82_FR_28172 82 FR 28055 - City of Radford; Notice of Application Tendered for Filing With the Commission and Soliciting Additional Study Requests and Establishing Procedural Schedule for Relicensing and a Deadline for Submission of Final Amendments

82 FR 28055 - City of Radford; Notice of Application Tendered for Filing With the Commission and Soliciting Additional Study Requests and Establishing Procedural Schedule for Relicensing and a Deadline for Submission of Final Amendments

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 82, Issue 117 (June 20, 2017)

Page Range28055-28056
FR Document2017-12864

Federal Register, Volume 82 Issue 117 (Tuesday, June 20, 2017)
[Federal Register Volume 82, Number 117 (Tuesday, June 20, 2017)]
[Notices]
[Pages 28055-28056]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2017-12864]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 1235-017]


City of Radford; Notice of Application Tendered for Filing With 
the Commission and Soliciting Additional Study Requests and 
Establishing Procedural Schedule for Relicensing and a Deadline for 
Submission of Final Amendments

    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection.
    a. Type of Application: Subsequent Minor License.
    b. Project No.: 1235-017.
    c. Date Filed: May 30, 2017.
    d. Applicant: City of Radford.
    e. Name of Project: Municipal Hydroelectric Project.
    f. Location: On the Little River near the City of Radford in 
Montgomery and Pulaski Counties, Virginia. The project does not affect 
federal lands.
    g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791 (a)-825(r).
    h. Applicant Contact: Tim Logwood, Director of Electric Utilities 
for the City of Radford, 701 17th Street, Radford, VA 24141; Telephone 
(540) 731-3641.
    i. FERC Contact: Allyson Conner, (202) 502-6082 or 
[email protected].
    j. Cooperating agencies: Federal, state, local, and tribal agencies 
with jurisdiction and/or special expertise with respect to 
environmental issues that wish to cooperate in the preparation of the 
environmental document should follow the instructions for filing such 
requests described in item l below. Cooperating agencies should note 
the Commission's policy that agencies that cooperate in the preparation 
of the environmental document cannot also intervene. See, 94 FERC ] 
61,076 (2001).
    k. Pursuant to section 4.32(b)(7) of 18 CFR of the Commission's 
regulations, if any resource agency, Indian Tribe, or person believes 
that an additional scientific study should be conducted in order to 
form an adequate factual basis for a complete analysis of the 
application on its merit, the resource agency, Indian Tribe, or person 
must file a request for a study with the Commission not later than 60 
days from the date of filing of the application, and serve a copy of 
the request on the applicant.
    l. Deadline for filing additional study requests and requests for 
cooperating agency status: July 29, 2017.
    The Commission strongly encourages electronic filing. Please file 
additional study requests and requests for cooperating agency status 
using the Commission's eFiling system at http://www.ferc.gov/docs-filing/efiling.asp. For assistance, please contact FERC Online Support 
at [email protected], (866) 208-3676 (toll free), or (202) 
502-8659 (TTY). In lieu of electronic filing, please send a paper copy 
to: Secretary, Federal Energy Regulatory Commission, 888 First Street 
NE., Washington, DC 20426. The first page of any filing should include 
docket number P-1235-017.
    m. This application is not ready for environmental analysis at this 
time.
    n. The existing Municipal Hydroelectric Project consists of: (1) A 
293-foot-long, 58-foot-high reinforced concrete slab and buttress dam 
that includes: (a) A south non-overflow section; (b) an overflow 
bulkhead section; (c) an eight-bay spillway section each with a steel 
tainter gate; (d) a powerhouse intake section; and (e) a north non-
overflow section; (2) a 77-acre impoundment with a gross storage 
capacity of 562 acre-feet at a normal pool elevation of 1,772 feet 
National Geodetic Vertical Datum of 1929 (NGVD29) and a net storage 
capacity of 220 acre-feet between elevations 1,768 and 1,772 feet 
NGVD29; (3) a 20-foot, 3-inch-wide intake section with angled steel 
trash racks (3-inch by 5/16th-inch trash rack bars spaced 2.5 inches on 
center) and a steel roller-type head gate; (4) a 27-foot-long steel-
lined penstock in concrete that transitions from a 13.5-foot-wide, 11-
foot-high entrance to an 8-foot-diameter conveyance to the turbine 
scroll case; (5) a 30-foot-long, 28-foot-wide, and 62-foot-high 
powerhouse containing a single 1,185 kilowatts turbine-generator unit; 
(6) a 2.7-mile-long transmission line connected to the grid; and (7) 
appurtenant facilities.
    The City of Radford proposes to revise its exhibit G to include 
transmission facilities composed of only three, 560-foot-long, 4.16-kV 
overhead conductors that transmit power to a switched disconnect/
interconnection with the local distribution grid. The City of Radford 
states that the formerly licensed transmission line now serves to 
distribute power to other sources along its length and is no longer 
part of the project.

