[Federal Register Volume 82, Number 97 (Monday, May 22, 2017)]
[Notices]
[Pages 23240-23241]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2017-10371]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 14831-000]


Merchant Hydro Developers, LLC; Notice of Preliminary Permit 
Application Accepted for Filing And Soliciting Comments, Motions To 
Intervene, and Competing Applications

    On January 18, 2017, Merchant Hydro Developers, LLC, filed an 
application for a preliminary permit, pursuant to section 4(f) of the 
Federal Power Act (FPA), proposing to study the feasibility of the 
Savage Mountain Pumped Storage Hydroelectric Project to be located in 
Allegany County, Maryland. The sole purpose of a preliminary permit, if 
issued, is to grant the permit holder priority to file a license 
application during the permit term. A preliminary permit does not 
authorize the permit holder to perform any land-disturbing activities 
or otherwise enter upon lands or waters owned by others without the 
owners' express permission.
    The proposed project would consist of the following: (1) A new 
upper reservoir with a surface area of 75 acres and a storage capacity 
of 1,125 acre-feet at a surface elevation of approximately 2,800 feet 
above mean sea level (msl) created through construction of a new 
roller-compacted concrete or rock-filled dam and/or dike; (2) 
excavating a new lower reservoir with a surface area of 50 acres and a 
total storage capacity of 1,350 acre-feet at a surface elevation of 
1,820 feet msl; (3) a new 6,762-foot-long, 48-inch-diameter penstock 
connecting the upper and lower reservoirs; (4) a new 150-foot-long, 50-
foot-wide powerhouse containing two turbine-generator units with a 
total rated capacity of 90 megawatts; (5) a new transmission line 
connecting the powerhouse to a nearby electric grid interconnection 
point at the Savage Mountain Wind Farm; and (6) appurtenant facilities. 
Possible initial fill water and make-up water would come from the 
nearby Casselman River, including groundwater. The proposed project 
would have an annual generation of 329,908 megawatt-hours.
    Applicant Contact: Adam Rousselle, Merchant Hydro Developers, LLC, 
5710 Oak Crest Drive, Doylestown, PA 18902; phone: 267-254-6107.
    FERC Contact: Monir Chowdhury; phone: (202) 502-6736.
    Deadline for filing comments, motions to intervene, competing 
applications (without notices of intent), or notices of intent to file 
competing applications: 60 days from the issuance of this notice. 
Competing applications and notices of

[[Page 23241]]

intent must meet the requirements of 18 CFR 4.36.
    The Commission strongly encourages electronic filing. Please file 
comments, motions to intervene, notices of intent, and competing 
applications using the Commission's eFiling system at http://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief 
comments up to 6,000 characters, without prior registration, using the 
eComment system at http://www.ferc.gov/docs-filing/ecomment.asp. You 
must include your name and contact information at the end of your 
comments. For assistance, please contact FERC Online Support at 
[email protected], (866) 208-3676 (toll free), or (202) 502-
8659 (TTY). In lieu of electronic filing, please send a paper copy to: 
Secretary, Federal Energy Regulatory Commission, 888 First Street NE., 
Washington, DC 20426. The first page of any filing should include 
docket number P-14831-000.
    More information about this project, including a copy of the 
application, can be viewed or printed on the ``eLibrary'' link of the 
Commission's Web site at http://www.ferc.gov/docs-filing/elibrary.asp. 
Enter the docket number (P-14831) in the docket number field to access 
the document. For assistance, contact FERC Online Support.

