82_FR_17720 82 FR 17651 - Transcontinental Gas Pipe Line Company, LLC; Notice of Application

82 FR 17651 - Transcontinental Gas Pipe Line Company, LLC; Notice of Application

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 82, Issue 69 (April 12, 2017)

Page Range17651-17652
FR Document2017-07354

Federal Register, Volume 82 Issue 69 (Wednesday, April 12, 2017)
[Federal Register Volume 82, Number 69 (Wednesday, April 12, 2017)]
[Notices]
[Pages 17651-17652]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2017-07354]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket Nos. CP17-101-000; PF16-5-000]


Transcontinental Gas Pipe Line Company, LLC; Notice of 
Application

    Take notice that on March 27, 2017, Transcontinental Gas Pipe Line 
Company, LLC (Transco), P.O. Box 1396, Houston, Texas 77251, filed in 
the above referenced docket an application pursuant to section 7(c) of 
the Natural Gas Act (NGA) for its proposed Northeast Supply Enhancement 
Project. Specifically, Transco proposes to: (i) Construct a 10.17-mile, 
42-inch-diameter loop in Lancaster County, Pennsylvania; (ii) construct 
a 3.43-mile, 26-inch-diameter loop in Middlesex County, New Jersey; 
(iii) construct a 23.49-mile, 26-inch-diameter loop in Middlesex 
County, New Jersey and in New York State waters; (iv) add 21,902 
horsepower (hp) at its existing Compressor Station 200 in Chester 
County, Pennsylvania; (v) construct a new 32,000 hp compressor station 
(Compressor Station 206) in Somerset County, New Jersey; and (vi) 
construct various additional facilities. Transco states that the 
Northeast Supply Enhancement Project will provide 400,000 dekatherms 
per day of firm transportation service. Transco estimates the cost of 
the project to be approximately $926.5 million, all as more fully set 
forth in the application which is on file with the Commission and open 
to public inspection. The filing is available for review at the 
Commission in the Public Reference Room or may be viewed on the 
Commission's Web site at http://www.ferc.gov using the ``eLibrary'' 
link. Enter the docket number excluding the last three digits in the 
docket number field to access the document. For assistance, contact 
FERC at [email protected] or call toll-free, (886) 208-3676 or 
TYY, (202) 502-8659.
    Any questions concerning this application may be directed to Bill 
Hammons, Transcontinental Gas Pipe Line Company, LLC, P.O. Box 1396, 
Houston, Texas 77251, by telephone at (713) 215-2130.
    On May 18, 2016, Commission staff granted Transco's request to 
utilize the Pre-Filing Process and assigned Docket No. PF16-5-000 to 
staff activities involved in the Northeast Supply Enhancement Project. 
Now, as of the March 27, 2017 application, the Pre-Filing Process for 
this project has ended. From this time forward, this proceeding will be 
conducted in Docket No. CP17-101-000, as noted in the caption of the 
Notice.
    Pursuant to section 157.9 of the Commission's rules (18 CFR 157.9), 
within 90 days of this Notice, the Commission staff will issue a Notice 
of Schedule for Environmental Review. If a Notice of Schedule for 
Environmental Review is issued, it will indicate, among other 
milestones, the anticipated date for the Commission staff's issuance of 
the final environmental impact statement (FEIS) for this proposal. The 
issuance of a Notice of Schedule for Environmental Review will serve to 
notify federal and state agencies of the timing for the completion of 
all necessary reviews, and the subsequent need to complete all federal 
authorizations within 90 days of the date of issuance of the Commission 
staff's FEIS.
    There are two ways to become involved in the Commission's review of 
this project. First, any person wishing to obtain legal status by 
becoming a party to the proceedings for this project should, on or 
before the comment date stated below file with the Federal Energy 
Regulatory Commission, 888 First Street NE., Washington, DC 20426, a 
motion to intervene in accordance with the requirements of the 
Commission's Rules of Practice and Procedure (18 CFR 385.214 or 
385.211) and the Regulations under the NGA (18 CFR 157.10). A person 
obtaining party status will be placed on the service list maintained by 
the Secretary of the Commission and will receive copies of all 
documents filed by the applicant and by all other parties. A party must 
submit seven copies of filings made in the proceeding with the 
Commission and must mail a copy to the applicant and to every other 
party. Only parties to the proceeding can ask for court review of 
Commission orders in the proceeding.
    However, a person does not have to intervene in order to have 
comments considered. The second way to participate is by filing with 
the Secretary of the Commission, as soon as possible, an original and 
two copies of comments in support of or in opposition to this project. 
The Commission will consider these comments in determining the 
appropriate action to be taken, but the filing of a comment alone will 
not serve to make the filer a party to the proceeding. The Commission's 
rules require that persons filing comments in opposition to the project 
provide copies of their protests only to the party or parties directly 
involved in the protest.
    Persons who wish to comment only on the environmental review of 
this

