82_FR_14267 82 FR 14216 - Eastern Shore Natural Gas Company; Notice of Schedule for Environmental Review of the 2017 Expansion Project

82 FR 14216 - Eastern Shore Natural Gas Company; Notice of Schedule for Environmental Review of the 2017 Expansion Project

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 82, Issue 51 (March 17, 2017)

Page Range14216-14217
FR Document2017-05308

Federal Register, Volume 82 Issue 51 (Friday, March 17, 2017)
[Federal Register Volume 82, Number 51 (Friday, March 17, 2017)]
[Notices]
[Pages 14216-14217]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2017-05308]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP17-28-000]


Eastern Shore Natural Gas Company; Notice of Schedule for 
Environmental Review of the 2017 Expansion Project

    On December 30, 2016, Eastern Shore Natural Gas Company (Eastern 
Shore) filed an application in Docket No. CP17-28-000 requesting a 
Certificate of Public Convenience and Necessity pursuant to Section 
7(c) of the Natural Gas Act to construct and operate certain natural 
gas pipeline facilities. Eastern Shore's proposal is known as the 2017

[[Page 14217]]

Expansion Project (Project), and would involve construction of 
approximately 40 miles of pipeline and appurtenant facilities located 
in Pennsylvania, Maryland, and Delaware to provide 61,162 dekatherms 
per day of additional firm transportation service.
    On January 11, 2017, the Federal Energy Regulatory Commission 
(Commission or FERC) issued its Notice of Application for the Project. 
Among other things, that notice alerted agencies issuing federal 
authorizations of the requirement to complete all necessary reviews and 
to reach a final decision on a request for a federal authorization 
within 90 days of the date of issuance of the Commission staff's 
Environmental Assessment (EA) for the Project. This instant notice 
identifies the FERC staff's planned schedule for the completion of the 
EA for the Project.

Schedule for Environmental Review

    Issuance of EA--May 12, 2017.
    90-day Federal Authorization Decision Deadline--August 10, 2017.
    If a schedule change becomes necessary, additional notice will be 
provided so that the relevant agencies are kept informed of the 
Project's progress.

Project Description

    The facilities to be constructed and operated under Section 7(c) 
include: (1) Six pipeline loop segments totaling 22.7 miles; (2) one 
10-inch-diameter 16.9-mile-long mainline extension; (3) upgrades to an 
existing Meter and Regulator Station in Lancaster County, Pennsylvania; 
(4) installation of an additional 3,750 horsepower compressor unit at 
the existing Daleville Compressor Station in Chester County, 
Pennsylvania; and (5) the addition of two pressure control stations in 
Sussex County, Delaware.

Background

    On August 1, 2016, the Commission issued a Notice of Intent To 
Prepare an Environmental Assessment for the Proposed 2017 Expansion 
Project and Request for Comments on Environmental Issues (NOI). The NOI 
was issued during the pre-filing review of the Project in Docket no. 
PF16-7 and was sent to federal, state, and local government 
representatives and agencies; elected officials; Native American 
tribes; potentially affected landowners; and other interested 
individuals and groups in the Project area. In response to the Notice 
of Intent, the Commission received comments from the Pennsylvania 
Department of Environmental Protection, West Sadsbury Township, the 
Chester Water Authority, the Maryland Historical Trust, the Delaware 
Department of Natural Resources and Environmental Control--Division of 
Fish and Wildlife, the Franklin Township Historical Commission, and the 
National Park Service. The primary concerns raised were regarding 
wetland and waterbody impacts; potential damage to water mains; impacts 
on the White Clay Creek National Wild and Scenic River; potential 
impacts on bog turtles and their habitat; and potential impacts on 
historic, scenic, or cultural resources. Five private landowners filed 
comments expressing questions or concerns regarding the right-of-way 
acquisition process, overall public safety and pipeline reliability, 
restoration efforts, and the procedures to be used should future 
roadway widening occur where the pipeline is installed under the 
highway.
    The U.S. Army Corps of Engineers and the U.S. Department of 
Agriculture Natural Resources Conservation Service are cooperating 
agencies in the preparation of the EA.

