82_FR_19838 82 FR 19757 - South Carolina Electric & Gas Company, South Carolina Public Service Authority, Virgil C. Summer Nuclear Station, Units 2 and 3, Inspections, Tests, Analyses, and Acceptance Criteria

82 FR 19757 - South Carolina Electric & Gas Company, South Carolina Public Service Authority, Virgil C. Summer Nuclear Station, Units 2 and 3, Inspections, Tests, Analyses, and Acceptance Criteria

NUCLEAR REGULATORY COMMISSION

Federal Register Volume 82, Issue 81 (April 28, 2017)

Page Range19757-19758
FR Document2017-08618

The U.S. Nuclear Regulatory Commission (NRC) staff has determined that the inspections, tests, and analyses have been successfully completed, and that the specified acceptance criteria are met for multiple inspections, tests, analyses, and acceptance criteria (ITAAC) for the Virgil C. Summer Nuclear Station (VCSNS), Units 2 and 3.

Federal Register, Volume 82 Issue 81 (Friday, April 28, 2017)
[Federal Register Volume 82, Number 81 (Friday, April 28, 2017)]
[Notices]
[Pages 19757-19758]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2017-08618]



[[Page 19757]]

-----------------------------------------------------------------------

NUCLEAR REGULATORY COMMISSION

[Docket Nos. 52-027 and 52-028; NRC-2008-0441]


South Carolina Electric & Gas Company, South Carolina Public 
Service Authority, Virgil C. Summer Nuclear Station, Units 2 and 3, 
Inspections, Tests, Analyses, and Acceptance Criteria

AGENCY: Nuclear Regulatory Commission.

ACTION: Determination of the successful completion of inspections, 
tests, and analyses.

-----------------------------------------------------------------------

SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) staff has 
determined that the inspections, tests, and analyses have been 
successfully completed, and that the specified acceptance criteria are 
met for multiple inspections, tests, analyses, and acceptance criteria 
(ITAAC) for the Virgil C. Summer Nuclear Station (VCSNS), Units 2 and 
3.

DATES: The determination of the successful completion of inspections, 
tests, and analyses for these ITAAC for VCSNS, Units 2 and 3 is 
effective April 28, 2017.

ADDRESSES: Please refer to Docket ID NRC-2008-0441 when contacting the 
NRC about the availability of information regarding this document. You 
may obtain publicly-available information related to this document 
using any of the following methods:
     Federal Rulemaking Web site: Go to http://www.regulations.gov and search for Docket ID NRC-2008-0441. Address 
questions about NRC dockets to Carol Gallagher; telephone: 301-415-
3463; email: [email protected]. For technical questions, contact 
the individual listed in the FOR FURTHER INFORMATION CONTACT section of 
this document.
     NRC's Agencywide Documents Access and Management System 
(ADAMS): You may obtain publicly available documents online in the 
ADAMS Public Documents collection at http://www.nrc.gov/reading-rm/adams.html. To begin the search, select ``ADAMS Public Documents'' and 
then select ``Begin Web-based ADAMS Search.'' For problems with ADAMS, 
please contact the NRC's Public Document Room (PDR) reference staff at 
1-800-397-4209, 301-415-4737, or by email to [email protected]. The 
ADAMS accession number for each document referenced in this document 
(if that document is available in ADAMS) is provided the first time 
that a document is referenced.
     NRC's PDR: You may examine and purchase copies of public 
documents at the NRC's PDR, Room O1-F21, One White Flint North, 11555 
Rockville Pike, Rockville, Maryland 20852.

FOR FURTHER INFORMATION CONTACT: Billy Gleaves, Office of New Reactors, 
U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001; 
telephone: 301-415-5848; email: [email protected].

SUPPLEMENTARY INFORMATION:

I. Licensee Notification of Completion of ITAAC

    South Carolina Electric & Gas (SCE&G), on behalf of itself and the 
South Carolina Public Service Authority, (both hereafter called the 
licensee) has submitted ITAAC closure notifications (ICNs) under title 
10 of the Code of Federal Regulations (10 CFR) 52.99(c)(1), informing 
the NRC that the licensee has successfully performed the required 
inspections, tests, and analyses, and that the acceptance criteria are 
met for:

VCSNS Unit 2 ITAAC
    2.1.01.06.ii (7), 2.1.03.09a.i (81), 2.5.01.03c (513), and 
C.3.8.01.02.03 (845)
VCSNS Unit 3 ITAAC
    2.1.01.06.ii (7), 2.1.03.09a.i (81), 2.5.01.03c (513), 3.3.00.09 
(814), and C.3.8.01.02.03 (845)

    The ITAAC for VCSNS Unit 2 are in Appendix C of the VCSNS Unit 2 
combined license (ADAMS Accession No. ML14100A092). The ITAAC for VCSNS 
Unit 3 are in Appendix C of VCSNS Unit 3 combined license (ADAMS 
Accession No. ML14100A101).

