The Coast Guard has issued a temporary deviation from the operating schedule that governs the Maine Department of Transportation (Barter's Island) Highway Bridge over the Back River, mile 4.6, between Barter's Island and Hodgdon Island, Maine. This deviation is necessary to conduct geotechnical borings needed to design a new bridge. This deviation allows the bridge to be closed to vessel traffic for three days.

Federal Register, Volume 82 Issue 117 (Tuesday, June 20, 2017)
[Federal Register Volume 82, Number 117 (Tuesday, June 20, 2017)]
[Rules and Regulations]
[Pages 28006-28007]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2017-12780]


-----------------------------------------------------------------------

DEPARTMENT OF HOMELAND SECURITY

Coast Guard

33 CFR Part 117

[Docket No. USCG-2017-0532]


Drawbridge Operation Regulation; Back River, Barter's Island, ME

AGENCY: Coast Guard, DHS.

ACTION: Notice of deviation from drawbridge regulation.

-----------------------------------------------------------------------

SUMMARY: The Coast Guard has issued a temporary deviation from the 
operating schedule that governs the Maine Department of Transportation 
(Barter's Island) Highway Bridge over the Back River, mile 4.6, between 
Barter's Island and Hodgdon Island, Maine. This deviation is necessary 
to conduct geotechnical borings needed to design a new bridge. This 
deviation allows the bridge to be closed to vessel traffic for three 
days.

DATES:  This deviation is effective without actual notice from June 20, 
2017 through 5:30 p.m. on June 14, 2017. For the purposes of 
enforcement, actual notice will be used from June 15, 2017, until June 
20, 2017.

ADDRESSES: The docket for this deviation, USCG-2017-0532, is available 
at http://www.regulations.gov. Type the docket number in the ``SEARCH'' 
box and click ``SEARCH''. Click on Open Docket Folder on the line 
associated with this deviation.

FOR FURTHER INFORMATION CONTACT: If you have questions on this 
temporary deviation, call or email Jeffrey Stieb; Bridge Management 
Specialist, First Coast Guard District, telephone 617-223-8364, email 
[email protected].

SUPPLEMENTARY INFORMATION: 
    The bridge owner, State of Maine Department of Transportation 
(Maine DOT), requested a temporary deviation from the normal operating 
schedule of the Maine Department of Transportation (Barter's Island) 
Highway Bridge, mile 4.6, across the Back River between Barter's Island 
and Hodgdon Island, Maine. The drawbridge navigation span has a 
vertical clearance of six feet at mean high water in the closed 
position. The existing bridge operating regulations are found at 33 CFR 
117.523. The approved temporary deviation allows the bridge to remain 
closed for vessel traffic between the hours of 7 a.m. through 5:30 p.m. 
from June 12 through June 14.
    The waterway is transited by fishing and sailing vessels of various 
sizes. For the last three years, the bridge averaged less than three 
openings a day during the month of June. Maine DOT contacted the 
primary stakeholders, none of which objected to the deviation. Vessels 
able to pass through the bridge

[[Page 28007]]

in the closed position may continue to do so at any time. Vessels have 
the option of going around the North Side of Barter's Island to reach 
the Sheepscot River. During the hours of deviation the bridge will not 
be able to open for emergencies.
    The Coast Guard will inform the users of the waterway through our 
Local Notice and Broadcast Notice to Mariners of the change in 
operating schedule so that vessel operators can arrange their transits 
to minimize any impact caused by the temporary deviation.
    In accordance with 33 CFR 117.35(e), the drawbridge must return to 
its regular operating schedule immediately at the end of the effective 
period of this deviation. This deviation from the operating regulations 
is authorized under 33 CFR 117.35.

