82_FR_29415 82 FR 29292 - Pioneer Valley, LLC; Notice of Preliminary Determination of a Qualifying Conduit Hydropower Facility and Soliciting Comments and Motions To Intervene

82 FR 29292 - Pioneer Valley, LLC; Notice of Preliminary Determination of a Qualifying Conduit Hydropower Facility and Soliciting Comments and Motions To Intervene

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 82, Issue 123 (June 28, 2017)

Page Range29292-29293
FR Document2017-13522

Federal Register, Volume 82 Issue 123 (Wednesday, June 28, 2017)
[Federal Register Volume 82, Number 123 (Wednesday, June 28, 2017)]
[Notices]
[Pages 29292-29293]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2017-13522]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CD17-13-000]


Pioneer Valley, LLC; Notice of Preliminary Determination of a 
Qualifying Conduit Hydropower Facility and Soliciting Comments and 
Motions To Intervene

    On June 20, 2017, Pioneer Valley, LLC, filed a notice of intent to 
construct a qualifying conduit hydropower facility, pursuant to section 
30 of the Federal Power Act (FPA), as amended by section 4 of the 
Hydropower Regulatory Efficiency Act of 2013 (HREA). The proposed 
Pioneer Valley Hydro Site Project would have a combined installed 
capacity of 6 kilowatts (kW), and would be located along two sections 
of an existing irrigation pipeline. The project would be located near 
the Town of Cimarron in Gunnison County, Colorado.
    Applicant Contact: Gary Stephens, 18876 6495 Road, Montrose, CO 
81403, Phone No. (970) 209-6104, email [email protected].
    FERC Contact: Robert Bell, Phone No. (202) 502-6062, email: 
[email protected].
    Qualifying Conduit Hydropower Facility Description: The proposed 
project would consist of: (1) A new 25-foot-long, 8-inch diameter 
intake pipe; (2) a new powerhouse containing 2 generating units (one 4 
kilowatt turbine and one 2 kilowatt turbine) with a total installed 
capacity of 6 kilowatts (kW); (3) a new 80-foot-long, 12-inch diameter 
discharge pipe to nearby pond; and (4) appurtenant facilities. The 
proposed project would have an estimated annual generating capacity of 
45,900 kilowatt-hours (kWh).
    A qualifying conduit hydropower facility is one that is determined 
or deemed to meet all of the criteria shown in the table below.

      Table 1--Criteria for Qualifying Conduit Hydropower Facility
------------------------------------------------------------------------
                                                            Satisfies (Y/
       Statutory provision               Description             N)
------------------------------------------------------------------------
FPA 30(a)(3)(A), as amended by    The conduit the facility            Y
 HREA.                             uses is a tunnel,
                                   canal, pipeline,
                                   aqueduct, flume, ditch,
                                   or similar manmade
                                   water conveyance that
                                   is operated for the
                                   distribution of water
                                   for agricultural,
                                   municipal, or
                                   industrial consumption
                                   and not primarily for
                                   the generation of
                                   electricity.
FPA 30(a)(3)(C)(i), as amended    The facility is                     Y
 by HREA.                          constructed, operated,
                                   or maintained for the
                                   generation of electric
                                   power and uses for such
                                   generation only the
                                   hydroelectric potential
                                   of a non-federally
                                   owned conduit.
FPA 30(a)(3)(C)(ii), as amended   The facility has an                 Y
 by HREA.                          installed capacity that
                                   does not exceed 5
                                   megawatts.
FPA 30(a)(3)(C)(iii), as amended  On or before August 9,              Y
 by HREA.                          2013, the facility is
                                   not licensed, or
                                   exempted from the
                                   licensing requirements
                                   of Part I of the FPA.
------------------------------------------------------------------------

    Preliminary Determination: The proposed hydroelectric project will 
utilize the existing water distribution pipeline, and its addition will 
not alter the distribution pipeline's primary purpose. Therefore, based 
upon the above criteria, Commission staff preliminarily determines that 
the proposal satisfies the requirements for a qualifying conduit 
hydropower facility, which is not required to be licensed or exempted 
from licensing.
    Comments and Motions to Intervene: Deadline for filing comments 
contesting whether the facility meets the qualifying criteria is 45 
days from the issuance date of this notice.
    Deadline for filing motions to intervene is 30 days from the 
issuance date of this notice.
    Anyone may submit comments or a motion to intervene in accordance 
with the requirements of Rules of Practice and Procedure, 18 CFR 
385.210 and 385.214. Any motions to intervene must be received on or 
before the specified deadline date for the particular proceeding.
    Filing and Service of Responsive Documents: All filings must (1) 
bear in all capital letters the COMMENTS CONTESTING QUALIFICATION FOR A 
CONDUIT HYDROPOWER FACILITY or MOTION TO INTERVENE, as applicable; (2) 
state in the heading the name of the applicant and the project number 
of the application to which the filing responds; (3) state the name, 
address, and telephone number of the person filing; and (4) otherwise 
comply with the requirements of sections 385.2001 through 385.2005 of 
the Commission's regulations.\1\ All comments contesting Commission 
staff's preliminary determination that the facility meets the 
qualifying criteria must set forth their evidentiary basis.
---------------------------------------------------------------------------