[[Page 17652]]

project should submit an original and two copies of their comments to 
the Secretary of the Commission. Environmental commentors will be 
placed on the Commission's environmental mailing list, will receive 
copies of the environmental documents, and will be notified of meetings 
associated with the Commission's environmental review process. 
Environmental commentors will not be required to serve copies of filed 
documents on all other parties. However, the non-party commentors will 
not receive copies of all documents filed by other parties or issued by 
the Commission (except for the mailing of environmental documents 
issued by the Commission) and will not have the right to seek court 
review of the Commission's final order.
    The Commission strongly encourages electronic filings of comments, 
protests and interventions in lieu of paper using the ``eFiling'' link 
at http://www.ferc.gov. Persons unable to file electronically should 
submit an original and seven copies of the protest or intervention to 
the Federal Energy Regulatory Commission, 888 First Street NE., 
Washington, DC 20426.
    Comment Date: 5:00 p.m. Eastern Time on April 27, 2017.

    Dated: April 6, 2017.
Kimberly D. Bose,
Secretary.
[FR Doc. 2017-07354 Filed 4-11-17; 8:45 am]
 BILLING CODE 6717-01-P



                                                                               Federal Register / Vol. 82, No. 69 / Wednesday, April 12, 2017 / Notices                                           17651

                                                  as set forth in the Notice of Availability.             DEPARTMENT OF ENERGY                                  will be conducted in Docket No. CP17–
                                                  76 FR 51357, 51358. This application                                                                          101–000, as noted in the caption of the
                                                  form is necessary in order for DOE to                   Federal Energy Regulatory                             Notice.
                                                  identify if applicants meet basic                       Commission                                               Pursuant to section 157.9 of the
                                                  requirements for use of the AFS and                     [Docket Nos. CP17–101–000; PF16–5–000]
                                                                                                                                                                Commission’s rules (18 CFR 157.9),
                                                  implement this important                                                                                      within 90 days of this Notice, the
                                                  nonproliferation initiative; (5) Annual                 Transcontinental Gas Pipe Line                        Commission staff will issue a Notice of
                                                  Estimated Number of Respondents: 10;                    Company, LLC; Notice of Application                   Schedule for Environmental Review. If
                                                  (6) Annual Estimated Number of Total                                                                          a Notice of Schedule for Environmental
                                                                                                             Take notice that on March 27, 2017,                Review is issued, it will indicate, among
                                                  Responses: 10; (7) Annual Estimated                     Transcontinental Gas Pipe Line
                                                  Number of Burden Hours: 8; (8) Annual                                                                         other milestones, the anticipated date
                                                                                                          Company, LLC (Transco), P.O. Box                      for the Commission staff’s issuance of
                                                  Estimated Reporting and Recordkeeping                   1396, Houston, Texas 77251, filed in the
                                                  Cost Burden: $1,800.                                                                                          the final environmental impact
                                                                                                          above referenced docket an application                statement (FEIS) for this proposal. The
                                                     Statutory Authority: The Secretary of                pursuant to section 7(c) of the Natural               issuance of a Notice of Schedule for
                                                  Energy is authorized pursuant to the                    Gas Act (NGA) for its proposed                        Environmental Review will serve to
                                                  Atomic Energy Act of 1954, as amended                   Northeast Supply Enhancement Project.                 notify federal and state agencies of the
                                                  (Pub. L. 83–703), and the Nuclear Non-                  Specifically, Transco proposes to: (i)                timing for the completion of all
                                                  Proliferation Act of 1978 (NNPA) (Pub.                  Construct a 10.17-mile, 42-inch-                      necessary reviews, and the subsequent
                                                  L. 95–242) to encourage the widespread                  diameter loop in Lancaster County,                    need to complete all federal
                                                  use of atomic energy for peaceful                       Pennsylvania; (ii) construct a 3.43-mile,             authorizations within 90 days of the
                                                  purposes, and to cooperate with other                   26-inch-diameter loop in Middlesex                    date of issuance of the Commission
                                                  nations by distributing nuclear material                County, New Jersey; (iii) construct a                 staff’s FEIS.
                                                  where appropriate safeguards measures                   23.49-mile, 26-inch-diameter loop in                     There are two ways to become
                                                  are in place to ensure the material is                  Middlesex County, New Jersey and in                   involved in the Commission’s review of
                                                  properly controlled and used for                        New York State waters; (iv) add 21,902                this project. First, any person wishing to
                                                  peaceful purposes. In 2005, DOE set                     horsepower (hp) at its existing                       obtain legal status by becoming a party
                                                  aside a portion of its LEU inventory to                 Compressor Station 200 in Chester                     to the proceedings for this project
                                                  be used to support the International                    County, Pennsylvania; (v) construct a                 should, on or before the comment date