II. NRC Staff Determination of Completion of ITAAC

    The NRC staff has determined that the specified inspections, tests, 
and analyses have been successfully completed, and that the specified 
acceptance criteria are met. The documentation of the NRC staff's 
determination is in the ITAAC Closure Verification Evaluation Form 
(VEF) for each ITAAC. The VEF is a form that represents the NRC staff's 
structured process for reviewing ICNs. Each ICN presents a narrative 
description of how the ITAAC was completed. The NRC's ICN review 
process involves a determination on whether, among other things: (1) 
Each ICN provides sufficient information, including a summary of the 
methodology used to perform the ITAAC, to demonstrate that the 
inspections, tests, and analyses have been successfully completed; (2) 
each ICN provides sufficient information to demonstrate that the 
acceptance criteria of the ITAAC are met; and (3) any NRC inspections 
for the ITAAC have been completed and any ITAAC findings associated 
with that ITAAC have been closed.
    The NRC staff's determination of the successful completion of these 
ITAAC is based on information available at this time and is subject to 
the licensee's ability to maintain the condition that the acceptance 
criteria are met. If the staff receives new information that suggests 
the staff's determination on any of these ITAAC is incorrect, then the 
staff will determine whether to reopen that ITAAC (including 
withdrawing the staff's determination on that ITAAC). The NRC staff's 
determination will be used to support a subsequent finding, pursuant to 
10 CFR 52.103(g), at the end of construction that all acceptance 
criteria in the combined license are met. The ITAAC closure process is 
not finalized for these ITAAC until the NRC makes an affirmative 
finding under 10 CFR 52.103(g). Any future updates to the status of 
these ITAAC will be reflected on the NRC's Web site at http://www.nrc.gov/reactors/new-reactors/oversight/itaac.html.
    This notice fulfills the staff's obligations under 10 CFR 
52.99(e)(1) to publish a notice in the Federal Register of the NRC 
staff's determination of the successful completion of inspections, 
tests, and analyses.

Virgil C. Summer Nuclear Station Unit 2, Docket No. 5200027

    A complete list of the review status for VCSNS Unit 2 ITAAC, 
including the submission date and ADAMS Accession Number for each ICN 
received, the ADAMS Accession Number for each VEF, and the ADAMS 
Accession Numbers for the inspection reports associated with these 
specific ITAAC, can be found on the NRC's Web site at http://www.nrc.gov/reactors/new-reactors/new-licensing-files/sum2-icnsr.pdf.

Virgil C. Summer Nuclear Station Unit 3, Docket No. 5200028

    A complete list of the review status for VCSNS Unit 3 ITAAC, 
including the submission date and ADAMS Accession Number for each ICN 
received, the ADAMS Accession Number for each VEF, and the ADAMS 
Accession Numbers for the inspection reports associated with these 
specific ITAAC, can be found on the NRC's Web site at http://www.nrc.gov/reactors/new-reactors/new-licensing-files/sum3-icnsr.pdf.

    Dated at Rockville, Maryland, this 17th day of April 2017.


[[Page 19758]]


    For the Nuclear Regulatory Commission.
Jennifer Dixon-Herrity,
Chief, Licensing Branch 4, Division of New Reactor Licensing, Office of 
New Reactors.
[FR Doc. 2017-08618 Filed 4-27-17; 8:45 am]
BILLING CODE 7590-01-P



                                                                                     Federal Register / Vol. 82, No. 81 / Friday, April 28, 2017 / Notices                                            19757