[[Page 28056]]

    The City of Radford operates the project in both run-of-river and 
peaking modes. For the period 1984 through 2013, the project's average 
annual generation was about 4,550 megawatt-hours.
    o. A copy of the application is available for review at the 
Commission in the Public Reference Room or may be viewed on the 
Commission's Web site at http://www.ferc.gov using the eLibrary link. 
Enter the docket number excluding the last three digits in the docket 
number field to access the document. For assistance, contact FERC 
Online Support. A copy is also available for inspection and 
reproduction at the address in item h above.
    You may also register online at http://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances 
related to this or other pending projects. For assistance, contact FERC 
Online Support.
    p. Procedural schedule and final amendments: The application will 
be processed according to the following preliminary Hydro Licensing 
Schedule. Revisions to the schedule will be made as appropriate.

Issue Acceptance or Deficiency Letter--August 2017
Issue Scoping Document for comment--September 2017
Notice that application is ready for environmental analysis--December 
2017
Notice of the availability of the EA--April 2018

    Final amendments to the application must be filed with the 
Commission no later than 30 days from the issuance date of the notice 
of ready for environmental analysis.

    Dated: June 14, 2017.
Kimberly D. Bose,
Secretary.
[FR Doc. 2017-12864 Filed 6-19-17; 8:45 am]
 BILLING CODE 6717-01-P



                                                                               Federal Register / Vol. 82, No. 117 / Tuesday, June 20, 2017 / Notices                                            28055