Additional Information

    In order to receive notification of the issuance of the EA and to 
keep track of all formal issuances and submittals in specific dockets, 
the Commission offers a free service called eSubscription. This can 
reduce the amount of time you spend researching proceedings by 
automatically providing you with notification of these filings, 
document summaries, and direct links to the documents. Go to 
www.ferc.gov/docs-filing/esubscription.asp. Additional information 
about the Project is available from the Commission's Office of External 
Affairs at (866) 208-FERC or on the FERC Web site (www.ferc.gov). Using 
the ``eLibrary'' link, select ``General Search'' from the eLibrary 
menu, enter the selected date range and ``Docket Number'' excluding the 
last three digits (i.e., CP17-28), and follow the instructions. For 
assistance with access to eLibrary, the helpline can be reached at 
(866) 208-3676, TTY (202) 502-8659, or at [email protected]. 
The eLibrary link on the FERC Web site also provides access to the 
texts of formal documents issued by the Commission, such as orders, 
notices, and rule makings.

    Dated: March 10, 2017.
Kimberly D. Bose,
Secretary.
[FR Doc. 2017-05308 Filed 3-16-17; 8:45 am]
BILLING CODE 6717-01-P



                                                    14216                                   Federal Register / Vol. 82, No. 51 / Friday, March 17, 2017 / Notices

                                                    category was averaged over 2014–2016.3                                   annual burden hours are now being                                        Estimate of Annual Burden: 5 The
                                                    The response requirements included in                                    removed.                                                               Commission estimates the annual public
                                                    this category were complete within 18                                      Type of Respondents: NERC                                            reporting burden for the information
                                                    months of the effective date of the                                      Registered entities (specifically                                      collection as:
                                                    standard 4 or by 10/1/2015. Due to                                       balancing authorities, generator owners,
                                                    completion, the corresponding 304                                        generator operators).

                                                        FERC–725T (MANDATORY RELIABILITY STANDARDS FOR THE BULK-POWER SYSTEM: TRE RELIABILITY STANDARDS)
                                                                                                                                     Annual                                             Average                         Total annual             Cost per
                                                                                                         Number of                  number of               Total number               burden and                       burden hours            respondent
                                                                                                        respondents              responses per              of responses                cost per                          and total                 ($)
                                                                                                                                   respondent                                          response 6                        annual cost

                                                                                                               (1)                        (2)               (1) * (2) = (3)                   (4)                       (3) * (4) = (5)            (5) ÷ (1)

                                                    Maintenance and Submission of                                        71                            1                    1    16 hrs.; $1,029 ......              16 hrs.; $1,029 ......               $1,029
                                                      Event Log Data.
                                                    Evidence Retention ...................                           8 130                            1                130       2 hrs.; $76 .............           260 hrs.; $9,815 ....                      $76

                                                         Total ...................................    ........................   ........................              131        ...............................    276 hrs.; $10,844 ..     ........................