    Dated: May 15, 2017.
 Kimberly D. Bose,
 Secretary.
[FR Doc. 2017-10371 Filed 5-19-17; 8:45 am]
 BILLING CODE 6717-01-P



                                                  23240                           Federal Register / Vol. 82, No. 97 / Monday, May 22, 2017 / Notices

                                                  foot-long tailrace; (8) a 12-foot-wide, 10-             number excluding the last three digits in             DEPARTMENT OF ENERGY
                                                  foot-high ice sluice; (9) three 80-foot-                the docket number field to access the
                                                  long, 6.6-kV generator leads that                       document. For assistance, please contact              Federal Energy Regulatory
                                                  connect the turbine-generator units to                  FERC Online Support at                                Commission
                                                  two step-up transformers; (10) a 920-                   FERCOnlineSupport@ferc.gov, (866)                     [Project No. 14831–000]
                                                  foot-long, 8-foot-wide fishway; (11) a                  208–3676 (toll free), or (202) 502–8659
                                                  concrete fish barrier dam in the                        (TTY). Copies are also available for                  Merchant Hydro Developers, LLC;
                                                  bypassed reach; and (12) appurtenant                    inspection and reproduction at the                    Notice of Preliminary Permit
                                                  facilities.                                             address in item (h) above.                            Application Accepted for Filing And
                                                  Vernon Project                                                                                                Soliciting Comments, Motions To
                                                                                                             m. You may also register online at                 Intervene, and Competing Applications
                                                     The existing Vernon Project consists                 http://www.ferc.gov/docs-filing/
                                                  of: (1) a 956-foot-long, 58-foot-high                   esubscription.asp to be notified via                     On January 18, 2017, Merchant Hydro
                                                  concrete dam that includes: (a) 356-foot-               email of new filings and issuances                    Developers, LLC, filed an application for
                                                  long section integral to the powerhouse;                related to these or other pending                     a preliminary permit, pursuant to
                                                  and (b) a 600-foot-long overflow                        projects. For assistance, contact FERC                section 4(f) of the Federal Power Act
                                                  spillway section that includes: (i) a 9-                Online Support.                                       (FPA), proposing to study the feasibility
                                                  foot-high, 6-foot-wide fishway sluice;                                                                        of the Savage Mountain Pumped Storage
                                                  (ii) a 13-foot-high, 13-foot-wide trash/ice                n. Procedural Schedule: In the final               Hydroelectric Project to be located in
                                                  sluice; (iii) two 20-foot-high, 50-foot-                license applications, Great River Hydro               Allegany County, Maryland. The sole
                                                  wide tainter gates; (iv) four 10-foot-high,             states that it will file amended final                purpose of a preliminary permit, if
                                                  50-foot-wide tainter gates; (v) two 10-                 license applications after it completes               issued, is to grant the permit holder
                                                  foot-high, 50-foot-wide hydraulic panel                 additional field work for two studies,                priority to file a license application
                                                  bays; (vi) two 10-foot-high, 50-foot-wide               conducts additional consultation with                 during the permit term. A preliminary
                                                  stanchion bays; (vii) a 10-foot-high,                   stakeholders on the study results, and                permit does not authorize the permit
                                                  42.5-foot-wide stanchion bay; and (viii)                models operational alternatives. After                holder to perform any land-disturbing
                                                  eight 7-foot-high, 9-foot-wide hydraulic                Great River Hydro completes and files                 activities or otherwise enter upon lands
                                                  flood gates; (2) a 26-mile-long, 2,550-                 the revised study reports and amended                 or waters owned by others without the
                                                  acre impoundment with a useable                         final license applications, Commission                owners’ express permission.
                                                  storage volume of 18,300 acre-feet                      staff will issue a revised procedural                    The proposed project would consist of
                                                  between elevations 212.13 and 220.13                    schedule with target dates for the post-              the following: (1) A new upper reservoir
                                                  feet NGVD 29; (3) eight approximately                   filing milestones listed below.                       with a surface area of 75 acres and a
                                                  30-foot-high trashracks with 1.75-inch                                                                        storage capacity of 1,125 acre-feet at a
                                                  clear bar spacing and two approximately                                                             Target    surface elevation of approximately 2,800
                                                                                                                        Milestone                               feet above mean sea level (msl) created
