82_FR_34657 82 FR 34516 - National Fuel Gas Supply Corporation; Notice of Request Under Blanket Authorization

82 FR 34516 - National Fuel Gas Supply Corporation; Notice of Request Under Blanket Authorization

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 82, Issue 141 (July 25, 2017)

Page Range34516-34517
FR Document2017-15546

Federal Register, Volume 82 Issue 141 (Tuesday, July 25, 2017)
[Federal Register Volume 82, Number 141 (Tuesday, July 25, 2017)]
[Notices]
[Pages 34516-34517]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2017-15546]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP17-472-000]


National Fuel Gas Supply Corporation; Notice of Request Under 
Blanket Authorization

    Take notice that on July 10, 2017, National Fuel Gas Supply 
Corporation (National Fuel) 6363 Main Street, Williamsville, New York 
14221, filed a prior notice application pursuant to sections 157.205, 
and 157.216 of the Federal Energy Regulatory Commission's (Commission) 
regulations under the Natural Gas Act (NGA), and National Fuel's 
blanket certificate issued in Docket No. CP83-4-000. National Fuel 
requests authorization to abandon one injection/withdrawal storage well 
and associated well line in its Colden Storage Field located in the 
Town of Aurora, Erie County, New York. Specifically, National Fuel 
proposes to plug and abandon one injection/withdrawal storage well, 
Well 0925-I, and abandon in place the associated Well Line CW-925, all 
as more fully set forth in the application, which is open to the public 
for inspection. There will be no abandonment or decrease in service to 
customers as a result of the proposed abandonment. The filing may also 
be viewed on the web at http://

[[Page 34517]]

www.ferc.gov using the ``eLibrary'' link. Enter the docket number 
excluding the last three digits in the docket number field to access 
the document. For assistance, contact FERC at 
[email protected] or call toll-free, (866) 208-3676 or TTY, 
(202) 502-8659.
    Any questions regarding this application should be directed to 
Alice A. Curtiss, Deputy General Counsel for National Fuel, 6363 Main 
Street, Williamsville, New York 14221, or phone (716) 857-7075, or by 
email [email protected].
    Any person or the Commission's staff may, within 60 days after 
issuance of the instant notice by the Commission, file pursuant to Rule 
214 of the Commission's Procedural Rules (18 CFR 385.214) a motion to 
intervene or notice of intervention and pursuant to Section 157.205 of 
the regulations under the NGA (18 CFR 157.205), a protest to the 
request. If no protest is filed within the time allowed therefore, the 
proposed activity shall be deemed to be authorized effective the day 
after the time allowed for filing a protest. If a protest is filed and 
not withdrawn within 30 days after the allowed time for filing a 
protest, the instant request shall be treated as an application for 
authorization pursuant to section 7 of the NGA.
    Pursuant to section 157.9 of the Commission's rules, 18 CFR 157.9, 
within 90 days of this Notice the Commission staff will either: 
Complete its environmental assessment (EA) and place it into the 
Commission's public record (eLibrary) for this proceeding, or issue a 
Notice of Schedule for Environmental Review. If a Notice of Schedule 
for Environmental Review is issued, it will indicate, among other 
milestones, the anticipated date for the Commission staff's issuance of 
the final environmental impact statement (FEIS) or EA for this 
proposal. The filing of the EA in the Commission's public record for 
this proceeding or the issuance of a Notice of Schedule for 
Environmental Review will serve to notify federal and state agencies of 
the timing for the completion of all necessary reviews, and the 
subsequent need to complete all federal authorizations within 90 days 
of the date of issuance of the Commission staff's FEIS or EA.
    Persons who wish to comment only on the environmental review of 
this project should submit an original and two copies of their comments 
to the Secretary of the Commission. Environmental commenters will be 
placed on the Commission's environmental mailing list, will receive 
copies of the environmental documents, and will be notified of meetings 
associated with the Commission's environmental review process. 
Environmental commenters will not be required to serve copies of filed 
documents on all other parties. However, the non-party commenter will 
not receive copies of all documents filed by other parties or issued by 
the Commission (except for the mailing of environmental documents 
issued by the Commission) and will not have the right to seek court 
review of the Commission's final order.
    The Commission strongly encourages electronic filings of comments, 
protests and interventions in lieu of paper using the eFiling link at 
http://www.ferc.gov. Persons unable to file electronically should 
submit an original and 5 copies of the protest or intervention to the 
Federal Energy Regulatory Commission, 888 First Street NE., Washington, 
DC 20426.

