The Bureau of Indian Affairs (BIA) owns or has an interest in irrigation projects located on or associated with various Indian reservations throughout the United States. We are required to establish irrigation assessment rates to recover the costs to administer, operate, maintain, and rehabilitate these projects. We are notifying you that we have adjusted the irrigation assessment rates at several of our irrigation projects and facilities to reflect current costs of administration, operation, maintenance, and rehabilitation.

Federal Register, Volume 82 Issue 65 (Thursday, April 6, 2017)
[Federal Register Volume 82, Number 65 (Thursday, April 6, 2017)]
[Notices]
[Pages 16849-16853]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2017-06829]


-----------------------------------------------------------------------

DEPARTMENT OF THE INTERIOR

Bureau of Indian Affairs

[178A2100DD/AAKC001030/A0A501010.999900 253G]


Rate Adjustments for Indian Irrigation Projects

AGENCY: Bureau of Indian Affairs, Interior.

ACTION: Notice.

-----------------------------------------------------------------------

SUMMARY: The Bureau of Indian Affairs (BIA) owns or has an interest in 
irrigation projects located on or associated with various Indian 
reservations throughout the United States. We are required to establish 
irrigation assessment rates to recover the costs to administer, 
operate, maintain, and rehabilitate these projects. We are notifying 
you that we have adjusted the irrigation assessment rates at several of 
our irrigation projects and facilities to reflect current costs of 
administration, operation, maintenance, and rehabilitation.

DATES: The irrigation assessment rates are current as of January 1, 
2016.

FOR FURTHER INFORMATION CONTACT: For details about a particular BIA 
irrigation project or facility, please use the tables in the 
SUPPLEMENTARY INFORMATION section to contact the regional or local 
office where the project or facility is located.

SUPPLEMENTARY INFORMATION: A Notice of Proposed Rate Adjustment was 
published in the Federal Register on August 5, 2016 (81 FR 51927) to 
propose adjustments to the irrigation assessment rates at several BIA 
irrigation projects. The public and interested parties were provided an 
opportunity to submit written comments during the 60-day period that 
ended October 4, 2016.

Did BIA defer or change any proposed rate increases?

    Yes. For the Flathead and Duck Valley Indian Irrigation Projects 
the rate increase to $33.50 and $6.30, respectively, as published in 
the proposed notice for the 2016 rate was not implemented. The final 
2016 rate will remain at the 2015 amounts of $26.00 and $5.30. All 
other rates are to be implemented at the respective irrigation project 
as published.

Did BIA receive any comments on the proposed irrigation assessment rate 
adjustments?

    No. The BIA did not receive any comments to the proposed irrigation 
assessment rate adjustment.

Does this notice affect me?

    This notice affects you if you own or lease land within the 
assessable acreage of one of our irrigation projects or if you have a 
carriage agreement with one of our irrigation projects.

Where can I get information on the regulatory and legal citations in 
this notice?

    You can contact the appropriate office(s) stated in the tables for 
the

[[Page 16850]]

irrigation project that serves you, or you can use the Internet site 
for the Government Printing Office at www.thefederalregister.org.

What authorizes you to issue this notice?

    Our authority to issue this notice is vested in the Secretary of 
the Interior (Secretary) by 5 U.S.C. 301 and the Act of August 14, 1914 
(38 Stat. 583; 25 U.S.C. 385). The Secretary has in turn delegated this 
authority to the Assistant Secretary--Indian Affairs under Part 209, 
Chapter 8.1A, of the Department of the Interior's Departmental Manual.

Whom can I contact for further information?

    The following tables are the regional and project/agency contacts 
for our irrigation facilities.

------------------------------------------------------------------------
           Project name                    Project/agency contacts
------------------------------------------------------------------------
                        Northwest Region Contacts
------------------------------------------------------------------------
 Stanley Speaks, Regional Director, Bureau of Indian Affairs, Northwest
     Regional Office, 911 NE. 11th Avenue, Portland, OR 97232-4169,
                       Telephone: (503) 231-6702.
------------------------------------------------------------------------
Flathead Indian Irrigation Project  Pete Plant, Acting Superintendent,
                                     Pete Plant, Irrigation Project
                                     Manager, P.O. Box 40, Pablo, MT
                                     59855, Telephones: (406) 675-2700
                                     ext. 1300 Superintendent, (406) 745-
                                     2661 ext. 2 Project Manager.
Fort Hall Irrigation Project......  David Bollinger, Irrigation Project
                                     Manager, Building #2 Bannock Ave,
                                     Fort Hall, ID 83203-0220,
                                     Telephone: (208) 238-6264
Wapato Irrigation Project.........  David Shaw, Superintendent, Larry
                                     Nelson, Acting Project
                                     Administrator, P.O. Box 220,
                                     Wapato, WA 98951-0220, Telephones:
                                     (509) 865-2421 Superintendent,
                                     (509) 877-3155 Acting Project
                                     Administrator.
------------------------------------------------------------------------
                     Rocky Mountain Region Contacts
------------------------------------------------------------------------
   Darryl LaCounte, Regional Director, Bureau of Indian Affairs, Rocky
  Mountain Regional Office, 2021 4th Avenue North, Billings, MT 59101,
                       Telephone: (406) 247-7943.
------------------------------------------------------------------------
Blackfeet Irrigation Project......  Thedis Crowe, Superintendent, Greg
                                     Tatsey, Irrigation Project Manager,
                                     Box 880, Browning, MT 59417,
                                     Telephones: (406) 338-7544,
                                     Superintendent, (406) 338-7519,
                                     Irrigation Project Manager.
Crow Irrigation Project...........  Vianna Stewart, Superintendent, John
                                     Anevski, Acting Irrigation Project
                                     Manager, P.O. Box 69, Crow Agency,
                                     MT 59022, Telephones: (406) 638-
                                     2672, Superintendent, (406) 247-
                                     7998, Acting Irrigation Project
                                     Manager.
Fort Belknap Irrigation Project...  John St. Pierre, Superintendent,
                                     Vacant, Irrigation Project Manager,
                                     (Project operation & maintenance
                                     contracted to Tribes), R.R.1, Box
                                     980, Harlem, MT 59526, Telephones:
                                     (406) 353-2901, Superintendent,
                                     (406) 353-8454, Irrigation Project
                                     Manager (Tribal Office).
Fort Peck Irrigation Project......  Howard Beemer, Superintendent, Huber
                                     Wright, Acting Irrigation Project
                                     Manager, P.O. Box 637, Poplar, MT
                                     59255, Telephones: (406) 768-5312,
                                     Superintendent, (406) 653-1752,
                                     Irrigation Project Manager.
Wind River Irrigation Project.....  Norma Gourneau, Superintendent, John
                                     Anevski, Acting Irrigation Project
                                     Manager, P.O. Box 158, Fort
                                     Washakie, WY 82514, Telephones:
                                     (307) 332-7810, Superintendent,
                                     (307) 247-7998, Acting Irrigation
                                     Project Manager.
------------------------------------------------------------------------
                        Southwest Region Contacts
------------------------------------------------------------------------
     William T. Walker, Regional Director, Bureau of Indian Affairs,
   Southwest Regional Office, 1001 Indian School Road, Albuquerque, NM
                    87104, Telephone: (505) 563-3100.
------------------------------------------------------------------------
Pine River Irrigation Project.....  Priscilla Bancroft, Superintendent,
                                     Vickie Begay, Irrigation Project
                                     Manager, P.O. Box 315, Ignacio, CO
                                     81137-0315, Telephones: (970) 563-
                                     4511, Superintendent, (970) 563-
                                     9484, Irrigation Project Manager.
------------------------------------------------------------------------
                         Western Region Contacts
------------------------------------------------------------------------
   Bryan Bowker, Regional Director, Bureau of Indian Affairs, Western
 Regional Office, 2600 N. Central Ave., 4th Floor Mailroom, Phoenix, AZ
                    85004, Telephone: (602) 379-6600.
------------------------------------------------------------------------
Colorado River Irrigation Project.  Kellie Youngbear Superintendent,
                                     Gary Colvin, Irrigation Project
                                     Manager, 12124 1st Avenue, Parker,
                                     AZ 85344, Telephone: (928) 669-
                                     7111.
Duck Valley Irrigation Project....  Joseph McDade, Superintendent,
                                     (Project operation & management
                                     compacted to Tribes), 2719 Argent
                                     Ave., Suite 4, Gateway Plaza, Elko,
                                     NV 89801, Telephone: (775) 738-
                                     5165, (208) 759-3100, (Tribal
                                     Office).
Yuma Project, Indian Unit.........  Denni Shields, Superintendent, 256
                                     South Second Avenue, Suite D, Yuma,
                                     AZ 85364, Telephone: (928) 782-
                                     1202.
San Carlos Irrigation Project,      Ferris Begay, Project Manager,
 Indian Works and Joint Works.       Clarence Begay, Irrigation Manager,
                                     13805 N. Arizona Boulevard,
                                     Coolidge, AZ 85128, Telephone:
                                     (520) 723-6225.
Uintah Irrigation Project.........  Bart Stevens Superintendent, Ken
                                     Asay, Irrigation System Manager,
                                     P.O. Box 130, Fort Duchesne, UT
                                     84026, Telephone: (435) 722-4300,
                                     (435) 722-4344.
Walker River Irrigation Project...  Robert Eben, Superintendent, 311 E.
                                     Washington Street, Carson City, NV
                                     89701, Telephone: (775) 887-3500.
------------------------------------------------------------------------