    Dated: June 15, 2017.
C.J. Bisignano,
Supervisory Bridge Management Specialist, First Coast Guard District.
[FR Doc. 2017-12780 Filed 6-19-17; 8:45 am]
 BILLING CODE 9110-04-P



                                                  28006                 Federal Register / Vol. 82, No. 117 / Tuesday, June 20, 2017 / Rules and Regulations

                                                  7.4   Jones Beach State Park Fireworks ...........                • Date: July 4, 2017.
                                                                                                                    • Rain Date: July 5, 2017.
                                                                                                                    • Time: 8:30 p.m. to 10:30 p.m.
                                                                                                                    • Location: ‘‘No Entry Area’’: All waters off of Jones Beach State Park, Wantagh, NY within a
                                                                                                                      1000 foot radius of the launch platform in approximate position 40°34′56.68″ N.,
                                                                                                                      073°30′31.19″ W. (NAD 83).
                                                                                                                    • Additional Stipulations: ‘‘Slow/No Wake Area’’: All navigable waters between Meadowbrook
                                                                                                                      State Parkway and Wantagh State Parkway and contained within the following area. Begin-
                                                                                                                      ning in position at 40°35′49.01″ N., 073°32′33.63″ W.; then north along the Meadowbrook
                                                                                                                      State Parkway to its intersection with Merrick Road in position at 40°39′14″ N., 073°34′0.76″
                                                                                                                      W.; then east along Merrick Road to its intersection with Wantagh State Parkway in position
                                                                                                                      at 40°39′51.32″ N., 073°30′43.36″ W.; then south along the Wantagh State Parkway to its
                                                                                                                      intersection with Ocean Parkway in position at 40°35′47.30″ N., 073°30′29.17″ W.; then
                                                                                                                      west along Ocean Parkway to its intersection with Meadowbrook State Parkway at the point
                                                                                                                      of origin (NAD 83). All positions are approximate. ‘‘No Southbound Traffic Area’’: All navi-
                                                                                                                      gable waters of Zach’s Bay south of the line connecting a point near the western entrance
                                                                                                                      to Zach’s Bay in position at 40°36′29.20″ N., 073°29′22.88″ W. and a point near the eastern
                                                                                                                      entrance of Zach’s Bay in position at 40°36′16.53″ N., 073°28′57.26″ W. (NAD 83). All posi-
                                                                                                                      tions are approximate.

                                                  8.1   Riverfront Dragon Boat and Asian Festival                   • Date: August 19, 2017.
                                                                                                                    • Time: 7:30 a.m. to 5:00 p.m.
                                                                                                                    • Location: All waters of the Connecticut River in Hartford, CT between the Bulkeley Bridge at
                                                                                                                      41°46′10.10″ N., 072°39′56.13″ W. and the Wilbur Cross Bridge at 41°45′11.67″ N.,
                                                                                                                      072°39′13.64″ W. (NAD 83). All positions are approximate.

                                                  8.4   Island Beach Two Mile Swim .....................            • Date: August 5, 2017.
                                                                                                                    • Time: 7:30 a.m. to 11:00 a.m.
                                                                                                                    • Location: All waters of Captain Harbor between Little Captain’s Island and Bower’s Island
                                                                                                                      that are located within the box formed by connecting four points in the following positions.
                                                                                                                      Beginning at 40°59′23.35″ N. 073°36′42.05″ W.; then northwest to 40°59′51.04″ N.
                                                                                                                      073°37′57.32″ W.; then southwest to 40°59′45.17″ N. 073°38′01.18″ W.; then southeast to
                                                                                                                      40°59′17.38″ N. 073°36′45.9″ W.; then northeast to the point of origin (NAD 83). All posi-
                                                                                                                      tions are approximate.

                                                  8.6   Smith Point Triathlon ..................................    • Date: August 13, 2017.
                                                                                                                    • Time: 6:30 a.m. to 9:30 a.m.
                                                                                                                    • Location: All waters of Narrow Bay near Smith Point Park in Mastic Beach, NY within the
                                                                                                                      area bounded by land along its southern edge and points in position at 40°44′14.28″ N.,
                                                                                                                      072°51′40.68″ W.; then north to a point at position 40°44′20.83″ N., 072°51′40.68″ W.; then
                                                                                                                      east to a point at position 40°44′20.83″ N., 072°51′19.73″ W.; then south to a point at posi-
                                                                                                                      tion 40°44′14.85″ N., 072°51′19.73″ W.; and then southwest along the shoreline back to the
                                                                                                                      point of origin (NAD 83). All positions are approximate.



