81_FR_91401 81 FR 91159 - Northern Natural Gas Company; Notice of Availability of the Environmental Assessment for the Proposed Cedar Station Upgrade Project

81 FR 91159 - Northern Natural Gas Company; Notice of Availability of the Environmental Assessment for the Proposed Cedar Station Upgrade Project

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 81, Issue 242 (December 16, 2016)

Page Range91159-91160
FR Document2016-30207

Federal Register, Volume 81 Issue 242 (Friday, December 16, 2016)
[Federal Register Volume 81, Number 242 (Friday, December 16, 2016)]
[Notices]
[Pages 91159-91160]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2016-30207]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP16-487-000]


Northern Natural Gas Company; Notice of Availability of the 
Environmental Assessment for the Proposed Cedar Station Upgrade Project

    The staff of the Federal Energy Regulatory Commission (FERC or 
Commission) has prepared an environmental assessment (EA) for the Cedar 
Station Upgrade Project, proposed by Northern Natural Gas Company 
(Northern) in the above-referenced docket. Northern requests 
authorization to construct approximately 7.86 miles of natural gas 
pipeline in Dakota County, Minnesota in order to fulfill its 
contractual obligation with Northern States Power Company, a Minnesota 
Corporation (NSP-MN) to increase the delivery pressure to NSP-MN's 
existing Black Dog Generating Station from 400 pounds per square inch 
gauge (psig) to 650 psig. As part of NSP-MN's process

[[Page 91160]]

of reducing its carbon footprint, it has increased its use of natural 
gas-fired generation.
    The EA assesses the potential environmental effects of the 
construction and operation of the Cedar Station Upgrade Project in 
accordance with the requirements of the National Environmental Policy 
Act (NEPA). The FERC staff concludes that approval of the proposed 
project, with appropriate mitigating measures, would not constitute a 
major federal action significantly affecting the quality of the human 
environment.
    The Cedar Station Upgrade Project includes the following 
facilities:
     Approximately 7.86 miles of new 20-inch-diameter pipeline 
loop; \1\
---------------------------------------------------------------------------

    \1\ A pipeline ``loop'' is a segment of pipe installed adjacent 
to an existing pipeline and connected to the existing pipeline at 
both ends.
---------------------------------------------------------------------------

     a new pig \2\ launcher and takeoff valve setting at 
Northern's existing Rosemount Junction facility; and
---------------------------------------------------------------------------

    \2\ A ``pig'' is an internal pipeline tool used to clean a 
pipeline and/or to inspect for damage or corrosion.
---------------------------------------------------------------------------

     a new pig receiver, tie-in valve setting, and modification 
of existing regulators and piping at Northern's existing Cedar Meter 
Station facility.
    The FERC staff mailed copies of the EA to federal, state, and local 
government representatives and agencies; elected officials; 
environmental and public interest groups; Native American tribes; 
potentially affected landowners and other interested individuals and 
groups; and newspapers and libraries in the project area. In addition, 
the EA is available for public viewing on the FERC's Web site 
(www.ferc.gov) using the eLibrary link. A limited number of copies of 
the EA are available for distribution and public inspection at: Federal 
Energy Regulatory Commission, Public Reference Room, 888 First Street 
NE., Room 2A, Washington, DC 20426, (202) 502-8371.
    Any person wishing to comment on the EA may do so. Your comments 
should focus on the potential environmental effects, reasonable 
alternatives, and measures to avoid or lessen environmental impacts. 
The more specific your comments, the more useful they will be. To 
ensure that the Commission has the opportunity to consider your 
comments prior to making its decision on this project, it is important 
that we receive your comments in Washington, DC on or before January 9, 
2017.
    For your convenience, there are three methods you can use to file 
your comments to the Commission. In all instances, please reference the 
project docket number (CP16-487-000) with your submission. The 
Commission encourages electronic filing of comments and has expert 
staff available to assist you at (202) 502-8258 or [email protected].
    (1) You can file your comments electronically using the eComment 
feature on the Commission's Web site (www.ferc.gov) under the link to 
Documents and Filings. This is an easy method for submitting brief, 
text-only comments on a project;
    (2) You can also file your comments electronically using the 
eFiling feature on the Commission's Web site (www.ferc.gov) under the 
link to Documents and Filings. With eFiling, you can provide comments 
in a variety of formats by attaching them as a file with your 
submission. New eFiling users must first create an account by clicking 
on ``eRegister.'' You must select the type of filing you are making. If 
you are filing a comment on a particular project, please select 
``Comment on a Filing''; or
    (3) You can file a paper copy of your comments by mailing them to 
the following address: Kimberly D. Bose, Secretary, Federal Energy 
Regulatory Commission, 888 First Street NE., Room 1A, Washington, DC 
20426.
    Any person seeking to become a party to the proceeding must file a 
motion to intervene pursuant to Rule 214 of the Commission's Rules of 
Practice and Procedures (18 CFR 385.214).\3\ Only intervenors have the 
right to seek rehearing of the Commission's decision. The Commission 
grants affected landowners and others with environmental concerns 
intervenor status upon showing good cause by stating that they have a 
clear and direct interest in this proceeding which no other party can 
adequately represent. Simply filing environmental comments will not 
give you intervenor status, but you do not need intervenor status to 
have your comments considered.
---------------------------------------------------------------------------