    \1\ 18 CFR 385.2001-2005 (2016).
---------------------------------------------------------------------------

    The Commission strongly encourages electronic filing. Please file 
motions to intervene and comments using the Commission's eFiling system 
at http://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit 
brief comments up to 6,000 characters, without prior registration, 
using the eComment system at http://www.ferc.gov/docs-filing/ecomment.asp. You must include your name and contact information at the 
end of your comments. For assistance, please contact FERC Online 
Support at [email protected], (866) 208-3676 (toll free), or 
(202) 502-8659 (TTY). In lieu of electronic filing, please send a paper 
copy to: Secretary, Federal Energy Regulatory Commission, 888 First 
Street NE., Washington, DC 20426. A copy of all other filings in 
reference to this application must be accompanied by proof of service 
on all persons listed in the service list prepared by the Commission in 
this proceeding, in

[[Page 29293]]

accordance with 18 CFR 4.34(b) and 385.2010.
    Locations of Notice of Intent: Copies of the notice of intent can 
be obtained directly from the applicant or such copies can be viewed 
and reproduced at the Commission in its Public Reference Room, Room 2A, 
888 First Street NE., Washington, DC 20426. The filing may also be 
viewed on the web at http://www.ferc.gov/docs-filing/elibrary.asp using 
the ``eLibrary'' link. Enter the docket number (i.e., CD17-13) in the 
docket number field to access the document. For assistance, call toll-
free 1-866-208-3676 or email [email protected]. For TTY, call 
(202) 502-8659.

    Dated: June 22, 2017.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2017-13522 Filed 6-27-17; 8:45 am]
 BILLING CODE 6717-01-P



                                                    29292                        Federal Register / Vol. 82, No. 123 / Wednesday, June 28, 2017 / Notices

                                                    requirements, interventions, protests,                  DEPARTMENT OF ENERGY                                     Applicant Contact: Gary Stephens,
                                                    service, and qualifying facilities filings                                                                     18876 6495 Road, Montrose, CO 81403,
                                                    can be found at: http://www.ferc.gov/                   Federal Energy Regulatory                              Phone No. (970) 209–6104, email
                                                    docs-filing/efiling/filing-req.pdf. For                 Commission                                             gwstephens49@gmail.com.
                                                    other information, call (866) 208–3676                  [Docket No. CD17–13–000]                                 FERC Contact: Robert Bell, Phone No.
                                                    (toll free). For TTY, call (202) 502–8659.                                                                     (202) 502–6062, email: robert.bell@
                                                                                                            Pioneer Valley, LLC; Notice of                         ferc.gov.
                                                      Dated: June 22, 2017.
                                                                                                            Preliminary Determination of a
                                                    Nathaniel J. Davis, Sr.,                                Qualifying Conduit Hydropower                            Qualifying Conduit Hydropower
                                                    Deputy Secretary.                                       Facility and Soliciting Comments and                   Facility Description: The proposed
                                                    [FR Doc. 2017–13523 Filed 6–27–17; 8:45 am]             Motions To Intervene                                   project would consist of: (1) A new 25-
                                                    BILLING CODE 6717–01–P
                                                                                                                                                                   foot-long, 8-inch diameter intake pipe;
                                                                                                               On June 20, 2017, Pioneer Valley,                   (2) a new powerhouse containing 2
                                                                                                            LLC, filed a notice of intent to construct             generating units (one 4 kilowatt turbine
                                                                                                            a qualifying conduit hydropower                        and one 2 kilowatt turbine) with a total
                                                                                                            facility, pursuant to section 30 of the                installed capacity of 6 kilowatts (kW);
                                                                                                            Federal Power Act (FPA), as amended                    (3) a new 80-foot-long, 12-inch diameter
                                                                                                            by section 4 of the Hydropower
                                                                                                                                                                   discharge pipe to nearby pond; and (4)
                                                                                                            Regulatory Efficiency Act of 2013
                                                                                                                                                                   appurtenant facilities. The proposed
                                                                                                            (HREA). The proposed Pioneer Valley
                                                                                                                                                                   project would have an estimated annual
                                                                                                            Hydro Site Project would have a
                                                                                                            combined installed capacity of 6                       generating capacity of 45,900 kilowatt-
                                                                                                            kilowatts (kW), and would be located                   hours (kWh).
                                                                                                            along two sections of an existing                        A qualifying conduit hydropower
                                                                                                            irrigation pipeline. The project would                 facility is one that is determined or
                                                                                                            be located near the Town of Cimarron                   deemed to meet all of the criteria shown
                                                                                                            in Gunnison County, Colorado.                          in the table below.