[[Page 16851]]

What irrigation assessments or charges are adjusted by this notice?

    The rate table below contains the current rates for all irrigation 
projects where we recover costs of administering, operating, 
maintaining, and rehabilitating them. The table also contains the final 
rates for the 2016 calendar year and subsequent years where applicable. 
An asterisk immediately following the rate category notes the 
irrigation projects where 2016 rates are different from the 2015 rates.

----------------------------------------------------------------------------------------------------------------
                                                                    Final 2015      Final 2016      Final 2017
             Project name                     Rate category            rate            rate           rate **
----------------------------------------------------------------------------------------------------------------
                                           Northwest Region Rate Table
----------------------------------------------------------------------------------------------------------------
Flathead Indian Irrigation Project      Basic-per acre--A.......          $26.00          $26.00          $26.00
 (See Note #1).
                                        Basic-per acre--B.......           13.00           13.00           13.00
                                        Minimum Charge per tract           75.00           75.00           75.00
----------------------------------------------------------------------------------------------------------------


----------------------------------------------------------------------------------------------------------------
                                                                                    Final 2015      Final 2016
                 Project name                             Rate category                rate            rate
----------------------------------------------------------------------------------------------------------------
Fort Hall Irrigation Project..................  Basic per acre *................          $49.00          $52.00
                                                Minimum Charge per tract *......           35.00           37.00
Fort Hall Irrigation Project--Minor Units.....  Basic per acre *................           27.00           31.00
                                                Minimum Charge per tract *......           35.00           37.00
Fort Hall Irrigation Project--Michaud.........  Basic per acre *................           50.50           55.00
                                                Pressure per acre *.............           72.50           83.00
                                                Minimum Charge per tract *......           35.00           37.00
Wapato Irrigation Project--Toppenish/Simcoe     Minimum Charge per bill *.......           24.00           25.00
 Units.
                                                Basic per acre *................           24.00           25.00
Wapato Irrigation Project--Ahtanum Units......  Minimum Charge per bill *.......           25.00           30.00
                                                Basic per acre *................           25.00           30.00
Wapato Irrigation Project--Satus Unit.........  Minimum Charge per bill.........           79.00           79.00
                                                ``A'' Basic per acre............           79.00           79.00
                                                ``B'' Basic per acre............           85.00           85.00
Wapato Irrigation Project--Additional Works...  Minimum Charge per bill *.......           75.00           78.00
                                                Basic per acre *................           75.00           78.00
Wapato Irrigation Project--Water Rental.......  Minimum Charge..................           86.00           86.00
                                                Basic per acre..................           86.00           86.00
----------------------------------------------------------------------------------------------------------------
                                        Rocky Mountain Region Rate Table
----------------------------------------------------------------------------------------------------------------
Blackfeet Irrigation Project..................  Basic-per acre..................           20.00           20.00
Crow Irrigation Project--Willow Creek O&M       Basic-per acre *................           24.80           26.00
 (includes Agency, Lodge Grass #1, Lodge Grass
 #2, Reno, Upper Little Horn, and Forty Mile
 Units).
Crow Irrigation Project--All Others (includes   Basic-per acre *................           24.80           26.00
 Bighorn, Soap Creek, and Pryor Units).
Crow Irrigation Project--Two Leggins Unit.....  Basic-per acre..................           14.00           14.00
Crow Irrigation Two Leggins Drainage District.  Basic-per acre..................            2.00            2.00
Fort Belknap Irrigation Project...............  Basic-per acre *................           15.00           16.00
Fort Peck Irrigation Project..................  Basic-per acre..................           26.00           26.00
Wind River Irrigation Project--Units 2, 3 and   Basic-per acre *................           21.00           22.50
 4.
Wind River Irrigation Project--Unit 6.........  Basic-per acre..................           21.00           21.00
Wind River Irrigation Project--LeClair          Basic-per acre *................           25.70           47.00
 District (see Note#2).
Wind River Irrigation Project--Crow Heart Unit  Basic-per acre *................           14.00           15.50
Wind River Irrigation Project--A Canal Unit...  Basic-per acre *................           14.00           15.50
Wind River Irrigation Project--Riverton Valley  Basic-per acre *................           21.00           26.00
 Irrigation District.
----------------------------------------------------------------------------------------------------------------
                                           Southwest Region Rate Table
----------------------------------------------------------------------------------------------------------------
Pine River Irrigation Project.................  Minimum Charge per tract........           50.00           50.00
                                                Basic-per acre *................           17.00           18.00
----------------------------------------------------------------------------------------------------------------
                                            Western Region Rate Table
----------------------------------------------------------------------------------------------------------------
Colorado River Irrigation Project.............  Basic per acre up to 5.75 acre-           $54.00          $54.00
                                                 feet.
                                                Excess Water per acre-foot over            17.00           17.00
                                                 5.75 acre-feet.
Duck Valley Irrigation Project................  Basic per acre..................            5.30            5.30
Yuma Project, Indian Unit (See Note #3).......  Basic per acre up to 5.0 acre-            108.50          113.00
                                                 feet *.
                                                Excess Water per acre-foot over            24.50           24.50
                                                 5.0 acre-feet.
                                                Basic per acre up to 5.0 acre-            108.50          113.00
                                                 feet (Ranch 5) *.
----------------------------------------------------------------------------------------------------------------