    \3\ See the previous discussion on the methods for filing 
comments.
---------------------------------------------------------------------------

    Additional information about the project is available from the 
Commission's Office of External Affairs, at (866) 208-FERC, or on the 
FERC Web site (www.ferc.gov) using the eLibrary link. Click on the 
eLibrary link, click on ``General Search,'' and enter the docket number 
excluding the last three digits in the Docket Number field (i.e., CP16-
487). Be sure you have selected an appropriate date range. For 
assistance, please contact FERC Online Support at 
[email protected] or toll free at (866) 208-3676, or for TTY, 
contact (202) 502-8659. The eLibrary link also provides access to the 
texts of formal documents issued by the Commission, such as orders, 
notices, and rulemakings.
    In addition, the Commission offers a free service called 
eSubscription which allows you to keep track of all formal issuances 
and submittals in specific dockets. This can reduce the amount of time 
you spend researching proceedings by automatically providing you with 
notification of these filings, document summaries, and direct links to 
the documents. Go to www.ferc.gov/docs-filing/esubscription.asp.

    Dated: December 9, 2016.
Kimberly D. Bose,
Secretary.
[FR Doc. 2016-30207 Filed 12-15-16; 8:45 am]
 BILLING CODE 6717-01-P



                                                                              Federal Register / Vol. 81, No. 242 / Friday, December 16, 2016 / Notices                                                91159