                                                  Atomic Energy Agency’s (IAEA)                           new 32,000 hp compressor station                      stated below file with the Federal
                                                  International Nuclear Fuel Bank (INFB)                  (Compressor Station 206) in Somerset                  Energy Regulatory Commission, 888
                                                  initiative, which is envisioned as an                   County, New Jersey; and (vi) construct                First Street NE., Washington, DC 20426,
                                                  LEU reserve that will be administered                   various additional facilities. Transco                a motion to intervene in accordance
                                                                                                          states that the Northeast Supply                      with the requirements of the
                                                  by the IAEA and that will serve as a
                                                                                                          Enhancement Project will provide                      Commission’s Rules of Practice and
                                                  back-up for global supply disruptions.
                                                                                                          400,000 dekatherms per day of firm                    Procedure (18 CFR 385.214 or 385.211)
                                                  Congress later appropriated $49,540,000
                                                                                                          transportation service. Transco                       and the Regulations under the NGA (18
                                                  in the Consolidated Appropriations Act,
                                                                                                          estimates the cost of the project to be               CFR 157.10). A person obtaining party
                                                  2008 (Pub. L. 110–161) to fund a portion
                                                                                                          approximately $926.5 million, all as                  status will be placed on the service list
                                                  of the INFB. Congress, in the
                                                                                                          more fully set forth in the application               maintained by the Secretary of the
                                                  Explanatory Statement accompanying
                                                                                                          which is on file with the Commission                  Commission and will receive copies of
                                                  the House Appropriations Committee
                                                                                                          and open to public inspection. The                    all documents filed by the applicant and
                                                  Print (which in the Act was given the
                                                                                                          filing is available for review at the                 by all other parties. A party must submit
                                                  same effect as a joint explanatory
                                                                                                          Commission in the Public Reference                    seven copies of filings made in the
                                                  statement), noted that the INFB freed up                Room or may be viewed on the                          proceeding with the Commission and
                                                  DOE’s LEU set-aside, and recommended                    Commission’s Web site at http://                      must mail a copy to the applicant and
                                                  DOE also ‘‘allow U.S. interests to                      www.ferc.gov using the ‘‘eLibrary’’ link.             to every other party. Only parties to the
                                                  purchase uranium fuel from the Reliable                 Enter the docket number excluding the                 proceeding can ask for court review of
                                                  Fuel Supply [now the AFS] in the event                  last three digits in the docket number                Commission orders in the proceeding.
                                                  of supply disruption.’’ (H. Approp.                     field to access the document. For                        However, a person does not have to
                                                  Cmte. Print at 592.)                                    assistance, contact FERC at                           intervene in order to have comments
                                                     The sale of LEU from the AFS will be                 FERCOnlineSupport@ferc.gov or call                    considered. The second way to
                                                  conducted consistent with applicable                    toll-free, (886) 208–3676 or TYY, (202)               participate is by filing with the
                                                  law, the policies and guidance in the                   502–8659.                                             Secretary of the Commission, as soon as
                                                  ‘‘Secretary of Energy’s 2008 Policy                        Any questions concerning this                      possible, an original and two copies of
                                                  Statement of Management of the                          application may be directed to Bill                   comments in support of or in opposition
                                                  Department of Energy’s Excess Uranium                   Hammons, Transcontinental Gas Pipe                    to this project. The Commission will
                                                  Inventory’’ (March 11, 2008), and the                   Line Company, LLC, P.O. Box 1396,                     consider these comments in
                                                  DOE Excess Uranium Inventory                            Houston, Texas 77251, by telephone at                 determining the appropriate action to be
                                                  Management Plan.                                        (713) 215–2130.                                       taken, but the filing of a comment alone
                                                                                                             On May 18, 2016, Commission staff                  will not serve to make the filer a party
                                                    Issued in Washington, DC on March 31,
                                                                                                          granted Transco’s request to utilize the              to the proceeding. The Commission’s
mstockstill on DSK30JT082PROD with NOTICES