                                                    NUCLEAR REGULATORY                                        • NRC’s PDR: You may examine and                    of the ITAAC are met; and (3) any NRC
                                                    COMMISSION                                              purchase copies of public documents at                inspections for the ITAAC have been
                                                                                                            the NRC’s PDR, Room O1–F21, One                       completed and any ITAAC findings
                                                    [Docket Nos. 52–027 and 52–028; NRC–
                                                                                                            White Flint North, 11555 Rockville                    associated with that ITAAC have been
                                                    2008–0441]
                                                                                                            Pike, Rockville, Maryland 20852.                      closed.
                                                    South Carolina Electric & Gas                           FOR FURTHER INFORMATION CONTACT:                         The NRC staff’s determination of the
                                                    Company, South Carolina Public                          Billy Gleaves, Office of New Reactors,                successful completion of these ITAAC is
                                                    Service Authority, Virgil C. Summer                     U.S. Nuclear Regulatory Commission,                   based on information available at this
                                                    Nuclear Station, Units 2 and 3,                         Washington, DC 20555–0001; telephone:                 time and is subject to the licensee’s
                                                    Inspections, Tests, Analyses, and                       301–415–5848; email:                                  ability to maintain the condition that
                                                    Acceptance Criteria                                     Bill.Gleaves@nrc.gov.                                 the acceptance criteria are met. If the
                                                                                                            SUPPLEMENTARY INFORMATION:
                                                                                                                                                                  staff receives new information that
                                                    AGENCY:  Nuclear Regulatory                                                                                   suggests the staff’s determination on any
                                                    Commission.                                             I. Licensee Notification of Completion                of these ITAAC is incorrect, then the
                                                    ACTION: Determination of the successful                 of ITAAC                                              staff will determine whether to reopen
                                                    completion of inspections, tests, and                      South Carolina Electric & Gas                      that ITAAC (including withdrawing the
                                                    analyses.                                               (SCE&G), on behalf of itself and the                  staff’s determination on that ITAAC).
                                                                                                            South Carolina Public Service                         The NRC staff’s determination will be
                                                    SUMMARY:   The U.S. Nuclear Regulatory                                                                        used to support a subsequent finding,
                                                                                                            Authority, (both hereafter called the
                                                    Commission (NRC) staff has determined                                                                         pursuant to 10 CFR 52.103(g), at the end
                                                                                                            licensee) has submitted ITAAC closure
                                                    that the inspections, tests, and analyses                                                                     of construction that all acceptance
                                                                                                            notifications (ICNs) under title 10 of the
                                                    have been successfully completed, and                                                                         criteria in the combined license are met.
                                                                                                            Code of Federal Regulations (10 CFR)
                                                    that the specified acceptance criteria are                                                                    The ITAAC closure process is not
                                                                                                            52.99(c)(1), informing the NRC that the
                                                    met for multiple inspections, tests,                                                                          finalized for these ITAAC until the NRC
                                                                                                            licensee has successfully performed the
                                                    analyses, and acceptance criteria                                                                             makes an affirmative finding under 10
                                                                                                            required inspections, tests, and
                                                    (ITAAC) for the Virgil C. Summer                                                                              CFR 52.103(g). Any future updates to
                                                                                                            analyses, and that the acceptance
                                                    Nuclear Station (VCSNS), Units 2 and 3.                                                                       the status of these ITAAC will be
                                                                                                            criteria are met for:
                                                    DATES: The determination of the                                                                               reflected on the NRC’s Web site at
                                                                                                            VCSNS Unit 2 ITAAC
                                                    successful completion of inspections,                      2.1.01.06.ii (7), 2.1.03.09a.i (81),               http://www.nrc.gov/reactors/new-
                                                    tests, and analyses for these ITAAC for                      2.5.01.03c (513), and C.3.8.01.02.03             reactors/oversight/itaac.html.
                                                    VCSNS, Units 2 and 3 is effective April                      (845)                                               This notice fulfills the staff’s
                                                    28, 2017.                                               VCSNS Unit 3 ITAAC                                    obligations under 10 CFR 52.99(e)(1) to
                                                    ADDRESSES: Please refer to Docket ID                       2.1.01.06.ii (7), 2.1.03.09a.i (81),               publish a notice in the Federal Register
                                                    NRC–2008–0441 when contacting the                            2.5.01.03c (513), 3.3.00.09 (814),               of the NRC staff’s determination of the
                                                    NRC about the availability of                                and C.3.8.01.02.03 (845)                         successful completion of inspections,
                                                    information regarding this document.                       The ITAAC for VCSNS Unit 2 are in                  tests, and analyses.
                                                    You may obtain publicly-available                       Appendix C of the VCSNS Unit 2                        Virgil C. Summer Nuclear Station Unit
                                                    information related to this document                    combined license (ADAMS Accession                     2, Docket No. 5200027
                                                    using any of the following methods:                     No. ML14100A092). The ITAAC for
                                                       • Federal Rulemaking Web site: Go to                 VCSNS Unit 3 are in Appendix C of                       A complete list of the review status
                                                    http://www.regulations.gov and search                   VCSNS Unit 3 combined license                         for VCSNS Unit 2 ITAAC, including the
                                                    for Docket ID NRC–2008–0441. Address                    (ADAMS Accession No. ML14100A101).                    submission date and ADAMS Accession
                                                    questions about NRC dockets to Carol                                                                          Number for each ICN received, the
                                                    Gallagher; telephone: 301–415–3463;                     II. NRC Staff Determination of                        ADAMS Accession Number for each
                                                    email: Carol.Gallagher@nrc.gov. For                     Completion of ITAAC                                   VEF, and the ADAMS Accession
                                                    technical questions, contact the                           The NRC staff has determined that the              Numbers for the inspection reports
                                                    individual listed in the FOR FURTHER                    specified inspections, tests, and                     associated with these specific ITAAC,
                                                    INFORMATION CONTACT section of this                     analyses have been successfully                       can be found on the NRC’s Web site at
                                                    document.                                               completed, and that the specified                     http://www.nrc.gov/reactors/new-
                                                       • NRC’s Agencywide Documents                         acceptance criteria are met. The                      reactors/new-licensing-files/sum2-
                                                    Access and Management System                            documentation of the NRC staff’s                      icnsr.pdf.
                                                    (ADAMS): You may obtain publicly                        determination is in the ITAAC Closure                 Virgil C. Summer Nuclear Station Unit
                                                    available documents online in the                       Verification Evaluation Form (VEF) for                3, Docket No. 5200028
                                                    ADAMS Public Documents collection at                    each ITAAC. The VEF is a form that
                                                    http://www.nrc.gov/reading-rm/                          represents the NRC staff’s structured                   A complete list of the review status
                                                    adams.html. To begin the search, select                 process for reviewing ICNs. Each ICN                  for VCSNS Unit 3 ITAAC, including the
                                                    ‘‘ADAMS Public Documents’’ and then                     presents a narrative description of how               submission date and ADAMS Accession
                                                    select ‘‘Begin Web-based ADAMS                          the ITAAC was completed. The NRC’s                    Number for each ICN received, the
                                                    Search.’’ For problems with ADAMS,                      ICN review process involves a                         ADAMS Accession Number for each
                                                    please contact the NRC’s Public                         determination on whether, among other                 VEF, and the ADAMS Accession
asabaliauskas on DSK3SPTVN1PROD with NOTICES