[[Page 16852]]


----------------------------------------------------------------------------------------------------------------
          Project name               Rate category      Final 2015 rate     Final 2016 rate   Final 2017 rate **
----------------------------------------------------------------------------------------------------------------
San Carlos Irrigation Project     Basic per acre *..  $35.00              $30.00              $25.00.
 (Joint Works) (See Note #4).
                                 -------------------------------------------------------------------------------
                                  Final 2016--2017 Construction Water Rate Schedule:
                                                      Off project         On project          On project
                                                       construction.       construction--gra   construction--pum
                                                                           vity water.         p water
----------------------------------------------------------------------------------------------------------------
                                  Administrative Fee  $300.00             $300.00             $300.00.
                                  Usage Fee.........  $250.00 per month.  No Fee............  $100.00 per acre
                                                                                               foot.
                                  Excess Water Rate   $5.00 per 1,000     No Charge.........  No Charge.
                                   [dagger].           gal.
----------------------------------------------------------------------------------------------------------------
                                  [dagger] The excess water rate applies to all water used in excess of 50,000
                                   gallons in any one month.
----------------------------------------------------------------------------------------------------------------


----------------------------------------------------------------------------------------------------------------
                                                                                    Final 2015      Final 2016
                 Project name                             Rate category                rate            rate
----------------------------------------------------------------------------------------------------------------
San Carlos Irrigation Project (Indian Works)    Basic per acre *................          $86.00          $81.00
 (See Note#5).
Uintah Irrigation Project.....................  Basic per acre..................           18.00           18.00
                                                Minimum Bill....................           25.00           25.00
Walker River Irrigation Project...............  Basic per acre..................           31.00           31.00
----------------------------------------------------------------------------------------------------------------
* Notes irrigation projects where rates are adjusted.
** The requirement for a final 2017 Rate is only applicable to the Flathead and San Carlos Irrigation Projects
  due to their specific billing requirements.
Note #1: Federal Register Notice on April 29, 2016 established the 2016 rate for the Flathead Irrigation Project
  (81 FR 25691). This notice makes final the 2017 rate for the Flathead Irrigation Project.
Note #2: The O&M rate varies yearly based upon the budget submitted by the LeClair District.
Note #3: The O&M rate for the Yuma Project, Indian Unit has two components. The first component is the O&M rate
  established by the Bureau of Reclamation (BOR), the owner and operator of the Project. The BOR rate for 2016
  is $110/acre. The second component is for the O&M rate established by BIA to cover administrative costs
  including billing and collections for the Project. The 2016 BIA rate is $3.00/acre.
Note #4:The construction water rate schedule identifies the fees assessed for use of irrigation water for non-
  irrigation purposes. Federal Register Notice on April 29, 2016 established the 2016 rate for the SCIP-JW (81
  FR 25691). This notice makes final the 2017 rate for the SCIP-JW.
Note #5: The 2016 O&M rate for the San Carlos Irrigation Project--Indian Works has three components. The first
  component is the O&M rate established by the San Carlos Irrigation Project--Indian Works, the owner and
  operator of the Project; this rate is $51 per acre. The second component is for the O&M rate established by
  the San Carlos Irrigation Project--Joint Works and is determined to be $25.00 per acre. The third component is
  the O&M rate established by the San Carlos Irrigation Project Joint Control Board and is $5 per acre.

Consultation and Coordination With Tribal Governments (Executive Order 
13175)

    The Department of the Interior strives to strengthen its 
government-to-government relationship with Indian Tribes through a 
commitment to consultation with Indian Tribes and recognition of their 
right to self-governance and Tribal sovereignty. We have evaluated this 
notice under the Department's consultation policy and under the 
criteria of Executive Order 13175 and have determined there to be 
substantial direct effects on federally recognized Tribes because the 
irrigation projects are located on or associated with Indian 
reservations. To fulfill its consultation responsibility to Tribes and 
Tribal organizations, BIA communicates, coordinates, and consults on a 
continuing basis with these entities on issues of water delivery, water 
availability, and costs of administration, operation, maintenance, and 
rehabilitation of projects that concern them. This is accomplished at 
the individual irrigation project by project, agency, and regional 
representatives, as appropriate, in accordance with local protocol and 
procedures. This notice is one component of our overall coordination 
and consultation process to provide notice to, and request comments 
from, these entities when we adjust irrigation assessment rates.

Actions Concerning Regulations That Significantly Affect Energy Supply, 
Distribution, or Use (Executive Order 13211)

    The rate adjustments are not a significant energy action under the 
definition in Executive Order 13211. A Statement of Energy Effects is 
not required.

Regulatory Planning and Review (Executive Order 12866)

    These rate adjustments are not a significant regulatory action and 
do not need to be reviewed by the Office of Management and Budget under 
Executive Order 12866.

Regulatory Flexibility Act

    These rate adjustments are not a rule for the purposes of the 
Regulatory Flexibility Act because they establish ``a rule of 
particular applicability relating to rates.'' 5 U.S.C. 601(2).

Unfunded Mandates Reform Act of 1995

    These rate adjustments do not impose an unfunded mandate on state, 
local, or tribal governments in the aggregate, or on the private 
sector, of more than $130 million per year. They do not have a 
significant or unique effect on state, local, or tribal governments or 
the private sector. Therefore, the Department is not required to 
prepare a statement containing the information required by the Unfunded 
Mandates Reform Act (2 U.S.C. 1531 et seq.).

Takings (Executive Order 12630)

    These rate adjustments do not effect a taking of private property 
or otherwise have ``takings'' implications under Executive Order 12630. 
The rate adjustments do not deprive the public, state, or local 
governments of rights or property.

Federalism (Executive Order 13132)

    Under the criteria in section 1 of Executive Order 13132, these 
rate adjustments do not have sufficient federalism implications to 
warrant the preparation of a federalism summary impact statement 
because they will not affect the States, the relationship between the 
national government and

[[Page 16853]]

the States, or the distribution of power and responsibilities among 
various levels of government. A federalism summary impact statement is 
not required.

Civil Justice Reform (Executive Order 12988)

    This notice complies with the requirements of Executive Order 
12988. Specifically, in issuing this notice, the Department has taken 
the necessary steps to eliminate drafting errors and ambiguity, 
minimize potential litigation, and provide a clear legal standard for 
affected conduct as required by section 3 of Executive Order 12988.

Paperwork Reduction Act of 1995

    These rate adjustments do not affect the collections of information 
which have been approved by the Office of Information and Regulatory 
Affairs, Office of Management and Budget, under the Paperwork Reduction 
Act of 1995. The OMB Control Number is 1076-0141 and expires June 30, 
2019.

National Environmental Policy Act

    The Department has determined that these rate adjustments do not 
constitute a major Federal action significantly affecting the quality 
of the human environment and that no detailed statement is required 
under the National Environmental Policy Act of 1969, 42 U.S.C. 4321-
4370(d), pursuant to 43 CFR 46.210(i). In addition, the rate 
adjustments do not present any of the 12 extraordinary circumstances 
listed at 43 CFR 46.215.