                                                      Comments: Comments are invited on:                                     submit their costs related to                                          questions about the technical
                                                    (1) Whether the collection of                                            Administering Part I of the Federal                                    conference should contact Norman
                                                    information is necessary for the proper                                  Power Act. Order On Rehearing                                          Richardson at (202) 502–6219 or via
                                                    performance of the functions of the                                      Consolidating Administrative Annual                                    email at annualcharges@ferc.gov.
                                                    Commission, including whether the                                        Charges Bill Appeals And Modifying                                       FERC conferences are accessible
                                                    information will have practical utility;                                 Annual Charges Billing Procedures, 109                                 under section 508 of the Rehabilitation
                                                    (2) the accuracy of the agency’s estimate                                FERC 61,040 (2004) (October 8 Order).                                  Act of 1973. For accessibility
                                                    of the burden and cost of the collection                                 The Commission required OFAs to                                        accommodations please send an email
                                                    of information, including the validity of                                submit their costs using the OFA Cost                                  to accessibility@ferc.gov or call toll free
                                                    the methodology and assumptions used;                                    Submission Form. The October 8 Order                                   (866) 208–3372 (voice), (202) 208–8659
                                                    (3) ways to enhance the quality, utility                                 also announced that a technical                                        (TTY), or send a FAX to 202–208–2106
                                                    and clarity of the information collection;                               conference would be held for the                                       with the required accommodations.
                                                    and (4) ways to minimize the burden of                                   purpose of reviewing the submitted cost                                  Dated: March 10, 2017.
                                                    the collection of information on those                                   forms and detailed supporting
                                                                                                                                                                                                    Kimberly D. Bose,
                                                    who are to respond, including the use                                    documentation.
                                                                                                                                The Commission will hold a technical                                Secretary.
                                                    of automated collection techniques or
                                                                                                                             conference for reviewing the submitted                                 [FR Doc. 2017–05306 Filed 3–16–17; 8:45 am]
                                                    other forms of information technology.
                                                                                                                             OFA costs. The purpose of the                                          BILLING CODE 6717–01–P
                                                      Dated: March 10, 2017.
                                                                                                                             conference will be for OFAs and
                                                    Kimberly D. Bose,                                                        licensees to discuss costs reported in the
                                                    Secretary.                                                               forms and any other supporting                                         DEPARTMENT OF ENERGY
                                                    [FR Doc. 2017–05309 Filed 3–16–17; 8:45 am]                              documentation or analyses.
                                                    BILLING CODE 6717–01–P                                                      The technical conference will be held                               Federal Energy Regulatory
                                                                                                                             on April 6, 2017, in Conference Room                                   Commission
                                                                                                                             3M–1 at the Commission’s headquarters,
                                                    DEPARTMENT OF ENERGY                                                                                                                            [Docket No. CP17–28–000]
                                                                                                                             888 First Street NE., Washington, DC.
                                                                                                                             The technical conference will begin at                                 Eastern Shore Natural Gas Company;
                                                    Federal Energy Regulatory                                                2:00 p.m. (EST).
                                                    Commission                                                                                                                                      Notice of Schedule for Environmental
                                                                                                                                The technical conference will also be                               Review of the 2017 Expansion Project
                                                                                                                             transcribed. Those interested in
                                                    [Docket No. AD17–1–000]                                                  obtaining a copy of the transcript                                        On December 30, 2016, Eastern Shore
                                                    Review of Cost Submittals by Other                                       immediately for a fee should contact the                               Natural Gas Company (Eastern Shore)
                                                    Federal Agencies for Administering                                       Ace-Federal Reporters, Inc., at 202–347–                               filed an application in Docket No.
                                                    Part I of the Federal Power Act; Notice                                  3700, or 1–800–336–6646. Two weeks                                     CP17–28–000 requesting a Certificate of
                                                    of Technical Conference                                                  after the post-forum meeting, the                                      Public Convenience and Necessity
                                                                                                                             transcript will be available for free on                               pursuant to Section 7(c) of the Natural
                                                      In an order issued on October 8, 2004,                                 the Commission’s e-library system.                                     Gas Act to construct and operate certain
                                                    the Commission set forth a guideline for                                 Anyone without access to the                                           natural gas pipeline facilities. Eastern
                                                    Other Federal Agencies (OFAs) to                                         Commission’s Web site or who has                                       Shore’s proposal is known as the 2017
asabaliauskas on DSK3SPTVN1PROD with NOTICES




                                                       3 The total annual figure for this response                           collection burden, reference 5 Code of Federal                         Labor Statistics at https://www.bls.gov/oes/current/
                                                    category was 304 hours.                                                  Regulations 1320.3.                                                    naics2_22.htm)
                                                       4 The effective date of the standard was 4/1/2014.                      6 The estimates for cost per hour are based on
                                                                                                                                                                                                      All calculated wage figures within the burden
                                                       5 Burden is defined as the total time, effort, or                     2015 wage figures and derived as follows:                              table are rounded to the nearest dollar.
                                                                                                                               • $64.29/hour, the average salary plus benefits
                                                    financial resources expended by persons to                                                                                                        7 BA (balancing authority).
                                                                                                                             per engineer (from Bureau of Labor Statistics at
                                                    generate, maintain, retain, or disclose or provide                       https://www.bls.gov/oes/current/naics2_22.htm)
                                                                                                                                                                                                      8 BA (balancing authority), GO (generator owner),

                                                    information to or for a Federal agency. For further                        • $37.75/hour, the salary plus benefits per                          and GOP (generator operator).
                                                    explanation of what is included in the information                       information and record clerks (from Bureau of



