82_FR_14766 82 FR 14712 - Town of Carbondale, Colorado; Notice of Preliminary Determination of a Qualifying Conduit Hydropower Facility and Soliciting Comments and Motions To Intervene

82 FR 14712 - Town of Carbondale, Colorado; Notice of Preliminary Determination of a Qualifying Conduit Hydropower Facility and Soliciting Comments and Motions To Intervene

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 82, Issue 54 (March 22, 2017)

Page Range14712-14713
FR Document2017-05669

Federal Register, Volume 82 Issue 54 (Wednesday, March 22, 2017)
[Federal Register Volume 82, Number 54 (Wednesday, March 22, 2017)]
[Notices]
[Pages 14712-14713]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2017-05669]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CD17-8-000]


Town of Carbondale, Colorado; Notice of Preliminary Determination 
of a Qualifying Conduit Hydropower Facility and Soliciting Comments and 
Motions To Intervene

    On March 9, 2017, the Town of Carbondale, Colorado, filed a notice 
of intent to construct a qualifying conduit hydropower facility, 
pursuant to section 30 of the Federal Power Act (FPA), as amended by 
section 4 of the Hydropower Regulatory Efficiency Act of 2013 (HREA). 
The proposed Town of Carbondale Nettle Creek WTP Hydro Project would 
have an installed capacity of 28 kilowatts (kW), and would be located 
along an existing raw water pipeline adjacent to the applicant's water 
treatment plant. The project would be located near the Town of 
Carbondale in Pitkin County, Colorado.
    Applicant Contact: Mark O'Meara, Utility Director, Town of 
Carbondale, 511 Colorado Avenue, Carbondale, CO 81623 Phone No. (970) 
963-3140.
    FERC Contact: Christopher Chaney, Phone No. (202) 502-6778, email: 
[email protected].
    Qualifying Conduit Hydropower Facility Description: The proposed 
project would consist of: (1) An new pressure reduction valve vault 
containing one turbine/generating unit with an installed capacity of 28 
kW; (2) a short, 10-inch-diameter penstock teeing off the existing raw 
water pipeline; (3) a short, 10-inch-diameter discharge pipe returning 
water to the existing raw water pipeline; and (4) appurtenant 
facilities. The proposed project would have an estimated annual 
generating capacity of 190,000 kilowatt-hours.
    A qualifying conduit hydropower facility is one that is determined 
or deemed to meet all of the criteria shown in the table below.

      Table 1--Criteria for Qualifying Conduit Hydropower Facility
------------------------------------------------------------------------
      Statutory provision              Description       Satisfies (Y/N)
------------------------------------------------------------------------
FPA 30(a)(3)(A), as amended by   The conduit the                      Y
 HREA.                            facility uses is a
                                  tunnel, canal,
                                  pipeline, aqueduct,
                                  flume, ditch, or
                                  similar manmade water
                                  conveyance that is
                                  operated for the
                                  distribution of water
                                  for agricultural,
                                  municipal, or
                                  industrial
                                  consumption and not
                                  primarily for the
                                  generation of
                                  electricity.
FPA 30(a)(3)(C)(i), as amended   The facility is                      Y
 by HREA.                         constructed,
                                  operated, or
                                  maintained for the
                                  generation of
                                  electric power and
                                  uses for such
                                  generation only the
                                  hydroelectric
                                  potential of a non-
                                  federally owned
                                  conduit.
FPA 30(a)(3)(C)(ii), as amended  The facility has an                  Y
 by HREA.                         installed capacity
                                  that does not exceed
                                  5 megawatts.

[[Page 14713]]

 
FPA 30(a)(3)(C)(iii), as         On or before August 9,               Y
 amended by HREA.                 2013, the facility is
                                  not licensed, or
                                  exempted from the
                                  licensing
                                  requirements of Part
                                  I of the FPA.
------------------------------------------------------------------------