                                                  30-foot-high trashracks with 3.625-inch                                                              date
                                                  clear bar spacing; (4) a 356-foot-long, 55-                                                                   through construction of a new roller-
                                                  foot-wide, 45-foot-high reinforced                      Amended Final License Applica-             TBD.       compacted concrete or rock-filled dam
                                                  concrete, steel, and brick powerhouse                      tions.                                             and/or dike; (2) excavating a new lower
                                                  containing four 2–MW vertical Francis                   Notice of Acceptance/Notice of             TBD.       reservoir with a surface area of 50 acres
                                                  turbine-generator units, four 4–MW                         Ready for Environmental Anal-                      and a total storage capacity of 1,350
                                                                                                             ysis.
                                                  vertical Kaplan turbine-generator units,                                                                      acre-feet at a surface elevation of 1,820
                                                                                                          Filing of recommendations, prelimi-        TBD.
                                                  and two 4.2–MW vertical Francis                            nary terms and conditions, and
                                                                                                                                                                feet msl; (3) a new 6,762-foot-long, 48-
                                                  turbine-generator units for a total project                fishway prescriptions.                             inch-diameter penstock connecting the
                                                  capacity of 32.4 MW; (5) ten concrete                   Commission issues Draft Environ-           TBD.       upper and lower reservoirs; (4) a new
                                                  draft tubes ranging from 16 to 27 feet in                  mental Impact Statement (EIS).                     150-foot-long, 50-foot-wide powerhouse
                                                  diameter; (6) a 500-foot-long, 13.8-kV                  Comments on Draft EIS ..................   TBD.       containing two turbine-generator units
                                                  underground generator lead that                         Modified terms and conditions ........     TBD.       with a total rated capacity of 90
                                                  connects the turbine-generator units to                 Commission issues Final EIS .........      TBD.       megawatts; (5) a new transmission line
                                                  two step-up transformers; (7) a 984-foot-                                                                     connecting the powerhouse to a nearby
                                                  long, 15-foot-wide fishway; (8)                                                                               electric grid interconnection point at the
                                                                                                            o. Final amendments to the
                                                  downstream fish passage facilities; and                                                                       Savage Mountain Wind Farm; and (6)
                                                                                                          applications must be filed with the
                                                  (9) appurtenant facilities.                                                                                   appurtenant facilities. Possible initial
                                                     Great River Hydro operates all three                 Commission no later than 30 days from
                                                                                                                                                                fill water and make-up water would
                                                  projects in coordination and in a                       the issuance date of the notice of ready
                                                                                                                                                                come from the nearby Casselman River,
                                                  peaking mode. Average annual                            for environmental analysis.                           including groundwater. The proposed
                                                  generation is approximately 161,739;                      Dated: May 15, 2017.                                project would have an annual
                                                  247,373; and 162,557 MW-hours at the                    Kimberly D. Bose,                                     generation of 329,908 megawatt-hours.
                                                  Wilder, Bellows Falls, and Vernon                                                                                Applicant Contact: Adam Rousselle,
                                                                                                          Secretary.
                                                  Projects, respectively. Great River Hydro                                                                     Merchant Hydro Developers, LLC, 5710
                                                                                                          [FR Doc. 2017–10385 Filed 5–19–17; 8:45 am]
                                                  is not proposing any new project                                                                              Oak Crest Drive, Doylestown, PA 18902;
                                                  facilities or changes to operation of                   BILLING CODE 6717–01–P
                                                                                                                                                                phone: 267–254–6107.
                                                  these projects at this time.                                                                                     FERC Contact: Monir Chowdhury;
mstockstill on DSK30JT082PROD with NOTICES