                                               VerDate Sep<11>2014       20:02 Mar 16, 2017          Jkt 241001      PO 00000       Frm 00019        Fmt 4703   Sfmt 4703       E:\FR\FM\17MRN1.SGM                 17MRN1


                                                                                    Federal Register / Vol. 82, No. 51 / Friday, March 17, 2017 / Notices                                                  14217

                                                    Expansion Project (Project), and would                  Authority, the Maryland Historical                    DEPARTMENT OF ENERGY
                                                    involve construction of approximately                   Trust, the Delaware Department of
                                                    40 miles of pipeline and appurtenant                    Natural Resources and Environmental                   Federal Energy Regulatory
                                                    facilities located in Pennsylvania,                     Control—Division of Fish and Wildlife,                Commission
                                                    Maryland, and Delaware to provide                       the Franklin Township Historical                      [Project No. 2787–007]
                                                    61,162 dekatherms per day of additional                 Commission, and the National Park
                                                    firm transportation service.                            Service. The primary concerns raised                  Green Mountain Power; Ottauquechee
                                                       On January 11, 2017, the Federal                     were regarding wetland and waterbody                  Hydro Company, Inc.; Notice of
                                                    Energy Regulatory Commission                            impacts; potential damage to water                    Transfer of Exemption
                                                    (Commission or FERC) issued its Notice                  mains; impacts on the White Clay Creek
                                                    of Application for the Project. Among                                                                           1. By letter filed February 21, 2017
                                                                                                            National Wild and Scenic River;                       and supplemented on March 2, 2017,
                                                    other things, that notice alerted agencies              potential impacts on bog turtles and
                                                    issuing federal authorizations of the                                                                         Enel Green Power North America, Inc.
                                                                                                            their habitat; and potential impacts on               informed the Commission that the
                                                    requirement to complete all necessary
                                                                                                            historic, scenic, or cultural resources.              exemption from licensing for the
                                                    reviews and to reach a final decision on
                                                                                                            Five private landowners filed comments                Ottauquechee Woolen Mill Project No.
                                                    a request for a federal authorization
                                                                                                            expressing questions or concerns                      2787, originally issued August 13,
                                                    within 90 days of the date of issuance
                                                    of the Commission staff’s Environmental                 regarding the right-of-way acquisition                1982 1 has been transferred to the Green
                                                    Assessment (EA) for the Project. This                   process, overall public safety and                    Mountain Power, effective January 29,
                                                    instant notice identifies the FERC staff’s              pipeline reliability, restoration efforts,            2017. The project is located on the
                                                    planned schedule for the completion of                  and the procedures to be used should                  Ottauquechee River in Windsor County,
                                                    the EA for the Project.                                 future roadway widening occur where                   Vermont. The transfer of an exemption
                                                                                                            the pipeline is installed under the                   does not require Commission approval.
                                                    Schedule for Environmental Review                       highway.                                                2. Green Mountain Power is now the
                                                      Issuance of EA—May 12, 2017.                            The U.S. Army Corps of Engineers                    exemptee of the Ottauquechee Woolen
                                                      90-day Federal Authorization                          and the U.S. Department of Agriculture                Mill Project No. 2787. All
                                                    Decision Deadline—August 10, 2017.                      Natural Resources Conservation Service                correspondence should be forwarded to:
                                                      If a schedule change becomes                                                                                Green Mountain Power, 163 Acorn
                                                                                                            are cooperating agencies in the
                                                    necessary, additional notice will be                                                                          Lane, Colchester, VT 05446.
                                                                                                            preparation of the EA.
                                                    provided so that the relevant agencies
                                                                                                                                                                    Dated: March 10, 2017.
                                                    are kept informed of the Project’s                      Additional Information
                                                                                                                                                                  Kimberly D. Bose,
                                                    progress.
                                                                                                               In order to receive notification of the            Secretary.
                                                    Project Description                                     issuance of the EA and to keep track of               [FR Doc. 2017–05310 Filed 3–16–17; 8:45 am]
                                                      The facilities to be constructed and                  all formal issuances and submittals in                BILLING CODE 6717–01–P
                                                    operated under Section 7(c) include: (1)                specific dockets, the Commission offers
                                                    Six pipeline loop segments totaling 22.7                a free service called eSubscription. This
                                                    miles; (2) one 10-inch-diameter 16.9-                   can reduce the amount of time you                     ENVIRONMENTAL PROTECTION
                                                    mile-long mainline extension; (3)                       spend researching proceedings by                      AGENCY
                                                    upgrades to an existing Meter and                       automatically providing you with                      [ER–FRL–9032–2]
                                                    Regulator Station in Lancaster County,                  notification of these filings, document
                                                    Pennsylvania; (4) installation of an                    summaries, and direct links to the                    Environmental Impact Statements;
                                                    additional 3,750 horsepower                             documents. Go to www.ferc.gov/docs-                   Notice of Availability
                                                    compressor unit at the existing Daleville               filing/esubscription.asp. Additional
                                                    Compressor Station in Chester County,                   information about the Project is                        Responsible Agency: Office of Federal
                                                    Pennsylvania; and (5) the addition of                   available from the Commission’s Office                Activities, General Information (202)
                                                    two pressure control stations in Sussex                                                                       564–7146 or http://www.epa.gov/nepa.
                                                                                                            of External Affairs at (866) 208–FERC or
                                                    County, Delaware.                                                                                             Weekly receipt of Environmental Impact
                                                                                                            on the FERC Web site (www.ferc.gov).
                                                    Background                                              Using the ‘‘eLibrary’’ link, select                     Statements (EISs),
                                                                                                            ‘‘General Search’’ from the eLibrary                    Filed 03/06/2017 Through 03/10/
                                                       On August 1, 2016, the Commission                                                                              2017.
                                                    issued a Notice of Intent To Prepare an                 menu, enter the selected date range and
                                                                                                            ‘‘Docket Number’’ excluding the last                  Pursuant to 40 CFR 1506.9.
                                                    Environmental Assessment for the
                                                    Proposed 2017 Expansion Project and                     three digits (i.e., CP17–28), and follow              Notice
                                                    Request for Comments on                                 the instructions. For assistance with
                                                                                                                                                                    Section 309(a) of the Clean Air Act
                                                    Environmental Issues (NOI). The NOI                     access to eLibrary, the helpline can be               requires that EPA make public its
                                                    was issued during the pre-filing review                 reached at (866) 208–3676, TTY (202)                  comments on EISs issued by other
                                                    of the Project in Docket no. PF16–7 and                 502–8659, or at FERCOnlineSupport@                    Federal agencies. EPA’s comment letters
                                                    was sent to federal, state, and local                   ferc.gov. The eLibrary link on the FERC               on EISs are available at: http://
                                                    government representatives and                          Web site also provides access to the                  www.epa.gov/compliance/nepa/
                                                    agencies; elected officials; Native                     texts of formal documents issued by the
asabaliauskas on DSK3SPTVN1PROD with NOTICES