    Preliminary Determination: The proposed addition of the 
hydroelectric project along the existing raw water pipeline will not 
alter its primary purpose. Therefore, based upon the above criteria, 
Commission staff preliminarily determines that the proposal satisfies 
the requirements for a qualifying conduit hydropower facility, which is 
not required to be licensed or exempted from licensing.
    Comments and Motions To Intervene: Deadline for filing comments 
contesting whether the facility meets the qualifying criteria is 45 
days from the issuance date of this notice.
    Deadline for filing motions to intervene is 30 days from the 
issuance date of this notice.
    Anyone may submit comments or a motion to intervene in accordance 
with the requirements of Rules of Practice and Procedure, 18 CFR 
385.210 and 385.214. Any motions to intervene must be received on or 
before the specified deadline date for the particular proceeding.
    Filing and Service of Responsive Documents: All filings must (1) 
bear in all capital letters the ``COMMENTS CONTESTING QUALIFICATION FOR 
A CONDUIT HYDROPOWER FACILITY'' or ``MOTION TO INTERVENE,'' as 
applicable; (2) state in the heading the name of the applicant and the 
project number of the application to which the filing responds; (3) 
state the name, address, and telephone number of the person filing; and 
(4) otherwise comply with the requirements of sections 385.2001 through 
385.2005 of the Commission's regulations.\1\ All comments contesting 
Commission staff's preliminary determination that the facility meets 
the qualifying criteria must set forth their evidentiary basis.
---------------------------------------------------------------------------

    \1\ 18 CFR 385.2001-2005 (2016).
---------------------------------------------------------------------------

    The Commission strongly encourages electronic filing. Please file 
motions to intervene and comments using the Commission's eFiling system 
at http://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit 
brief comments up to 6,000 characters, without prior registration, 
using the eComment system at http://www.ferc.gov/docs-filing/ecomment.asp. You must include your name and contact information at the 
end of your comments. For assistance, please contact FERC Online 
Support at [email protected], (866) 208-3676 (toll free), or 
(202) 502-8659 (TTY). In lieu of electronic filing, please send a paper 
copy to: Secretary, Federal Energy Regulatory Commission, 888 First 
Street NE., Washington, DC 20426. A copy of all other filings in 
reference to this application must be accompanied by proof of service 
on all persons listed in the service list prepared by the Commission in 
this proceeding, in accordance with 18 CFR 4.34(b) and 385.2010.
    Locations of Notice of Intent: Copies of the notice of intent can 
be obtained directly from the applicant or such copies can be viewed 
and reproduced at the Commission in its Public Reference Room, Room 2A, 
888 First Street NE., Washington, DC 20426. The filing may also be 
viewed on the web at http://www.ferc.gov/docs-filing/elibrary.asp using 
the ``eLibrary'' link. Enter the docket number (i.e., CD17-8) in the 
docket number field to access the document. For assistance, call toll-
free 1-866-208-3676 or email [email protected]. For TTY, call 
(202) 502-8659.

    Dated: March 13, 2017.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2017-05669 Filed 3-21-17; 8:45 am]
 BILLING CODE 6717-01-P