Data Quality Act

    In developing this notice, we did not conduct or use a study, 
experiment, or survey requiring peer review under the Data Quality Act 
(Pub. L. 106-554).

    Dated: March 29, 2017.
Michael S. Black,
Acting Assistant Secretary--Indian Affairs.
[FR Doc. 2017-06829 Filed 4-5-17; 8:45 am]
 BILLING CODE 4337-15-P



                                                                                 Federal Register / Vol. 82, No. 65 / Thursday, April 6, 2017 / Notices                                            16849

                                                  Background                                              negligible effects on federally listed or             ACTION:   Notice.
                                                     Section 9 of the Act (16 U.S.C. 1531                 candidate species and their habitats,
                                                                                                          and (2) minor or negligible effects on                SUMMARY:   The Bureau of Indian Affairs
                                                  et seq.) and our implementing Federal                                                                         (BIA) owns or has an interest in
                                                  regulations in the Code of Federal                      other environmental values or
                                                                                                          resources.                                            irrigation projects located on or
                                                  Regulations (CFR) at 50 CFR part 17                                                                           associated with various Indian
                                                  prohibit the ‘‘take’’ of fish or wildlife               Next Steps                                            reservations throughout the United
                                                  species listed as endangered or                            We will evaluate the HCP and                       States. We are required to establish
                                                  threatened. Take of listed fish or                      comments we receive to determine                      irrigation assessment rates to recover the
                                                  wildlife is defined under the Act as ‘‘to               whether the ITP application meets the                 costs to administer, operate, maintain,
                                                  harass, harm, pursue, hunt, shoot,                      requirements of section 10(a) of the Act.             and rehabilitate these projects. We are
                                                  wound, kill, trap, capture, or collect, or              If we determine that the application                  notifying you that we have adjusted the
                                                  to attempt to engage in any such                        meets these requirements, we will issue               irrigation assessment rates at several of
                                                  conduct’’ (16 U.S.C. 1532). However,                    ITP number TE19759C–0. We will also                   our irrigation projects and facilities to
                                                  under limited circumstances, we issue                   evaluate whether issuance of the section              reflect current costs of administration,
                                                  permits to authorize incidental take—                   10(a)(1)(B) ITP complies with section 7               operation, maintenance, and
                                                  i.e., take that is incidental to, and not               of the Act by conducting an intra-                    rehabilitation.
                                                  the purpose of, the carrying out of an                  Service section 7 consultation. We will               DATES: The irrigation assessment rates
                                                  otherwise lawful activity.                              use the results of this consultation, in              are current as of January 1, 2016.
                                                     Regulations governing incidental take                combination with the above findings, in               FOR FURTHER INFORMATION CONTACT: For
                                                  permits for threatened and endangered                   our final analysis to determine whether               details about a particular BIA irrigation
                                                  species are at 50 CFR 17.32 and 17.22,                  or not to issue the ITP. If the                       project or facility, please use the tables
                                                  respectively. The Act’s take prohibitions               requirements are met, we will issue the               in the SUPPLEMENTARY INFORMATION
                                                  do not apply to federally listed plants                 permit to the applicant.                              section to contact the regional or local
                                                  on private lands unless such take would
                                                                                                          Public Comments                                       office where the project or facility is
                                                  violate State law. In addition to meeting
                                                                                                                                                                located.
                                                  other criteria, an incidental take                        If you wish to comment on the permit
                                                  permit’s proposed actions must not                                                                            SUPPLEMENTARY INFORMATION: A Notice
                                                                                                          application, HCP, and associated
                                                  jeopardize the existence of federally                                                                         of Proposed Rate Adjustment was
                                                                                                          documents, you may submit comments
                                                  listed fish, wildlife, or plants.                                                                             published in the Federal Register on
                                                                                                          by any one of the methods in
                                                                                                                                                                August 5, 2016 (81 FR 51927) to propose
                                                  Applicant’s Proposal                                    ADDRESSES.
                                                                                                                                                                adjustments to the irrigation assessment
                                                    New Beginnings of Central Florida,                    Public Availability of Comments                       rates at several BIA irrigation projects.
                                                  Inc. is requesting take of approximately                  Before including your address, phone                The public and interested parties were
                                                  3.3 acres of occupied sand skink                        number, email address, or other                       provided an opportunity to submit
                                                  foraging and sheltering habitat                         personal identifying information in your              written comments during the 60-day
                                                  incidental to the construction of a                     comments, you should be aware that                    period that ended October 4, 2016.
                                                  residential apartment complex and                       your entire comment—including your                    Did BIA defer or change any proposed
                                                  seeks a 5-year permit. The sand skink                   personal identifying information—may                  rate increases?
                                                  (Neoseps reynoldsi) is listed in 50 CFR                 be made publicly available at any time.
                                                  17.11(h) as a threatened species. The                                                                            Yes. For the Flathead and Duck Valley
                                                                                                          While you can ask us in your comment                  Indian Irrigation Projects the rate
                                                  9.67-ac New Beginnings of Central                       to withhold your personal identifying
                                                  Florida, Inc. project is located on parcel                                                                    increase to $33.50 and $6.30,
                                                                                                          information from public review, we                    respectively, as published in the
                                                  09–22–26–080500900000, within                           cannot guarantee that we will be able to              proposed notice for the 2016 rate was
                                                  Section 20, Township 22 South, Range                    do so.                                                not implemented. The final 2016 rate
                                                  26 East, Lake County, Florida. The
                                                                                                          Authority                                             will remain at the 2015 amounts of
                                                  project includes the construction of a
                                                                                                                                                                $26.00 and $5.30. All other rates are to
                                                  residential apartment complex,                            We provide this notice under section
                                                                                                                                                                be implemented at the respective
                                                  associated infrastructure, and                          10 of the Act and NEPA regulations (40
                                                                                                                                                                irrigation project as published.
                                                  landscaping. New Beginnings of Central                  CFR 1506.6).
                                                  Florida, Inc. proposes to mitigate for the                Dated: February 24, 2017.                           Did BIA receive any comments on the
                                                  take of sand skinks by purchasing 6.6                   Jay B. Herrington,
                                                                                                                                                                proposed irrigation assessment rate
                                                  mitigation credits within the Scrub                                                                           adjustments?
                                                                                                          Field Supervisor, Jacksonville Field Office,
                                                  Conservation Bank.                                      Southeast Region.                                       No. The BIA did not receive any
                                                  Our Preliminary Determination                           [FR Doc. 2017–06801 Filed 4–5–17; 8:45 am]            comments to the proposed irrigation
                                                                                                          BILLING CODE 4333–15–P
                                                                                                                                                                assessment rate adjustment.
                                                     We have determined that the
                                                  applicant’s proposal, including the                                                                           Does this notice affect me?
                                                  proposed mitigation measures, would                                                                             This notice affects you if you own or
                                                                                                          DEPARTMENT OF THE INTERIOR
                                                  have minor or negligible effects on the                                                                       lease land within the assessable acreage
                                                  species covered in the HCP. Therefore,                  Bureau of Indian Affairs                              of one of our irrigation projects or if you
                                                  we determined that the ITP would be for
mstockstill on DSK3G9T082PROD with NOTICES