                                                subpopulations of students and to                         Issued at Washington, DC, on June 14,                a request for a study with the
                                                monitor progress over time. The nature                  2017.                                                  Commission not later than 60 days from
                                                of NAEP is that burden alternates from                  LaTanya R. Butler,                                     the date of filing of the application, and
                                                a relatively low burden in national-level               Deputy Committee Management Officer.                   serve a copy of the request on the
                                                administration years to a substantial                   [FR Doc. 2017–12788 Filed 6–19–17; 8:45 am]            applicant.
                                                burden increase in state-level                          BILLING CODE 6405–01–P
                                                                                                                                                                  l. Deadline for filing additional study
                                                administration years when the sample                                                                           requests and requests for cooperating
                                                has to allow for estimates for individual                                                                      agency status: July 29, 2017.
                                                states and some of the large urban                      DEPARTMENT OF ENERGY                                      The Commission strongly encourages
                                                districts. The NAEP results are reported                                                                       electronic filing. Please file additional
                                                to the public through the Nation’s                      Federal Energy Regulatory                              study requests and requests for
                                                Report Card as well as other online                     Commission                                             cooperating agency status using the
                                                NAEP tools. This request is to conduct                                                                         Commission’s eFiling system at http://
                                                                                                        [Project No. 1235–017]
                                                NAEP in 2018 and 2019, including                                                                               www.ferc.gov/docs-filing/efiling.asp. For
                                                operational assessments, pilot tests, and               City of Radford; Notice of Application                 assistance, please contact FERC Online
                                                special studies. NAEP 2018–2019 data                    Tendered for Filing With the                           Support at FERCOnlineSupport@
                                                collections, including operational                      Commission and Soliciting Additional                   ferc.gov, (866) 208–3676 (toll free), or
                                                assessments, pilot tests, and special                   Study Requests and Establishing                        (202) 502–8659 (TTY). In lieu of
                                                studies, are currently under OMB                        Procedural Schedule for Relicensing                    electronic filing, please send a paper
                                                review (OMB# 1850–0928–v.5). This                       and a Deadline for Submission of Final                 copy to: Secretary, Federal Energy
                                                request is to add Oral Ready Fluency                    Amendments                                             Regulatory Commission, 888 First Street
                                                (ORF) items to the NAEP 2018–2019                                                                              NE., Washington, DC 20426. The first
                                                questionnaire item library (Appendix F).                  Take notice that the following                       page of any filing should include docket
                                                We are announcing a second 30-day                       hydroelectric application has been filed               number P–1235–017.
                                                comment period for NAEP 2018–2019                       with the Commission and is available                      m. This application is not ready for
                                                                                                        for public inspection.                                 environmental analysis at this time.
                                                for the inclusion of these additional
                                                                                                          a. Type of Application: Subsequent                      n. The existing Municipal
                                                ORF questionnaire items.
                                                                                                        Minor License.                                         Hydroelectric Project consists of: (1) A
                                                  Dated: June 15, 2017.                                   b. Project No.: 1235–017.                            293-foot-long, 58-foot-high reinforced
                                                Kate Mullan,                                              c. Date Filed: May 30, 2017.                         concrete slab and buttress dam that
                                                Acting Director, Information Collection                   d. Applicant: City of Radford.                       includes: (a) A south non-overflow
                                                Clearance Division, Office of the Chief Privacy           e. Name of Project: Municipal                        section; (b) an overflow bulkhead
                                                Officer, Office of Management.                          Hydroelectric Project.                                 section; (c) an eight-bay spillway section
                                                [FR Doc. 2017–12861 Filed 6–19–17; 8:45 am]               f. Location: On the Little River near                each with a steel tainter gate; (d) a
                                                BILLING CODE 4000–01–P                                  the City of Radford in Montgomery and                  powerhouse intake section; and (e) a
                                                                                                        Pulaski Counties, Virginia. The project                north non-overflow section; (2) a 77-acre
                                                                                                        does not affect federal lands.                         impoundment with a gross storage
                                                DEPARTMENT OF ENERGY                                      g. Filed Pursuant to: Federal Power                  capacity of 562 acre-feet at a normal
                                                                                                        Act 16 U.S.C. 791 (a)–825(r).                          pool elevation of 1,772 feet National
                                                Nuclear Energy Advisory Committee;                        h. Applicant Contact: Tim Logwood,                   Geodetic Vertical Datum of 1929
                                                Meeting                                                 Director of Electric Utilities for the City            (NGVD29) and a net storage capacity of
                                                                                                        of Radford, 701 17th Street, Radford, VA               220 acre-feet between elevations 1,768
                                                AGENCY:  Office of Nuclear Energy,                      24141; Telephone (540) 731–3641.                       and 1,772 feet NGVD29; (3) a 20-foot, 3-
                                                Department of Energy.                                     i. FERC Contact: Allyson Conner,                     inch-wide intake section with angled
                                                ACTION: Notice of cancellation of open                  (202) 502–6082 or allyson.conner@                      steel trash racks (3-inch by 5/16th-inch
                                                meeting.                                                ferc.gov.                                              trash rack bars spaced 2.5 inches on
                                                                                                          j. Cooperating agencies: Federal, state,             center) and a steel roller-type head gate;
                                                SUMMARY:   On May 26, 2017, the
                                                                                                        local, and tribal agencies with                        (4) a 27-foot-long steel-lined penstock in
                                                Department of Energy (DOE) published
                                                                                                        jurisdiction and/or special expertise                  concrete that transitions from a 13.5-
                                                a notice of open meeting, scheduled for
                                                                                                        with respect to environmental issues                   foot-wide, 11-foot-high entrance to an 8-
                                                June 20, 2017, and request for comment,
                                                                                                        that wish to cooperate in the                          foot-diameter conveyance to the turbine
                                                of the Nuclear Energy Advisory
                                                                                                        preparation of the environmental                       scroll case; (5) a 30-foot-long, 28-foot-
                                                Committee (NEAC). This notice
                                                                                                        document should follow the                             wide, and 62-foot-high powerhouse
                                                announces the cancellation of this
                                                                                                        instructions for filing such requests                  containing a single 1,185 kilowatts
                                                meeting. The rescheduled meeting will
                                                                                                        described in item l below. Cooperating                 turbine-generator unit; (6) a 2.7-mile-
                                                be held at a date to be determined
                                                                                                        agencies should note the Commission’s                  long transmission line connected to the
                                                (August or September).
                                                                                                        policy that agencies that cooperate in                 grid; and (7) appurtenant facilities.
                                                DATES: The meeting scheduled for June                   the preparation of the environmental                      The City of Radford proposes to revise
                                                20, 2017, announced in the May 26,                      document cannot also intervene. See, 94                its exhibit G to include transmission
                                                2017, issue of the Federal Register (FR                 FERC ¶ 61,076 (2001).                                  facilities composed of only three, 560-
                                                Doc. 2017–10877, 82 FR 101), is                           k. Pursuant to section 4.32(b)(7) of 18              foot-long, 4.16-kV overhead conductors
                                                cancelled.                                              CFR of the Commission’s regulations, if                that transmit power to a switched
sradovich on DSK3GMQ082PROD with NOTICES




