NUCLEAR REGULATORY COMMISSION

Federal Register Volume 82, Issue 32 (February 17, 2017)

Page Range11069-11069
FR Document2017-03246

The U.S. Nuclear Regulatory Commission (NRC) is issuing Revision 1 to Regulatory Guide (RG) 5.70, ``Guidance for the Application of the Theft and Diversion Design-Basis Threat for Category I Fuel Cycle Facilities.'' This regulatory guide provides methods that the NRC staff finds acceptable for an applicant or licensee to meet the requirements of the underlying NRC's regulations. Revision 1 of RG 5.70 contains clarifying information regarding technical matters and rule language, administrative changes, and lessons learned from inspection activities, operating experience, and current threat data.

Federal Register, Volume 82 Issue 32 (Friday, February 17, 2017)
[Federal Register Volume 82, Number 32 (Friday, February 17, 2017)]
[Notices]
[Page 11069]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2017-03246]


-----------------------------------------------------------------------

NUCLEAR REGULATORY COMMISSION

[NRC-2017-0042]


Guidance for the Application of the Theft and Diversion Design-
Basis Threat for Category I Fuel Cycle Facilities

AGENCY: Nuclear Regulatory Commission.

ACTION: Regulatory guide; issuance.

-----------------------------------------------------------------------

SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) is issuing 
Revision 1 to Regulatory Guide (RG) 5.70, ``Guidance for the 
Application of the Theft and Diversion Design-Basis Threat for Category 
I Fuel Cycle Facilities.'' This regulatory guide provides methods that 
the NRC staff finds acceptable for an applicant or licensee to meet the 
requirements of the underlying NRC's regulations. Revision 1 of RG 5.70 
contains clarifying information regarding technical matters and rule 
language, administrative changes, and lessons learned from inspection 
activities, operating experience, and current threat data.

DATES: Revision 1 to RG 5.70 is available on February 17, 2017.

ADDRESSES: Revision 1 to RG 5.70 contains classified information. 
Therefore, this RG is being withheld from public disclosure, but is 
available to those affected licensees and cleared stakeholders who 
qualify for access and have a demonstrated need to know. For access to 
RG 5.70, contact the individuals listed in the FOR FURTHER INFORMATION 
CONTACT section.

FOR FURTHER INFORMATION CONTACT: William Gott, Office of Nuclear 
Security and Incident Response, telephone: 301-287-9256, email: 
[email protected]; or Mekonen Bayssie, Office of Nuclear Regulatory 
Research, telephone: 301-415-1699, email: [email protected]. Both 
are staff of the U.S. Nuclear Regulatory Commission, Washington, DC 
20555-0001. Alternatively, you may make suggestions or comments on RG 
5.70 via email to: [email protected]. 
Please do not include any potentially classified or sensitive 
information in your email.

SUPPLEMENTARY INFORMATION:

I. Discussion

    The NRC is issuing a revision to an existing guide in the NRC's 
``Regulatory Guide'' series. This series was developed to describe and 
make available to the public information regarding methods that are 
acceptable to the NRC staff for implementing specific parts of the 
agency's regulations, techniques that the NRC staff uses in evaluating 
specific issues or postulated events, and data that the NRC staff needs 
in its review of applications for permits and licenses.
    Regulatory Guide 5.70 contains classified information. This RG is 
being withheld from public disclosure, but is available to those 
affected licensees and cleared stakeholders who qualify for access and 
have a demonstrated need to know.

II. Additional Information

    The NRC did not announce the availaibility for comment on the draft 
guide because the guide contains classified information. Instead, the 
NRC transmitted the draft guide for comment to cleared stakeholders who 
demonstrated a need-to-know in a memorandum (Agencywide Documents 
Access and Management System (ADAMS) Accession No. ML16007A604) on 
January 4, 2016. Nonetheless, the NRC is issuing this notice to inform 
the public of the issuance of the final RG.
    The stakeholders' comment period closed on March 19, 2016. The NRC 
received comments from four stakeholders. The comments and the 
associated comment resolutions contain classified information and are 
not available to the public. These comment resolutions can be obtained 
by those who have a demonstrated need-to-know and are cleared to access 
classified information. For access to RG 5.70, contact the individuals 
listed in the FOR FURTHER INFORMATION CONTACT section.

III. Congressional Review Act

    This RG is a rule as defined in the Congressional Review Act (5 
U.S.C. 801-808). However, the Office of Management and Budget has not 
found it to be a major rule as defined in the Congressional Review Act.