                                                    Document Room (PDR) reference staff at                  things: (1) Each ICN provides sufficient              Numbers for the inspection reports
                                                    1–800–397–4209, 301–415–4737, or by                     information, including a summary of the               associated with these specific ITAAC,
                                                    email to pdr.resource@nrc.gov. The                      methodology used to perform the                       can be found on the NRC’s Web site at
                                                    ADAMS accession number for each                         ITAAC, to demonstrate that the                        http://www.nrc.gov/reactors/new-
                                                    document referenced in this document                    inspections, tests, and analyses have                 reactors/new-licensing-files/sum3-
                                                    (if that document is available in                       been successfully completed; (2) each                 icnsr.pdf.
                                                    ADAMS) is provided the first time that                  ICN provides sufficient information to                  Dated at Rockville, Maryland, this 17th day
                                                    a document is referenced.                               demonstrate that the acceptance criteria              of April 2017.



                                               VerDate Sep<11>2014   17:38 Apr 27, 2017   Jkt 241001   PO 00000   Frm 00106   Fmt 4703   Sfmt 4703   E:\FR\FM\28APN1.SGM   28APN1


                                                    19758                            Federal Register / Vol. 82, No. 81 / Friday, April 28, 2017 / Notices

                                                      For the Nuclear Regulatory Commission.                   The NRC provides reasonable                        information related to this document
                                                    Jennifer Dixon-Herrity,                                 accommodation to individuals with                     using any of the following methods:
                                                    Chief, Licensing Branch 4, Division of New              disabilities where appropriate. If you                   • Federal Rulemaking Web site: Go to
                                                    Reactor Licensing, Office of New Reactors.              need a reasonable accommodation to                    http://www.regulations.gov and search
                                                    [FR Doc. 2017–08618 Filed 4–27–17; 8:45 am]             participate in these public meetings, or              for Docket ID NRC–2008–0252. Address
                                                    BILLING CODE 7590–01–P                                  need this meeting notice or the                       questions about NRC dockets to Carol
                                                                                                            transcript or other information from the              Gallagher; telephone: 301–415–3463;
                                                                                                            public meetings in another format (e.g.,              email: Carol.Gallagher@nrc.gov. For
                                                    NUCLEAR REGULATORY                                      braille, large print), please notify                  technical questions, contact the
                                                    COMMISSION                                              Kimberly Meyer, NRC Disability                        individual listed in the FOR FURTHER
                                                                                                            Program Manager, at 301–287–0739, by                  INFORMATION CONTACT section of this
                                                    [NRC–2017–0001]
                                                                                                            videophone at 240–428–3217, or by                     document.
                                                    Sunshine Act Meeting Notice                             email at Kimberly.Meyer-Chambers@                        • NRC’s Agencywide Documents
                                                                                                            nrc.gov. Determinations on requests for               Access and Management System
                                                    DATE: Weeks of May 1, 8, 15, 22, 29,                    reasonable accommodation will be                      (ADAMS): You may obtain publicly
                                                    June 5, 2017.                                           made on a case-by-case basis.                         available documents online in the
                                                    PLACE: Commissioners’ Conference                        *     *      *    *      *                            ADAMS Public Documents collection at
                                                    Room, 11555 Rockville Pike, Rockville,                     Members of the public may request to               http://www.nrc.gov/reading-rm/
                                                    Maryland.                                               receive this information electronically.              adams.html. To begin the search, select
                                                    STATUS: Public and Closed.                              If you would like to be added to the                  ‘‘ADAMS Public Documents’’ and then
                                                                                                            distribution, please contact the Nuclear              select ‘‘Begin Web-based ADAMS
                                                    Week of May 1, 2017                                     Regulatory Commission, Office of the                  Search.’’ For problems with ADAMS,
                                                      There are no meetings scheduled for                   Secretary, Washington, DC 20555 (301–                 please contact the NRC’s Public
                                                    the week of May 1, 2017.                                415–1969), or email                                   Document Room (PDR) reference staff at
                                                                                                            Brenda.Akstulewicz@nrc.gov or                         1–800–397–4209, 301–415–4737, or by
                                                    Week of May 8, 2017—Tentative                                                                                 email to pdr.resource@nrc.gov. The
                                                                                                            Patricia.Jimenez@nrc.gov.
                                                    Tuesday, May 9, 2017                                                                                          ADAMS accession number for each