                                                FOR FURTHER INFORMATION CONTACT: Rob                    any resource agency, Indian Tribe, or                  disconnect/interconnection with the
                                                Rova, Designated Federal Officer, U.S.                  person believes that an additional                     local distribution grid. The City of
                                                Department of Energy, 1000                              scientific study should be conducted in                Radford states that the formerly licensed
                                                Independence Avenue SW.,                                order to form an adequate factual basis                transmission line now serves to
                                                Washington, DC 20585; email:                            for a complete analysis of the                         distribute power to other sources along
                                                robert.rova@nuclear.energy.gov or                       application on its merit, the resource                 its length and is no longer part of the
                                                phone: 301–903–9096.                                    agency, Indian Tribe, or person must file              project.


                                           VerDate Sep<11>2014   18:01 Jun 19, 2017   Jkt 241001   PO 00000   Frm 00013   Fmt 4703   Sfmt 4703   E:\FR\FM\20JNN1.SGM   20JNN1


                                                28056                          Federal Register / Vol. 82, No. 117 / Tuesday, June 20, 2017 / Notices

                                                   The City of Radford operates the                     required by the Paperwork Reduction                    information on the respondents,
                                                project in both run-of-river and peaking                Act of 1995 (PRA), the Federal                         including the use of automated
                                                modes. For the period 1984 through                      Communications Commission (FCC or                      collection techniques or other forms of
                                                2013, the project’s average annual                      Commission) invites the general public                 information technology; and ways to
                                                generation was about 4,550 megawatt-                    and other Federal agencies to take this                further reduce the information
                                                hours.                                                  opportunity to comment on the                          collection burden on small business
                                                   o. A copy of the application is                      following information collections.                     concerns with fewer than 25 employees.
                                                available for review at the Commission                  Comments are requested concerning:                        OMB Control Number: 3060–1070.
                                                in the Public Reference Room or may be                  Whether the proposed collection of                        Title: Allocation and Service Rules for
                                                viewed on the Commission’s Web site at                  information is necessary for the proper                the 71–76 GHz, 81–86 GHz, and 92–95
                                                http://www.ferc.gov using the eLibrary                  performance of the functions of the                    GHz Bands.
                                                link. Enter the docket number excluding                 Commission, including whether the                         Form Number: N/A.
                                                the last three digits in the docket                     information shall have practical utility;                 Type of Review: Extension of a
                                                number field to access the document.                    the accuracy of the Commission’s                       currently approved collection.
                                                For assistance, contact FERC Online                     burden estimate; ways to enhance the                      Respondents: Business or other for-
                                                Support. A copy is also available for                   quality, utility, and clarity of the                   profit entities; not-for-profit institutions;
                                                inspection and reproduction at the                      information collected; ways to minimize                and State, local, or Tribal Government.
                                                address in item h above.                                the burden of the collection of                           Number of Respondents: 754
                                                   You may also register online at http://              information on the respondents,                        respondents; 3,000 responses.
                                                www.ferc.gov/docs-filing/                               including the use of automated                            Estimated Time per Response: 1.5 to
                                                esubscription.asp to be notified via                    collection techniques or other forms of                9 hours.
                                                                                                        information technology; and ways to                       Frequency of Response: On occasion
                                                email of new filings and issuances
                                                                                                        further reduce the information                         reporting requirement, recordkeeping
                                                related to this or other pending projects.
                                                                                                        collection burden on small business                    requirement, and third-party disclosure
                                                For assistance, contact FERC Online
                                                                                                        concerns with fewer than 25 employees.                 requirement.
                                                Support.
                                                                                                           The FCC may not conduct or sponsor                     Obligation To Respond: Required to
                                                   p. Procedural schedule and final
                                                                                                        a collection of information unless it                  obtain or retain benefits. Statutory
                                                amendments: The application will be
                                                                                                        displays a currently valid Office of                   authority for this information collection
                                                processed according to the following
                                                                                                        Management and Budget (OMB) control                    is contained in 47 U.S.C. 151, 154(i),
                                                preliminary Hydro Licensing Schedule.
                                                                                                        number. No person shall be subject to                  303(f) and (r), 309, 316, and 332 of the
                                                Revisions to the schedule will be made
                                                                                                        any penalty for failing to comply with                 Communications Act of 1934, as
                                                as appropriate.
                                                                                                        a collection of information subject to the             amended.
                                                Issue Acceptance or Deficiency Letter—                  PRA that does not display a valid OMB                     Total Annual Burden: 11,250 hours.