                                                                                                                                                                have a carriage agreement with one of
                                                  a ‘‘low-effect’’ project and qualifies for              [178A2100DD/AAKC001030/
                                                                                                                                                                our irrigation projects.
                                                  categorical exclusion under the National                A0A501010.999900 253G]
                                                  Environmental Policy Act (NEPA; 42                                                                            Where can I get information on the
                                                                                                          Rate Adjustments for Indian Irrigation                regulatory and legal citations in this
                                                  U.S.C. 4321 et seq.), as provided by the
                                                                                                          Projects                                              notice?
                                                  Department of the Interior NEPA
                                                  regulations (43 CFR part 46). A low-                    AGENCY:     Bureau of Indian Affairs,                   You can contact the appropriate
                                                  effect HCP is one involving (1) Minor or                Interior.                                             office(s) stated in the tables for the


                                             VerDate Sep<11>2014   18:51 Apr 05, 2017   Jkt 241001   PO 00000   Frm 00071   Fmt 4703   Sfmt 4703   E:\FR\FM\06APN1.SGM   06APN1


                                                  16850                             Federal Register / Vol. 82, No. 65 / Thursday, April 6, 2017 / Notices

                                                  irrigation project that serves you, or you                (Secretary) by 5 U.S.C. 301 and the Act               Whom can I contact for further
                                                  can use the Internet site for the                         of August 14, 1914 (38 Stat. 583; 25                  information?
                                                  Government Printing Office at                             U.S.C. 385). The Secretary has in turn
                                                  www.gpo.gov.                                              delegated this authority to the Assistant                The following tables are the regional
                                                                                                            Secretary—Indian Affairs under Part                   and project/agency contacts for our
                                                  What authorizes you to issue this                                                                               irrigation facilities.
                                                  notice?                                                   209, Chapter 8.1A, of the Department of
                                                                                                            the Interior’s Departmental Manual.
                                                    Our authority to issue this notice is
                                                  vested in the Secretary of the Interior

                                                               Project name                                                                    Project/agency contacts

                                                                                                                      Northwest Region Contacts

                                                      Stanley Speaks, Regional Director, Bureau of Indian Affairs, Northwest Regional Office, 911 NE. 11th Avenue, Portland, OR 97232–4169,
                                                                                                           Telephone: (503) 231–6702.

                                                  Flathead Indian Irrigation Project ....        Pete Plant, Acting Superintendent, Pete Plant, Irrigation Project Manager, P.O. Box 40, Pablo, MT 59855,
                                                                                                   Telephones: (406) 675–2700 ext. 1300 Superintendent, (406) 745–2661 ext. 2 Project Manager.
                                                  Fort Hall Irrigation Project ...............   David Bollinger, Irrigation Project Manager, Building #2 Bannock Ave, Fort Hall, ID 83203–0220, Tele-
                                                                                                   phone: (208) 238–6264
                                                  Wapato Irrigation Project ................     David Shaw, Superintendent, Larry Nelson, Acting Project Administrator, P.O. Box 220, Wapato, WA
                                                                                                   98951–0220, Telephones: (509) 865–2421 Superintendent, (509) 877–3155 Acting Project Administrator.

                                                                                                                   Rocky Mountain Region Contacts

                                                      Darryl LaCounte, Regional Director, Bureau of Indian Affairs, Rocky Mountain Regional Office, 2021 4th Avenue North, Billings, MT 59101,
                                                                                                            Telephone: (406) 247–7943.

                                                  Blackfeet Irrigation Project ..............    Thedis Crowe, Superintendent, Greg Tatsey, Irrigation Project Manager, Box 880, Browning, MT 59417,
                                                                                                   Telephones: (406) 338–7544, Superintendent, (406) 338–7519, Irrigation Project Manager.
                                                  Crow Irrigation Project ....................   Vianna Stewart, Superintendent, John Anevski, Acting Irrigation Project Manager, P.O. Box 69, Crow
                                                                                                   Agency, MT 59022, Telephones: (406) 638–2672, Superintendent, (406) 247–7998, Acting Irrigation
                                                                                                   Project Manager.
                                                  Fort Belknap Irrigation Project ........       John St. Pierre, Superintendent, Vacant, Irrigation Project Manager, (Project operation & maintenance con-
                                                                                                   tracted to Tribes), R.R.1, Box 980, Harlem, MT 59526, Telephones: (406) 353–2901, Superintendent,
                                                                                                   (406) 353–8454, Irrigation Project Manager (Tribal Office).
                                                  Fort Peck Irrigation Project .............     Howard Beemer, Superintendent, Huber Wright, Acting Irrigation Project Manager, P.O. Box 637, Poplar,
                                                                                                   MT 59255, Telephones: (406) 768–5312, Superintendent, (406) 653–1752, Irrigation Project Manager.
                                                  Wind River Irrigation Project ...........      Norma Gourneau, Superintendent, John Anevski, Acting Irrigation Project Manager, P.O. Box 158, Fort
                                                                                                   Washakie, WY 82514, Telephones: (307) 332–7810, Superintendent, (307) 247–7998, Acting Irrigation
                                                                                                   Project Manager.

                                                                                                                      Southwest Region Contacts

                                                    William T. Walker, Regional Director, Bureau of Indian Affairs, Southwest Regional Office, 1001 Indian School Road, Albuquerque, NM 87104,
                                                                                                             Telephone: (505) 563–3100.

                                                  Pine River Irrigation Project ............     Priscilla Bancroft, Superintendent, Vickie Begay, Irrigation Project Manager, P.O. Box 315, Ignacio, CO
                                                                                                   81137–0315, Telephones: (970) 563–4511, Superintendent, (970) 563–9484, Irrigation Project Manager.

                                                                                                                       Western Region Contacts

                                                     Bryan Bowker, Regional Director, Bureau of Indian Affairs, Western Regional Office, 2600 N. Central Ave., 4th Floor Mailroom, Phoenix, AZ
                                                                                                       85004, Telephone: (602) 379–6600.

                                                  Colorado River Irrigation Project ....         Kellie Youngbear Superintendent, Gary Colvin, Irrigation Project Manager, 12124 1st Avenue, Parker, AZ
                                                                                                   85344, Telephone: (928) 669–7111.
                                                  Duck Valley Irrigation Project .........       Joseph McDade, Superintendent, (Project operation & management compacted to Tribes), 2719 Argent
                                                                                                   Ave., Suite 4, Gateway Plaza, Elko, NV 89801, Telephone: (775) 738–5165, (208) 759–3100, (Tribal Of-
                                                                                                   fice).
                                                  Yuma Project, Indian Unit ...............      Denni Shields, Superintendent, 256 South Second Avenue, Suite D, Yuma, AZ 85364, Telephone: (928)
                                                                                                   782–1202.
                                                  San Carlos Irrigation Project, Indian          Ferris Begay, Project Manager, Clarence Begay, Irrigation Manager, 13805 N. Arizona Boulevard, Coo-
                                                    Works and Joint Works.                         lidge, AZ 85128, Telephone: (520) 723–6225.
                                                  Uintah Irrigation Project ..................   Bart Stevens Superintendent, Ken Asay, Irrigation System Manager, P.O. Box 130, Fort Duchesne, UT
                                                                                                   84026, Telephone: (435) 722–4300, (435) 722–4344.
mstockstill on DSK3G9T082PROD with NOTICES




                                                  Walker River Irrigation Project ........       Robert Eben, Superintendent, 311 E. Washington Street, Carson City, NV 89701, Telephone: (775) 887–
                                                                                                   3500.