                                                  2017.
                                                                                                          Pre-Filing Process and assigned Docket                rules require that persons filing
                                                  David Huizenga,                                         No. PF16–5–000 to staff activities                    comments in opposition to the project
                                                  Acting Deputy Administrator, Defense                    involved in the Northeast Supply                      provide copies of their protests only to
                                                  Nuclear Nonproliferation, National Nuclear              Enhancement Project. Now, as of the                   the party or parties directly involved in
                                                  Security Administration.                                March 27, 2017 application, the Pre-                  the protest.
                                                  [FR Doc. 2017–07384 Filed 4–11–17; 8:45 am]             Filing Process for this project has ended.               Persons who wish to comment only
                                                  BILLING CODE 6450–P                                     From this time forward, this proceeding               on the environmental review of this


                                             VerDate Sep<11>2014   18:45 Apr 11, 2017   Jkt 241001   PO 00000   Frm 00027   Fmt 4703   Sfmt 4703   E:\FR\FM\12APN1.SGM   12APN1


                                                  17652                        Federal Register / Vol. 82, No. 69 / Wednesday, April 12, 2017 / Notices

                                                  project should submit an original and                      i. FERC Contact: Mr. M. Joseph                     obstruct, or divert international
                                                  two copies of their comments to the                     Fayyad, (202) 502–8759, Mo.Fayyad@                    boundary waters. The licensee states
                                                  Secretary of the Commission.                            ferc.gov.                                             that the removal of the gates will lower
                                                  Environmental commentors will be                           j. Deadline for filing comments,                   the water elevation at the dam to 427.94
                                                  placed on the Commission’s                              motions to intervene and protests, is 30              feet msl, but the minimum elevation
                                                  environmental mailing list, will receive                days from the issuance date of this                   will be 428.69 msl because of a natural
                                                  copies of the environmental documents,                  notice. The Commission strongly                       obstruction upstream of the dam.
                                                  and will be notified of meetings                        encourages electronic filing. Please file                m. Locations of the Application: A
                                                  associated with the Commission’s                        motions to intervene, protests,                       copy of the application is available for
                                                  environmental review process.                           comments, and recommendations, using                  inspection and reproduction at the
                                                  Environmental commentors will not be                    the Commission’s eFiling system at                    Commission’s Public Reference Room,
                                                  required to serve copies of filed                       http://www.ferc.gov/docs-filing/                      located at 888 First Street NE., Room
                                                  documents on all other parties.                         efiling.asp. Commenters can submit                    2A, Washington, DC 20426, or by calling
                                                  However, the non-party commentors                       brief comments up to 6,000 characters,                (202) 502–8371. This filing may also be
                                                  will not receive copies of all documents                without prior registration, using the                 viewed on the Commission’s Web site at
                                                  filed by other parties or issued by the                 eComment system at http://                            http://www.ferc.gov/docs-filing/
                                                  Commission (except for the mailing of                   www.ferc.gov/docs-filing/                             elibrary.asp. Enter the docket number
                                                  environmental documents issued by the                   ecomment.asp. You must include your                   excluding the last three digits in the
                                                  Commission) and will not have the right                 name and contact information at the end               docket number field to access the
                                                  to seek court review of the                             of your comments. For assistance,                     document. You may also register online
                                                  Commission’s final order.                               please contact FERC Online Support at                 at http://www.ferc.gov/docs-filing/
                                                     The Commission strongly encourages                   FERCOnlineSupport@ferc.gov, (866)                     esubscription.asp to be notified via
                                                  electronic filings of comments, protests                208–3676 (toll free), or (202) 502–8659               email of new filings and issuances
                                                  and interventions in lieu of paper using                (TTY). In lieu of electronic filing, please           related to this or other pending projects.
                                                  the ‘‘eFiling’’ link at http://                         send a paper copy to: Secretary, Federal              For assistance, call 1–866–208–3676 or
                                                  www.ferc.gov. Persons unable to file                    Energy Regulatory Commission, 888                     email FERCOnlineSupport@ferc.gov, for
                                                  electronically should submit an original                First Street NE., Washington, DC 20426.               TTY, call (202) 502–8659. A copy is also
                                                  and seven copies of the protest or                      The first page of any filing should                   available for inspection and
                                                  intervention to the Federal Energy                      include docket number P–2660–028.                     reproduction at the address in item (h)
                                                  Regulatory Commission, 888 First Street                    k. Description of Project Facilities:              above.
                                                  NE., Washington, DC 20426.                              The Forest City Project is located at                    n. Individuals desiring to be included
                                                     Comment Date: 5:00 p.m. Eastern                      river mile 58 of the East Branch of the               on the Commission’s mailing list should
                                                  Time on April 27, 2017.                                 St. Croix River on the international                  so indicate by writing to the Secretary
                                                                                                          boundary between the United States and                of the Commission.
                                                    Dated: April 6, 2017.                                 Canada. The existing project as licensed                 o. Comments, Protests, or Motions to
                                                  Kimberly D. Bose,                                       includes only the lands, waters, and                  Intervene: Anyone may submit
                                                  Secretary.                                              structures that are located in the United             comments, a protest, or a motion to
                                                  [FR Doc. 2017–07354 Filed 4–11–17; 8:45 am]             States, which consist of: (a) A 147-foot-             intervene in accordance with the
                                                  BILLING CODE 6717–01–P                                  long section of the 540-foot-long, 12-                requirements of Rules of Practice and
                                                                                                          foot-high earth Forest City Dam that                  Procedure, 18 CFR 385.210, .211, and
                                                                                                          includes: (i) A 110-foot-long west earth              .214. In determining the appropriate
                                                  DEPARTMENT OF ENERGY                                    embankment, and (ii) a 37-foot-long                   action to take, the Commission will
                                                                                                          section of the timber-crib spillway                   consider all protests or other comments
                                                  Federal Energy Regulatory                               section with two 8.3-foot-wide, 10-foot-              filed, but only those who file a motion
                                                  Commission                                              high spillway gates on the west side of               to intervene in accordance with the
                                                  [Project No. 2660–028]                                  the spillway, which control the                       Commission’s Rules may become a
                                                                                                          impoundment between a minimum                         party to the proceeding. Any comments,
                                                  Woodland Pulp LLC; Notice of                            elevation of 427.94 feet mean sea level               protests, or motions to intervene must
                                                  Application Accepted for Filing,                        (msl) and a maximum elevation of                      be received on or before the specified
                                                  Soliciting Comments, Motions To                         434.94 feet msl; (b) a 9,141-acre portion             comment date for the particular
                                                  Intervene, and Protests                                 of the 17,040-acre multi-lake                         application.
                                                                                                          impoundment (North Lake and East                         p. Filing and Service of Responsive
                                                    Take notice that the following                                                                              Documents: Any filing must (1) Bear in
                                                                                                          Grand Lake); and (c) appurtenant
                                                  hydroelectric application has been filed                                                                      all capital letters the title
                                                                                                          facilities. The project does not occupy
                                                  with the Commission and is available                                                                          ‘‘COMMENTS’’, ‘‘PROTEST’’, or
                                                                                                          federal lands and there are no
                                                  for public inspection:                                                                                        ‘‘MOTION TO INTERVENE’’ as
                                                                                                          generating facilities located at the
                                                    a. Type of Application: Surrender of                                                                        applicable; (2) set forth in the heading
                                                                                                          project.
                                                  License.                                                                                                      the name of the applicant and the
                                                                                                             l. Description of Request: The licensee
                                                    b. Project No.: 2660–028.
                                                    c. Date Filed: December 23, 2016.                     proposes to surrender the license for the             project number of the application to
                                                    d. Applicant: Woodland Pulp LLC.                      Forest City Project due to economic                   which the filing responds; (3) furnish
                                                    e. Name of Project: Forest City Project.              considerations. As part of its surrender,             the name, address, and telephone
                                                    f. Location: On the East Branch of the                the licensee plans to remove the two                  number of the person protesting or
mstockstill on DSK30JT082PROD with NOTICES