                                                                                      TABLE 1—CRITERIA FOR QUALIFYING CONDUIT HYDROPOWER FACILITY
                                                                                                                                                                                                        Satisfies
                                                                 Statutory provision                                                             Description                                             (Y/N)

                                                    FPA 30(a)(3)(A), as amended by HREA ...             The conduit the facility uses is a tunnel, canal, pipeline, aqueduct, flume, ditch, or             Y
                                                                                                          similar manmade water conveyance that is operated for the distribution of water for
                                                                                                          agricultural, municipal, or industrial consumption and not primarily for the genera-
                                                                                                          tion of electricity.
                                                    FPA 30(a)(3)(C)(i), as amended by HREA              The facility is constructed, operated, or maintained for the generation of electric                Y
                                                                                                          power and uses for such generation only the hydroelectric potential of a non-feder-
                                                                                                          ally owned conduit.
                                                    FPA 30(a)(3)(C)(ii), as amended by HREA             The facility has an installed capacity that does not exceed 5 megawatts .....................      Y
                                                    FPA 30(a)(3)(C)(iii), as amended by                 On or before August 9, 2013, the facility is not licensed, or exempted from the licens-            Y
                                                      HREA.                                               ing requirements of Part I of the FPA.



                                                      Preliminary Determination: The                        be received on or before the specified                    The Commission strongly encourages
                                                    proposed hydroelectric project will                     deadline date for the particular                       electronic filing. Please file motions to
                                                    utilize the existing water distribution                 proceeding.                                            intervene and comments using the
                                                    pipeline, and its addition will not alter                  Filing and Service of Responsive                    Commission’s eFiling system at http://
                                                    the distribution pipeline’s primary                     Documents: All filings must (1) bear in                www.ferc.gov/docs-filing/efiling.asp.
                                                    purpose. Therefore, based upon the                                                                             Commenters can submit brief comments
                                                                                                            all capital letters the COMMENTS
                                                    above criteria, Commission staff                                                                               up to 6,000 characters, without prior
                                                                                                            CONTESTING QUALIFICATION FOR A
                                                    preliminarily determines that the                                                                              registration, using the eComment system
                                                    proposal satisfies the requirements for a               CONDUIT HYDROPOWER FACILITY or
                                                                                                            MOTION TO INTERVENE, as                                at http://www.ferc.gov/docs-filing/
                                                    qualifying conduit hydropower facility,                                                                        ecomment.asp. You must include your
                                                    which is not required to be licensed or                 applicable; (2) state in the heading the
                                                                                                            name of the applicant and the project                  name and contact information at the end
                                                    exempted from licensing.                                                                                       of your comments. For assistance,
                                                      Comments and Motions to Intervene:                    number of the application to which the
                                                                                                            filing responds; (3) state the name,                   please contact FERC Online Support at
                                                    Deadline for filing comments contesting
                                                                                                            address, and telephone number of the                   FERCOnlineSupport@ferc.gov, (866)
                                                    whether the facility meets the qualifying
                                                                                                            person filing; and (4) otherwise comply                208–3676 (toll free), or (202) 502–8659
                                                    criteria is 45 days from the issuance
                                                    date of this notice.                                    with the requirements of sections                      (TTY). In lieu of electronic filing, please
asabaliauskas on DSKBBXCHB2PROD with NOTICES




                                                                                                            385.2001 through 385.2005 of the                       send a paper copy to: Secretary, Federal
                                                      Deadline for filing motions to
                                                    intervene is 30 days from the issuance                  Commission’s regulations.1 All                         Energy Regulatory Commission, 888
                                                    date of this notice.                                    comments contesting Commission staff’s                 First Street NE., Washington, DC 20426.
                                                      Anyone may submit comments or a                       preliminary determination that the                     A copy of all other filings in reference
                                                    motion to intervene in accordance with                  facility meets the qualifying criteria                 to this application must be accompanied
                                                    the requirements of Rules of Practice                   must set forth their evidentiary basis.                by proof of service on all persons listed
                                                    and Procedure, 18 CFR 385.210 and                                                                              in the service list prepared by the
                                                    385.214. Any motions to intervene must                    1 18   CFR 385.2001–2005 (2016).                     Commission in this proceeding, in