                                                    14712                       Federal Register / Vol. 82, No. 54 / Wednesday, March 22, 2017 / Notices

                                                    208–3676 (toll free), or (202) 502–8659                 party to the proceeding. Any comments,                DEPARTMENT OF ENERGY
                                                    (TTY). In lieu of electronic filing, please             protests, or motions to intervene must
                                                    send a paper copy to: Secretary, Federal                be received on or before the specified                Federal Energy Regulatory
                                                    Energy Regulatory Commission, 888                       comment date for the particular                       Commission
                                                    First Street NE., Washington, DC 20426.                 application.                                          [Docket No. CD17–8–000]
                                                    The first page of any filing should
                                                                                                               o. Filing and Service of Responsive
                                                    include docket number P–2302–085.                                                                             Town of Carbondale, Colorado; Notice
                                                                                                            Documents: Any filing must (1) bear in
                                                       k. Description of Request: The                                                                             of Preliminary Determination of a
                                                    licensee requests to remove the Canal                   all capital letters the title
                                                                                                            ‘‘COMMENTS’’, ‘‘PROTEST’’, or                         Qualifying Conduit Hydropower
                                                    System and its four non-operating canal                                                                       Facility and Soliciting Comments and
                                                    generating facilities from the Lewiston                 ‘‘MOTION TO INTERVENE’’ as
                                                                                                            applicable; (2) set forth in the heading              Motions To Intervene
                                                    Falls Project and convey the canals and
                                                    the conveyance facilities to the City of                the name of the applicant and the                        On March 9, 2017, the Town of
                                                    Lewiston for non-hydropower                             project number of the application to                  Carbondale, Colorado, filed a notice of
                                                    redevelopment and public use. This                      which the filing responds; (3) furnish                intent to construct a qualifying conduit
                                                    would reduce the project’s installed                    the name, address, and telephone                      hydropower facility, pursuant to section
                                                    capacity from 35.6 MW to 28 MW, but                     number of the person protesting or                    30 of the Federal Power Act (FPA), as
                                                    the operation of the project would                      intervening; and (4) otherwise comply                 amended by section 4 of the
                                                    remain unchanged.                                       with the requirements of 18 CFR                       Hydropower Regulatory Efficiency Act
                                                       l. This filing may be viewed on the                  385.2001 through 385.2005. All                        of 2013 (HREA). The proposed Town of
                                                    Commission’s Web site at http://                        comments, motions to intervene, or                    Carbondale Nettle Creek WTP Hydro
                                                    www.ferc.gov/docs-filing/elibrary.asp.                  protests must set forth their evidentiary             Project would have an installed capacity
                                                    Enter the docket number excluding the                   basis and otherwise comply with the                   of 28 kilowatts (kW), and would be
                                                    last three digits in the docket number                  requirements of 18 CFR 4.34(b). All                   located along an existing raw water
                                                    field to access the document. You may                   comments, motions to intervene, or                    pipeline adjacent to the applicant’s
                                                    also register online at http://                         protests should relate to project works               water treatment plant. The project
                                                    www.ferc.gov/docs-filing/                               which are the subject of the license                  would be located near the Town of
                                                    esubscription.asp to be notified via                    amendment. Agencies may obtain                        Carbondale in Pitkin County, Colorado.
                                                    email of new filings and issuances                      copies of the application directly from                  Applicant Contact: Mark O’Meara,
                                                    related to this or other pending projects.              the applicant. A copy of any protest or               Utility Director, Town of Carbondale,
                                                    For assistance, call 1–866–208–3676 or                                                                        511 Colorado Avenue, Carbondale, CO
                                                                                                            motion to intervene must be served
                                                    email FERCOnlineSupport@ferc.gov, for                                                                         81623 Phone No. (970) 963–3140.
                                                                                                            upon each representative of the
                                                    TTY, call (202) 502–8659. A copy is also                                                                         FERC Contact: Christopher Chaney,
                                                                                                            applicant specified in the particular
                                                    available for inspection and                                                                                  Phone No. (202) 502–6778, email:
                                                    reproduction in the Commission’s                        application. If an intervener files                   Christopher.Chaney@ferc.gov.
                                                    Public Reference Room located at 888                    comments or documents with the                           Qualifying Conduit Hydropower
                                                    First Street NE., Room 2A, Washington,                  Commission relating to the merits of an               Facility Description: The proposed
                                                    DC 20426, or by calling (202) 502–8371.                 issue that may affect the responsibilities            project would consist of: (1) An new
                                                       m. Individuals desiring to be included               of a particular resource agency, they                 pressure reduction valve vault
                                                    on the Commission’s mailing list should                 must also serve a copy of the document                containing one turbine/generating unit
                                                    so indicate by writing to the Secretary                 on that resource agency. A copy of all                with an installed capacity of 28 kW; (2)
                                                    of the Commission.                                      other filings in reference to this                    a short, 10-inch-diameter penstock
                                                       n. Comments, Protests, or Motions to                 application must be accompanied by                    teeing off the existing raw water
                                                    Intervene: Anyone may submit                            proof of service on all persons listed in             pipeline; (3) a short, 10-inch-diameter
                                                    comments, a protest, or a motion to                     the service list prepared by the                      discharge pipe returning water to the
                                                    intervene in accordance with the                        Commission in this proceeding, in                     existing raw water pipeline; and (4)
                                                    requirements of Rules of Practice and                   accordance with 18 CFR 4.34(b) and                    appurtenant facilities. The proposed
                                                    Procedure, 18 CFR 385.210, .211, .212                   385.2010.                                             project would have an estimated annual
                                                    and .214. In determining the appropriate                  Dated: March 13, 2017.                              generating capacity of 190,000 kilowatt-
                                                    action to take, the Commission will                                                                           hours.
                                                                                                            Nathaniel J. Davis, Sr.,
                                                    consider all protests or other comments                                                                          A qualifying conduit hydropower
                                                    filed, but only those who file a motion                 Deputy Secretary.                                     facility is one that is determined or
                                                    to intervene in accordance with the                     [FR Doc. 2017–05674 Filed 3–21–17; 8:45 am]           deemed to meet all of the criteria shown
                                                    Commission’s Rules may become a                         BILLING CODE 6717–01–P                                in the table below.