                                                     l. Locations of the Applications:                                                                          phone: (202) 502–6736.
                                                  Copies of the applications are available                                                                         Deadline for filing comments, motions
                                                  for review at the Commission in the                                                                           to intervene, competing applications
                                                  Public Reference Room or may be                                                                               (without notices of intent), or notices of
                                                  viewed on the Commission’s Web site at                                                                        intent to file competing applications: 60
                                                  http://www.ferc.gov using the                                                                                 days from the issuance of this notice.
                                                  ‘‘eLibrary’’ link. Enter the docket                                                                           Competing applications and notices of


                                             VerDate Sep<11>2014   23:17 May 19, 2017   Jkt 241001   PO 00000   Frm 00071   Fmt 4703   Sfmt 4703   E:\FR\FM\22MYN1.SGM   22MYN1


                                                                                  Federal Register / Vol. 82, No. 97 / Monday, May 22, 2017 / Notices                                                   23241

                                                  intent must meet the requirements of 18                 System underneath the channel of the                  for this proceeding or the issuance of a
                                                  CFR 4.36.                                               Mystic River and Alewife Brook in                     Notice of Schedule for Environmental
                                                     The Commission strongly encourages                   Somerville, Medford, and Arlington,                   Review will serve to notify federal and
                                                  electronic filing. Please file comments,                Massachusetts. Algonquin states that the              state agencies of the timing for the
                                                  motions to intervene, notices of intent,                Mystic River Project will have no                     completion of all necessary reviews, and
                                                  and competing applications using the                    impact on the certificated capacity of                the subsequent need to complete all
                                                  Commission’s eFiling system at http://                  Algonquin system, and there will be no                federal authorizations within 90 days of
                                                  www.ferc.gov/docs-filing/efiling.asp.                   abandonment or reduction in service to                the date of issuance of the Commission
                                                  Commenters can submit brief comments                    any customer of Algonquin as a result                 staff’s FEIS or EA.
                                                  up to 6,000 characters, without prior                   of the project. Algonquin estimates the                  Persons who wish to comment only
                                                  registration, using the eComment system                 cost of the Mystic River Project to be                on the environmental review of this
                                                  at http://www.ferc.gov/docs-filing/                     approximately $15 million, all as more                project should submit an original and
                                                  ecomment.asp. You must include your                     fully set forth in the application which              two copies of their comments to the
                                                  name and contact information at the end                 is on file with the Commission and open               Secretary of the Commission.
                                                  of your comments. For assistance,                       to public inspection. The filing may also             Environmental commenter’s will be
                                                  please contact FERC Online Support at                   be viewed on the Web at http://                       placed on the Commission’s
                                                  FERCOnlineSupport@ferc.gov, (866)                       www.ferc.gov using the eLibrary link.                 environmental mailing list, will receive
                                                  208–3676 (toll free), or (202) 502–8659                 Enter the docket number excluding the                 copies of the environmental documents,
                                                  (TTY). In lieu of electronic filing, please             last three digits in the docket number                and will be notified of meetings
                                                  send a paper copy to: Secretary, Federal                field to access the document. For                     associated with the Commission’s
                                                  Energy Regulatory Commission, 888                       assistance, please contact FERC Online                environmental review process.
                                                  First Street NE., Washington, DC 20426.                 Support at FERCOnlineSupport@                         Environmental commenter’s will not be
                                                  The first page of any filing should                     ferc.gov or toll free at (866) 208–3676, or           required to serve copies of filed
                                                  include docket number P–14831–000.                      TTY, contact (202) 502–8659.                          documents on all other parties.
                                                     More information about this project,                    Any questions concerning this                      However, the non-party commentary,
                                                  including a copy of the application, can                application may be directed to Lisa A.                will not receive copies of all documents
                                                  be viewed or printed on the ‘‘eLibrary’’                Connolly, Director, Rates and                         filed by other parties or issued by the
                                                  link of the Commission’s Web site at                    Certificates, Algonquin Gas                           Commission (except for the mailing of
                                                  http://www.ferc.gov/docs-filing/                        Transmission, LLC, P.O. Box 1642,                     environmental documents issued by the
                                                  elibrary.asp. Enter the docket number                   Houston, Texas 77251–1642, by                         Commission) and will not have the right
                                                  (P–14831) in the docket number field to                 telephone at (713) 627–4102, by fax at                to seek court review of the