                                                    Dated: May 18, 2017.                                           River, mile 4.6, between Barter’s Island              SUPPLEMENTARY INFORMATION:
                                                  A.E. Tucci,                                                      and Hodgdon Island, Maine. This                          The bridge owner, State of Maine
                                                  Captain, U.S. Coast Guard, Captain of the                        deviation is necessary to conduct                     Department of Transportation (Maine
                                                  Port Sector Long Island Sound.                                   geotechnical borings needed to design a               DOT), requested a temporary deviation
                                                  [FR Doc. 2017–12742 Filed 6–19–17; 8:45 am]                      new bridge. This deviation allows the                 from the normal operating schedule of
                                                  BILLING CODE 9110–04–P                                           bridge to be closed to vessel traffic for             the Maine Department of Transportation
                                                                                                                   three days.                                           (Barter’s Island) Highway Bridge, mile
                                                                                                                   DATES: This deviation is effective                    4.6, across the Back River between
                                                  DEPARTMENT OF HOMELAND                                           without actual notice from June 20,                   Barter’s Island and Hodgdon Island,
                                                  SECURITY                                                         2017 through 5:30 p.m. on June 14,                    Maine. The drawbridge navigation span
                                                                                                                   2017. For the purposes of enforcement,                has a vertical clearance of six feet at
                                                  Coast Guard                                                      actual notice will be used from June 15,              mean high water in the closed position.
                                                                                                                   2017, until June 20, 2017.                            The existing bridge operating
                                                  33 CFR Part 117                                                  ADDRESSES: The docket for this                        regulations are found at 33 CFR 117.523.
                                                  [Docket No. USCG–2017–0532]                                      deviation, USCG–2017–0532, is                         The approved temporary deviation
                                                                                                                   available at http://www.regulations.gov.              allows the bridge to remain closed for
                                                  Drawbridge Operation Regulation;                                 Type the docket number in the                         vessel traffic between the hours of 7
                                                  Back River, Barter’s Island, ME                                  ‘‘SEARCH’’ box and click ‘‘SEARCH’’.                  a.m. through 5:30 p.m. from June 12
                                                  AGENCY: Coast Guard, DHS.                                        Click on Open Docket Folder on the line               through June 14.
asabaliauskas on DSKBBXCHB2PROD with RULES




                                                                                                                   associated with this deviation.                          The waterway is transited by fishing
                                                  ACTION:Notice of deviation from
                                                  drawbridge regulation.                                           FOR FURTHER INFORMATION CONTACT: If                   and sailing vessels of various sizes. For
                                                                                                                   you have questions on this temporary                  the last three years, the bridge averaged
                                                  SUMMARY:  The Coast Guard has issued a                           deviation, call or email Jeffrey Stieb;               less than three openings a day during
                                                  temporary deviation from the operating                           Bridge Management Specialist, First                   the month of June. Maine DOT
                                                  schedule that governs the Maine                                  Coast Guard District, telephone 617–                  contacted the primary stakeholders,
                                                  Department of Transportation (Barter’s                           223–8364, email Jeffrey.D.Stieb@                      none of which objected to the deviation.
                                                  Island) Highway Bridge over the Back                             uscg.mil.                                             Vessels able to pass through the bridge


                                             VerDate Sep<11>2014     16:57 Jun 19, 2017    Jkt 241001     PO 00000      Frm 00040   Fmt 4700   Sfmt 4700   E:\FR\FM\20JNR1.SGM   20JNR1


                                                                     Federal Register / Vol. 82, No. 117 / Tuesday, June 20, 2017 / Rules and Regulations                                            28007