                                             VerDate Sep<11>2014    18:51 Apr 05, 2017    Jkt 241001   PO 00000   Frm 00072   Fmt 4703   Sfmt 4703   E:\FR\FM\06APN1.SGM   06APN1


                                                                                         Federal Register / Vol. 82, No. 65 / Thursday, April 6, 2017 / Notices                                                                     16851

                                                  What irrigation assessments or charges                                where we recover costs of                                            where applicable. An asterisk
                                                  are adjusted by this notice?                                          administering, operating, maintaining,                               immediately following the rate category
                                                                                                                        and rehabilitating them. The table also                              notes the irrigation projects where 2016
                                                    The rate table below contains the                                   contains the final rates for the 2016                                rates are different from the 2015 rates.
                                                  current rates for all irrigation projects                             calendar year and subsequent years

                                                                                                                                                                                            Final 2015            Final 2016    Final 2017
                                                                                   Project name                                                        Rate category                           rate                  rate         rate **

                                                                                                                                   Northwest Region Rate Table

                                                  Flathead Indian Irrigation Project (See Note #1) ....................                    Basic-per acre—A ..................                       $26.00            $26.00        $26.00
                                                                                                                                           Basic-per acre—B ..................                        13.00             13.00         13.00
                                                                                                                                           Minimum Charge per tract .....                             75.00             75.00         75.00


                                                                                                                                                                                                                  Final 2015    Final 2016
                                                                                            Project name                                                                  Rate category                              rate          rate

                                                  Fort Hall Irrigation Project ..........................................................................   Basic per acre * ...............................           $49.00        $52.00
                                                                                                                                                            Minimum Charge per tract * ............                     35.00         37.00
                                                  Fort Hall Irrigation Project—Minor Units ....................................................             Basic per acre * ...............................            27.00         31.00
                                                                                                                                                            Minimum Charge per tract * ............                     35.00         37.00
                                                  Fort Hall Irrigation Project—Michaud ........................................................             Basic per acre * ...............................            50.50         55.00
                                                                                                                                                            Pressure per acre * ..........................              72.50         83.00
                                                                                                                                                            Minimum Charge per tract * ............                     35.00         37.00
                                                  Wapato Irrigation Project—Toppenish/Simcoe Units ................................                         Minimum Charge per bill * ...............                   24.00         25.00
                                                                                                                                                            Basic per acre * ...............................            24.00         25.00
                                                  Wapato Irrigation Project—Ahtanum Units ................................................                  Minimum Charge per bill * ...............                   25.00         30.00
                                                                                                                                                            Basic per acre * ...............................            25.00         30.00
                                                  Wapato Irrigation Project—Satus Unit .......................................................              Minimum Charge per bill .................                   79.00         79.00
                                                                                                                                                            ‘‘A’’ Basic per acre ..........................             79.00         79.00
                                                                                                                                                            ‘‘B’’ Basic per acre ..........................             85.00         85.00
                                                  Wapato Irrigation Project—Additional Works ............................................                   Minimum Charge per bill * ...............                   75.00         78.00
                                                                                                                                                            Basic per acre * ...............................            75.00         78.00
                                                  Wapato Irrigation Project—Water Rental ..................................................                 Minimum Charge .............................                86.00         86.00
                                                                                                                                                            Basic per acre .................................            86.00         86.00

                                                                                                                              Rocky Mountain Region Rate Table

                                                  Blackfeet Irrigation Project .........................................................................    Basic-per acre .................................            20.00         20.00
                                                  Crow Irrigation Project—Willow Creek O&M (includes Agency, Lodge                                          Basic-per acre * ...............................            24.80         26.00
                                                    Grass #1, Lodge Grass #2, Reno, Upper Little Horn, and Forty Mile
                                                    Units).
                                                  Crow Irrigation Project—All Others (includes Bighorn, Soap Creek, and                                     Basic-per acre * ...............................            24.80         26.00
                                                    Pryor Units).
                                                  Crow Irrigation Project—Two Leggins Unit ...............................................                  Basic-per    acre .................................         14.00         14.00
                                                  Crow Irrigation Two Leggins Drainage District ..........................................                  Basic-per    acre .................................          2.00          2.00
                                                  Fort Belknap Irrigation Project ...................................................................       Basic-per    acre * ...............................         15.00         16.00
                                                  Fort Peck Irrigation Project ........................................................................     Basic-per    acre .................................         26.00         26.00
                                                  Wind River Irrigation Project—Units 2, 3 and 4 ........................................                   Basic-per    acre * ...............................         21.00         22.50
                                                  Wind River Irrigation Project—Unit 6 ........................................................             Basic-per    acre .................................         21.00         21.00
                                                  Wind River Irrigation Project—LeClair District (see Note#2) ....................                          Basic-per    acre * ...............................         25.70         47.00
                                                  Wind River Irrigation Project—Crow Heart Unit ........................................                    Basic-per    acre * ...............................         14.00         15.50
                                                  Wind River Irrigation Project—A Canal Unit .............................................                  Basic-per    acre * ...............................         14.00         15.50
                                                  Wind River Irrigation Project—Riverton Valley Irrigation District ..............                          Basic-per    acre * ...............................         21.00         26.00

                                                                                                                                  Southwest Region Rate Table

                                                  Pine River Irrigation Project .......................................................................     Minimum Charge per tract ..............                     50.00         50.00
                                                                                                                                                            Basic-per acre * ...............................            17.00         18.00

                                                                                                                                    Western Region Rate Table

                                                  Colorado River Irrigation Project ...............................................................         Basic per acre up to 5.75 acre-feet                        $54.00        $54.00
                                                                                                                                                            Excess Water per acre-foot over                             17.00         17.00
mstockstill on DSK3G9T082PROD with NOTICES




                                                                                                                                                              5.75 acre-feet.
                                                  Duck Valley Irrigation Project ....................................................................       Basic per acre .................................             5.30          5.30
                                                  Yuma Project, Indian Unit (See Note #3) ..................................................                Basic per acre up to 5.0 acre-feet *                       108.50        113.00
                                                                                                                                                            Excess Water per acre-foot over                             24.50         24.50
                                                                                                                                                              5.0 acre-feet.
                                                                                                                                                            Basic per acre up to 5.0 acre-feet                         108.50        113.00
                                                                                                                                                              (Ranch 5) *.




                                             VerDate Sep<11>2014       18:51 Apr 05, 2017       Jkt 241001     PO 00000       Frm 00073      Fmt 4703       Sfmt 4703   E:\FR\FM\06APN1.SGM            06APN1


                                                  16852                                  Federal Register / Vol. 82, No. 65 / Thursday, April 6, 2017 / Notices

                                                                        Project name                                       Rate category                        Final 2015 rate                   Final 2016 rate                Final 2017 rate **

                                                  San Carlos Irrigation Project (Joint Works)                        Basic per acre * ..........            $35.00                           $30.00                            $25.00.
                                                    (See Note #4).