                                                  access the document. For assistance,                    (713) 627–5947, or by email at
                                                                                                                                                                Commission’s final order.
                                                  contact FERC Online Support.                            lisa.connolly@enbridge.com.
                                                                                                             Any person or the Commission’s staff                  The Commission strongly encourages
                                                    Dated: May 15, 2017.                                  may, within 60 days after issuance of                 electronic filings of comments, protests
                                                  Kimberly D. Bose,                                       the instant notice by the Commission,                 and interventions in lieu of paper using
                                                  Secretary.                                              file pursuant to Rule 214 of the                      the eFiling link at http://www.ferc.gov.
                                                  [FR Doc. 2017–10371 Filed 5–19–17; 8:45 am]             Commission’s Procedural Rules (18 CFR                 Persons unable to file electronically
                                                                                                          385.214) a motion to intervene or notice              should submit an original and 7 copies
                                                  BILLING CODE 6717–01–P
                                                                                                          of intervention and pursuant to section               of the protest or intervention to the
                                                                                                          157.205 of the regulations under the                  Federal Energy Regulatory Commission,
                                                  DEPARTMENT OF ENERGY                                    NGA (18 CFR 157.205), a protest to the                888 First Street NE., Washington, DC
                                                                                                          request. If no protest is filed within the            20426.
                                                  Federal Energy Regulatory                               time allowed therefor, the proposed                     Dated: May 15, 2017.
                                                  Commission                                              activity shall be deemed to be                        Kimberly D. Bose,
                                                  [Docket No. CP17–438–000]                               authorized effective the day after the                Secretary.
                                                                                                          time allowed for filing a protest. If a               [FR Doc. 2017–10384 Filed 5–19–17; 8:45 am]
                                                  Algonquin Gas Transmission, LLC;                        protest is filed and not withdrawn
                                                                                                                                                                BILLING CODE 6717–01–P
                                                  Notice of Request Under Blanket                         within 30 days after the allowed time
                                                  Authorization                                           for filing a protest, the instant request
                                                                                                          shall be treated as an application for                DEPARTMENT OF ENERGY
                                                    Take notice that on May 5, 2017,                      authorization pursuant to section 7 of
                                                  Algonquin Gas Transmission, LLC                         the NGA.                                              Federal Energy Regulatory
                                                  (Algonquin), P.O. Box 1642, Houston,                       Pursuant to section 157.9 of the                   Commission
                                                  Texas 77251–1642, filed in Docket No.                   Commission’s rules, 18 CFR 157.9,
                                                  CP17–438–000 a prior notice request                     within 90 days of this Notice the
                                                                                                                                                                [Docket No. ER17–1594–000]
                                                  pursuant to sections 157.205 and                        Commission staff will either: Complete
                                                  157.208 of the Commission’s regulations                 its environmental assessment (EA) and                 Archer Energy, LLC; Supplemental
                                                  under the Natural Gas Act (NGA), as                     place it into the Commission’s public                 Notice That Initial Market-Based Rate
                                                  amended, requesting authorization to                    record (eLibrary) for this proceeding; or             Filing Includes Request for Blanket
                                                  replace a segment of 24-inch-diameter                   issue a Notice of Schedule for                        Section 204 Authorization
                                                  pipeline at a crossing of the Mystic                    Environmental Review. If a Notice of
mstockstill on DSK30JT082PROD with NOTICES




                                                  River with an offset located adjacent to                Schedule for Environmental Review is                    This is a supplemental notice in the
                                                  the existing pipeline at the confluence                 issued, it will indicate, among other                 above-referenced proceeding of Archer
                                                  of the Mystic River and Alewife Brook                   milestones, the anticipated date for the              Energy, LLC’s application for market-
                                                  (Mystic River Project). Specifically,                   Commission staff’s issuance of the final              based rate authority, with an
                                                  Algonquin proposes to install a new,                    environmental impact statement (FEIS)                 accompanying rate tariff, noting that
                                                  approximate 1,300-foot section of 24-                   or EA for this proposal. The filing of the            such application includes a request for
                                                  inch-diameter pipeline on its J–1                       EA in the Commission’s public record                  blanket authorization, under 18 CFR


                                             VerDate Sep<11>2014   23:17 May 19, 2017   Jkt 241001   PO 00000   Frm 00072   Fmt 4703   Sfmt 4703   E:\FR\FM\22MYN1.SGM   22MYN1



Document Created: 2018-11-08 08:51:12
Document Modified: 2018-11-08 08:51:12
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation82 FR 23240 

2025 Federal Register | Disclaimer | Privacy Policy
USC | CFR | eCFR