                                                                                      TABLE 1—CRITERIA FOR QUALIFYING CONDUIT HYDROPOWER FACILITY
                                                                                                                                                                                                    Satisfies
                                                                Statutory provision                                                            Description                                           (Y/N)
asabaliauskas on DSK3SPTVN1PROD with NOTICES




                                                    FPA 30(a)(3)(A), as amended by HREA ..             The conduit the facility uses is a tunnel, canal, pipeline, aqueduct, flume, ditch, or          Y
                                                                                                         similar manmade water conveyance that is operated for the distribution of water
                                                                                                         for agricultural, municipal, or industrial consumption and not primarily for the gen-
                                                                                                         eration of electricity.
                                                    FPA 30(a)(3)(C)(i), as amended by HREA             The facility is constructed, operated, or maintained for the generation of electric             Y
                                                                                                         power and uses for such generation only the hydroelectric potential of a non-fed-
                                                                                                         erally owned conduit.
                                                    FPA 30(a)(3)(C)(ii),      as   amended       by    The facility has an installed capacity that does not exceed 5 megawatts ..................      Y
                                                      HREA.



                                               VerDate Sep<11>2014   18:14 Mar 21, 2017   Jkt 241001   PO 00000   Frm 00040   Fmt 4703   Sfmt 4703   E:\FR\FM\22MRN1.SGM   22MRN1


                                                                                 Federal Register / Vol. 82, No. 54 / Wednesday, March 22, 2017 / Notices                                             14713

                                                                              TABLE 1—CRITERIA FOR QUALIFYING CONDUIT HYDROPOWER FACILITY—Continued
                                                                                                                                                                                                   Satisfies
                                                                   Statutory provision                                                          Description                                         (Y/N)

                                                    FPA 30(a)(3)(C)(iii),      as   amended       by    On or before August 9, 2013, the facility is not licensed, or exempted from the li-           Y
                                                      HREA.                                              censing requirements of Part I of the FPA.