                                                  St. Croix River in Washington and                       8.3-foot-wide, 10-foot-high gates on the              intervening; and (4) otherwise comply
                                                  Aroostook Counties, Maine.                              west side of the spillway. The licensee               with the requirements of 18 CFR
                                                    g. Filed Pursuant to: 18 CFR 6.1.                     states that by removing the gates, water              385.2001 through 385.2005. All
                                                    h. Applicant Contact: Mr. Scott Beal,                 flow will return to natural flow                      comments, motions to intervene, or
                                                  Woodland Pulp LLC, 144 Main Street,                     conditions and the Forest City Dam will               protests must set forth their evidentiary
                                                  Baileyville, ME 04694, Tel: 207–427–                    no longer act as the water control                    basis and otherwise comply with the
                                                  4004.                                                   structure for East Grand Lake or use,                 requirements of 18 CFR 4.34(b). All


                                             VerDate Sep<11>2014   18:45 Apr 11, 2017   Jkt 241001   PO 00000   Frm 00028   Fmt 4703   Sfmt 4703   E:\FR\FM\12APN1.SGM   12APN1



Document Created: 2017-04-12 00:23:12
Document Modified: 2017-04-12 00:23:12
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
Dates5:00 p.m. Eastern Time on April 27, 2017.
FR Citation82 FR 17651 

2025 Federal Register | Disclaimer | Privacy Policy
USC | CFR | eCFR