                                                                                                                     Final 2016—2017 Construction Water Rate Schedule:
                                                                                                                                            Off project construc-  On project construc-                                         On project construc-
                                                                                                                                                      tion           tion—gravity water                                           tion—pump water

                                                                                                                     Administrative Fee .....               $300.00                          $300.00                           $300.00.
                                                                                                                     Usage Fee .................            $250.00 per month ....           No Fee .......................    $100.00 per acre foot.
                                                                                                                     Excess Water Rate †                    $5.00 per 1,000 gal ...          No Charge .................       No Charge.

                                                                                                                     † The excess water rate applies to all water used in excess of 50,000 gallons in any one month.


                                                                                                                                                                                                                    Final 2015           Final 2016
                                                                                            Project name                                                                     Rate category                             rate                 rate

                                                  San Carlos Irrigation Project (Indian Works) (See Note#5) ......................                            Basic per acre * ...............................                $86.00          $81.00
                                                  Uintah Irrigation Project .............................................................................     Basic per acre .................................                 18.00           18.00
                                                                                                                                                              Minimum Bill ....................................                25.00           25.00
                                                  Walker River Irrigation Project ...................................................................         Basic per acre .................................                 31.00           31.00
                                                    * Notes irrigation projects where rates are adjusted.
                                                    ** The requirement for a final 2017 Rate is only applicable to the Flathead and San Carlos Irrigation Projects due to their specific billing re-
                                                  quirements.
                                                    Note #1: Federal Register Notice on April 29, 2016 established the 2016 rate for the Flathead Irrigation Project (81 FR 25691). This notice
                                                  makes final the 2017 rate for the Flathead Irrigation Project.
                                                    Note #2: The O&M rate varies yearly based upon the budget submitted by the LeClair District.
                                                    Note #3: The O&M rate for the Yuma Project, Indian Unit has two components. The first component is the O&M rate established by the Bu-
                                                  reau of Reclamation (BOR), the owner and operator of the Project. The BOR rate for 2016 is $110/acre. The second component is for the O&M
                                                  rate established by BIA to cover administrative costs including billing and collections for the Project. The 2016 BIA rate is $3.00/acre.
                                                    Note #4:The construction water rate schedule identifies the fees assessed for use of irrigation water for non-irrigation purposes. Federal Reg-
                                                  ister Notice on April 29, 2016 established the 2016 rate for the SCIP–JW (81 FR 25691). This notice makes final the 2017 rate for the SCIP–
                                                  JW.
                                                    Note #5: The 2016 O&M rate for the San Carlos Irrigation Project—Indian Works has three components. The first component is the O&M rate
                                                  established by the San Carlos Irrigation Project—Indian Works, the owner and operator of the Project; this rate is $51 per acre. The second
                                                  component is for the O&M rate established by the San Carlos Irrigation Project—Joint Works and is determined to be $25.00 per acre. The third
                                                  component is the O&M rate established by the San Carlos Irrigation Project Joint Control Board and is $5 per acre.


                                                  Consultation and Coordination With                                    component of our overall coordination                                 Unfunded Mandates Reform Act of
                                                  Tribal Governments (Executive Order                                   and consultation process to provide                                   1995
                                                  13175)                                                                notice to, and request comments from,                                    These rate adjustments do not impose
                                                                                                                        these entities when we adjust irrigation                              an unfunded mandate on state, local, or
                                                    The Department of the Interior strives                              assessment rates.                                                     tribal governments in the aggregate, or
                                                  to strengthen its government-to-
                                                                                                                                                                                              on the private sector, of more than $130
                                                  government relationship with Indian                                   Actions Concerning Regulations That
                                                                                                                                                                                              million per year. They do not have a
                                                  Tribes through a commitment to                                        Significantly Affect Energy Supply,
                                                                                                                                                                                              significant or unique effect on state,
                                                  consultation with Indian Tribes and                                   Distribution, or Use (Executive Order                                 local, or tribal governments or the
                                                  recognition of their right to self-                                   13211)                                                                private sector. Therefore, the
                                                  governance and Tribal sovereignty. We                                                                                                       Department is not required to prepare a
                                                  have evaluated this notice under the                                    The rate adjustments are not a
                                                                                                                        significant energy action under the                                   statement containing the information
                                                  Department’s consultation policy and                                                                                                        required by the Unfunded Mandates
                                                  under the criteria of Executive Order                                 definition in Executive Order 13211. A
                                                                                                                                                                                              Reform Act (2 U.S.C. 1531 et seq.).
                                                  13175 and have determined there to be                                 Statement of Energy Effects is not
                                                  substantial direct effects on federally                               required.                                                             Takings (Executive Order 12630)
                                                  recognized Tribes because the irrigation                                                                                                      These rate adjustments do not effect a
                                                                                                                        Regulatory Planning and Review
                                                  projects are located on or associated                                                                                                       taking of private property or otherwise
                                                                                                                        (Executive Order 12866)
                                                  with Indian reservations. To fulfill its                                                                                                    have ‘‘takings’’ implications under
                                                  consultation responsibility to Tribes and                               These rate adjustments are not a                                    Executive Order 12630. The rate
                                                  Tribal organizations, BIA                                             significant regulatory action and do not                              adjustments do not deprive the public,
                                                  communicates, coordinates, and                                        need to be reviewed by the Office of                                  state, or local governments of rights or
                                                  consults on a continuing basis with                                   Management and Budget under                                           property.
                                                  these entities on issues of water                                     Executive Order 12866.
                                                  delivery, water availability, and costs of                                                                                                  Federalism (Executive Order 13132)
                                                  administration, operation, maintenance,                               Regulatory Flexibility Act                                               Under the criteria in section 1 of
mstockstill on DSK3G9T082PROD with NOTICES




                                                  and rehabilitation of projects that                                                                                                         Executive Order 13132, these rate
                                                  concern them. This is accomplished at                                   These rate adjustments are not a rule                               adjustments do not have sufficient
                                                  the individual irrigation project by                                  for the purposes of the Regulatory                                    federalism implications to warrant the
                                                  project, agency, and regional                                         Flexibility Act because they establish ‘‘a                            preparation of a federalism summary
                                                  representatives, as appropriate, in                                   rule of particular applicability relating                             impact statement because they will not
                                                  accordance with local protocol and                                    to rates.’’ 5 U.S.C. 601(2).                                          affect the States, the relationship
                                                  procedures. This notice is one                                                                                                              between the national government and


                                             VerDate Sep<11>2014       18:51 Apr 05, 2017       Jkt 241001     PO 00000       Frm 00074      Fmt 4703        Sfmt 4703    E:\FR\FM\06APN1.SGM           06APN1


                                                                                 Federal Register / Vol. 82, No. 65 / Thursday, April 6, 2017 / Notices                                                 16853