    Dated: July 19, 2017.
Kimberly D. Bose,
Secretary.
[FR Doc. 2017-15546 Filed 7-24-17; 8:45 am]
 BILLING CODE 6717-01-P



                                                  34516                           Federal Register / Vol. 82, No. 141 / Tuesday, July 25, 2017 / Notices

                                                  Paiute to abandon and replace certain                    milestones, the anticipated date for the              Environmental commentors will not be
                                                  pipeline facilities, and to construct and                Commission staff’s issuance of the EA                 required to serve copies of filed
                                                  operate certain pipeline and associated                  for this proposal. The filing of the EA               documents on all other parties.
                                                  facilities located in Douglas County,                    in the Commission’s public record for                 However, the non-party commentors
                                                  Lyon County, and Carson City, Nevada                     this proceeding or the issuance of a                  will not receive copies of all documents
                                                  (2018 Expansion Project or Project), all                 Notice of Schedule for Environmental                  filed by other parties or issued by the
                                                  as more fully set forth in the                           Review will serve to notify federal and               Commission (except for the mailing of
                                                  application, which is open to the public                 state agencies of the timing for the                  environmental documents issued by the
                                                  for inspection. The filing may also be                   completion of all necessary reviews, and              Commission) and will not have the right
                                                  viewed on the web at http://                             the subsequent need to complete all                   to seek court review of the
                                                  www.ferc.gov using the ‘‘eLibrary’’ link.                federal authorizations within 90 days of              Commission’s final order.
                                                  Enter the docket number excluding the                    the date of issuance of the Commission                   The Commission strongly encourages
                                                  last three digits in the docket number                   staff’s EA.                                           electronic filings of comments, protests
                                                  field to access the document. For                           There are two ways to become                       and interventions in lieu of paper using
                                                  assistance, contact FERC at                              involved in the Commission’s review of                the eFiling link at http://www.ferc.gov.
                                                  FERCOnlineSupport@ferc.gov or call                       this project. First, any person wishing to            Persons unable to file electronically
                                                  toll-free, (866) 208–3676 or TTY, (202)                  obtain legal status by becoming a party               should submit an original and 5 copies
                                                  502–8659.                                                to the proceedings for this project                   of the protest or intervention to the
                                                     Any questions regarding the Paiute                    should, on or before the comment date                 Federal Energy regulatory Commission,
                                                  application should be directed to Mark                   stated below file with the Federal                    888 First Street NE., Washington, DC
                                                  A. Litwin, Vice President/General                        Energy Regulatory Commission, 888                     20426.
                                                  Manager, Paiute Pipeline Company, P.O.                   First Street NE., Washington, DC 20426,                  Comment Date: 5:00 p.m. Eastern
                                                  Box 94197, Las Vegas, Nevada 89193–                      a motion to intervene in accordance                   Time on August 9, 2017.
                                                  4197, or (702) 364–3195, or by email                     with the requirements of the
                                                  mark.litwin@swgas.com.                                   Commission’s Rules of Practice and                      Dated: July 19, 2017.
                                                     Specifically, the 2018 Expansion                      Procedure (18 CFR 385.214 or 385.211)                 Kimberly D. Bose,
                                                  Project will involve: (1) Installation of                and the Regulations under the NGA (18                 Secretary.
                                                  0.42 miles of a new 12-inch-diameter                     CFR 157.10). A person obtaining party                 [FR Doc. 2017–15550 Filed 7–24–17; 8:45 am]
                                                  steel pipeline loop, (2) installation of                 status will be placed on the service list             BILLING CODE 6717–01–P
                                                  4.19 miles of a new 20-inch-diameter                     maintained by the Secretary of the
                                                  steel pipeline loop, (3) abandonment                     Commission and will receive copies of
                                                  and replacement of 1.58 miles of                         all documents filed by the applicant and              DEPARTMENT OF ENERGY
                                                  existing 8-inch-diameter steel pipeline                  by all other parties. A party must submit
                                                  with 12-inch-diameter steel pipeline, (4)                7 copies of filings made in the                       Federal Energy Regulatory