                                                       Preliminary Determination: The                        please contact FERC Online Support at                 teleconference. The meeting will be
                                                    proposed addition of the hydroelectric                   FERCOnlineSupport@ferc.gov, (866)                     held on Tuesday, March 28, 2017 from
                                                    project along the existing raw water                     208–3676 (toll free), or (202) 502–8659               11:00 a.m. to 12:30 p.m. All times noted
                                                    pipeline will not alter its primary                      (TTY). In lieu of electronic filing, please           are Eastern Time and are approximate.
                                                    purpose. Therefore, based upon the                       send a paper copy to: Secretary, Federal              The primary discussions will focus on
                                                    above criteria, Commission staff                         Energy Regulatory Commission, 888                     finalizing the draft report on the
                                                    preliminarily determines that the                        First Street NE., Washington, DC 20426.               effective and efficient tools, strategies
                                                    proposal satisfies the requirements for a                A copy of all other filings in reference              and methods to characterize and assess
                                                    qualifying conduit hydropower facility,                  to this application must be accompanied               exposure and decontamination
                                                    which is not required to be licensed or                  by proof of service on all persons listed             following a biological contamination
                                                    exempted from licensing.                                 in the service list prepared by the                   incident. There will be a public
                                                       Comments and Motions To Intervene:                    Commission in this proceeding, in                     comment period at 11:15 a.m. For
                                                    Deadline for filing comments contesting                  accordance with 18 CFR 4.34(b) and                    information on registering to participate
                                                    whether the facility meets the qualifying                385.2010.                                             on the call or to provide public
                                                    criteria is 45 days from the issuance                      Locations of Notice of Intent: Copies               comment, please see the SUPPLEMENTARY
                                                    date of this notice.                                     of the notice of intent can be obtained               INFORMATION section below. Due to
                                                       Deadline for filing motions to                        directly from the applicant or such                   unforeseen administrative
                                                    intervene is 30 days from the issuance                   copies can be viewed and reproduced at                circumstances, EPA is announcing this
                                                    date of this notice.                                     the Commission in its Public Reference                meeting with less than fifteen calendar
                                                       Anyone may submit comments or a                       Room, Room 2A, 888 First Street NE.,                  days’ notice.
                                                    motion to intervene in accordance with                   Washington, DC 20426. The filing may                  DATES: The BOSC HSS meeting will be
                                                    the requirements of Rules of Practice                    also be viewed on the web at http://                  held on Tuesday, March 28, 2017 from
                                                    and Procedure, 18 CFR 385.210 and                        www.ferc.gov/docs-filing/elibrary.asp                 11:00 a.m. to 12:30 p.m. All times noted
                                                    385.214. Any motions to intervene must                   using the ‘‘eLibrary’’ link. Enter the                are Eastern Time and are approximate.
                                                    be received on or before the specified                   docket number (i.e., CD17–8) in the
                                                    deadline date for the particular                                                                               FOR FURTHER INFORMATION CONTACT:
                                                                                                             docket number field to access the                     Questions or correspondence
                                                    proceeding.                                              document. For assistance, call toll-free
                                                       Filing and Service of Responsive                                                                            concerning the meeting should be
                                                                                                             1–866–208–3676 or email                               directed to Tom Tracy, Designated
                                                    Documents: All filings must (1) bear in                  FERCOnlineSupport@ferc.gov. For TTY,
                                                    all capital letters the ‘‘COMMENTS                                                                             Federal Officer, Environmental
                                                                                                             call (202) 502–8659.                                  Protection Agency, by mail at 1200
                                                    CONTESTING QUALIFICATION FOR A
                                                    CONDUIT HYDROPOWER FACILITY’’                              Dated: March 13, 2017.                              Pennsylvania Avenue NW., (MC 8104
                                                    or ‘‘MOTION TO INTERVENE,’’ as                           Nathaniel J. Davis, Sr.,                              R), Washington, DC 20460; by telephone
                                                    applicable; (2) state in the heading the                 Deputy Secretary.                                     at 202–564–6518; fax at 202–565–2911;
                                                    name of the applicant and the project                    [FR Doc. 2017–05669 Filed 3–21–17; 8:45 am]           or via email at tracy.tom@epa.gov.
                                                    number of the application to which the                   BILLING CODE 6717–01–P                                SUPPLEMENTARY INFORMATION: The
                                                    filing responds; (3) state the name,                                                                           Charter of the BOSC states that the
                                                    address, and telephone number of the                                                                           advisory committee shall provide
                                                    person filing; and (4) otherwise comply                  ENVIRONMENTAL PROTECTION                              independent advice to the
                                                    with the requirements of sections                        AGENCY                                                Administrator on technical and
                                                    385.2001 through 385.2005 of the                                                                               management aspects of the ORD’s
                                                    Commission’s regulations.1 All                           [EPA–HQ–ORD–2015–0765; FRL–9960–04–                   research program. Additional
                                                                                                             ORD]                                                  information about the BOSC is available
                                                    comments contesting Commission staff’s
                                                    preliminary determination that the                       Board of Scientific Counselors                        at: http://www2.epa.gov/bosc.
                                                    facility meets the qualifying criteria                                                                            Registration: In order to participate in
                                                                                                             Homeland Security Subcommittee;
                                                    must set forth their evidentiary basis.                                                                        the meeting, you must register at the
                                                                                                             Notification of Public Teleconference
                                                       The Commission strongly encourages                                                                          following site: https://us-epa-2017-bosc-
                                                                                                             and Public Comment
                                                    electronic filing. Please file motions to                                                                      hs-subcommittee-
                                                    intervene and comments using the                         AGENCY: Environmental Protection                      teleconference.eventbrite.com. Once you
                                                    Commission’s eFiling system at http://                   Agency (EPA).                                         have completed the online registration,
                                                    www.ferc.gov/docs-filing/efiling.asp.                    ACTION: Notification of public meeting                you will be contacted and provided
                                                    Commenters can submit brief comments                                                                           with the meeting information.
asabaliauskas on DSK3SPTVN1PROD with NOTICES




                                                                                                             and public comment.
                                                    up to 6,000 characters, without prior                                                                          Registration will close on March 27,
                                                    registration, using the eComment system                  SUMMARY:   Pursuant to the Federal                    2017.
                                                    at http://www.ferc.gov/docs-filing/                      Advisory Committee Act, Public Law                       Oral Statements: Members of the
                                                    ecomment.asp. You must include your                      92–463, the U.S. Environmental                        public who wish to provide oral
                                                    name and contact information at the end                  Protection Agency hereby provides                     comment during the meeting must
                                                    of your comments. For assistance,                        notice that the Board of Scientific                   preregister. Individuals or groups
                                                                                                             Counselors (BOSC) Homeland Security                   making remarks during the public
                                                      1 18   CFR 385.2001–2005 (2016).                       Subcommittee (HSS) will host a public                 comment period will be limited to five


                                               VerDate Sep<11>2014    18:14 Mar 21, 2017   Jkt 241001   PO 00000   Frm 00041   Fmt 4703   Sfmt 4703   E:\FR\FM\22MRN1.SGM   22MRN1



Document Created: 2017-03-22 03:58:57
Document Modified: 2017-03-22 03:58:57
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation82 FR 14712 

2025 Federal Register | Disclaimer | Privacy Policy
USC | CFR | eCFR