                                                  Commission’s Public Reference Room in                   Project Description                                   Additional Information
                                                  Washington, DC. There is an                                                                                      In order to receive notification of the
                                                  eSubscription link on the Web site that                   The Project would involve the
                                                                                                                                                                issuance of the EA and to keep track of
                                                  enables subscribers to receive email                    replacement of 26.2 miles of
                                                                                                                                                                all formal issuances and submittals in
                                                  notification when a document is added                   replacement pipeline and 3.1 miles of
                                                                                                                                                                specific dockets, the Commission offers
                                                  to a subscribed docket(s). For assistance               new pipeline composed of varying
                                                                                                                                                                a free service called eSubscription. This
                                                  with any FERC Online service, please                    diameters, two new compressor stations                can reduce the amount of time you
                                                  email FERCOnlineSupport@ferc.gov. or                    (one gas and one electric), expansions                spend researching proceedings by
                                                  call (866) 208–3676 (toll free). For TTY,               and modifications at seven existing gas               automatically providing you with
                                                  call (202) 502–8659.                                    compressor stations, and other minor                  notification of these filings, document
                                                    Comment Date: 5:00 p.m. Eastern time                  aboveground facilities in West Virginia               summaries, and direct links to the
                                                  on January 9, 2017.                                     and Virginia.                                         documents. Go to www.ferc.gov/docs-
                                                    Dated: December 12, 2016.                                                                                   filing/esubscription.asp.
                                                                                                          Background
                                                  Kimberly D. Bose,                                                                                                Additional information about the
                                                  Secretary.                                                 On July 22, 2015, the Commission                   Project is available from the
                                                  [FR Doc. 2016–30290 Filed 12–15–16; 8:45 am]            issued a Notice of Intent to Prepare an               Commission’s Office of External Affairs
                                                  BILLING CODE 6717–01–P                                  Environmental Assessment for the                      at (866) 208–FERC or on the FERC Web
                                                                                                          Proposed WB XPress Project and                        site (www.ferc.gov). Using the
                                                                                                          Request for Comments on                               ‘‘eLibrary’’ link, select ‘‘General Search’’
                                                  DEPARTMENT OF ENERGY                                    Environmental Issues (NOI). The NOI                   from the eLibrary menu, enter the
                                                                                                          was issued during the pre-filing review               selected date range and ‘‘Docket
                                                  Federal Energy Regulatory                                                                                     Number’’ excluding the last three digits
                                                  Commission                                              of the Project in Docket No. PF15–21–
                                                                                                          000 and was sent to affected                          (i.e., CP16–38), and follow the
                                                  [Docket No. CP16–38–000; PF15–21–000]                   landowners; federal, state, and local                 instructions. For assistance with access
                                                                                                                                                                to eLibrary, the helpline can be reached
                                                                                                          government agencies; elected officials;
                                                  Columbia Gas Transmission, LLC;                                                                               at (866) 208–3676, TTY (202) 502–8659,
                                                                                                          environmental and public interest
                                                  Notice of Schedule For Environmental                                                                          or at FERCOnlineSupport@ferc.gov. The
                                                                                                          groups; Native American tribes; other
                                                  Review of the WB XPress Project                                                                               eLibrary link on the FERC Web site also
                                                                                                          interested parties; and local libraries
                                                                                                                                                                provides access to the texts of formal
                                                     On December 30, 2015, Columbia Gas                   and newspapers. In response to the NOI,               documents issued by the Commission,
                                                  Transmission, LLC (Columbia) filed an                   the Commission received comments                      such as orders, notices, and rule
                                                  application in Docket No. CP16–38–000                   from Virginia and West Virginia state                 makings.
                                                  requesting a Certificate of Public                      agencies; Fairfax County, and five
                                                  Convenience and Necessity pursuant to                   landowners. After the NOI period                        Dated: December 9, 2016.
                                                  Section 7(c) of the Natural Gas Act to                  closed, we received additional                        Kimberly D. Bose,
                                                  construct and operate certain natural gas               comments from the U.S. Environmental                  Secretary.
                                                  pipeline facilities. The proposed project               Protection Agency (Region 3), U.S.                    [FR Doc. 2016–30206 Filed 12–15–16; 8:45 am]
                                                  is known as the WB XPress Project                       Forest Service, West Virginia                         BILLING CODE 6717–01–P
                                                  (Project), and would expand the                         Department of Natural Resources, Town
                                                  capacity of Columbia’s existing natural
                                                                                                          of Strasburg, Virginia, and organizations
                                                  gas pipeline system by 1.3 million                                                                            DEPARTMENT OF ENERGY
                                                                                                          such as the Dulles Regional Chamber of
                                                  dekatherms per day and provide bi-
                                                                                                          Commerce, the Southern Environmental                  Federal Energy Regulatory
                                                  directional transportation service in
                                                  order to meet growing market demands.                   Law Center, West Virginia Oil and Gas                 Commission
                                                     On January 14, 2016, the Federal                     Association, Virginia Run Community
                                                                                                          Association, Sierra Club et al.,                      [Docket No. CP16–487–000]
                                                  Energy Regulatory Commission
                                                  (Commission or FERC) issued its Notice                  Shenandoah Valley Network et al., Oil                 Northern Natural Gas Company; Notice
                                                  of Application for the Project. Among                   Change International et al., and 26                   of Availability of the Environmental
                                                  other things, that notice alerted agencies              interested individuals. The primary                   Assessment for the Proposed Cedar
                                                  issuing federal authorizations of the                   issues raised included the need for the               Station Upgrade Project
                                                  requirement to complete all necessary                   project; impacts on soils, karst geology,
                                                  reviews and to reach a final decision on                groundwater, waterbodies, wetlands,                     The staff of the Federal Energy
                                                  a request for a federal authorization                   sensitive and listed species, forests,                Regulatory Commission (FERC or
                                                  within 90 days of the date of issuance                  sensitive National Forest Service lands,              Commission) has prepared an
                                                  of the Commission staff’s Environmental                 air quality, climate change; and                      environmental assessment (EA) for the
                                                  Assessment (EA) for the Project. This                   cumulative and indirect impacts.                      Cedar Station Upgrade Project, proposed
                                                  instant notice identifies the FERC staff’s              Alternatives, public safety, general                  by Northern Natural Gas Company
                                                  planned schedule for the completion of                  support for the project, and the need for             (Northern) in the above-referenced
                                                  the EA for the Project.                                 a programmatic environmental impact                   docket. Northern requests authorization
                                                                                                                                                                to construct approximately 7.86 miles of
                                                  Schedule for Environmental Review                       statement (EIS) were also raised.
                                                                                                                                                                natural gas pipeline in Dakota County,
                                                  Issuance of EA—March 24, 2017                              The U.S. Forest Service, U.S. Army                 Minnesota in order to fulfill its
mstockstill on DSK3G9T082PROD with NOTICES