                                                  replacement of 2.27 miles of existing 10-                proceeding with the Commission and                    Commission
                                                  inch-diameter steel pipeline with 20-                    must mail a copy to the applicant and                 [Docket No. CP17–472–000]
                                                  inch-diameter steel pipeline, and (5)                    to every other party. Only parties to the
                                                  installation of associated auxiliary or                  proceeding can ask for court review of                National Fuel Gas Supply Corporation;
                                                  appurtenant facilities. The Project is                   Commission orders in the proceeding.                  Notice of Request Under Blanket
                                                  designed to provide incremental firm                        However, a person does not have to                 Authorization
                                                  transportation services of 5,635                         intervene in order to have comments
                                                  dekatherms per day on Paiute’s system.                   considered. The second way to                            Take notice that on July 10, 2017,
                                                  Paiute proposes an initial incremental                   participate is by filing with the                     National Fuel Gas Supply Corporation
                                                  rate to recover the costs of the Project                 Secretary of the Commission, as soon as               (National Fuel) 6363 Main Street,
                                                  facilities. The estimated cost for Paiute’s              possible, an original and two copies of               Williamsville, New York 14221, filed a
                                                  construction of the Project is                           comments in support of or in opposition               prior notice application pursuant to
                                                  $17,950,000.                                             to this project. The Commission will                  sections 157.205, and 157.216 of the
                                                     On October 24, 2016, Commission                       consider these comments in                            Federal Energy Regulatory
                                                  staff granted Paiute’s request to use the                determining the appropriate action to be              Commission’s (Commission) regulations
                                                  pre-filing process and assigned Docket                   taken, but the filing of a comment alone              under the Natural Gas Act (NGA), and
                                                  No. PF17–2–000 to staff activities                       will not serve to make the filer a party              National Fuel’s blanket certificate
                                                  involving the Projects. Now, as of the                   to the proceeding. The Commission’s                   issued in Docket No. CP83–4–000.
                                                  filing of this application on July 5, 2017,              rules require that persons filing                     National Fuel requests authorization to
                                                  the NEPA Pre-Filing Process for this                     comments in opposition to the project                 abandon one injection/withdrawal
                                                  project has ended. From this time                        provide copies of their protests only to              storage well and associated well line in
                                                  forward, this proceeding will be                         the party or parties directly involved in             its Colden Storage Field located in the
                                                  conducted in Docket No. CP17–471–000                     the protest.                                          Town of Aurora, Erie County, New
                                                  as noted in the caption of this Notice.                     Persons who wish to comment only                   York. Specifically, National Fuel
                                                     Pursuant to Section 157.9 of the                      on the environmental review of this                   proposes to plug and abandon one
                                                  Commission’s rules, 18 CFR 157.9,                        project should submit an original and                 injection/withdrawal storage well, Well
                                                  within 90 days of this Notice the                        two copies of their comments to the                   0925–I, and abandon in place the
                                                  Commission staff will either: Complete                   Secretary of the Commission.                          associated Well Line CW–925, all as
mstockstill on DSK30JT082PROD with NOTICES




                                                  its environmental assessment (EA) and                    Environmental commentors will be                      more fully set forth in the application,
                                                  place it into the Commission’s public                    placed on the Commission’s                            which is open to the public for
                                                  record (eLibrary) for this proceeding, or                environmental mailing list, will receive              inspection. There will be no
                                                  issue a Notice of Schedule for                           copies of the environmental documents,                abandonment or decrease in service to
                                                  Environmental Review. If a Notice of                     and will be notified of meetings                      customers as a result of the proposed
                                                  Schedule for Environmental Review is                     associated with the Commission’s                      abandonment. The filing may also be
                                                  issued, it will indicate, among other                    environmental review process.                         viewed on the web at http://


