  County, New Jersey (the PSEG Site).2                  not have access to the internet or who
                                                  element ores in the Black Hills National                  This mandatory hearing will concern                   encounter problems in accessing the
                                                  Forest in Crook County, Wyoming and                       safety and environmental matters                      documents located on the NRC’s Web
                                                  a rare earth element processing plant in                  relating to the proposed issuance of the              site may contact the NRC Public
                                                  Weston County, Wyoming. In response                       requested ESP.3                                       Document Room reference staff by email
                                                  to a notice filed in the Federal Register,                I. Hearing Date, Time, and Location                   to pdr@nrc.gov or by telephone at (800)
                                                  see 80 FR 70,846 (Nov. 16, 2015), the                                                                           397–4209 or (301) 415–4737. Reference
                                                  Defenders of the Black Hills filed a                         The evidentiary hearing will                       staff are available Monday through
                                                  Request for a Hearing dated January 14,                   commence on Thursday, March 24,                       Friday between 8:00 a.m. and 4:00 p.m.
                                                  2016, and received by Office of the                       2016 at 9:00 a.m. EDT, and, if necessary,             ET, except federal holidays. For
                                                  Secretary on January 15, 2016.                            will continue day-to-day thereafter until             additional information regarding the
                                                     The Board is comprised of the                          concluded. The evidentiary hearing will               NRC Public Document Room please see
                                                  following Administrative Judges:                          take place in the Atomic Safety and                   http://www.nrc.gov/reading-rm/
                                                  William J. Froehlich, Chair, Atomic                       Licensing Board Panel’s hearing room,                 pdr.html.
                                                     Safety and Licensing Board Panel,                      located within the Nuclear Regulatory                    It is so ordered.
                                                     U.S. Nuclear Regulatory Commission,                    Commission’s headquarters at 11555
                                                                                                                                                                    For The Atomic Safety and Licensing
                                                     Washington, DC 20555–0001                              Rockville Pike, Rockville, Maryland
                                                                                                                                                                  Board. Rockville, Maryland.
                                                  G. Paul Bollwerk, III, Atomic Safety and                  20852. Members of the public who wish
                                                                                                                                                                    Dated: February 8, 2016.
                                                     Licensing Board Panel, U.S. Nuclear                    to observe the mandatory hearing are
                                                                                                            advised to arrive early. Security                     Paul S. Ryerson,
                                                     Regulatory Commission, Washington,
                                                                                                            measures will include searches of                     Chairman, Administrative Judge.
                                                     DC 20555–0001
                                                  Nicholas G. Trikouros, Atomic Safety                      handcarried items such as briefcases or               [FR Doc. 2016–03054 Filed 2–12–16; 8:45 am]
                                                     and Licensing Board Panel, U.S.                        backpacks.                                            BILLING CODE 7590–01–P