                                                  the States, or the distribution of power                SUMMARY:   In compliance with the                     location listed in the ADDRESSES section.
                                                  and responsibilities among various                      Paperwork Reduction Act of 1995, the                  Before including your address, phone
                                                  levels of government. A federalism                      Assistant Secretary—Indian Affairs is                 number, email address or other personal
                                                  summary impact statement is not                         seeking comments on the renewal of                    identifying information in your
                                                  required.                                               Office of Management and Budget                       comment, you should be aware that
                                                                                                          (OMB) approval for the collection of                  your entire comment—including your
                                                  Civil Justice Reform (Executive Order
                                                                                                          information for the ‘‘Financial                       personal identifying information—may
                                                  12988)
                                                                                                          Assistance and Social Services’’                      be made publicly available at any time.
                                                     This notice complies with the                        authorized by OMB Control Number                      While you can ask us in your comment
                                                  requirements of Executive Order 12988.                  1076–0017. This information collection                to withhold your personal identifying
                                                  Specifically, in issuing this notice, the               expires June 30, 2017.                                information from public review, we
                                                  Department has taken the necessary                      DATES: Submit comments on or before                   cannot guarantee that we will be able to
                                                  steps to eliminate drafting errors and                  June 5, 2017.
                                                  ambiguity, minimize potential litigation,                                                                     do so.
                                                                                                          ADDRESSES: You may submit comments
                                                  and provide a clear legal standard for                  on the information collection to Ms.                  III. Data
                                                  affected conduct as required by section                 Evangeline Campbell, Chief, Division of
                                                  3 of Executive Order 12988.                                                                                      OMB Control Number: 1076–0017.
                                                                                                          Human Services, Office of Indian
                                                  Paperwork Reduction Act of 1995                         Services, Bureau of Indian Affairs, 1849                 Title: Financial Assistance and Social
                                                                                                          C Street NW., MS–4513–MIB,                            Services, 25 CFR 20.
                                                    These rate adjustments do not affect                  Washington, DC 20240; facsimile: (202)
                                                  the collections of information which                                                                             Brief Description of Collection:
                                                                                                          208–5113; email: Evangline.Campbell@                  Submission of this information is
                                                  have been approved by the Office of                     bia.gov.
                                                  Information and Regulatory Affairs,                                                                           required of Indian applicants of BIA
                                                  Office of Management and Budget,                        FOR FURTHER INFORMATION CONTACT: Ms.                  financial assistance and social services.
                                                  under the Paperwork Reduction Act of                    Evangeline Campbell, telephone: (202)                 BIA uses the information to determine
                                                  1995. The OMB Control Number is                         513–7621.                                             if an individual is eligible for services
                                                  1076–0141 and expires June 30, 2019.                    SUPPLEMENTARY INFORMATION:                            and, where appropriate, to conduct an
                                                                                                          I. Abstract                                           employability assessment and jointly
                                                  National Environmental Policy Act
                                                                                                                                                                develop with the individual an
                                                     The Department has determined that                      The Bureau of Indian Affairs (BIA) is              Individual Self-Sufficiency Plan (ISP)
                                                  these rate adjustments do not constitute                seeking to renew the information                      outlining how the individual can attain
                                                  a major Federal action significantly                    collection it conducts to provide                     self-sufficiency. A response is required
                                                  affecting the quality of the human                      assistance under 25 CFR 20 to eligible                to obtain or retain a benefit.
                                                  environment and that no detailed                        Indians when comparable financial
                                                  statement is required under the National                assistance or social services either are                 Type of Review: Extension without
                                                  Environmental Policy Act of 1969, 42                    not available or not provided by State,               change of currently approved collection.
                                                  U.S.C. 4321–4370(d), pursuant to 43                     tribal, county, local, or other Federal                  Respondents: Individual Indians
                                                  CFR 46.210(i). In addition, the rate                    agencies. Approval for this collection                seeking financial assistance or social
                                                  adjustments do not present any of the 12                expires June 30, 2017. The information                services from BIA.
                                                  extraordinary circumstances listed at 43                collection allows BIA to determine
                                                                                                                                                                   Estimated Number of Respondents:
                                                  CFR 46.215.                                             whether an individual is eligible for
                                                                                                          assistance and services. No third party               240,000 provide information on the
                                                  Data Quality Act                                        notification or public disclosure burden              application, of those, 95,000 contribute
                                                    In developing this notice, we did not                 is associated with this collection.                   information to an employability
                                                  conduct or use a study, experiment, or                                                                        assessment and ISP.
                                                                                                          II. Request for Comments
                                                  survey requiring peer review under the                                                                           Frequency of Response: Once, on
                                                  Data Quality Act (Pub. L. 106–554).                        The BIA requests your comments on                  occasion.
                                                                                                          this collection concerning: (a) The
                                                   Dated: March 29, 2017.                                                                                          Estimated Time per Response: 1.5 (0.5
                                                                                                          necessity of this information collection
                                                  Michael S. Black,                                       for the proper performance of the                     hours for the application + 1 hour for
                                                  Acting Assistant Secretary—Indian Affairs.              functions of the agency, including                    the employability assessment and ISP).
                                                  [FR Doc. 2017–06829 Filed 4–5–17; 8:45 am]              whether the information will have                        Obligation to Respond: Response
                                                  BILLING CODE 4337–15–P                                  practical utility; (b) The accuracy of the            required to obtain a benefit.
                                                                                                          agency’s estimate of the burden (hours                   Estimated Total Annual Hour Burden:
                                                                                                          and cost) of the collection of                        215,000 hours ((240,000 × .05 hours for
                                                  DEPARTMENT OF THE INTERIOR                              information, including the validity of                applications) + (95,000 × 1 hour for
                                                                                                          the methodology and assumptions used;                 employability assessment and ISP)).
                                                  Bureau of Indian Affairs                                (c) Ways we could enhance the quality,
                                                                                                          utility, and clarity of the information to               Estimated Total Annual Non-Hour
                                                  [178A2100DD/AAKC001030/                                 be collected; and (d) Ways we could                   Dollar Cost: $0.
                                                  A0A501010.999900 253G]                                  minimize the burden of the collection of              Elizabeth K. Appel,
mstockstill on DSK3G9T082PROD with NOTICES




                                                                                                          the information on the respondents.
                                                  Renewal of Agency Information                              Please note that an agency may not                 Director, Office of Regulatory Affairs and
                                                  Collection for Financial Assistance and                                                                       Collaborative Action—Indian Affairs.
                                                                                                          conduct or sponsor, and an individual
                                                  Social Services                                         need not respond to, a collection of                  [FR Doc. 2017–06795 Filed 4–5–17; 8:45 am]

                                                  AGENCY:    Bureau of Indian Affairs,                    information unless it has a valid OMB                 BILLING CODE 4337–15–P

                                                  Interior.                                               Control Number.
                                                                                                             It is our policy to make all comments
                                                  ACTION:  Notice of request for comments.
                                                                                                          available to the public for review at the


                                             VerDate Sep<11>2014   18:51 Apr 05, 2017   Jkt 241001   PO 00000   Frm 00075   Fmt 4703   Sfmt 9990   E:\FR\FM\06APN1.SGM   06APN1



Document Created: 2017-04-06 01:46:48
Document Modified: 2017-04-06 01:46:48
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
ActionNotice.
DatesThe irrigation assessment rates are current as of January 1, 2016.
ContactFor details about a particular BIA irrigation project or facility, please use the tables in the SUPPLEMENTARY INFORMATION section to contact the regional or local office where the project or facility is located.