                                                   August 2017                                          control number.                                           Total Annual Cost: $910,000.
                                                Issue Scoping Document for comment—                                                                               Privacy Impact Assessment: No
                                                                                                        DATES: Written comments should be
                                                   September 2017                                                                                              impact(s).
                                                                                                        submitted on or before August 21, 2017.
                                                Notice that application is ready for                                                                              Nature and Extent of Confidentiality:
                                                                                                        If you anticipate that you will be
                                                   environmental analysis—December                                                                             There is no need for confidentiality. The
                                                                                                        submitting comments, but find it
                                                   2017                                                                                                        Commission has not granted assurances
                                                                                                        difficult to do so within the period of
                                                Notice of the availability of the EA—                                                                          of confidentially to those parties
                                                                                                        time allowed by this notice, you should
                                                   April 2018                                                                                                  submitting the information. In those
                                                                                                        advise the contacts below as soon as
                                                   Final amendments to the application                  possible.                                              cases where a respondent believes
                                                must be filed with the Commission no                                                                           information requires confidentiality, the
                                                                                                        ADDRESSES: Direct all PRA comments to                  respondent can request confidential
                                                later than 30 days from the issuance
                                                date of the notice of ready for                         Cathy Williams, FCC, via email: PRA@                   treatment and the Commission will
                                                environmental analysis.                                 fcc.gov and to Cathy.Williams@fcc.gov.                 afford such confidentiality for 20 days,
                                                                                                        FOR FURTHER INFORMATION CONTACT: For                   after which the information will be
                                                  Dated: June 14, 2017.                                 additional information about the                       available to the public.
                                                Kimberly D. Bose,                                       information collection, contact Cathy                     Needs and Uses: The Commission is
                                                Secretary.                                              Williams at (202) 418–2918.                            seeking an extension of this information
                                                [FR Doc. 2017–12864 Filed 6–19–17; 8:45 am]             SUPPLEMENTARY INFORMATION: As part of                  collection in order to obtain the full
                                                BILLING CODE 6717–01–P                                  its continuing effort to reduce                        three year approval from OMB. There
                                                                                                        paperwork burdens, and as required by                  are no program changes to the reporting,
                                                                                                        the PRA, 44 U.S.C. 3501–3520, the FCC                  recordkeeping and/or third-party
                                                FEDERAL COMMUNICATIONS                                  invites the general public and other                   disclosure requirements but we are
                                                COMMISSION                                              Federal agencies to take this                          revising estimates based on experience
                                                                                                        opportunity to comment on the                          and the possible addition of a fourth
                                                [OMB 3060–1070]                                         following information collections.                     database manager. The recordkeeping,
                                                                                                        Comments are requested concerning:                     reporting, and third party disclosure
                                                Information Collection Being Reviewed
                                                                                                        Whether the proposed collection of                     requirements will be used by the
                                                by the Federal Communications
                                                                                                        information is necessary for the proper                Commission to verify licensee
                                                Commission
                                                                                                        performance of the functions of the                    compliance with the Commission rules
sradovich on DSK3GMQ082PROD with NOTICES




                                                AGENCY: Federal Communications                          Commission, including whether the                      and regulations, and to ensure that
                                                Commission.                                             information shall have practical utility;              licensees continue to fulfill their
                                                ACTION: Notice and request for                          the accuracy of the Commission’s                       statutory responsibilities in accordance
                                                comments.                                               burden estimate; ways to enhance the                   with the Communications Act of 1934.
                                                                                                        quality, utility, and clarity of the                   The Commission’s rules promote the
                                                SUMMARY:  As part of its continuing effort              information collected; ways to minimize                private sector development and use of
                                                to reduce paperwork burdens, and as                     the burden of the collection of                        71–76 GHz, 81–86 GHz, and 92–95 GHz


                                           VerDate Sep<11>2014   18:01 Jun 19, 2017   Jkt 241001   PO 00000   Frm 00014   Fmt 4703   Sfmt 4703   E:\FR\FM\20JNN1.SGM   20JNN1



Document Created: 2017-06-20 02:20:39
Document Modified: 2017-06-20 02:20:39
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation82 FR 28055 

2025 Federal Register | Disclaimer | Privacy Policy
USC | CFR | eCFR