                                             VerDate Sep<11>2014   19:30 Jul 24, 2017   Jkt 241001   PO 00000   Frm 00045   Fmt 4703   Sfmt 4703   E:\FR\FM\25JYN1.SGM   25JYN1


                                                                                  Federal Register / Vol. 82, No. 141 / Tuesday, July 25, 2017 / Notices                                            34517

                                                  www.ferc.gov using the ‘‘eLibrary’’ link.                and will be notified of meetings                      schedule for the completion of the EA
                                                  Enter the docket number excluding the                    associated with the Commission’s                      for the Project.
                                                  last three digits in the docket number                   environmental review process.
                                                                                                                                                                 Schedule for Environmental Review
                                                  field to access the document. For                        Environmental commenters will not be
                                                  assistance, contact FERC at                              required to serve copies of filed                     Issuance of EA—November 13, 2017
                                                  FERCOnlineSupport@ferc.gov or call                       documents on all other parties.                       90-day Federal Authorization Decision
                                                  toll-free, (866) 208–3676 or TTY, (202)                  However, the non-party commenter will                    Deadline—February 11, 2018
                                                  502–8659.                                                not receive copies of all documents filed                If a schedule change becomes
                                                     Any questions regarding this                          by other parties or issued by the                     necessary, additional notice will be
                                                  application should be directed to Alice                  Commission (except for the mailing of                 provided so that the relevant agencies
                                                  A. Curtiss, Deputy General Counsel for                   environmental documents issued by the                 are kept informed of the Project’s
                                                  National Fuel, 6363 Main Street,                         Commission) and will not have the right               progress.
                                                  Williamsville, New York 14221, or                        to seek court review of the                           Project Description
                                                  phone (716) 857–7075, or by email                        Commission’s final order.
                                                  curtissa@natfuel.com.                                      The Commission strongly encourages                     Northwest proposes to remove,
                                                     Any person or the Commission’s staff                  electronic filings of comments, protests              replace, and lower about 1,700 feet of
                                                  may, within 60 days after issuance of                    and interventions in lieu of paper using              30-inch-diameter pipeline in the north
                                                  the instant notice by the Commission,                    the eFiling link at http://www.ferc.gov.              floodplain of the North Fork Nooksack
                                                  file pursuant to Rule 214 of the                         Persons unable to file electronically                 River. The project also includes removal
                                                  Commission’s Procedural Rules (18 CFR                    should submit an original and 5 copies                of about 1,550 feet of previously
                                                  385.214) a motion to intervene or notice                 of the protest or intervention to the                 abandoned 26-inch-diameter pipeline
                                                  of intervention and pursuant to Section                  Federal Energy Regulatory Commission,                 that would become exposed during the
                                                  157.205 of the regulations under the                     888 First Street NE., Washington, DC                  replacement of the 30-inch pipeline.
                                                  NGA (18 CFR 157.205), a protest to the                   20426.                                                The Project is located in Whatcom
                                                  request. If no protest is filed within the                                                                     County, near Deming, Washington.
                                                  time allowed therefore, the proposed                       Dated: July 19, 2017.
                                                                                                           Kimberly D. Bose,                                     Background
                                                  activity shall be deemed to be
                                                  authorized effective the day after the                   Secretary.                                               On May 9, 2017, the Commission
                                                  time allowed for filing a protest. If a                  [FR Doc. 2017–15546 Filed 7–24–17; 8:45 am]           issued a Notice of Intent to Prepare an
                                                  protest is filed and not withdrawn                       BILLING CODE 6717–01–P                                Environmental Assessment for the
                                                  within 30 days after the allowed time                                                                          Proposed North Fork Nooksack Line
                                                  for filing a protest, the instant request                                                                      Lowering Project and Request for
                                                  shall be treated as an application for                   DEPARTMENT OF ENERGY                                  Comments on Environmental Issues
                                                  authorization pursuant to section 7 of                                                                         (NOI). The NOI was sent to affected
                                                  the NGA.                                                 Federal Energy Regulatory                             landowners; federal, state, and local