                                                                                                              Dated: April 26, 2017.
                                                                                                                                                                  document referenced in this document
                                                    10:00 a.m. Briefing on Security Issues                  Denise L. McGovern,
                                                                                                                                                                  (if that document is available in
                                                        (Closed Ex. 1).                                     Policy Coordinator, Office of the Secretary.          ADAMS) is provided the first time that
                                                    2:00 p.m. Briefing on Security Issues                   [FR Doc. 2017–08793 Filed 4–26–17; 4:15 pm]           a document is referenced.
                                                        (Closed Ex. 1).                                     BILLING CODE 7590–01–P                                   • NRC’s PDR: You may examine and
                                                    Thursday, May 11, 2017                                                                                        purchase copies of public documents at
                                                    9:00 a.m. Briefing on Risk-Informed                                                                           the NRC’s PDR, Room O1–F21, One
                                                                                                            NUCLEAR REGULATORY                                    White Flint North, 11555 Rockville
                                                        Regulation (Public Meeting);                        COMMISSION
                                                        (Contact: Steve Ruffin: 301–415–                                                                          Pike, Rockville, Maryland 20852.
                                                        1985).                                              [Docket Nos. 52–025 and 52–026; NRC–                  FOR FURTHER INFORMATION CONTACT:
                                                                                                            2008–0252]                                            Chandu Patel, Office of New Reactors,
                                                      This meeting will be webcast live at
                                                    the Web address—http://www.nrc.gov/.                                                                          U.S. Nuclear Regulatory Commission,
                                                                                                            Southern Nuclear Operating Company,                   Washington, DC 20555–0001; telephone:
                                                    Week of May 15, 2017—Tentative                          Inc. Vogtle Electric Generating Plant,                301–415–3025; email: Chandu.Patel@
                                                                                                            Units 3 and 4 Inspections, Tests,                     nrc.gov.
                                                      There are no meetings scheduled for
                                                                                                            Analyses, and Acceptance Criteria
                                                    the week of May 15, 2017.                                                                                     SUPPLEMENTARY INFORMATION:
                                                                                                            AGENCY:  Nuclear Regulatory
                                                    Week of May 22, 2017—Tentative                                                                                I. Licensee Notification of Completion
                                                                                                            Commission.
                                                      There are no meetings scheduled for                                                                         of ITAAC
                                                                                                            ACTION: Determination of the successful
                                                    the week of May 22, 2017.                               completion of inspections, tests, and                    Southern Nuclear Operating
                                                    Week of May 29, 2017—Tentative                          analyses.                                             Company, Inc. (SNC), Georgia Power
                                                                                                                                                                  Company, Oglethorpe Power
                                                      There are no meetings scheduled for                   SUMMARY:   The U.S. Nuclear Regulatory                Corporation, MEAG Power SPVM, LLC.,
                                                    the week of May 29, 2017.                               Commission (NRC) staff has determined                 MEAG Power SPVJ, LLC., MEAG Power
                                                    Week of June 5, 2017—Tentative                          that the inspections, tests, and analyses             SPVP, LLC., and the City of Dalton,
                                                                                                            have been successfully completed, and                 Georgia, (hereafter called the licensee)
                                                       There are no meetings scheduled for                  that the specified acceptance criteria are            has submitted ITAAC closure
                                                    the week of June 5, 2017.                               met for multiple inspections, tests,                  notifications (ICNs) under title 10 of the
                                                    *      *    *    *     *                                analyses, and acceptance criteria                     Code of Federal Regulations (10 CFR)
                                                       The schedule for Commission                          (ITAAC) for the Vogtle Electric                       52.99(c)(1), informing the NRC that the
                                                    meetings is subject to change on short                  Generating Plant (VEGP), Units 3 and 4.               licensee has successfully performed the
                                                    notice. For more information or to verify               DATES: The determination of the                       required inspections, tests, and
                                                    the status of meetings, contact Denise                  successful completion of inspections,                 analyses, and that the acceptance
asabaliauskas on DSK3SPTVN1PROD with NOTICES