IV. Backfitting

    This regulatory guide provides guidance on the application of the 
design basis threat to the design and implementation of physical 
protection systems and programs required to meet the requirements set 
forth in 10 CFR 73.45 and 10 CFR 73.46. The regulatory guide provides 
methods that the NRC staff finds acceptable for an applicant or 
licensee to meet the requirements of the underlying NRC regulations. 
The issuance of the guidance in this regulatory guide is not 
backfitting, as that term is defined in 10 CFR 70.76, because security 
is not included within the scope of the NRC's backfitting protection.

    Dated at Rockville, Maryland, this 10th day of February, 2017.

    For the Nuclear Regulatory Commission.
Harriet Karagiannis,
Acting Chief, Regulatory Guidance and Generic Issues Branch, Division 
of Engineering, Office of Nuclear Regulatory Research.
[FR Doc. 2017-03246 Filed 2-16-17; 8:45 am]
 BILLING CODE 7590-01-P



                                                                                Federal Register / Vol. 82, No. 32 / Friday, February 17, 2017 / Notices                                                11069

                                                    This meeting will be webcast live at                  ACTION:   Regulatory guide; issuance.                 access and have a demonstrated need to
                                                  the Web address—http://www.nrc.gov/.                                                                          know.
                                                                                                          SUMMARY:    The U.S. Nuclear Regulatory
                                                  Friday, March 24, 2017                                  Commission (NRC) is issuing Revision 1                II. Additional Information
                                                  10:00 a.m. Briefing on the Annual                       to Regulatory Guide (RG) 5.70,                           The NRC did not announce the
                                                      Threat Environment (Closed Ex. 1)                   ‘‘Guidance for the Application of the                 availaibility for comment on the draft
                                                                                                          Theft and Diversion Design-Basis Threat               guide because the guide contains
                                                  Week of March 27, 2017—Tentative                        for Category I Fuel Cycle Facilities.’’               classified information. Instead, the NRC
                                                     There are no meetings scheduled for                  This regulatory guide provides methods                transmitted the draft guide for comment
                                                  the week of March 27, 2017.                             that the NRC staff finds acceptable for               to cleared stakeholders who
                                                  *     *      *    *      *                              an applicant or licensee to meet the                  demonstrated a need-to-know in a
                                                     The schedule for Commission                          requirements of the underlying NRC’s                  memorandum (Agencywide Documents
                                                  meetings is subject to change on short                  regulations. Revision 1 of RG 5.70                    Access and Management System
                                                  notice. For more information or to verify               contains clarifying information                       (ADAMS) Accession No.
                                                  the status of meetings, contact Denise                  regarding technical matters and rule                  ML16007A604) on January 4, 2016.
                                                  McGovern at 301–415–0981 or via email                   language, administrative changes, and                 Nonetheless, the NRC is issuing this
                                                  at Denise.McGovern@nrc.gov.                             lessons learned from inspection                       notice to inform the public of the
                                                                                                          activities, operating experience, and                 issuance of the final RG.
                                                  *     *      *    *      *
                                                                                                          current threat data.                                     The stakeholders’ comment period
                                                     The NRC Commission Meeting
                                                  Schedule can be found on the Internet                   DATES: Revision 1 to RG 5.70 is available             closed on March 19, 2016. The NRC
                                                  at http://www.nrc.gov/public-involve/                   on February 17, 2017.                                 received comments from four
                                                  public-meetings/schedule.html.                          ADDRESSES: Revision 1 to RG 5.70                      stakeholders. The comments and the
                                                  *     *      *    *      *                              contains classified information.                      associated comment resolutions contain
                                                     The NRC provides reasonable                          Therefore, this RG is being withheld                  classified information and are not
                                                  accommodation to individuals with                       from public disclosure, but is available              available to the public. These comment
                                                  disabilities where appropriate. If you                  to those affected licensees and cleared               resolutions can be obtained by those
                                                  need a reasonable accommodation to                      stakeholders who qualify for access and               who have a demonstrated need-to-know
                                                  participate in these public meetings, or                have a demonstrated need to know. For                 and are cleared to access classified
                                                  need this meeting notice or the                         access to RG 5.70, contact the                        information. For access to RG 5.70,
                                                  transcript or other information from the                individuals listed in the FOR FURTHER                 contact the individuals listed in the FOR
                                                                                                          INFORMATION CONTACT section.                          FURTHER INFORMATION CONTACT section.
                                                  public meetings in another format (e.g.,
                                                  braille, large print), please notify                    FOR FURTHER INFORMATION CONTACT:                      III. Congressional Review Act
                                                  Kimberly Meyer, NRC Disability                          William Gott, Office of Nuclear Security
                                                                                                          and Incident Response, telephone: 301–                   This RG is a rule as defined in the
                                                  Program Manager, at 301–287–0739, by
                                                                                                          287–9256, email: William.Gott@nrc.gov;                Congressional Review Act (5 U.S.C.
                                                  videophone at 240–428–3217, or by
                                                                                                          or Mekonen Bayssie, Office of Nuclear                 801–808). However, the Office of
                                                  email at Kimberly.Meyer-Chambers@
                                                                                                          Regulatory Research, telephone: 301–                  Management and Budget has not found
                                                  nrc.gov. Determinations on requests for
                                                                                                          415–1699, email: Mekonen.Bayssie@                     it to be a major rule as defined in the
                                                  reasonable accommodation will be
                                                                                                          nrc.gov. Both are staff of the U.S.                   Congressional Review Act.
                                                  made on a case-by-case basis.
                                                  *     *      *    *      *                              Nuclear Regulatory Commission,                        IV. Backfitting
                                                     Members of the public may request to                 Washington, DC 20555–0001.
                                                                                                          Alternatively, you may make                              This regulatory guide provides
                                                  receive this information electronically.                                                                      guidance on the application of the
                                                  If you would like to be added to the                    suggestions or comments on RG 5.70 via
                                                                                                          email to: RegulatoryGuideDevelopment                  design basis threat to the design and
                                                  distribution, please contact the Nuclear                                                                      implementation of physical protection
                                                  Regulatory Commission, Office of the                    Branch.Resource@nrc.gov. Please do not
                                                                                                          include any potentially classified or                 systems and programs required to meet
                                                  Secretary, Washington, DC 20555 (301–                                                                         the requirements set forth in 10 CFR
                                                  415–1969), or email                                     sensitive information in your email.
                                                                                                                                                                73.45 and 10 CFR 73.46. The regulatory
                                                  Brenda.Akstulewicz@nrc.gov or                           SUPPLEMENTARY INFORMATION:
                                                                                                                                                                guide provides methods that the NRC
                                                  Patricia.Jimenez@nrc.gov.                               I. Discussion                                         staff finds acceptable for an applicant or
                                                    Dated: February 15, 2017.                               The NRC is issuing a revision to an                 licensee to meet the requirements of the
                                                  Denise L. McGovern,                                     existing guide in the NRC’s ‘‘Regulatory              underlying NRC regulations. The
                                                  Policy Coordinator, Office of the Secretary.            Guide’’ series. This series was                       issuance of the guidance in this
                                                  [FR Doc. 2017–03315 Filed 2–15–17; 11:15 am]            developed to describe and make                        regulatory guide is not backfitting, as
                                                                                                          available to the public information                   that term is defined in 10 CFR 70.76,
                                                  BILLING CODE 7590–01–P
                                                                                                          regarding methods that are acceptable to              because security is not included within
                                                                                                          the NRC staff for implementing specific               the scope of the NRC’s backfitting
                                                  NUCLEAR REGULATORY                                      parts of the agency’s regulations,                    protection.
                                                  COMMISSION                                              techniques that the NRC staff uses in                   Dated at Rockville, Maryland, this 10th day
                                                                                                          evaluating specific issues or postulated              of February, 2017.
                                                  [NRC–2017–0042]                                                                                                 For the Nuclear Regulatory Commission.
                                                                                                          events, and data that the NRC staff
mstockstill on DSK3G9T082PROD with NOTICES