                                               VerDate Sep<11>2014   17:22 Jun 27, 2017   Jkt 241001   PO 00000   Frm 00019   Fmt 4703   Sfmt 4703   E:\FR\FM\28JNN1.SGM   28JNN1


                                                                                 Federal Register / Vol. 82, No. 123 / Wednesday, June 28, 2017 / Notices                                                  29293

                                                    accordance with 18 CFR 4.34(b) and                      http://www.ferc.gov using the eLibrary                 environmental mailing list, will receive
                                                    385.2010.                                               link. Enter the docket number excluding                copies of the environmental documents,
                                                      Locations of Notice of Intent: Copies                 the last three digits in the docket                    and will be notified of meetings
                                                    of the notice of intent can be obtained                 number field to access the document.                   associated with the Commission’s
                                                    directly from the applicant or such                     For assistance, contact FERC at                        environmental review process.
                                                    copies can be viewed and reproduced at                  FERCOnlineSupport@ferc.gov or call                     Environmental commenter’s will not be
                                                    the Commission in its Public Reference                  toll-free, (866) 208–3676 or TTY, (202)                required to serve copies of filed
                                                    Room, Room 2A, 888 First Street NE.,                    502–8659.                                              documents on all other parties.
                                                    Washington, DC 20426. The filing may                       Any questions regarding this                        However, the non-party commentary,
                                                    also be viewed on the web at http://                    Application should be directed to                      will not receive copies of all documents
                                                    www.ferc.gov/docs-filing/elibrary.asp                   Kenan W. Carioti, Regulatory &                         filed by other parties or issued by the
                                                    using the ‘‘eLibrary’’ link. Enter the                  Certificates Analyst III, Dominion                     Commission (except for the mailing of
                                                    docket number (i.e., CD17–13) in the                    Energy Transmission, Inc., 707 East                    environmental documents issued by the
                                                    docket number field to access the                       Main Street, Richmond, VA 23219, by                    Commission) and ill not have the right
                                                    document. For assistance, call toll-free                phone (804) 771–4018 or by Email:                      to seek court review of the
                                                    1–866–208–3676 or email                                 Kenan.W.Carioti@DominionEnergy.com.                    Commission’s final order.
                                                    FERCOnlineSupport@ferc.gov. For TTY,                       Any person may, within 60 days after                   The Commission strongly encourages
                                                    call (202) 502–8659.                                    the issuance of the instant notice by the              electronic filings of comments, protests,
                                                                                                            Commission, file pursuant to Rule 214                  and interventions via the internet in lieu
                                                      Dated: June 22, 2017.                                 of the Commission’s Procedural Rules                   of paper. See 18 CFR 385.2001(a)(1)(iii)
                                                    Nathaniel J. Davis, Sr.,                                (18 CFR 385.214) a motion to intervene                 and the instructions on the
                                                    Deputy Secretary.                                       or notice of intervention. Any person                  Commission’s Web site (www.ferc.gov)
                                                    [FR Doc. 2017–13522 Filed 6–27–17; 8:45 am]             filing to intervene or the Commission’s                under the e-Filing link. Persons unable
                                                    BILLING CODE 6717–01–P                                  staff may, pursuant to section 157.205 of              to file electronically should submit an
                                                                                                            the Commission’s Regulations under the                 original and 5 copies of the protest or
                                                                                                            NGA (18 CFR 157.205) file a protest to                 intervention to the Federal Energy
                                                    DEPARTMENT OF ENERGY                                    the request. If no protest is filed within             regulatory Commission, 888 First Street
                                                                                                            the time allowed therefore, the proposed               NE., Washington, DC 20426.
                                                    Federal Energy Regulatory                               activity shall be deemed to be
                                                    Commission                                              authorized effective the day after the                   Dated: June 22, 2017.
                                                                                                            time allowed for protest. If a protest is              Nathaniel J. Davis, Sr.,
                                                    [Docket No. CP17–465–000]
                                                                                                            filed and not withdrawn within 30 days                 Deputy Secretary.
                                                    Dominion Energy Transmission, Inc.;                     after the time allowed for filing a                    [FR Doc. 2017–13525 Filed 6–27–17; 8:45 am]
                                                    Notice of Request Under Blanket                         protest, the instant request shall be                  BILLING CODE 6717–01–P
                                                    Authorization                                           treated as an application for
                                                                                                            authorization pursuant to section 7 of
                                                       Take notice that on June 16, 2017,                   the NGA.                                               ENVIRONMENTAL PROTECTION
                                                    Dominion Energy Transmission, Inc.                         Pursuant to section 157.9 of the                    AGENCY
                                                    (DETI), located at 707 East Main Street,                Commission’s rules, 18 CFR 157.9,
                                                    Richmond, VA 23219, filed a prior                       within 90 days of this Notice the                      [FRL–9962–04–Region 5]
                                                    notice request pursuant to sections                     Commission staff will either: complete
                                                    157.205 and 157.216 of the Federal                                                                             Proposed De minimis Settlement With
                                                                                                            its environmental assessment (EA) and
                                                    Energy Regulatory Commission’s                                                                                 Sunoco (R&M), LLC at Lammers Barrel
                                                                                                            place it into the Commission’s public
                                                    regulations under the Natural Gas Act                   record (eLibrary) for this proceeding; or              Site in Beavercreek, Ohio
                                                    (NGA), seeking authorization to plug                    issue a Notice of Schedule for                         AGENCY: Environmental Protection
                                                    and abandon ‘‘future storage’’ wells:                   Environmental Review. If a Notice of                   Agency (EPA).
                                                    JW–452F, JW–453F, JW–539F and                           Schedule for Environmental Review is                   ACTION: Notice; request for public
                                                    associated pipelines: JP–419, JP–421,                   issued, it will indicate, among other                  comment.
                                                    JP–448, JP–449, JP–451, JP–453 and                      milestones, the anticipated date for the
                                                    Meter: 5104601 located in the Oakford                   Commission staff’s issuance of the final               SUMMARY:     In accordance with Section
                                                    Storage Complex in Westmoreland                         environmental impact statement (FEIS)                  122(i) of the Comprehensive
                                                    County, Pennsylvania. DETI and Texas                    or EA for this proposal. The filing of the             Environmental Response,
                                                    Eastern Transmission, LP jointly own                    EA in the Commission’s public record                   Compensation, and Liability Act of
                                                    the Oakford Storage Complex as tenants                  for this proceeding or the issuance of a               1980, as amended (‘‘CERCLA’’), notice
                                                    in common with equal undivided one-                     Notice of Schedule for Environmental                   is hereby given by the U.S.
                                                    half interests. DETI is the operator of the             Review will serve to notify federal and                Environmental Protection Agency
                                                    Oakford Storage Complex and as the                      state agencies of the timing for the                   (‘‘EPA’’), Region 5, of a proposed de
                                                    operator is making this filing on behalf                completion of all necessary reviews, and               minimis administrative agreement
                                                    of both parties. The certificated physical              the subsequent need to complete all                    under Section 122(g) of CERCLA,
                                                    parameters, including total inventory,                  federal authorizations within 90 days of               between EPA and Sunoco (R&M), LLC.
asabaliauskas on DSKBBXCHB2PROD with NOTICES