                                                  90-day Federal Authorization Decision                   Corps of Engineers, U.S. Fish and                     contractual obligation with Northern
                                                     Deadline—June 22, 2017                               Wildlife Service, West Virginia                       States Power Company, a Minnesota
                                                     If a schedule change becomes                         Department of Environmental                           Corporation (NSP–MN) to increase the
                                                  necessary, additional notice will be                    Protection, and West Virginia                         delivery pressure to NSP–MN’s existing
                                                  provided so that the relevant agencies                  Department of Natural Resources are                   Black Dog Generating Station from 400
                                                  are kept informed of the Project’s                      cooperating agencies in the preparation               pounds per square inch gauge (psig) to
                                                  progress.                                               of the EA.                                            650 psig. As part of NSP–MN’s process


                                             VerDate Sep<11>2014   18:42 Dec 15, 2016   Jkt 241001   PO 00000   Frm 00045   Fmt 4703   Sfmt 4703   E:\FR\FM\16DEN1.SGM   16DEN1


                                                  91160                         Federal Register / Vol. 81, No. 242 / Friday, December 16, 2016 / Notices

                                                  of reducing its carbon footprint, it has                   docket number (CP16–487–000) with                     provides access to the texts of formal
                                                  increased its use of natural gas-fired                     your submission. The Commission                       documents issued by the Commission,
                                                  generation.                                                encourages electronic filing of                       such as orders, notices, and
                                                     The EA assesses the potential                           comments and has expert staff available               rulemakings.
                                                  environmental effects of the                               to assist you at (202) 502–8258 or                       In addition, the Commission offers a
                                                  construction and operation of the Cedar                    efiling@ferc.gov.                                     free service called eSubscription which
                                                  Station Upgrade Project in accordance                         (1) You can file your comments                     allows you to keep track of all formal
                                                  with the requirements of the National                      electronically using the eComment                     issuances and submittals in specific
                                                  Environmental Policy Act (NEPA). The                       feature on the Commission’s Web site                  dockets. This can reduce the amount of
                                                  FERC staff concludes that approval of                      (www.ferc.gov) under the link to                      time you spend researching proceedings
                                                  the proposed project, with appropriate                     Documents and Filings. This is an easy                by automatically providing you with
                                                  mitigating measures, would not                             method for submitting brief, text-only                notification of these filings, document
                                                  constitute a major federal action                          comments on a project;                                summaries, and direct links to the
                                                  significantly affecting the quality of the                    (2) You can also file your comments                documents. Go to www.ferc.gov/docs-
                                                  human environment.                                         electronically using the eFiling feature              filing/esubscription.asp.
                                                     The Cedar Station Upgrade Project                       on the Commission’s Web site                            Dated: December 9, 2016.
                                                  includes the following facilities:                         (www.ferc.gov) under the link to
                                                                                                                                                                   Kimberly D. Bose,
                                                     • Approximately 7.86 miles of new                       Documents and Filings. With eFiling,
                                                  20-inch-diameter pipeline loop; 1                                                                                Secretary.
                                                                                                             you can provide comments in a variety
                                                    • a new pig 2 launcher and takeoff                       of formats by attaching them as a file                [FR Doc. 2016–30207 Filed 12–15–16; 8:45 am]
                                                  valve setting at Northern’s existing                       with your submission. New eFiling                     BILLING CODE 6717–01–P
                                                  Rosemount Junction facility; and                           users must first create an account by
                                                     • a new pig receiver, tie-in valve                      clicking on ‘‘eRegister.’’ You must select
                                                  setting, and modification of existing                                                                            DEPARTMENT OF ENERGY
                                                                                                             the type of filing you are making. If you
                                                  regulators and piping at Northern’s                        are filing a comment on a particular
                                                  existing Cedar Meter Station facility.                                                                           Federal Energy Regulatory
                                                                                                             project, please select ‘‘Comment on a                 Commission
                                                     The FERC staff mailed copies of the                     Filing’’; or
                                                  EA to federal, state, and local                               (3) You can file a paper copy of your              [Docket No. IC17–2–000]
                                                  government representatives and                             comments by mailing them to the
                                                  agencies; elected officials;                               following address: Kimberly D. Bose,                  Commission Information Collection
                                                  environmental and public interest                          Secretary, Federal Energy Regulatory                  Activities (FERC–549D and FERC–733);
                                                  groups; Native American tribes;                            Commission, 888 First Street NE., Room                Consolidated Comment Request;
                                                  potentially affected landowners and                        1A, Washington, DC 20426.                             Extension
                                                  other interested individuals and groups;                      Any person seeking to become a party               AGENCY:  Federal Energy Regulatory
                                                  and newspapers and libraries in the                        to the proceeding must file a motion to               Commission, Department of Energy.
                                                  project area. In addition, the EA is                       intervene pursuant to Rule 214 of the                 ACTION: Notice of information
                                                  available for public viewing on the                        Commission’s Rules of Practice and                    collections and request for comments.
                                                  FERC’s Web site (www.ferc.gov) using                       Procedures (18 CFR 385.214).3 Only
                                                  the eLibrary link. A limited number of                     intervenors have the right to seek                    SUMMARY:   In compliance with the
                                                  copies of the EA are available for                         rehearing of the Commission’s decision.               requirements of the Paperwork
                                                  distribution and public inspection at:                     The Commission grants affected                        Reduction Act of 1995, 44 U.S.C.
                                                  Federal Energy Regulatory Commission,                      landowners and others with                            3506(c)(2)(A), the Federal Energy
                                                  Public Reference Room, 888 First Street                    environmental concerns intervenor                     Regulatory Commission (Commission or
                                                  NE., Room 2A, Washington, DC 20426,                        status upon showing good cause by                     FERC) is soliciting public comment on
                                                  (202) 502–8371.                                            stating that they have a clear and direct             the requirements and burden 1 of the
                                                     Any person wishing to comment on                        interest in this proceeding which no                  information collections described
                                                  the EA may do so. Your comments                            other party can adequately represent.                 below.
                                                  should focus on the potential                              Simply filing environmental comments                  DATES: Comments on the collections of
                                                  environmental effects, reasonable                          will not give you intervenor status, but              information are due February 14, 2017.
                                                  alternatives, and measures to avoid or                     you do not need intervenor status to                  ADDRESSES: You may submit comments
                                                  lessen environmental impacts. The more                     have your comments considered.                        (identified by Docket No. IC17–2–000)
                                                  specific your comments, the more useful                       Additional information about the                   by either of the following methods:
                                                  they will be. To ensure that the                           project is available from the                            • eFiling at Commission’s Web site:
                                                  Commission has the opportunity to                          Commission’s Office of External Affairs,              http://www.ferc.gov/docs-filing/
                                                  consider your comments prior to                            at (866) 208–FERC, or on the FERC Web                 efiling.asp.
                                                  making its decision on this project, it is                 site (www.ferc.gov) using the eLibrary                   • Mail/Hand Delivery/Courier:
                                                  important that we receive your                             link. Click on the eLibrary link, click on            Federal Energy Regulatory Commission,
                                                  comments in Washington, DC on or                           ‘‘General Search,’’ and enter the docket              Secretary of the Commission, 888 First
                                                  before January 9, 2017.                                    number excluding the last three digits in             Street NE., Washington, DC 20426.
                                                     For your convenience, there are three                   the Docket Number field (i.e., CP16–                     Please reference the specific
                                                  methods you can use to file your                           487). Be sure you have selected an                    collection number and/or title in your
                                                  comments to the Commission. In all
mstockstill on DSK3G9T082PROD with NOTICES