                                                  Guidance for the Application of the                     needs in its review of applications for               Harriet Karagiannis,
                                                  Theft and Diversion Design-Basis                        permits and licenses.                                 Acting Chief, Regulatory Guidance and
                                                  Threat for Category I Fuel Cycle                          Regulatory Guide 5.70 contains                      Generic Issues Branch, Division of
                                                                                                          classified information. This RG is being              Engineering, Office of Nuclear Regulatory
                                                  Facilities                                                                                                    Research.
                                                                                                          withheld from public disclosure, but is
                                                  AGENCY:Nuclear Regulatory                               available to those affected licensees and             [FR Doc. 2017–03246 Filed 2–16–17; 8:45 am]
                                                  Commission.                                             cleared stakeholders who qualify for                  BILLING CODE 7590–01–P




                                             VerDate Sep<11>2014   17:38 Feb 16, 2017   Jkt 241001   PO 00000   Frm 00070   Fmt 4703   Sfmt 9990   E:\FR\FM\17FEN1.SGM   17FEN1



Document Created: 2017-02-17 00:29:08
Document Modified: 2017-02-17 00:29:08
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
ActionRegulatory guide; issuance.
DatesRevision 1 to RG 5.70 is available on February 17, 2017.
ContactWilliam Gott, Office of Nuclear Security and Incident Response, telephone: 301-287-9256, email: [email protected]; or Mekonen Bayssie, Office of Nuclear Regulatory Research, telephone: 301-415-1699, email: [email protected] Both are staff of the U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001. Alternatively, you may make suggestions or comments on RG 5.70 via email to: [email protected] Please do not include any potentially classified or sensitive information in your email.