                                                                                                                                                                  eisdata.html.
                                                    American tribes; potentially affected                   Commission, such as orders, notices,
                                                                                                                                                                  EIS No. 20170032, Draft, USFS, OR,
                                                    landowners; and other interested                        and rule makings.
                                                                                                                                                                    Ringo Project, Comment Period Ends:
                                                    individuals and groups in the Project                     Dated: March 10, 2017.                                05/01/2017, Contact: Lillian Cross,
                                                    area. In response to the Notice of Intent,
                                                                                                            Kimberly D. Bose,                                       541–433–3200.
                                                    the Commission received comments
                                                    from the Pennsylvania Department of                     Secretary.
                                                                                                                                                                    1 Order Granting Exemption from Licensing of a
                                                    Environmental Protection, West                          [FR Doc. 2017–05308 Filed 3–16–17; 8:45 am]
                                                                                                                                                                  Small Hydroelectric Project of 5 MW or Less. White
                                                    Sadsbury Township, the Chester Water                    BILLING CODE 6717–01–P                                Current Corporation, 20 FERC ¶ 62,271 (1982).



                                               VerDate Sep<11>2014   20:02 Mar 16, 2017   Jkt 241001   PO 00000   Frm 00020   Fmt 4703   Sfmt 4703   E:\FR\FM\17MRN1.SGM   17MRN1



Document Created: 2017-03-17 02:48:38
Document Modified: 2017-03-17 02:48:38
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation82 FR 14216 

2025 Federal Register | Disclaimer | Privacy Policy
USC | CFR | eCFR