                                                     Pursuant to section 157.9 of the                      Commission                                            government agencies; elected officials;
                                                  Commission’s rules, 18 CFR 157.9,                        [Docket No. CP17–133–000]                             environmental and public interest
                                                  within 90 days of this Notice the                                                                              groups; Native American tribes; other
                                                  Commission staff will either: Complete                   Northwest Pipeline LLC; Notice of                     interested parties; and local libraries
                                                  its environmental assessment (EA) and                    Schedule for Environmental Review of                  and newspapers. In response to the NOI,
                                                  place it into the Commission’s public                    the North Fork Nooksack Line                          the Commission received comments
                                                  record (eLibrary) for this proceeding, or                Lowering Project                                      from the U.S. Environmental Protection
                                                  issue a Notice of Schedule for                                                                                 Agency and the Lummi Indian Business
                                                  Environmental Review. If a Notice of                        On April 6, 2017, Northwest Pipeline               Council. The primary issues raised by
                                                  Schedule for Environmental Review is                     LLC (Northwest) filed an application in               the U.S. Environmental Protection
                                                  issued, it will indicate, among other                    Docket No. CP17–133–000 requesting a                  Agency are impacts on water quality
                                                  milestones, the anticipated date for the                 Certificate of Public Convenience and                 during pipeline construction; impacts
                                                  Commission staff’s issuance of the final                 Necessity pursuant to section 7(c) of the             on wetlands, floodplains, and riparian
                                                  environmental impact statement (FEIS)                    Natural Gas Act to construct and operate              resources; control of invasive and
                                                  or EA for this proposal. The filing of the               certain natural gas pipeline facilities.              noxious weeds; and impacts on
                                                  EA in the Commission’s public record                     The proposed project is known as the                  endangered species. The Lummi
                                                  for this proceeding or the issuance of a                 North Fork Nooksack Line Lowering                     Business Council identified that it has
                                                  Notice of Schedule for Environmental                     Project (Project), and would involve                  an active interest in the proposed
                                                  Review will serve to notify federal and                  replacing and lowering approximately                  Project and requested additional time to
                                                  state agencies of the timing for the                     1,700 feet of 30-inch-diameter pipeline               prepare and submit scoping comments.
                                                  completion of all necessary reviews, and                 in Whatcom County, Washington.                           The U.S. Army Corps of Engineers has
                                                  the subsequent need to complete all                         On April 20, 2017, the Federal Energy              agreed to participate as a cooperating
                                                  federal authorizations within 90 days of                 Regulatory Commission (Commission or                  agency in the preparation of the EA.
                                                  the date of issuance of the Commission                   FERC) issued its Notice of Application
                                                  staff’s FEIS or EA.                                      for the Project. Among other things, that             Additional Information
                                                     Persons who wish to comment only                      notice alerted agencies issuing federal                  In order to receive notification of the
                                                  on the environmental review of this                      authorizations of the requirement to                  issuance of the EA and to keep track of
mstockstill on DSK30JT082PROD with NOTICES




                                                  project should submit an original and                    complete all necessary reviews and to                 all formal issuances and submittals in
                                                  two copies of their comments to the                      reach a final decision on a request for               specific dockets, the Commission offers
                                                  Secretary of the Commission.                             a federal authorization within 90 days of             a free service called eSubscription. This
                                                  Environmental commenters will be                         the date of issuance of the Commission                can reduce the amount of time you
                                                  placed on the Commission’s                               staff’s Environmental Assessment (EA)                 spend researching proceedings by
                                                  environmental mailing list, will receive                 for the Project. This instant notice                  automatically providing you with
                                                  copies of the environmental documents,                   identifies the FERC staff’s planned                   notification of these filings, document


                                             VerDate Sep<11>2014   19:30 Jul 24, 2017   Jkt 241001   PO 00000   Frm 00046   Fmt 4703   Sfmt 4703   E:\FR\FM\25JYN1.SGM   25JYN1



Document Created: 2018-10-24 11:21:04
Document Modified: 2018-10-24 11:21:04
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation82 FR 34516 