                                                    reservoir pressure, reservoir and buffer                the date of issuance of the Commission                 pertaining to the Lammers Barrel
                                                    boundaries, and certificated capacity                   staff’s FEIS or EA.                                    Superfund Site located in the
                                                    (including injection and withdrawal                        Persons who wish to comment only                    Beavercreek, Greene County, Ohio
                                                    capacity) of the Oakford Storage                        on the environmental review of this                    (‘‘Site’’). The settlement requires a
                                                    Complex will remain unchanged, all as                   project should submit an original and                  $85,253.85 payment by Sunoco (R&M),
                                                    more fully set forth in the application,                two copies of their comments to the                    LLC. to the EPA Hazardous Substance
                                                    which is on file with the Commission                    Secretary of the Commission.                           Superfund Lammers Barrel Superfund
                                                    and open to public inspection. The                      Environmental commenter’s will be                      Site Special Account set aside for the
                                                    filing may also be viewed on the web at                 placed on the Commission’s                             remedial design and remedial action


                                               VerDate Sep<11>2014   17:22 Jun 27, 2017   Jkt 241001   PO 00000   Frm 00020   Fmt 4703   Sfmt 4703   E:\FR\FM\28JNN1.SGM   28JNN1



Document Created: 2017-06-28 01:10:12
Document Modified: 2017-06-28 01:10:12
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation82 FR 29292 