                                                  in the closed position may continue to                  rulemaking prohibits persons and                       two barges. The contractor has informed
                                                  do so at any time. Vessels have the                     vessels from being in the safety zones                 the Coast Guard that the backup dates
                                                  option of going around the North Side                   unless authorized by the Captain of the                for the removal and transport of the
                                                  of Barter’s Island to reach the Sheepscot               Port New York or a designated                          existing center are June 28–29 and July
                                                  River. During the hours of deviation the                representative.                                        5–6, 2017.
                                                  bridge will not be able to open for                     DATES: This rule is effective from June
                                                                                                                                                                    The Coast Guard is making this
                                                  emergencies.                                                                                                   temporary rule effective less than 30
                                                                                                          20, 2017 through December 31, 2017.
                                                     The Coast Guard will inform the users                                                                       days after publication in the Federal
                                                                                                          ADDRESSES: To view documents
                                                  of the waterway through our Local                                                                              Register pursuant to authority under
                                                                                                          mentioned in this preamble as being                    section 4(a) of the Administrative
                                                  Notice and Broadcast Notice to Mariners
                                                                                                          available in the docket, go to http://                 Procedure Act (APA) (5 U.S.C. 553(d)).
                                                  of the change in operating schedule so
                                                                                                          www.regulations.gov, type USCG–2016–                   This provision authorizes an agency to
                                                  that vessel operators can arrange their
                                                                                                          1048 in the ‘‘SEARCH’’ box and click                   make a rule effective less than 30 days
                                                  transits to minimize any impact caused
                                                                                                          ‘‘SEARCH.’’ Click on Open Docket                       after publication for good cause. We are
                                                  by the temporary deviation.
                                                                                                          Folder on the line associated with this                issuing this rule, and under 5 U.S.C.
                                                     In accordance with 33 CFR 117.35(e),
                                                                                                          rule.                                                  553(d)(3), the Coast Guard finds that
                                                  the drawbridge must return to its regular
                                                  operating schedule immediately at the                   FOR FURTHER INFORMATION CONTACT: If                    good cause exists for making it effective
                                                  end of the effective period of this                     you have questions on this rule, call or               less than 30 days after publication in the
                                                  deviation. This deviation from the                      email Mr. Jeff Yunker, Sector New York                 Federal Register because waiting 30
                                                  operating regulations is authorized                     Waterways Management Division;                         days would be impracticable and
                                                  under 33 CFR 117.35.                                    telephone 718–354–4195, email                          contrary to the public interest. It is
                                                                                                          jeff.m.yunker@uscg.mil.                                impracticable and contrary to the public
                                                    Dated: June 15, 2017.
                                                                                                          SUPPLEMENTARY INFORMATION:                             interest to provide a full 30-days notice
                                                  C.J. Bisignano,                                                                                                because this rule must be effective on
                                                  Supervisory Bridge Management Specialist,               I. Table of Abbreviations
                                                                                                                                                                 June 21–22, 2017 due to favorable tides
                                                  First Coast Guard District.                             COTP Captain of the Port New York                      on that day necessary for the barge
                                                  [FR Doc. 2017–12780 Filed 6–19–17; 8:45 am]             CFR Code of Federal Regulations                        transits. If this rule is not made effective
                                                  BILLING CODE 9110–04–P                                  DHS Department of Homeland Security                    by this date, then it would inhibit the
                                                                                                          FDNY New York City Fire Department
                                                                                                          FR Federal Register
                                                                                                                                                                 Coast Guard’s ability to perform its
                                                                                                          NPRM Notice of proposed rulemaking                     statutory mission to ensure the safety of
                                                  DEPARTMENT OF HOMELAND                                                                                         the maritime public. Though we are not
                                                                                                          NYSDOT New York State Department of
                                                  SECURITY                                                  Transportation                                       providing a full 30 day notice period
                                                                                                          § Section                                              before the rule becomes effective, the
                                                  Coast Guard                                             U.S.C. United States Code                              Coast Guard did provide notice and
                                                                                                          II. Background Information and                         opportunity to comment through the
                                                  33 CFR Part 165
                                                                                                          Regulatory History                                     NPRM process.
                                                  [Docket Number USCG–2016–1048]
                                                                                                             The Coast Guard issued a Bridge                     III. Legal Authority and Need for Rule
                                                  RIN 1625–AA00                                           Permit dated August 21, 2013 approving                    The Coast Guard is issuing this rule
                                                                                                          the location and construction of the                   under authority in 33 U.S.C. 1231. The
                                                  Safety Zone; Kosciuszko Bridge
                                                                                                          Kosciuszko Bridge across Newtown                       COTP has determined that potential
                                                  Construction, Newtown Creek,
                                                                                                          Creek, mile 2.1, between the Boroughs                  hazards associated with these
                                                  Brooklyn and Queens, NY
                                                                                                          of Queens and Brooklyn, NY. On                         operations will be a safety concern for
                                                  AGENCY:    Coast Guard, DHS.                            November 29, 2016, NYSDOT notified                     anyone within a 500-foot radius of the
                                                  ACTION:   Temporary final rule.                         the Coast Guard that it will be lowering               tugs and barges. The purpose of this rule
                                                                                                          the existing center span from the                      is to ensure safety of vessels and the
                                                  SUMMARY:    The Coast Guard is                          Kosciuszko Bridge over Newtown Creek                   navigable waters within a 500-foot
                                                  establishing two safety zones on the                    at mile 2.1 onto two barges within the                 radius of the two barges and assist
                                                  navigable waters of Newtown Creek,                      Newtown Creek Federal navigation                       vessels when loading, securing, and
                                                  NY. The first safety zone is within 500                 channel, securing the center span to the               transporting the center span of the
                                                  feet of the two barges and assist vessels               barges for transit, rotating the barges,               Kosciuszko Bridge through Newtown
                                                  to be used for the removal and loading                  and towing the barges through Newtown                  Creek before, during, and after the
                                                  of the existing center span from the                    Creek to the East River for final upland               operations.
                                                  Kosciuszko Bridge at mile 2.1. The                      disposal.
                                                  second is from approximately 370 yards                     In response, on February 22, 2017, the              IV. Discussion of Comments, Changes,
                                                  south (upstream) of the Kosciuszko                      Coast Guard published a NPRM titled                    and the Rule
                                                  Bridge at mile 2.1 and Newtown Creek’s                  ‘‘Safety Zone; Kosciuszko Bridge                          As noted above, we received no
                                                  confluence with the East River at mile                  Construction, Newtown Creek, Brooklyn                  comments on our NPRM published
                                                  0.0 during transport of the existing                    and Queens, NY’’ (82 FR 11332). There                  February 22, 2017. There are no changes
                                                  center span to an offsite location. This                we stated why we issued the NPRM,                      to the regulatory text of this rule from
                                                  action is necessary to provide for the                  and invited comments on our proposed                   the proposed rule in the NPRM.
asabaliauskas on DSKBBXCHB2PROD with RULES