                                                    McGovern at 301–415–0681 or via email                   tests, and analyses for these ITAAC for               criteria are met for:
                                                    at Denise.McGovern@nrc.gov.                             VEGP, Units 3 and 4 is effective April                VEGP Unit 3 ITAAC
                                                    *      *    *    *     *                                28, 2017.                                                2.1.01.07.iii (10), 2.1.02.08d.iv (35),
                                                       The NRC Commission Meeting                           ADDRESSES: Please refer to Docket ID                       2.1.03.02c (71), and 2.2.03.08c.xi
                                                    Schedule can be found on the Internet                   NRC–2008–0252 when contacting the                          (196)
                                                    at: http://www.nrc.gov/public-involve/                  NRC about the availability of                         VEGP Unit 4 ITAAC
                                                    public-meetings/schedule.html.                          information regarding this document.                     2.1.01.07.iii (10), 2.1.02.08d.iv (35),
                                                    *      *    *    *     *                                You may obtain publicly-available                          and 2.2.03.08c.xi (196)


                                               VerDate Sep<11>2014   17:38 Apr 27, 2017   Jkt 241001   PO 00000   Frm 00107   Fmt 4703   Sfmt 4703   E:\FR\FM\28APN1.SGM   28APN1



Document Created: 2017-04-28 03:02:12
Document Modified: 2017-04-28 03:02:12
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
ActionDetermination of the successful completion of inspections, tests, and analyses.
DatesThe determination of the successful completion of inspections, tests, and analyses for these ITAAC for VCSNS, Units 2 and 3 is effective April 28, 2017.
ContactBilly Gleaves, Office of New Reactors, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001; telephone: 301-415-5848; email: [email protected]
FR Citation82 FR 19757 