                                                                                                             appropriate date range. For assistance,               comments.
                                                  instances, please reference the project                    please contact FERC Online Support at
                                                                                                             FercOnlineSupport@ferc.gov or toll free                 1 The Commission defines burden as the total
                                                    1A  pipeline ‘‘loop’’ is a segment of pipe installed
                                                                                                             at (866) 208–3676, or for TTY, contact                time, effort, or financial resources expended by
                                                  adjacent to an existing pipeline and connected to                                                                persons to generate, maintain, retain, or disclose or
                                                  the existing pipeline at both ends.                        (202) 502–8659. The eLibrary link also                provide information to or for a Federal agency. For
                                                    2 A ‘‘pig’’ is an internal pipeline tool used to clean                                                         further explanation of what is included in the
                                                  a pipeline and/or to inspect for damage or                    3 See the previous discussion on the methods for   information collection burden, reference 5 Code of
                                                  corrosion.                                                 filing comments.                                      Federal Regulations 1320.3.



                                             VerDate Sep<11>2014    18:42 Dec 15, 2016   Jkt 241001   PO 00000    Frm 00046   Fmt 4703   Sfmt 4703   E:\FR\FM\16DEN1.SGM   16DEN1



Document Created: 2018-02-14 09:07:59
Document Modified: 2018-02-14 09:07:59
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation81 FR 91159 