                                                  safety of life on these navigable waters                regulatory action related to this bridge                  This rule establishes a safety zone
                                                  during the lowering and securing of the                 project. During the comment period that                from June 21 through December 31,
                                                  existing bridge’s center span onto two                  ended March 24, 2017, we received no                   2017. The safety zone will cover all
                                                  barges within the Federal navigation                    comments.                                              navigable waters of Newtown Creek
                                                  channel and during the barge’s                             On May 1, 2017, the contractor                      within 500 feet of the two barges and
                                                  outbound transit through Newtown                        provided June 21–22 as the expected                    assist vessels to be used for the removal
                                                  Creek to the East River, tentatively                    primary dates for the removal and                      and loading of the existing center span
                                                  scheduled on June 21–22, 2017. This                     loading of the existing center span onto               from the Kosciuszko Bridge at mile 2.1,


                                             VerDate Sep<11>2014   16:57 Jun 19, 2017   Jkt 241001   PO 00000   Frm 00041   Fmt 4700   Sfmt 4700   E:\FR\FM\20JNR1.SGM   20JNR1



Document Created: 2017-06-20 02:20:40
Document Modified: 2017-06-20 02:20:40
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionRules and Regulations
ActionNotice of deviation from drawbridge regulation.
DatesThis deviation is effective without actual notice from June 20, 2017 through 5:30 p.m. on June 14, 2017. For the purposes of enforcement, actual notice will be used from June 15, 2017, until June 20, 2017.
ContactIf you have questions on this temporary deviation, call or email Jeffrey Stieb; Bridge Management Specialist, First Coast Guard District, telephone 617-223-8364, email [email protected]
FR Citation82 FR 28006 

2025 Federal Register | Disclaimer | Privacy Policy
USC | CFR | eCFR