                                                     Nuclear Regulatory Commission,                         II. Limited Appearance Statements
                                                     Washington, DC 20555–0001
                                                                                                               No petition was received in response               NUCLEAR REGULATORY
                                                     All correspondence, documents, and                     to the NRC’s notice in the Federal                    COMMISSION
                                                  other materials shall be filed in                         Register of an opportunity to seek to
                                                  accordance with the NRC E-Filing rule.                                                                          [NRC–2016–0026]
                                                                                                            intervene.4 Participation in the
                                                  See 10 CFR 2.302.                                         evidentiary hearing will be limited to                Biweekly Notice; Applications and
                                                  Rockville, Maryland.                                      the designated witnesses and counsel                  Amendments to Facility Operating
                                                    Dated: February 9, 2016.                                for the parties.                                      Licenses and Combined Licenses
                                                  E. Roy Hawkens,                                              Prior to the evidentiary hearing, any              Involving No Significant Hazards
                                                  Chief Administrative Judge, Atomic Safety                 person (other than a party or the                     Considerations
                                                  and Licensing Board Panel.                                representative of a party to this
                                                  [FR Doc. 2016–03055 Filed 2–12–16; 8:45 am]               proceeding) may nonetheless submit a                  AGENCY:  Nuclear Regulatory
                                                  BILLING CODE 7590–01–P
                                                                                                            written limited appearance statement                  Commission.
                                                                                                            pursuant to 10 CFR 2.315(a) that sets                 ACTION: Biweekly notice.
                                                                                                            forth a position on matters related to
                                                                                                            this proceeding. Limited appearance                   SUMMARY:   Pursuant to Section 189a. (2)
                                                  NUCLEAR REGULATORY
                                                                                                            statements should be emailed to                       of the Atomic Energy Act of 1954, as
                                                  COMMISSION
                                                                                                            hearing.docket@nrc.gov. As provided by                amended (AEA), the U.S. Nuclear
                                                  [Docket No. 52–043–ESP; ASLBP No. 15–                     NRC regulations, however, no limited                  Regulatory Commission (NRC) is
                                                  943–01–ESP–BD01]                                          appearance statement shall be                         publishing this regular biweekly notice.
                                                                                                            considered as evidence.5                              The Act requires the Commission to
                                                  Atomic Safety And Licensing Board;                                                                              publish notice of any amendments
                                                  Before Administrative Judges: Paul S.                     III. Document Availability                            issued, or proposed to be issued, and
                                                  Ryerson, Chairman, Dr. Gary S. Arnold,                       Documents relating to this proceeding              grants the Commission the authority to
                                                  Dr. Craig M. White; In the Matter of                      (including any updated or revised                     issue and make immediately effective
                                                  PSEG Power, LLC and PSEG Nuclear,                         scheduling information regarding the                  any amendment to an operating license
                                                  LLC (Early Site Permit Application);                      evidentiary hearing) are available for                or combined license, as applicable,
                                                  Notice of Hearing                                         public inspection electronically on the               upon a determination by the
                                                  February 8, 2016.                                         NRC’s Electronic Hearing Docket (EHD).                Commission that such amendment
                                                    The Atomic Safety and Licensing                         EHD is accessible from the NRC Web                    involves no significant hazards
                                                  Board gives notice that, pursuant to                      site at https://adams.nrc.gov/ehd. For                consideration, notwithstanding the
                                                  section 189a(1)(A) of the Atomic Energy                   additional information regarding the                  pendency before the Commission of a
                                                  Act, 42 U.S.C. 2239(a)(1)(A), and 10 CFR                  EHD please see http://www.nrc.gov/                    request for a hearing from any person.
                                                  52.21, it will convene an uncontested                     about-nrc/regulatory/                                    This biweekly notice includes all
                                                  mandatory hearing on March 24, 2016 to                                                                          notices of amendments issued, or
                                                  receive testimony and exhibits regarding
                                                                                                              2 The existing nuclear power facilities are Salem
                                                                                                                                                                  proposed to be issued from January 16,
                                                                                                            Generating Station Units 1 and 2 and Hope Creek       2016, to February 1, 2016. The last
mstockstill on DSK4VPTVN1PROD with NOTICES




                                                  an application from PSEG Power, LLC                       Generating Station Unit 1. Safety Evaluation of the
                                                  and PSEG Nuclear, LLC (collectively                       Early Site Permit Application in the Matter of PSEG
                                                                                                                                                                  biweekly notice was published on
                                                  PSEG) for a 10 CFR part 52, subpart A                     Power, LLC and PSEG Nuclear, LLC for the PSEG         February 2, 2016.
                                                                                                            Early Site Permit Site (Sept. 29, 2015) at 1–1        DATES: Comments must be filed by
                                                  Early Site Permit (ESP).1 In its ESP                      (ADAMS Accession No. ML14302A447).
                                                  application, PSEG proposes a site for a                     3 See Licensing Board Order (Initial Scheduling
                                                                                                                                                                  March 17, 2016. A request for a hearing
                                                  potential nuclear power facility adjacent                 Order) (Nov. 16, 2015) at Attach. A (unpublished).    must be filed by April 18, 2016.
                                                                                                              4 See 75 FR 68,625.                                 ADDRESSES: You may submit comments
                                                    1 See   75 FR 68,624, 68,624 (Nov. 8, 2010).              5 10 CFR 2.315(a).                                  by any of the following methods (unless


                                             VerDate Sep<11>2014     22:15 Feb 12, 2016   Jkt 238001   PO 00000   Frm 00094   Fmt 4703   Sfmt 4703   E:\FR\FM\16FEN1.SGM   16FEN1



Document Created: 2016-02-13 03:13:11
Document Modified: 2016-02-13 03:13:11
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation81 FR 7835 

2025 Federal Register | Disclaimer | Privacy Policy
USC | CFR | eCFR